imagine! dixon street office remodel progress – 5/08/2015
TRANSCRIPT
Imagine! Dixon
Street Office
Remodel Progress
Before Remodel 2/13/2015
Before Remodel 2/13/2015
Before Remodel 2/13/2015
Before Remodel 2/13/2015
2/20/2015
Staff, Equipment Moved Out
2/20/2015
Staff, Equipment Moved Out
2/20/2015
Staff, Equipment Moved Out
2/20/2015
Staff, Equipment Moved Out
2/27/2015
Furniture Is (Mostly) Gone
2/27/2015
Furniture Is (Mostly) Gone
2/27/2015
Temporary walls installed to block off areas so staff in a few
departments (HR, Finance, Administration) may continue to work in
limited areas
3/6/2015
Demolition Is Underway
3/6/2015
Don’t worry – we saved all the pictures of the monthly recipients of
Imagine!’s Excellence in Customer Service Award
3/6/2015
For those hearty souls still working at Dixon,
bathroom availability is at a premium
3/13/2015
First floor break area
3/13/2015
1st
floor looking southeast, former IBHS and EI
support offices
3/13/2015
2nd
floor looking South and West on Case
Management wing
3/13/2015
2nd
floor Case Management wing
3/13/2015
1st
floor looking through O’Shea Room
3/13/2015
1st
floor looking South and West through O’Shea
Room
3/13/2015
Two new ten person conference rooms framed
(near former IBHS space), new
office for HR Director
3/20/2015
1st
floor meeting room,
adjacent to Human Resources
3/20/2015
Reception area
3/20/2015
First floor hallway looking into patio and break area
3/20/2015
First floor large meeting room West wing
3/20/2015
First floor large meeting room West wing
3/20/2015
First floor small meeting room West wing
3/20/2015
First floor office West wing (old FSSP area)
3/20/2015
First floor old FSSP area, looking East
3/20/2015
Women’s second floor bathroom
3/20/2015
First floor IBHS office
3/20/2015
First floor South Wing meeting room
3/27/2015
New meeting room adjacent to IBHS
3/27/2015
IBHS on right side of hall. Meeting rooms on left.
3/27/2015
Meeting room adjacent to HR on left. Meeting room
across from IBHS on right.
3/27/2015
HR Director’s Office
3/27/2015
Door from HR Director’s office to HR office
3/27/2015
New meeting room adjacent to work stations, 1st
floor, Southeast wing
3/27/2015
Two offices, 1st floor, Southeast wing
3/27/2015
IBHS office and treatment room
4/3/2015
This week walls started to go up, like the walls for
this small meeting room in South wing first floor.
4/17/2015
We have a hint of color! These pictures are from the
Southeast 1st floor.
4/17/2015
We have a hint of color! These pictures are from the
Southeast 1st floor.
4/17/2015
We have a hint of color! These pictures are from the
West wing 2nd
floor.
4/17/2015
We have a hint of color! These pictures are from the
West wing 2nd
floor.
4/24/2015
1st
floor break area
4/24/2015
1st
floor reception area
4/24/2015
2nd floor break area
4/24/2015
Got mail? We’ve go the space for it.
4/24/2015
1st
floor West wing office
4/24/2015
Tiling the reception area
4/24/2015
Tile for the kitchen backsplash, created by Imagine!
CORE/Labor Source artists
5/1/2015
Reception area with finished tile
5/1/2015
Meeting rooms near reception area
5/1/2015
1st
floor break area
5/1/2015
1st
floor South wing with carpet
5/8/2015
Ceilings
5/8/2015
Furnishings first floor South wing
5/8/2015
Second floor copy area
5/8/2015
Second floor kitchen
5/8/2015
First floor West wing furniture