impact of growing renewable energy generation onto thermal ...€¦ · “impact of growing...
TRANSCRIPT
“Impact of growing renewable energy generation onto thermal power plant operation
in Germany”
July 7th – 9th ECM3, Aberdeen
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 1
Dipl.-Ing. Christian ZiemsProf. Dr. Harald Weber
Dr.-Ing. Sebastian Meinke (Vattenfall R&D)Dr.-Ing. Ibrahim Nassar
Dipl.-Ing. Matthias Huber (TU Munich)
Institute of Electrical Power Engineering & Department of Technical ThermodynamicsUniversity of Rostock
Motivation: Substitute the limited fossil fuels with unlimited renewable energy sources
Massive reduction of the CO2 emissions
Stop the production of nuclear waste
Eliminate the threat of nuclear accidents like Fukushima 2011
Motivation, Goals and ChallengesTransition to renewable energy sources
Eliminate the threat of nuclear accidents like Fukushima 2011
Goals: Reduce the CO2 emissions up to 80% until 2050 in Germany
Nuclear phase-out planned until the end of 2022
Increase the total fraction of all renewables sources up to 45% of the electrical energy demand until 2025 and up to 80% until 2050
Challenges: Use as much renewable power as possible directly when it is produced
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 2
Challenges: Use as much renewable power as possible directly when it is produced
To achieve the highest efficiency of the potentials
Due to the high losses of storage systems store only as much as necessary
Problem of power transmission because of limitations of the transmission lines etc.
Problem of balancing power of intermittent sources by thermal power plants
Guarantee the safety of supply
controlled power productionof fossil and (nuclear) power plants
with limited fuels, nuclear waste & high CO2 emissions
fuel: lignite, hard coal, natural gas, Uranium
Motivation, Goals and ChallengesTransition to renewable energy sources
uncontrolled power production
of wind and photovoltaic systems
with intermittent feed-in (not reliable)
Wind turbinesfuel: lignite, hard coal, natural gas, Uranium Wind turbines
Photovoltaic systems
Situation 2014:
34 GW
expected 2020:
50+ GW
Situation 2014:
Power plant
operation depends
on intermittent
feedin
Integration of
intermittent
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 3
Goal: - massive reduction of CO2 emissions
- nuclear phase-out until 2022
Situation 2014:
36 GW
expected 2020:
50+ GW
intermittent
feedin depends
on flexibility of
conv. Power
plants
Expected installed capacity until 2020:
>100 GW (>33% of annual electricity demand)
Expected growth of installed capacities ofGerman wind turbines & photovoltaic systems
50,0 GW
60,0 GW
70,0 GW
Wind onshore Wind offshore
50,0 GW
60,0 GW
70,0 GW
Installed capacity PV
Installed 2020:
Wind PV
Peak load in Germany: app. 80 GW (expected to remain constant)
Expected installed power until 2025
0,0 GW
10,0 GW
20,0 GW
30,0 GW
40,0 GW
50,0 GW
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
200,0 TWh
Wind onshore Wind offshore
0,0 GW
10,0 GW
20,0 GW
30,0 GW
40,0 GW
50,0 GW
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
PV Einspeisung
70,0 TWh
Wind PV
51,0 GW + 51,7 GW
Σ 102,7 GW
Expected energy to be “harvested” until 2025Consumption in Germany 2011: app. 600 TWh (expected to remain constant)
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 4
0,0 TWh
20,0 TWh
40,0 TWh
60,0 TWh
80,0 TWh
100,0 TWh
120,0 TWh
140,0 TWh
160,0 TWh
180,0 TWh
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
0,0 TWh
10,0 TWh
20,0 TWh
30,0 TWh
40,0 TWh
50,0 TWh
60,0 TWh
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Annual harvest
2020:
Wind PV
138,8 TWh + 54,2 TWh
Σ 193 TWh
Capacities of renewable energy from windand solar systems expected until 2025 in Germany
120,0 GW
140,0 GW
Wind onshore Wind offshore PV Max. load
40,0 GW
60,0 GW
80,0 GW
100,0 GW
120,0 GW
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 5
0,0 GW
20,0 GW
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025
Combinations of different load andintermittent feed-in (non-dispatchable feed-in)
In the Future (2020)In the past (2008)
Winter period in January
70.000
80.000
90.000
100.000
70.000
80.000
90.000
100.000
70.000
80.000
90.000
100.000
Lei
stu
ng
in M
W
Summer period in May/June
0
10.000
20.000
30.000
40.000
50.000
60.000
Leis
tun
g in
MW
0
10.000
20.000
30.000
40.000
50.000
60.000
70.000
Lei
stu
ng
in M
W
70.000
80.000
90.000
100.000
Lei
stu
ng
in M
W
Residual load provided by dispatchable plants
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 6
0
10.000
20.000
30.000
40.000
50.000
60.000
Lei
stu
ng
in M
W
0
10.000
20.000
30.000
40.000
50.000
60.000
Lei
stu
ng
in M
WResidual load provided by dispatchable plants
Hydro (run-of-river) Combined-Heat&Power (CHP) Photovoltaic (PV) Offshore Wind
Onshore Wind Residual Load Total demand (load)
Wind and PV
Transition of the power systeminto a renewable system
A simplified scheme of the powerbalance of the generation system
Non-dispatchable feed-in
ThermalPower Plants &
Pumped Storage
One nodenetwork model
Residual load++
-
Wind and PV
(CHP & Hydro)
+
Pdispatchable Presidual load
Pnon-dispatchable
Pload
Dispatchable generation
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 7
Pumped Storage
Always Zero,Frequency „∆f“ is indicator of power balance
Consumers
Actually noDemand Side Management
40
60
80
Resulting annual residual load curve
Residual load curve isshifted
-40
-20
0
20
40
Po
we
r [G
W]
Po
we
r d
em
an
d i
n G
W
Requirements forbackup power>50 GW will remain
2011
2020
2030
20502040
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 8
-80
-60
-40
0 730 1.460 2.190 2.920 3.650 4.380 5.110 5.840 6.570 7.300 8.030
Hours
Increasing generationsurplus has to be
exported or stored
Merit Order Method (example prices)
Current power demand
One hour oriented
Day-Ahead-Scheduling
Sou
rce:
DI D
r. G
erol
d P
etrit
sch,
Uni
vers
ity o
f Vie
nna,
Fac
ulty
of M
athe
mat
ics
Oil and
gas turbines
Sou
rce:
DI D
r. G
erol
d P
etrit
sch,
Uni
vers
ity o
f Vie
nna,
Fac
ulty
of M
athe
mat
ics
Run-of-river and
storage water
LigniteHard coal
Pumped storage power
Hard coal
Gas
Pro
du
ctio
n c
ost
s in
Eu
ro/M
Wh
Nuclear energy
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 9
Optimization goal:Meet the demand at any time with minized production costs
00:0001:00
02:00…
Sou
rce:
DI D
r. G
erol
d P
etrit
sch,
Uni
vers
ity o
f Vie
nna,
Fac
ulty
of M
athe
mat
ics
Cumulated installed electrical power in GW
Flexibility assumptions for scenariosof different thermal types (refers to the rated power)
10,0% 10,0% 10,0%
2,5%5,0% 5,0% 5,0% 2,5%100%
+∆P primary control
55,0%60,0% 60,0%
5,0%
5,0%
5,0% 2,5%
10,0%
10,0%
10,0%
2,5%+/- 50,0%
40%
60%
80%
op
era
tio
n p
oin
t
+∆P primary control
+∆P secondary
control
∆P schedule
-∆P secondary
control
-∆P primary control
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 10
55,0%50,0%
30,0%
0%
20%
Lignite Hard coal CCPP Nuclear Gasturbines
minimum load if
control enabled
Nuclear
17,1%
Industrial
incl. CHP
8,0%
Nuclear
0,0%
Lignite
20,1%
Industrial
incl. CHP
7,5%
Resulting generation structure in GermanyPercentage basis referred to net electr. generation
17,1%
Lignite
24,3%
Hard coal
PV
4,1%
Wind
10,8%
Hydro
4,1%
CHP general
10,0%
20,1%
Hard coal
16,6%
Wind
26,1%
Hydro
3,9%
CHP general
14,5%
Renewablesw/o biomass:
19 %
Renewables
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 11
Hard coal
18,2%natural gas
w/o CHP
3,4%
4,1%
2011Net electr. generation: 587,4 TWh
--> thereof surplus: 0 TWh
--> thereof export: 18,3 TWh
natural gas
w/o CHP
1,7%PV
9,6%
2023Net electr. generation: 625,1 TWh
--> thereof surplus: 4,5 TWh
--> thereof export: 50,5 TWh
Renewablesw/o biomass:
40 %
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
Winter 2010 2015 2020 2025
Displacement of conventional power Exemplary power plant scheduling for one week
P_Gesamtlast
Residual_load
Consumption Germany
Residual load
90
80
70
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
70
60
50
40
30
20
10
0
Po
we
r in
GW
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 12
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
0
-10
-20Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
Winter 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 13
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
Winter 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 14
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
Winter 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 15
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
Summer 2010 2015 2020 2025
Displacement of conventional power Exemplary power plant scheduling for one week
P_Gesamtlast
Residual_load
Consumption Germany
Residual load
90
80
70
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
70
60
50
40
30
20
10
0
Po
we
r in
GW
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 16
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7 8 9 10
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
0
-10
-20Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
Summer 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 17
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7 8 9 10
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
Summer 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 18
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7 8 9 10
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
70.000,0
80.000,0
90.000,0 P_PV
P_Wind_onshore
P_Wind_offshore
Summer 2010 2015 2020 202590
80
70
P_Gesamtlast
Residual_load
Displacement of conventional power Exemplary power plant scheduling for one week
Consumption Germany
Residual load
0,0
10.000,0
20.000,0
30.000,0
40.000,0
50.000,0
60.000,0
70.000,0
Lei
stu
ng
in M
W
P_KWK
P_Wasser
import
PSW_turb
GuD
SKW
BKW
KKW
surplus
PSW_pump
70
60
50
40
30
20
10
0
Po
we
r in
GW
P_PV
P_Wind_onshore
P_Wind_offshore
P_KWK
P_Wasser
PSW_turb
GuD
SKW
BKW
KKW
Photovoltaic (PV)
Onshore Wind
Offshore Wind
Combined Heat & Power (CHP)
Run-of-river
Pumped Storage Turbine Mode
Combined Cycle Power Plant (CCPP)
Hard coal
Lignite
Nuclear
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 19
-20.000,0
-10.000,0
0,01 2 3 4 5 6 7 8 9 10
Ausgewählte Tage
PSW_pump
export
P_Gesamtlast
Residual_load
0
-10
-20
KKW
surplus
PSW_pump
Nuclear
Surplus
Pumped Storage Pump Mode
Days
Increasing
capacity of wind and solar generators:
Change of single thermal power plant
operation and utilizationProject 333
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 20
Load gradient Scenarios
2.5%, 4%, 6%
Lastgradient
Limits of a thermal power plantVariation of different flexibility parameters
Simulate different operation modes
operation parameters
Pmin
Gradmax
2.5%, 4%, 6%
Mindestlast
Min load scenarios
50%, 37.5%, 33%, 20 %
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 21
Simulation of critical load and intermittent
scenarios under variation of load gradient, min
load of PP Rostock or operation of the power
plant in unconventional partial load
special operation modes
„shut down & restart“
„reduce to circulation mode“
Stillstand
10,0%
20,0% 20,0%
5,0% 5,0% 5,0%
80%
100%
+∆P primary control
+∆P secondary control
Compared Flexibility Options (TPP Rostock)Pmax=500MW net, eta=43.2%, hard coal, comm. In 1994
35,0% 35,0%
25,0%
5,0%
5,0%
5,0%
10,0%
20,0%
20,0%
0%
20%
40%
60%
Op
erat
ion
po
int
∆P schedule
-∆P secondary control
-∆P primary control
unconventional
sector
technical
minimum load
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 22
0%
Flex today
Ramping: 2%/min
FlexOption 1
4%/min
FlexOption 2
4%/min
Unconventional sector: If primary and secondary control is used this operation point normally is not useddue to coal mill switching
Potential for optimization to achieve higher flexibility
Optimization in existing plant
For new plants
40,0
60,0
80,0
20
30
40
50
60
70
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt-u
ps
Annual start-up cycles
Results for „Flex today“Without enhanced flexibility
10,0%
10,0%
5,0%
60%
80%
100%
Op
erat
ion
po
int
Flexibility in this case
2011 2020 2023
Flex
today
Flex
today
Flex
today
cold start 0 35 29
warm start 11 27 31
hot start 3 2 6
specific 1,9 19,3 16,6
0,0
20,0
0
10
20
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt
Annual full load and operating hours
35,0%
5,0%
10,0%
0%
20%
40%
60%
Flex today
Ramping: 2%/min
Op
erat
ion
po
int
8.000
600
2011 Flex today 2020 Flex today 2023 Flex today
Annual partial load operation
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 23
2011 2020 2023
Flex
today
Flex
today
Flex
today
full load hours 7399 3321 3977
operating hours 7629 3774 4423
0
2.000
4.000
6.000h
ou
rs
0
100
200
300
400
500
600
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
po
we
r in
MW
annual operating hours
Annual start-up cycles
Results for „Flex Option 1“With enhancements in the existing plant
Flexibility in this case
20,0%
5,0%
60%
80%
100%
Op
erat
ion
po
int
40,0
60,0
80,0
20
30
40
50
60
70
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt-u
ps
Annual full load and operating hours
35,0%
5,0%
20,0%
0%
20%
40%
60%
FlexOption 1
4%/min
Op
erat
ion
po
int
2011 2020 2023
Flex
today
Flex
Option 1
Flex
Option 1
cold start 0 17 8
warm start 11 22 17
hot start 3 5 6
specific 1,9 13,2 7,7
0,0
20,0
0
10
20
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt
8.000
600
2011 Flex today 2020 FlexOption 1 2023 FlexOption 1
Annual partial load operation
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 24
2011 2020 2023
Flex
today
Flex
Option 1
Flex
Option 1
full load hours 7399 3330 4024
operating hours 7629 5828 6860
0
2.000
4.000
6.000h
ou
rs
0
100
200
300
400
500
600
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
po
we
r in
MW
annual operating hours
Annual start-up cycles
Results for „Flex Option 2“With enhanced design parameters for new plants
Flexibility in this case
20,0%
5,0%
60%
80%
100%
Op
erat
ion
po
int
40,0
60,0
80,0
20
30
40
50
60
70
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt-u
ps
Annual full load and operating hours
25,0%
5,0%
20,0%
0%
20%
40%
60%
FlexOption 2
4%/min
Op
erat
ion
po
int
2011 2023
Flex
today
Flex
Option 2
cold start 0 0
warm start 11 5
hot start 3 1
specific 1,9 1,6
0,0
20,0
0
10
20
spe
cifi
c s
tart
s e
ach
10
00
fu
ll l
oa
d h
nu
mb
er
of
sta
rt
8.000
600
2011 Flex today 2023 FlexOption 2
Annual partial load operation
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 25
2011 2023
Flex
today
Flex
Option 2
full load hours 7399 3646
operating hours 7629 7738
0
2.000
4.000
6.000h
ou
rs
0
100
200
300
400
500
600
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
po
we
r in
MW
annual operating hours
Investigation of power plant schedulesHourly resolution (example Thermal Plant Rostock)
450
500
Minimum load Neg. primary res Neg. secondary res
Pos. secondary res Pos. primary res Scheduled setpoint
150
200
250
300
350
400
ele
ctric
al p
ow
er o
utp
ut i
n M
W
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 26
0
50
100
150
ele
ctric
al p
ow
er o
utp
ut i
n M
W
time
Results for annual ordered utilizationlignite fired power plant 2015/2025 –No information for load step frequency evaluation in this figure type
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 27
Results for annual utilizationAnnually ordered load change steps (weeks over the year)
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 28
Results for annual utilizationAnnually ordered load change steps (weeks over the year)
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 29
Results for annual pos. ReservesAnnually ordered reserved power (weeks over the year)
Tertiary
Secondary
Primary
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 30
Primary
Results for annual pos. ReservesAnnually ordered reserved power (weeks over the year)
Tertiary
Secondary
Primary
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 31
Primary
Detection of Restrictions
Degradation of the regulating
capabilities due to low mass flow rates
overview
50% 4% Pressure deviations in the furnace due capabilities due to low mass flow rates
Shut down of coal mills
Low exhaust temperature prior DENOX
Switch over to circulation mode
Life steam temperature decreases
which cause thermal stress cycles
50%
34%
Pressure deviations in the furnace due
to low regulation capabilities of the
forced draft fan
Regulating capabilites of the coal mills is
restrictive
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 32
which cause thermal stress cycles
Low primary air temperatures in coal
mills
Single feed water pump operation
lowering minimum load
20%
enhancedload gradient
2%
Increasing fatigue due to temperature
deviations
Possible Optimizations
Modified control parameters for low
Identification & quantification
50% 4%
potential by expanding the data basis, Modified control parameters for low
partial load
Analysis of the potential of map based
coal mill control and coal dust mass
flow rate
Optimization of the switch events (1/2
Pump operation, on/off switching of
coal mills and change from circulation
to Benson operation)
50%
34%
potential by expanding the data basis,
e.g. map based determination of
heating value, measurement of coal
dust mass flow
Optimization of the control parameters,
e.g. dynamic of the ratio fuel rate to
feed water mass flow
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 33
Investigation of the circulation mode as
an alternative operation to shut down
and restart
20% 2%
lowering minimum load
enhancedload gradient
Overview of dynamic power plant model
Scope of Power Plant Model
• Water steam cycle from feed watertank until
condenser, including start up devices
• Air Duct from forced draft fan until air preheater• Air Duct from forced draft fan until air preheater
exhaust gas outlet
• reproduction of the independent coal mills and of
combustion with regard to the coal composition
• reduced copy of the Control system including control
for fuel mass flow rate, feed water pump, spray
attemporators, coal mills, circulation cycle, turbine
bypass and forced draft and mill fan
• Can be operated with arbitrary load schedule
Modeling of:
exhaust gas
coal
steam air
preheater
air
preheater
coal mills
economizer
reheater 1
superheater 3
reheater 2
superheater 4
superheater 2
superheater 1
HP IP LPHPB
IPBevaporator
circula-
tion
cyclone
start bottle
to condensor
to LPP
air
preheater
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 34
Structure of the power plant model
• Temperature distribution in thick walled
components fatigue investigations
• Calculation of process parameters (e.g. DENOX-
inlet temperature, efficiency, etc.)
• Modular structure enables model extension or
substitution of components (e.g. simple
Implementation of new control concepts)
firingfresh
air
forced
draft fan
mill fan
feed water
pump
HPP
tion
pump
from
feed water
tank
Power plant Rostock
Demonstration scenario:12 h of load schedule operation
Pelek
Results of power plant simulation
Load schedule
Pelek
t
Net-power
t
Component fatigue
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 35
• Creation of an fictitious load schedule with load set points between 37 % und 100% load
• Model calculates the resulting generator output
• Benchmark of the operation mode – evaluation of component fatigue for the
corresponding basic operation , e.g. Start or schedule load change/step
Component fatigue
Presentation of the base scenario of the evaluation
Last
Sekundärregelsignal
Industrie
Gewerbe
Windeinspeisung Netto-Leistung Fahrplan
Netzregelmodell
Haushalte
Gewerbe
Windkraftanlagen
Kraftwerk Rostock
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 36
Kohle
Kernenergie
Gas
Windkraftanlagen
Structure of Base scenario
• coupling of the detailed model of power plant Rostock with simplified model of the
rest power plant fleet in the control area
• application of a load schedule (from power plant scheduling model)
• input of a critical load and wind scenario
• evaluation of secondary reserve demand from power difference in the control area
power plant Rostock
Derivation of compare scenario
Pelek
tPelek
Pmin
Gradmax
load schedule
t
secondary reserve signal
t
Pelek
net power
t
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 37
type of coal automation control types of operation
Pmin
• Variation der used coal
• Implementation of optimized automation control
• usage of different operation parameters
Influence of decreasing inertia:
A short introduction into
power system control Project 345
08/12/16 © 2011 UNIVERSITÄT ROSTOCK 38
Control of Electrical Power Systems
Acceleration-power
of Inertiasof conventionalPower Plants
Primary-control
(Load-FrequencyControl
Secondary-control
Tertiary ControlMinute-
reserve and„Intra day“
Tertiary Control„Day ahead
Planing“
In rotating
machines
+/-3.000MW ENTSO-E
+/-610MW GER
In rotating
machines
+/- 2.230MW GER
(not) rotating
+ 1.800MW GER
- 2.500MW GER
Time constant
TN=2*H
N:
today TN=10s-15s
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 39
Time frame
Milliseconds Seconds 15 Minutes Hours
N
NN P
ΩJ=H
2
2
1 ⋅⋅
Development of the time constant TNin the Entso-e-system
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 40
ENTSO-E-System
Case 1: Winter 2011 (0% Wind and PV)TN = 10,6 s
CHPHPPCCPP
CCPP
tnuclear
Lignite
Hard coal
Primary control positive
nuclear
lignite
hard coal
CCPP
GT
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 41
SKWSKWHard coalGT
Primary control negative
nuclear
lignite
hard coal
CCPP
GT
Case 2: Winter 2011 (47% Wind and PV)TN = 5,7 s
Wind
Lignite
Hard coal
nuclear
Lignite coal
CHPHPP
Hard coal
Primary control positive
nuclear
lignite
hard coal
CCPP
GT
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 42
Lignite GT
Primary control negative
nuclear
lignite
hard coal
CCPP
GT
Case 3: Sommer 2023 (81% Wind and PV)TN = 2,1 s
Wind onshore
Solar
Lignite
Wind offshoreGPPs/CCGPPsCHP
HPPHard coal
Hard coal
CCPPs
Primary control positive
nuclear
lignite
hard coal
CCPP
GT
GTPPs
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 43
Lignite
Hard coalGT
Primary control negative
nuclear
lignite
hard coal
CCPP
GT
Simulated Frequency Cases 1 - 3
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 44
Measurements in the Irish NetworkSystem frequency begins to oscillate due to reduced inertia26 of December 2014 at 10:38 pm
Due to a changed strategy of power plant operation from partial load with several thermal power stations to only a few nearfull load, inertia was reduce to level that the systems startet to oscillate
• Fraction of Wind 37%• Only a few turbo-generators
left
• Unit C30 Trip at 22:38• MW; Hz • 7 Min Oscillation• Pk-Pk: ~0.3 – 0.4 Hz
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 45
• Pk-Pk: ~0.3 – 0.4 Hz• Period of Osc: 15 s (0.066
Hz)
Quelle: ESB, Electric Ireland
Thank you for your attention!Thank you for your attention!
Department of Electrical and Electronic Engineering
Department of Technical Thermodynamics
08/12/16 © 2009 UNIVERSITÄT ROSTOCK 46
Prof. Dr.-Ing. H. WeberProf. Dr.-Ing. habil. E. Hassel
Dipl.-Ing. C. Ziems
Dr.-Ing. J. Nocke
Dipl.-Ing. S. Meinke
Dr.-Ing. I. Nassar