imindq user manual for project management

65

Upload: seavus-products

Post on 22-Jan-2018

414 views

Category:

Business


0 download

TRANSCRIPT

Page 1: iMindQ User Manual for Project Management
Page 2: iMindQ User Manual for Project Management

Contents

2

CONTENTS .........................................................................................................................................2

CHAPTER 1.: WELCOME TO IMINDQ® ..................................................................................................3

CHAPTER 2.: PROJECT MANAGEMENT IN IMINDQ® ........................................................................... 10

CHAPTER 3.: CREATE PROJECT PLAN ................................................................................................. 16

CHAPTER 4.: WORK WITH WBS CHART .............................................................................................. 41

CHAPTER 5.: IMPORT/EXPORT PROJECT INFORMATION .................................................................... 51

CHAPTER 6.: PRINT PROJECT PLAN .................................................................................................... 56

Contents

Page 3: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

3

In this section you will learn:

About the Working space

Ribbons

Working space

After installing and starting iMindQ® you will see user interface as it is presented on the

figure below.

Figure 1. iMindQ® Working space

1.Chapter : Welcome To

iMindQ®

Page 4: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

4

The main elements of the working space in iMindQ® user interface are:

area – Area showing the space where the map is created, edited and

viewed

area – Area (ribbons) containing all commands available in iMindQ®

grouped by the type of action.

area – Area showing marked activity data.

Quick Start

The main purpose of the Quick Start is to give introduction to the users how to create

small project plan in several steps. In the next sections, as well as in the iMindQ® User

Manual (http://www.imindq.com/resources/documents), detail description of the

implemented functionalities are presented.

The first step is to create a map. This small exercise will be practical introduction to

iMindQ® main features and possibilities. You will create a map that contains topics, you

will add tasks properties to the topic (start and finish date, resources, % Complete and

finally view the project plan in Gantt Chart.

Create mind map

After starting iMindQ®, you will see the Introduction map, in which are presented all

possibilities of the iMindQ® software. In order to start working with the application and

create your first map you have to begin with blank map. For that purpose perform the

following steps:

1. Click on the Application menu button .

2. Point the mouse cursor on the New sub-menu.

3. From the available map types (Mind Map, Organic Mind Map, White Board,

Org Chart and WBS Chart), select the one that is most appropriate for your

work.

Tips: You can start a new map by using the “Ctrl + N” shortcut or using the New

Map feature from the Quick Access toolbar

After performing the steps above you will see the screen presented on the figure below.

Page 5: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

5

Figure 2. New Map

To insert topic (sub-topic of existing one) i.e. to create parent-child relationship in the map

perform the follow procedure:

1. Select the topic that you want to add sub-topics (in this case the Central

topic)

2. Click on the Insert button on the keyboard to insert the topic from the next

level (Sub-topics of the Central Topic)

3. To insert new topic (level 3) use the Insert button or if you want to add sibling

topic use the Enter button on the keyboard

After several times performing the mentioned procedure, you will get the following map:

Page 6: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

6

Figure 3. Add Topic to map

Add task properties to topic

Although you have created a map, your Gantt Chart is still empty. This is due to the fact

that topics don’t contain task properties. You have to assign Start and Finish date to the

topic in order to convert it into a project task.

For that purpose

1. Select the topic in the map that will present project task.

2. In the Task Elements group click on the Task Info button

3. In the Task Info panel select the Start Date check box and select the appropriate

date.

Page 7: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

7

Figure 4. Add Task parameters to topic

4. In the same panel select the Finish Date check box and insert the date for task’s

finish.

5. Add the required duration in the Duration field.

6. Assign the appropriate resource by typing the name in the Resource field.

These four steps are enough to create task and this task to be presented in Gantt Chart

(View ribbonViews groupGantt Chart).

Page 8: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

8

Figure 5. Gantt Chart in iMindQ®

View tasks in Gantt Chart

In order to start working with the Gantt Chart you have to make the chart active i.e. to

make it visible to the user. For that purpose, you have to perform the following steps:

1. Click on the View ribbon.

2. From the Views group, click on the Gantt Chart icon.

The Gantt Chart functionality is consists of two features:

Activating the Gantt Chart, presented with the icon

Choose the position of the chart in the working space, presented trough the

drop-down menu

After making the Gantt chart visible, iMindQ® gives you the possibility to choose the

location of the Gantt Chart inside the working space. This is possible by using the options

located in the drop-down menu that is positioned under the Gantt Chart icon. User can

choose between the following positions:

Top

Page 9: iMindQ User Manual for Project Management

Chapter : Welcome To iMindQ®

9

Bottom

Left

Right

In the following figure, the Gantt Chart is located under the mind map.

Figure 6. iMindQ working space with active Gantt chart

The main elements of the working space in iMindQ® user interface are:

area – Area showing the plan presented as mind map with topics (block

form) with specified dependencies.

area – Area for Gantt chart like Microsoft® Project but with limited

functionality

area – Area showing marked activity data.

Page 10: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

10

Introduction

What is project? According the “PM Body of Knowledge” project is “temporary endeavor

undertaken to create a unique product, service or result”. PRINCE 2 methodologies define

the project as "a management environment that is created for the purpose of delivering

one or more business products according to a specified business case". If you search the

World Wide Web, you can find more definitions for project or project plan. You don’t need

to know all these terms in order to make or to manage one project plan. Just remember

that project is something that has start and finish, and deliver material or nonmaterial

goods.

One good example for project is shopping at the local supermarket. Although it seems too

trivial as example, actually you will find that it is not as simple as it looks like. At the

beginning you are defining the timeframe for the shopping, keeping in mind the

supermarket’s working hours and the time needed for going to the mall and for shopping.

Next, you are writing on a piece of paper the product that you will buy and prioritize them.

The last step is planning the budget i.e. how much money you are planning to spend for

shopping. Of course, there is always a backup plan in case something goes wrong. After

fulfilling these steps, you are ready for spending some money.

As you can see, this example contains the main characteristics for one project: timeframe,

planning, prioritizing, budgeting and backup plan. You can use the same technique for

creating projects in iMindQ® but instead organizing entire process in your mind and

writing it on a piece of paper you will use views and other features for better and faster

creation of projects.

Tasks and resource will be introduced in this chapter, since they are basic elements of any

project plan.

2.Chapter : Project

Management in iMindQ®

Page 11: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

11

Gantt Chart

Gantt chart view is the most used view while creating project. It gives tabular and

graphical presentation of the tasks in the project plan. Gantt chart view consists of two

parts: Gantt Table which is located on the left side of the application and Gantt chart on

the right side.

Gantt Table (or Gantt Sheet) consists of columns that contain information for the tasks.

Depending on which table you are working, different columns will be presented in the

Gantt Sheet. A default table for the Gantt chart is the Entry table. Task’s attributes can be

entered in the Gantt Sheet by typing the appropriate information in the cells, selecting

from the drop-down list in the cell or by using the Task Info window.

The look of the Gantt chart view is presented on the figure below.

Figure 7. Gantt Chart view in iMindQ

Gantt chart contains bars that are graphical presentation of the tasks entered in the Gantt

Table. The length of the bar corresponds to the task’s duration. At the top of the Gantt

chart is the timescale with two layers. The bottom layer presents the working days in the

week and the top layer presents the working weeks in the year. The non-working days are

colored blue. The Gantt chart has gridlines for background in order to help you in

determining starting or finishing day of some particular task or to view task’s duration.

You can use the Gantt chart for:

Page 12: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

12

Planning and Organizing project plans to the

Monitoring project’s progress

Task

There are several symbols that represent task in iMindQ®. The task’s bars that are used in

Gantt chart view and their description can be found in the table below:

Bar Description

Summary Task

Task

Milestone

Summary Task can be graphical symbol for one group of tasks that are logically connected

or can be representation for project summary task. When representing one group of tasks,

Summary Task summarizes the information for duration, progress and costs for the tasks.

Milestone is a task that represents achieving major point in the project. Characteristic for

this type of task is the duration. Milestone has 0-day duration and it can hardly be

considered as a task since they are point in time. You can use milestones to emphasis the

breaking points (major releases of product, starting marketing and sales campaign, etc.)

when you present the project plan in front of the upper management in your company.

Dependencies

After you entered the task, you need to connect the tasks in order to get visual flow of the

project plan. You can link tasks on several ways: by selecting tasks in Gantt Sheet and

clicking on the icon in the Standard toolbar; using the Link Task function in the Edit

menu; connect tasks using the connector in the Gantt chart. If you use one of these

possibilities for linking tasks, they will be connected with Finish to Start dependency

because this is a default dependency in iMindQ®.

iMindQ® has the following dependencies:

Finish to Start (FS)

Start to Finish (SF)

Start to Start (SS)

Finish to Finish (FF)

Page 13: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

13

Finish to Start (FS)

Finish to Start is a default dependency in iMindQ®. This means that the successor task

cannot start until the predecessor task finishes. The line’s arrow that connects two tasks is

pointed from the task that is assumed to be predecessor (task’s Finish Date) to the task

that is successor (task’s Start Date).

For example, there are two tasks: Task Blue and Task Red, connected with Finish to Start

dependency, as it is presented on Figure 8. Finish to Start dependency determines that the

Task Red can not start until Task Blue is 100 % complete. Also, you can notice that the

arrow is pointed from the Task Blue Finish Date (predecessor) to the Task Red Start Date

(successor).

Figure 8. Example for Finish to Start dependency

Start to Finish (SF)

Next dependency that is supported by iMindQ® is the Start to Finish, where the successor

task cannot finish until the predecessor task starts. The Finish Date of the successor task

can be equal or greater than the Start Date of the predecessor task:

𝑆𝑢𝑐𝑐𝑒𝑠𝑠𝑜𝑟(𝐹𝑖𝑛𝑖𝑠ℎ 𝐷𝑎𝑡𝑒) ≥ 𝑃𝑟𝑒𝑑𝑒𝑐𝑒𝑠𝑠𝑜𝑟(𝑆𝑡𝑎𝑟𝑡 𝐷𝑎𝑡𝑒)

The link that connects the task starts from the predecessor’s Start Date and ends at the

successor’s Start Date.

Figure 9. Example for Start to Finish dependency

Let’s see the Start to Finish dependency trough example. On Figure 9 Task Red cannot

finish until Task Blue starts. This means that Task Red can finish on the same date when

Task Blue starts, or later. The dependency link starts from Task Blue Start Date and ends to

Task Red Finish Date.

Page 14: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

14

Start to Start (SS)

Another dependency in iMindQ® is Start to Start dependency. Definition for this

dependency is: “The successor task cannot start until the predecessor task starts”. Tasks

may or may not have the same Start Date. The successor task may start at any time after

predecessor task starts, or expressed with equation:

𝑆𝑢𝑐𝑐𝑒𝑠𝑠𝑜𝑟(𝑆𝑡𝑎𝑟𝑡 𝐷𝑎𝑡𝑒) ≥ 𝑃𝑟𝑒𝑑𝑒𝑐𝑒𝑠𝑠𝑜𝑟(𝑆𝑡𝑎𝑟𝑡 𝐷𝑎𝑡𝑒)

The arrow that connects these tasks is pointed from predecessor’s Start Date to

successor’s Start Date.

Once again, let us see the example with the Task Blue and Task Red, presented on Figure

10. According to the definition, Task Red cannot starts until the Task Blue starts. Also, you

can notice that the arrow is pointed from the Task Blue Start Date (predecessor) to the

Task Red Start Date (successor).

Figure 10. Example for Start to Start dependency

Finish to Finish (FF)

The last dependency in iMindQ® is Finish to Finish. This means that the successor task

cannot finish until the predecessor task finishes. Tasks may or may not have identical

Finish Date. The successor task can finish at any date after predecessor task’s finish.

Expressed with equation:

𝑆𝑢𝑐𝑐𝑒𝑠𝑜𝑟(𝐹𝑖𝑛𝑖𝑠ℎ 𝐷𝑎𝑡𝑒) ≥ 𝑃𝑟𝑒𝑑𝑒𝑐𝑒𝑠𝑠𝑜𝑟(𝐹𝑖𝑛𝑖𝑠ℎ 𝐷𝑎𝑡𝑒)

The line arrow that connects these two tasks starts from predecessor task’s finish date and

pointed to successor task’s finish date.

On the figure below are presented two tasks connected with Finish to Finish dependency.

Task Red can finish at any date after Task Blue is 100% complete. You can see that the

connection line starts at Task Blue Finish date and ends at Task Red Finish Date.

Page 15: iMindQ User Manual for Project Management

Chapter : Project Management in iMindQ®

15

Figure 11. Example for Finish to Finish dependency

Page 16: iMindQ User Manual for Project Management

Chapter : Create project plan

16

In this section you will learn:

How to create project plan in iMindQ®

Create project plan in iMindQ®

After the introduction with the main elements of the Project Management and iMindQ®

project management features, you are ready to create tasks from the topics and create

project plans.

Project plan tasks are created using the Task Info feature:

1. Select the topic from the map that will be transformed into task or the location for

the new topic

Figure 12. Main window

3.Chapter : Create project

plan

Page 17: iMindQ User Manual for Project Management

Chapter : Create project plan

17

2. Select location in the map for the new topic and then select the Insert ribbon and

from the Map Elements group click on the Topic button

Figure 13. Insert topic in map

3. In the Task Elements group click on the Task Info button

4. In the Task Info panel select the Start Date check box and select the appropriate

date.

Figure 14. Add Task parameters to topic

5. In the same panel select the Finish Date check box and insert the date for task’s

finish.

These four steps are enough to create task and this task to be presented in Gantt Chart

(View ribbonViews groupGantt Chart).

Page 18: iMindQ User Manual for Project Management

Chapter : Create project plan

18

An alternative way to create a new activity is to mark an activity and click on the right-

mouse button, as it is presented on the figure below.

Figure 15. Add task parameters to topic via contextual menu

The process of creating tasks using the contextual menu in iMindQ® is very easy and

consists of the following steps:

1. Mark the activity and double-click on the left-mouse button in the activity name

area.

2. Fill in the name in the marked area, as it is presented on the image below.

Figure 16. Topic with task parameter

Page 19: iMindQ User Manual for Project Management

Chapter : Create project plan

19

3. Mark the activity and double-click on the left-mouse button in the date area.

4. Fill in the date

Figure 17. Edit topic’s task parameter

The process of inserting the date can be done using the Task info panel, as it is presented

on Figure 18.

Figure 18.

Insert links between project tasks

To connect two topics from different branches for emphasizing the link between them,

you can use the relationship functionality. The relationship between two topics can use

only for visualizing the connection or it can be used for defining the dependency when

working with task properties (Project Management part in iMindQ®).

To connect two topics in the map, perform the following steps:

1. Click on the activity to be linked with left mouse button

2. Click on “Relationship”

3. Click on the activity to be linked (again)

4. Click on the activity to be linked to

5. If needed: Change the constraint type (Dependency) by clicking on the symbol

Page 20: iMindQ User Manual for Project Management

Chapter : Create project plan

20

All steps from 1 to 5 are presented on Figure 19.

Figure 19. Inserting link between topics in the map

After you have inserted the relationship, you can edit the line that connects the topics. You

can change the color, weight and pattern of the line, the styles of the beginning and

ending points. This is done from the Format Relationship dialog, presented on the figure

below.

Page 21: iMindQ User Manual for Project Management

Chapter : Create project plan

21

Figure 20. Format Relationship dialog

Alternative way for inserting links between project tasks is to use the Gantt chart. The

process is presented trough the steps below and illustrated on Figure 21.

1. Mark an activity with left mouse button.

2. Hold down the button and drag it to another activity to create a link.

Figure 21. Insert dependency between tasks in Gantt chart

Links can be added using the Task Information window.

The process is as follow:

1. With left mouse button click the activity and then double click on it.

2. Choose ”Predecessor” and fill in the link data and the contraint type, as it is

presented on Figure 22.

Page 22: iMindQ User Manual for Project Management

Chapter : Create project plan

22

Figure 22. Inserting links using Task Information window

Insert Priority, Resources, % Complete

Advanced Microsoft Project users knows that the “Priority” field indicates the level of

importance of the task in the created project plan and the adaptability of the task for

delaying or splitting during the resource allocation process. In addition, the priority is

assigned to the tasks in order to assess their relative values as part of the project

management strategy.

When importing project plans from Microsoft Project, iMindQ® imports the “Priority”

field, converts the value and presented it in the Topic as icon, next to the Task Name. Since

iMindQ® doesn’t level project’s resources, the task priority is only a symbol, visual marker

for emphasizing task’s importance in the project plan.

Figure 23. Task Priority marker in topic

Priority level varies from 1-9 according the task importance. All tasks marked with Level 1 -

have the maximum priority, while the Level 9 - have the lowest one. For imported

project plans from Microsoft Project, the conversion is presented in the table below.

Page 23: iMindQ User Manual for Project Management

Chapter : Create project plan

23

Table 1. Mapped

Priority in Microsoft Project Priority in IMindQ Symbol

1000-900 1 900-800 1 800-700 2 700-600 3 600-500 4 500-400 5 400-300 6 300-200 7 200-100 8 100-1 9

Inserting task priority is very easy and consists of two steps:

1. Select the task that you will add priority parameter

2. Click on the Task Panel and from the Priority drop-down menu select the

appropriate Priority level.

Figure 24. Insert Task Priority

Usually when we talk or think about Resources in project management, we are thinking

about the people inside the company or out team that should be assigned on the project’s

tasks.

To add resource to your project, perform the following steps:

1. Select the task in the project plan.

Page 24: iMindQ User Manual for Project Management

Chapter : Create project plan

24

2. In the Task Info panel click on the Resource field and start typing the resource’s

name. In case the resource already exists, click on the drop-down button to

get the resource list and select the appropriate resource.

3. Hit the Enter button.

Figure 25. Insert resource in project plan

4. The resource’s name will appear inside the topic.

Figure 26.

You can added resources to the tasks using the Task Information window – Resource tab

by selecting the appropriate task in the Gantt Chart and double-click on cell.

1. Select the Gantt Chart.

2. Double-click on the cell with the task that you want to assign resource.

3. Select the Resource tab from Task Information window.

4. Click on the Add… button.

5. If the resource is new then start typing the name in the Resource Name field. If

the resource exists, use the drop-down list for selecting the appropriate one.

The entire process for assigning resource to task is presented on Figure 36.

Page 25: iMindQ User Manual for Project Management

Chapter : Create project plan

25

Figure 27. Insert resources through Task Information window

The % Complete fields contain the current status of a task, expressed as the percentage of

the task's duration that has been completed.

By default, the drop-down list contains 5 values for updating the task (0%, 25%, 50%, 75%

and 100%) but you can insert any value for % Complete by typing it inside the field.

Inserting % complete is very easy and consists of two steps:

1. Select the task that you will add priority parameter

2. Click on the Task Panel and from the % Complete drop-down menu select the

appropriate value.

Figure 28. Insert % Complete to task

Page 26: iMindQ User Manual for Project Management

Chapter : Create project plan

26

3. Next to the name of the topic, icon will appear,

Figure 29.

You can added % Complete to the tasks using the Task Information window – General tab

by inserting the appropriate value in the % Complete field.

1. Select the Gantt Chart.

2. Double-click on the cell with the task that you want to update.

3. Select the General tab from Task Information window.

4. Type the % Complete value in the Percent Complete field

The entire process for assigning resource to task is presented on Figure 30

Figure 30. Inserting % Complete trough Task Information window

Page 27: iMindQ User Manual for Project Management

Chapter : Create project plan

27

Mark at risk task and Mark past due task

Mark at risk task is feature that colors those topics which are not updated until the

immediate date. It is activated trough button inside the Plan ribbon, as it is presented on

Figure 31.

Figure 31. Mark at risk task

Let’s see through an example how Mark at risk task feature works. On Figure 32, four days

task is presented. To be completed successfully, team member must accomplish 25 % of

the task in each day.

Figure 32. Four day task

At the end of the third day (marked with the red pointer) it is expected that team member

finished 75% of the task. If the reported % Complete is smaller than 75%, in that case the

topic will be colored yellow (by default) and the task will be marked as task with risk.

Figure 33.

Mark past due tasks are those tasks that are not 100% completed when immediate date

over past task’s finish date. In that case the task will be colored red in the map. This

Page 28: iMindQ User Manual for Project Management

Chapter : Create project plan

28

feature is activated in same way as Mark at risk task is feature i.e. using the check box in

front of the feature, at it is presented on Figure 34.

Figure 34. Mark past due task

Let’s explain this feature via example. On Figure 35 the same task from previous example

is presented, but this time with time axis.

Figure 35.

Our task will be marked as past due task if in the point called “Current Date” the %

complete of the task is smaller than 100%.

Create project plan in Gantt Chart

Another option for creating tasks is by typing the tasks’ names or values directly in the

sheet. For this purpose you can use the Gantt table part from the Gantt Chart view. You

can edit task’s names, Start and Finish dates, Duration and Predecessors.

The process of inserting project tasks in the Gantt Chart is very simple and consists of 3

steps:

1. Mark an activity (task) and click on the right-mouse button.

2. Chose “Insert Task” or “Insert Subtask” from the contextual menu.

Page 29: iMindQ User Manual for Project Management

Chapter : Create project plan

29

Figure 36. Insert task from Contextual menu

3. Double click on a row and fill in the data in ”Task Information” dialog.

Figure 37. Task Information dialog

Edit tasks parameters

Editing tasks parameters can be done Task Info Panel, Gantt Chart or by changing the

parameters directly in the topic.

To edit task’s start or finish date using Task Info panel in iMindQ, perform the next steps:

Page 30: iMindQ User Manual for Project Management

Chapter : Create project plan

30

1. Mark the activity.

2. Open the “Task info” tab.

3. Fill in the date or use the calendar.

These two steps for modification are presented on Figure 38.

Figure 38. Modify task's date from Task Info panel

The easiest and the fastest way for edit task is to use the Gantt chart. Point the mouse cursor at

the day that will be start date of the task, click on the left-mouse button and draw the length of

the task.

The steps for modifying the task are:

1. Hold place the cursor where activity shall start.

2. Down the left mouse button and drag the activity to its end point.

Figure 39. Modify tasks using Gantt Chart

Note: To move the tasks in the Gantt Chart, just click on the activity, hold down the left mouse

button and drag it to the wanted position

Page 31: iMindQ User Manual for Project Management

Chapter : Create project plan

31

Gantt Table customizing

Gantt Table in iMindQ® is customizable which means that user can inserts a new field (column)

in the associated table of the active view or removes the columns that are not important for the

project plan.

Adding or removing columns is performed trough the contextual menu, that pop-ups when user

points the mouse cursor over the header of the table and make right-button click.

The steps

1. Point the mouse cursor over the table’s header.

Figure 40. Mouse cursor over table header

2. Right click on the mouse while the cursor is still on the previously mentioned

position.

Figure 41. Modify Gantt table from Contextual menu

3. From the contextual menu select the columns that will be inserted/removed from

the table.

Page 32: iMindQ User Manual for Project Management

Chapter : Create project plan

32

Timescale formatting

Gantt Chart view has a timescale at the top of the chart. By default, in iMindQ®, the timescale is

displayed with two tiers. Using Microsoft® Project terminology, the timescale tiers can be

defined as: top tier and bottom tier. You can adjust all timescale tiers to view your project at the

level of detail you need.

The Gantt chart have five different time settings:

Hours

Days

Three Days

Weeks

Months

The non-working days are colored blue in the Gantt Chart.

Modifying the timescale can be done in several steps:

1. Point the mouse cursor over the timescale.

2. Right click on the mouse while the cursor is still on the previously mentioned

position.

Page 33: iMindQ User Manual for Project Management

Chapter : Create project plan

33

Figure 42. Modify timescale from Contextual menu

3. From the contextual menu select the time range that is most appropriate for your

project. By default, Days option is selected in the menu.

Work with Constraint Dates

Constraint means restrictions. While creating a project plan you can set a restriction on

task’s start or finish date. This means that some specific task must start on or finish no

later than a particular date.

There are three types of constraints:

Flexible constraints

Semi-flexible constraints

Non-flexible (Inflexible) constraint

Flexible constraints doesn’t content specific date. Using these constrains, users can start

the project tasks as early as possible or as late as possible as long as the tasks with

constraint dates ends before project’s finish date.

Semi-flexible constraints requires an association with dates that controls the earliest or

latest start or finish date of the task. Tasks with semi-flexible constraints can finish at any

time as long as it meets the start or finish deadline of the project plan.

Non-flexible constraints requires an association with dates that controls the start or finish

date of the task. These constraints are used when there are many external factors that are

associated with the task/project plan.

All constraints that are implemented in iMindQ® are presented in the table below.

Page 34: iMindQ User Manual for Project Management

Chapter : Create project plan

34

Symbol Type Name Description

SNET Start No Earlier Than Schedules the task to start on or after a

specified date. Use this constraint to ensure

that a task does not start before a specified

date

FNET Finish No Earlier Than Schedules the task to finish on or after a

specified date. Use this constraint to ensure

that a task does not finish before a certain

date

SNLT Start No Later Than Schedules the task to start on or before a

specified date. Use this constraint to ensure

that a task does not start after a specified date

FNLT Finish No Later Than Schedules the task to finish on or before a

specified date. Use this constraint to ensure

that a task does not finish after a certain date

MFO Must Finish On Schedules the task to finish on a specified

date. Sets the early, scheduled, and late finish

dates to the date that you type and anchors

the task in the schedule

MSO Must Start On Schedules the task to start on a specified date.

Sets the early, scheduled, and late start dates

to the date that you type and anchors the task

in the schedule

Set Constraint Date

iMindQ® works with Semi-flexible and Non-flexible constraints. Constraint Date and

Constraint Type are located in the Task Information window, in the General tab. Setting

Constraint Date and Type to the task is very easy and it can be done in several steps:

1. Select the task in the Gantt Chart.

2. Double-click on the cell in order to open the Task Information window.

3. In the General tab click on the Constraint drop-down list to assign a

Constraint type to the task.

4. In the General tab click on the Date drop-down list to assign a Constraint

date to the task.

Page 35: iMindQ User Manual for Project Management

Chapter : Create project plan

35

Figure 43. Assign Constraint Date and Type to task

Importing project plan with Constraint dates in iMindQ®

If you import project plan created in Microsoft Project and the project plan contains

Constraint Type and Constraint date, then the same information will be imported and

presented in iMindQ®. The symbol for Constraint Type in the Indicator column will appear

in front of the task name and in the Task Information window you can view the necessary

information.

Change Working Time

Project plans are scheduled according calendars. They defined the working days in the

week, how many hours project participant will be spend on daily basis and etc. The

“Standard” calendar is defaulted calendar in iMindQ, with working days from Monday

through Friday, from 8 A.M. to 5 P.M. The other two calendars that are available for

scheduling are:

Night Shift

24 Hours

But sometimes, you need to modify it. You need to change the working hours, to make

particular day non-working or to set the working weeks according the project needs. For

Page 36: iMindQ User Manual for Project Management

Chapter : Create project plan

36

this case you will use the “Change Working Time” feature, located in the “Plan” ribbon.

Using mentioned feature, you can:

Insert Exceptions

Make custom Work Weeks

Exceptions

Exception days are days in the working week with different working time as the usual one.

Resource’s vacation, national holidays, time off days can be considered as exceptions for

the project plan and must exists in the project calendar. It very important for the project

manager to take them into consideration when estimates the project deadlines.

Exception day with specific working time

In iMindQ, by default, all exception days are created as non-working days. If you want to

make them working days, but with different working times, perform the following steps:

1. From the “Plan” ribbon click on the “Change Working Time” icon

2. Once the new dialog is opened, choose the base calendar for which you want to

insert exception day (presented on the image below with number 1.)

3. Insert the name of the exception along with the Start and Finish dates (presented

on the image below with number 2.)

4. Once the exception is created, click on the “Details” button (presented on the

image below with number 3.)

Page 37: iMindQ User Manual for Project Management

Chapter : Create project plan

37

Figure 44. Change Working Time dialog

The newly created exception day will be colored blue in the calendar preview. Next step is

to define the working hours for this particular day.

Page 38: iMindQ User Manual for Project Management

Chapter : Create project plan

38

Figure 45. Details for Exception Day

1. In the “Set working times for Exceptions” section click on the “Working times”

radio-button

2. Inserts the working time using the “From” and “To” column in the table.

Exception days as repeating holidays

National holidays are days with recurrence pattern. They are not included in the

application’s calendar, but you can add them manually.

1. Repeat the first 3 steps from the previous section.

2. In the “Recurrence pattern” section select the recurrence of the holiday.

3. In the “Range of recurrence” pick how often the holiday repeats during the

project time-frame.

Page 39: iMindQ User Manual for Project Management

Chapter : Create project plan

39

Figure 46. Recurrence Pattern in Exception Day dialog

Work Week

Based on the selected project calendar, the work schedule for all project’s tasks varies.

Their schedule depends from the working days and the working times. iMindQ provides

three base calendar that can be used as templates for the project plans, with the following

working days and times:

Standard – The Standard calendar reflects the traditional western work schedule:

From Monday to Friday, from 08:00 A.M. until 5:00 P.M., with and hour break

between 12:00 A.M. and 1:00 P.M.

Night Shift – The Night Shift calendar is scheduled from Monday night to Saturday

morning, from 11:00 P.M. until 08:00 A.M., with and one hour break from 03:00

A.M. to 04:00 A.M.

24 Hours – The 24 hours calendar characterizes with continues work, 24 hours a

day, 7 days a week.

Page 40: iMindQ User Manual for Project Management

Chapter : Create project plan

40

Very often, project plan required modifications of the working times, working days. You

can customize them using the steps that are described below:

1. From the Plan ribbon, click on the Change Working Time icon

2. Once the new dialog is opened, choose the base calendar for which you want to

insert custom week (presented on the image below with number 1.)

3. Click on the "Work Week" tab (presented on the image below with number 2.)

4. Insert the name of the exception along with the Start and Finish dates

Once the exception is created, click on the “Details” button (presented on the image below

with number 3.)

Page 41: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

41

In this section you will learn:

How to work with WBS chart in iMindQ®

Intro

WBS or Work Breakdown Structure is a method for a deliverable-oriented decomposition

of the project plan into smaller components. It is used primarily for defining the total

scope of the project i.e. for plan and manage project’s schedules, costs, resources and

updates.

WBS defines and groups a project's discrete work elements in a way that helps organize

and define the total work scope of the project using the decomposition as working system.

Using the decomposition, which is subdividing project deliverables into smaller pieces,

user can divide the project’s work up to the lowest level of the WBS, called work package.

An example of simple WBS is presented on Figure 47.

Figure 47. Example Work Breakdown Structure

4.Chapter : Work with WBS

chart

Page 42: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

42

Create WBS Chart in iMindQ®

After the introduction with the WBS definition and the main elements that are used for

creating WBS chart, you are ready to create tasks from the topics and create project plans.

Project plan tasks are created using the Task Info feature:

1. Create new WBS chart. For that purpose click on the File tab, select the New sub-

tab and click on the WBS chart feature.

Figure 48. Create WBS chart

2. Start adding tasks using the Insert button for inserting tasks in depth (vertically) or

Enter button for inserting tasks on same level (horizontally)

Page 43: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

43

Figure 49. Main window for WBS chart

3. In the Task Elements group click on the Task Info button

4. In the Task Info panel select the Start Date check box and select the appropriate

date.

Figure 50. Add Task parameters to topic

5. In the same panel select the Finish Date check box and insert the date for task’s

finish.

Page 44: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

44

These four steps are enough to create task and this task to be presented in Gantt Chart

(View ribbonViews groupGantt Chart).

Note: Enter button from the keyboard is used when you want to insert task on the same

level with the task that you have selected. Example: If you want to add sibling task to the

New Task task (marked with blue line) just select it and hit the Enter button. The result that

you get is presented on Figure 51.

Figure 51. Insert sibling task

Insert button from the keyboard is used when you want to insert child task to the selected

task (create parent-child relation). Example: If you want to add sibling topic to the New

Task (marked with blue line) just select it and hit the Enter button. The result that you get

is presented on Figure 52.

Page 45: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

45

Figure 52. Insert task-child

An alternative way to create a new task is to mark an existing task and click on the right-

mouse button, as it is presented on the figure below.

Figure 53. Add task parameters to topic via contextual menu

Page 46: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

46

The process of creating tasks using the contextual menu in iMindQ® is very easy and

consists of the following steps:

1. Mark the activity and double-click on the left-mouse button in the activity name

area.

2. Fill in the name in the marked area, as it is presented on the image below.

Figure 54. Topic with task parameter

3. Mark the activity and double-click on the left-mouse button in the date area.

4. Fill in the date

Figure 55. Edit topic’s task parameter

The process of inserting the date can be done using the Task info panel, as it is presented

on Figure 56.

Figure 56. Task Info panel with mapped parameters in topic

Page 47: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

47

Insert links between project tasks

To connect two topics from different branches for emphasizing the link between them,

you can use the relationship functionality. The relationship between two topics can use

only for visualizing the connection or it can be used for defining the dependency when

working with task properties (Project Management part in iMindQ®).

To connect two topics in the map, perform the following steps:

1. Click on the activity to be linked with left mouse button

2. Click on “Relationship”

3. Click on the activity to be linked (again)

4. Click on the activity to be linked to

5. If needed: Change the constraint type (Dependency) by clicking on the symbol

All steps from 1 to 5 are presented on Figure 57.

Page 48: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

48

Figure 57. Inserting link between topics in the map

After you have inserted the relationship, you can edit the line that connects the topics. You

can change the color, weight and pattern of the line, the styles of the beginning and

ending points. This is done from the Format Relationship dialog, presented on the figure

below.

Page 49: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

49

Figure 58. Format Relationship dialog

Alternative way for inserting links between project tasks is to use the Gantt chart. The

process is presented trough the steps below and illustrated on Figure 59.

1. Mark an activity with left mouse button.

2. Hold down the button and drag it to another activity to create a link.

Figure 59. Insert dependency between tasks in Gantt chart

Links can be added using the Task Information window.

The process is as follow:

1. With left mouse button click the activity and then double click on it.

2. Choose ”Predecessor” and fill in the link data and the constraint type, as it is

presented on Figure 60.

Page 50: iMindQ User Manual for Project Management

Chapter : Work with WBS chart

50

Figure 60. Inserting links using Task Information window

Page 51: iMindQ User Manual for Project Management

Chapter : Import/Export project information

51

In this section you will learn:

Import and Export possibilities of iMindQ®

Export

Export to Microsoft Project

Selecting the “MPP” icon in the from the Export group in the Integrate ribbon, you will

export the content from the iMindQ® map into Microsoft Project 2007/2010 document.

The import process is very simple. When the appropriate feature is selected, the “Save”

dialog starts up, from where you can browse the desired location where the file will be

saved.

The start exporting your project plan into Microsoft Project’s format, perform the

following steps:

1. Select Integrate ribbon.

2. In the Export group click on the Microsoft Project icon .

3. In the newly opened, presented on Figure 61, insert the project name as well as

the location where the project plan will be saved

5.Chapter : Import/Export

project information

Page 52: iMindQ User Manual for Project Management

Chapter : Import/Export project information

52

Figure 61. Export map to Microsoft Project

4. Click on the Save button.

5. In the Export Options window, set the exporting options for the project plan. You

have three choices:

a. “Export only topics with task info” – this option will export those topics

from the map that are marked as project tasks. This topics has properties

in the Task Info panel, such as Start and Finish date, Duration,

Resources, % Complete, etc.

b. “Export all iMindQ® topics” – Selecting the “Export all iMindQ® topics”

radio button all topics will be exported in the project file, no matter if

they are ordinary topics from the mind map without any properties in the

Task Info panel or topic containing Task Info parameters, as part from

project plan.

c. “Skip completed tasks” – Selecting this options, all tasks that are finished

i.e. marked as 100% Complete, they wouldn’t be exported into Microsoft

Project file and you will not be able to see them when the project file is

opened in Microsoft® Project.

Page 53: iMindQ User Manual for Project Management

Chapter : Import/Export project information

53

Figure 62. Exporting options for the project plan

6. Click on the Export button.

7. After exporting the project file, iMindQ® will ask you whether to open the

project file in Microsoft® Project or not. Click on the Open button for viewing

and editing the plan.

Import

Import from Microsoft Project

Selecting the “Project” icon in the from the Import group in the Integrate ribbon, you will

import the content of the document created with Microsoft® Project 2007/2010.

The import process is very simple. When the appropriate feature is selected, the “Open”

dialog starts up, from where you can browse the desired file. After selecting the file, a

window with several options will pop-up allowing you to select how the tasks from

Microsoft® Project file will be imported in iMindQ®.

The importing steps are:

1. Select Integrate ribbon.

2. In the Import group click on the Microsoft Project icon .

3. In the newly opened, presented on Figure 63, browse the location of the project

plan that will be imported into iMindQ®.

Page 54: iMindQ User Manual for Project Management

Chapter : Import/Export project information

54

Figure 63. Import map to Microsoft Project

4. Click on the Open button.

5. In the Import Options window, set the importing options for the project plan. You

have three choices:

a. “Add tasks to central topic” –.

b. “Add tasks to new main topic” –.

c. “Skip completed tasks” – Selecting this options, all tasks that are finished

i.e. marked as 100% Complete, they wouldn’t be imported into iMindQ®

and you will not be able to see them when the project file, now presented

as map is opened in iMindQ®.

6. Click on the Import button.

Page 55: iMindQ User Manual for Project Management

Chapter : Import/Export project information

55

Supported fields

iMindQ® supports the following fields when importing project plans created in

Microsoft Project.

% Complete;

Actual Finish;

Actual Start;

Constraint Date;

Constraint Type;

Duration;

Finish;

Predecessor Type;

Predecessors;

Priority (converted according the table from section “Insert Priority,

Resources, % Complete”);

Resources;

Start;

Unit;

Work.

Page 56: iMindQ User Manual for Project Management

Chapter : Print project plan

56

In this section you will learn:

How to customize the printout

How to print project plan

Print the project plan

In order to manage the map or the project plan effectively, you will often need to share

information. The usual way for doing this is to print an entire map/project plan or a

specific parts such as map parts or the Gantt Chart view. When using Print function, the

printout will be the currently selected view in iMindQ®.

The Print tab contains the following sections:

Print – Start printing the mind map.

Copies - Spin box for inserting the number of printing outcomes of the mind map.

Printer - Drop - down list containing all available printers.

Page Setup – Pops up the Page Setup dialog, where you can adjust the printout

settings, such as Paper size, Orientation, Margins, Header and Footer.

Settings:

o Page Orientation

o Paper Size

o Print Mind map, Gantt chart or Notes

You can start the Print function from the File menu File ->Print, from the Standard toolbar

by pressing on the icon or from the Standard Quick bar.

Before printing the project plan, you can customize the Gantt chart table by adding or

removing the columns that you want to be visible in the printout.

6.Chapter : Print project

plan

Page 57: iMindQ User Manual for Project Management

Chapter : Print project plan

57

Adding or removing columns is performed trough the contextual menu, that pop-ups

when user points the mouse cursor over the header of the table and make right-button

click.

The steps for customizing the table are:

1. Point the mouse cursor over the table’s header.

Figure 64. Mouse cursor over table header

2. Right click on the mouse while the cursor is still on the previously mentioned

position.

Figure 65. Modify Gantt table from Contextual menu

3. From the contextual menu select the columns that will be inserted/removed from

the table.

Page 58: iMindQ User Manual for Project Management

Chapter : Print project plan

58

Page Setup

After selecting the Page Setup option from the File menu, new dialog form (Page Setup

dialog box) will pop up allowing you to make the necessary preparation before printing. In

terms of selecting the page orientation, paper format, inserting header and footer and etc.

The Page Setup dialog box has a tab structure and contains 4 tabs: Page, Margins, Header

and Footer.

Page Tab

Page tab, presented in Figure 66, allows you to adjust the page layout before printing

project information. You can select whether the project printout will be Portrait or

Landscape, printed on A4, A3 or Letter paper size, etc. Default values are: Landscape and

A4 for Page and Orientation section and 1.27 cm for all margins in the Margins section.

Figure 66. Page tab

Margin tab

The Margin tab allows you to define the area between the main content of a page and the

page edges, i.e. it helps you to define where the line of text or the chart begins and ends.

By default, the top and the bottom margins are set to 1 inch, while 0.75 inches are given to

the left and the right margins. In addition, you can change the margin unit.

Page 59: iMindQ User Manual for Project Management

Chapter : Print project plan

59

The look of the Margin tab is presented on Figure 67.

Figure 67. Margin tab

Header Tab

Many companies have a company template(s) when printing official documents. One

example for printing template is to have the name of the project in central position,

company logo on the left side of the paper and the project manager name on the right

side. This information should be placed in the upper part of the paper. Using the Header

tab can help you to establish the company’s policy when printing project files in iMindQ®.

The look of the Header tab is presented in Figure 68.

Header tab has 3 tabs: left, center and right that refers to the positions of the inserted text

in the printing paper. In the fields you can enter your own text or insert previously

prepared project information text such as: page number, total page number, date, time

and file name.

Page 60: iMindQ User Manual for Project Management

Chapter : Print project plan

60

Figure 68. Header tab

Footer tab

The look of the Footer tab, Figure 69, is identical to the Header tab. You can insert various

information that will be placed in the lower part of the printing paper, under the project’s

legend.

Page 61: iMindQ User Manual for Project Management

Chapter : Print project plan

61

Figure 69. Footer tab

Print

To manage a mind maps effectively, you may need to communicate map information to a

variety of people. With iMindQ®, you can print maps and charts that present the exact

information you want.

The process of printing the information you need can be as simple as clicking a button or

as refined as customizing and previewing the existing views. No matter how simple or

refined the process, printing a map or chart consists of essentially the same steps:

Select the map or chart that best presents the information you want – If a

predefined map or chart does not meet your exact needs, you can apply different

styles.

Make display changes to the map or chart – For example, you may want to scale

information to fit on a single page.

Preview a map or chart before it is printed – Previewing a view or report can help

you verify content and display changes you made so you can adjust them again if

necessary.

Print the map or chart – To make printing as efficient as possible you can specify

the options you want. For example, you can print a range of pages (defined by

page numbers or dates), suppress blank pages, and print multiple copies.

Page 62: iMindQ User Manual for Project Management

Chapter : Print project plan

62

You can make changes to the way a printed view or report looks by specifying page setup

options such as page orientation, scale, or paper size.

Once you open the Page Setup dialog, you can follow the steps below to specify the page

and other printing options for a view or a report. Note that some of the options in the

Page Setup dialog available for views may not be available for the reports. Some options

may differ between different views as well:

Click the Page tab in the Page Setup dialog.

1. To change page orientation, under Orientation, click Portrait (vertical)

or Landscape (horizontal).

2. To scale pages, under Scaling, click Adjust to, and then type the percentage at

which you want information to appear on your printed pages in the% normal

size box.

3. To adjust page fit (some views only), underScaling, click Fit to, and then specify

the number of pages you want in the pages wide by and tall boxes.

4. To change the paper size, click the paper size you want in the Paper Size box.

5. Click the Margins tab.

6. In the Top, Bottom, Left, and Right boxes, type or select the new margin settings

7. To place the map in the center of the page, select

the Horizontally and Vertically check boxes in the Center on page frame.

8. Click on the Header tab

9. To select the font of the Custom header, click on the Font button

10. To insert an image in the Custom header, click on the Image button

11. To select the alignment of the header’s text or image, click on the Right,

Center or Left button

12. Click on the Footer tab

13. To select the font of the Custom header, click on the Font button

14. To insert an image in the Custom footer, click on the Image button

15. To select the alignment of the footer’s text or image, click on the Right,

Center or Left button.

Before printing a map or chart, in addition to the page setup options, you can specify print

options such as the printer and its properties, the print range for pages, the number of

copies, and the date range.

1. In the File tab, click on the Print sub-tab.

2. From the Printer drop-down menu select the appropriate printer.

Page 63: iMindQ User Manual for Project Management

Chapter : Print project plan

63

3. In the Settings portion of the Print sub-tab select the page orientation, paper size

and the map’s part (mind map, outline or notes).

4. To print the map or chart click on the Print button

Print Gantt Chart

To manage a project effectively, you may need to communicate project information to a

variety of people. With iMindQ®, you can print the Gantt Chart view that present the exact

information you want.

The process of printing the information you need can be as simple as clicking a button or

as refined as customizing and previewing the existing view. No matter how simple or

refined the process, printing a view or report consists of essentially the same steps:

1. Click on File menu

2. From the File menu, select Print tab and in the Settings label click on the lowest

drop-down list and select the Gantt feature.

Figure 70. Application menu presenting Print functionality

Another alternative is to use the Printing shortcut located in the Quick Access Toolbar.

Page 64: iMindQ User Manual for Project Management

Chapter : Print project plan

64

Figure 71. Print feature in Quick Access Toolbar

Note: See section “Print the project plan” for customizing the Gantt table for the printout.

Page 65: iMindQ User Manual for Project Management

Chapter : Print project plan

65