IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FISCAL YEAR 2011-2012
OVERALL WORK PLAN &
BUDGET July 2011
“Our mission is to enhance the quality of life and regional economy of Imperial County
by ensuring safe, responsive and efficient transportation and transit solutions.”
ii
This page is intentionally left blank.
iii
Fiscal Year 2011-2012
Overall Work Plan & Budget
Ryan E. Kelley, Council Member
City of Brawley
Hector Cervantes, Council Member
City of Calipatria
John Moreno, Council Member
City of Calexico
Sedalia Sanders, Vice-Chair
Mayor Pro-Tem,
City of El Centro
David Bradshaw, Chair
Mayor, City of Holtville
Mark Gran, Mayor
City of Imperial
Larry Ritchie, Council Member
City of Westmorland
Jack Terrazas, Supervisor
County of Imperial
Mike Kelley, Supervisor
County of Imperial
John Pierre Menvielle, Director
Imperial Irrigation District
Laurie Berman, Director
California Department of Transporta-
tion District 11 (Ex-Officio)
Mark Baza,
Executive Director
iv
This page is intentionally left blank.
v
TABLE OF CONTENTS
EXECUTIVE SUMMARY 1-6
STRATEGIC PLANNING WORKSHOP REPORT—EXECUTIVE SUMMARY 8-9
THE ICTC AND ITS RESPONSIBILITIES 11
ORGANIZATIONAL STRUCTURE 12-13
Regional Coordination/ Committee Structure 12
ICTC Staff Organization Structure 13
COMMUNITY OVERVIEW AND INTRODUCTION 14
The Community We Serve 14
Introduction 14
REVENUES AND FUNDING SOURCES 15-16
Federal Revenues and Fund Sources 15
State Revenues and Fund Sources 16
Local Revenues and Fund Sources 16
EXPENDITURES 17-19
Expenses 17
Table 1— Fund Sources of the ICTC 18
Table 2—OWP and Budget Summary 19
REGIONAL TRANSPORTATION PLANNING AND PROGRAM MANAGEMENT 20-21
Table 3—Regional PPM Revenues and Expenditures 21
ICTC TRANSIT PLANNING AND PROGRAM MANAGEMENT 23-26
Overview 23
The Previous Years 23
Table 4—Transit PPM Revenues and Expenditures 24
Table 5—Transit Finance Plan 25
Table 6—Conparison of Budgeted Transit Revenues 26
Table 7—Comparison of Budgeted Transit Expenditures 26
REGIONAL TRANSIT PLANNING 27
REGIONAL PUBLIC TRANSIT SERVICES 28-29
INDIVIDUAL AGENCY PUBLIC TRANSIT SERVICES 29-30
BICYCLE AND PEDESTRIAN PROJECTS (TDA-LTF ARTICLE 3) 31
LOCAL BUS STOP AND SHELTERS PROGRAM (TDA-LTF ARTICLE 8e) 31
STREETS AND ROADS (TDA-LTF ARTICLE 8a) 31
CAPITAL IMPROVEMENT PROGRAM 32-33
ADMINISTRATION / OPERATIONS / PROGRAMS 34
Table 8—LTF Distribution Table 35
Table 9—Comparison of LTF Distribution 36
Table 10—FTA 5307 Urban Funding 7 Year Budget (ICTC) 37
Table 11—FTA 5307 Urban Funding 7 Year Budget (County) 38
APPENDIX A—ICTC Cost Sharing Agreement 39
APPENDIX B—Strategic Planning Workshop Report, June 2011 40-44
vi
This page is intentionally left blank.
1
1405 N. IMPERIAL AVE. SUITE 1
EL CENTRO, CA 92243-2875
PHONE: (760) 592-4494
FAX: (760) 592-4497
July 25, 2011
David Bradshaw, Chairman
Imperial County Transportation Commission
1405 N. Imperial Avenue, Suite 1
El Centro, CA 92243
SUBJECT: ICTC Overall Work Program (OWP) and Budget for the Allocation of Funds,
FY 2011/2012
Dear Members of the Commission;
The Draft Fiscal Year (FY) 2011/2012 Imperial County Transportation Commission (ICTC) Overall Work Program (OWP)
and Budget is hereby presented for your review and approval. In spite of the weak economy, our Draft OWP and Budget is
balanced and minimizes impacts to vital transportation projects and programs for our region.
As the Commission is aware, last year was a historic period as the ICTC was created through Senate Bill 607 (Ducheny)
and was in operation in January 2010. In June 2010, the Board approved the ICTC’s first budget and work plan for FY
2010-2011. Other key accomplishments in 2010-2011, include the following milestones:
Development and adoption of the ICTC Bylaws
Completed the transfer of legal responsibilities from the Imperial Valley Association of Governments (IVAG) to ICTC
Achieved Grantee status with the Federal Transit Administration (FTA), California Department of Transportation
(Caltrans) and the Federal Highway Administration (FWHA) for eligibility and receipt of state and federal transporta-
tion funds of nearly $10 million for FY 2011/2012.
Completed required audits, policies and procedures for management of state and federal funds
Transfer of administrative duties of the Local Transportation Authority (Measure D Sales Tax Program) to the ICTC
Initiated and developed partnerships with our Southern California transportation leaders within Southern California
Association of Governments (SCAG) multi-county region of Los Angeles, Orange, Riverside, San Bernardino, and
Ventura, the Ports of Los Angeles and Long Beach, the San Diego Association of Governments, Caltrans, California
Transportation Commission, FTA, FHWA, the U.S. Customs and Border Protection, and General Services Administra-
tion.
A new ICTC website was launched and will be further enhanced in the coming year (www.imperialctc.org)
Completed the procurement process and the award of our turn-key transit operations contracts for the Imperial Valley
Transit (IVT) system and created a new identity for our ADA paratransit service called “IVT ACCESS”
The IVT ACCESS will have roll out of a new vehicle fleet in the coming months and launched a new website for
greater access to information for ADA passengers (www.IVTAcess.org)
CITIES OF BRAWLEY, CALEXICO, CALIPATRIA, EL CENTRO, HOLTVILLE, IMPERIAL, WESTMORLAND, CITIES OF BRAWLEY, CALEXICO, CALIPATRIA, EL CENTRO, HOLTVILLE, IMPERIAL, WESTMORLAND,
IMPERIAL IRRIGATION DISTRICT AND COUNTY OF IMPERIALIMPERIAL IRRIGATION DISTRICT AND COUNTY OF IMPERIAL
2
Mayor David Bradshaw (2) July 27, 2010
Imperial County Transportation Commission
The IVT fixed route services will have a new fleet of 40 ft. buses within in year two of the contract and a
complete redesign of the outdated IVT website is planned (ivtransit.org)
Implemented the computerized dispatch and scheduling software for greater efficiencies.
Completed our relocation to a new shared office with SCAG and the Imperial Valley Economic Development Corpora-
tion (IVEDC)
Completed the ICTC’s first Strategic Plan that guides our priorities in this work plan and budget and the foreseeable
future
The FY 2011/2012 OWP and Budget will be our second step toward implementation of a comprehensive agency-wide
budget that thoroughly conveys the work to be performed by the Commission in the coming year. The budget is divided into
three sections: the Budget Summary and the core programs of Regional Transportation Planning and Programming, and,
Transit Planning and Program Management. Our Budget Summary contains all the program overviews and projections and
is intended to provide a general understanding of ICTC’s budgeted activities and programs for the coming fiscal year.
Within each of the other program sections, the key services and programs are also described. A summary description of the
revenue sources, work activities, overall budget summary and work program elements are provided in the report attached.
This budget proposes minimal staffing of five full-time positions and one temporary office assistant proposed to manage the
programs and services described in this budget. The full-time positions proposed, includes the Secretary/Clerk to Commis-
sion, three transportation planner positions from entry-level to senior-level in classifications (responsible for: Regional
Transportation Planning and Programming, and Transit Planning, Programming, Contracts and Transit Service Administra-
tion), and the Executive Director’s position. As identified in the Strategic Plan, the ICTC will initiate a dedicated Human
Resources (HR) effort to complete the employment transition for all ICTC permanent positions.
The budget also includes funding for consultant services to continue to support the Commission’s administrative functions,
i.e., accounts payable, accounts receivable, payroll, various program and fiscal audits, HR activities and legal counsel. In
addition to our on-going planning, programming, and transit programs our work program elements and budget identifies spe-
cific priorities identified in our ICTC Strategic Plan and the associated costs.
Attached for your reference is the final version of the FY 2011/2012 Overall Work Plan and Budget adopted by the Commission
on July 27, 2011.
Respectfully Submitted,
MARK BAZA
Executive Director
3
Summary of Major Programs and Initiatives:
Financial Management
ICTC will strive provide efficient fiscally responsible services that produces timely and accurate reports for the Commission
and the public. Staff and consultant services have been established for performing the day to day accounting functions con-
sisting of cash management, accounts receivable, accounts payable, payroll, general ledger and financial reports for each of
the various federal, state and local program fund sources and the agency’s budget.
Community Outreach/Public Information/Marketing
The Fiscal Year 2011/2012 ICTC Community Outreach/Public Information/Marketing program will consider ways to incor-
porate all ICTC services into one comprehensive identifiable entity. For this year, our focus will be to enhance our new
ICTC website as well as the IVT ACCESS web site. Our goal will be to provide easy access to our member agencies, key
stakeholders and the general public. We will continue our work to create a recognizable brand with the services and pro-
grams offered by the ICTC. In partnership with SCAG key outreach activities will be undertaken during the development
and completion of SCAG’s 2012 Regional Transportation Plan (RTP) and Sustainable Communities Strategy (SCS). Other
outreach activities for Imperial Valley studies include, the Short Range Transit Plan, the recently funded Transit Circulator
Study, and a proposed Calexico Border Intermodal Transportation Facility Study, a grant submitted and is under considera-
tion for funding by Caltrans in FY 2011/2012.
Other aspects of the Outreach program include the administration and management of information provided for Commis-
sion and Management Committee meetings and the Technical Advisory Committee’s of ICTC, as well as other public out-
reach opportunities within Imperial Valley.
Regional Transportation Planning and Program Management
Fiscal Year 2011/2012 will see an even greater emphasis in regional transportation planning than in previous years. In the
passage of SB 375, the relationship between land use and transportation planning has been formalized and ICTC must be
prepared to provide leadership in the development of Sustainable Community Strategies (SCS) for Imperial County. In the
upcoming year, ICTC and Southern California Association of Governments (SCAG) will work in partnership with each of
the Cities and the County’s planning agencies and our regional planning partners to reach consensus on an approach to re-
duce greenhouse gases generated in Imperial County. Under ICTC this work began for the first time in FY 2009/2010 with
our regional partners at SCAG, together we reached out to the community at large to gather the public’s input. While ICTC
will not be alone in the SB 375 effort it will take a substantial amount of ICTC’s resources to support this effort.
ICTC will continue efforts with SCAG and Caltrans District 11 to update the Imperial County Transportation Model. This
regional transportation model is a critical planning tool for evaluating and prioritizing major transportation improvements in
the County. Staff will also work to identify funding opportunities to pursue critical planning studies necessary for the For-
rester Road Corridor from I-8 to SR-78/86.
For Regional Transportation Programming, the ICTC efforts for Fiscal Year 2011/2012 will be focused on the Capital Pro-
jects Program and the Transportation Improvement Program.
Capital Projects The Capital Projects programs provide oversight, planning, project management and monitoring for on-
going roadway and highway improvement projects. One of the highest priorities in
this program in recent years has been to expedite the completion of the State Route 78 Brawley Bypass. Caltrans District 11
has completed construction of Stage 2 and began construction of Stage 3, the final stage of the project during FY
2010/2011. Completion is scheduled for December 2012.
Other key regional projects include the, I-8/Dogwood Road Bridge Widening, I-8/Imperial Avenue Interchange, State Route
98 Widening (West of SR-111)/Cesar Chavez Blvd. Improvements, Proposed Widening of existing Forrester Road Corri-
dor, Phase 1 construction and expansion of the Calexico West Port of Entry, Proposed Expansion of the Calexico East Port
of Entry; and, other transit, pedestrian, and bicycle capital improvements referenced in the following sections.
EXECUTIVE SUMMARY—FY 2011/2012 Overall Work Plan & Budget
4
Transportation Improvement Program (TIP) The Transportation Improvement Program activity encompasses development
and amendments to the State and Federal Transportation Improvement Programs (TIPs), including selection of projects to
provide the greatest benefit based on approved criteria. With on-going extensions of the previous federal transportation bill
the Safe, Accountable, Flexible, Efficient Transportation Equity Act – A Legacy for Users (SAFETEA-LU) and the poten-
tial authorizations of a “TIGER 3” of the American Reinvestment and Recovery Act (ARRA), we anticipate submitting
projects previously identified for programming once the proposed funds are approved by the federal government. Staff will
also be finalizing development of the 2011 Federal TIP incorporating all federally funded transportation projects. ICTC has
also submitted project nominations to the California Transportation Commission (CTC) for inclusion in the State TIP
(STIP).
Transit Planning and Program Management
This budget receives input from three sources; the Annual Unmet Transit Needs Public Hearing, a review of available revenue,
and the development of service budgets from member agencies. The attached document contains this year's recommended plan
for funding transit planning, programs and operational requirements throughout Imperial County.
Approximately ninety-five additional persons are employed indirectly through contracts with transit operators and consult-
ants in support of these programs and services. Funding is also spent locally when and where possible for additional ser-
vices including; fuel, tires, uniforms, heavy duty mechanical, internet and marketing services.
The budget reflects revenue and expenses of approximately $15 million. Approximately $3.5 million of this funding is re-
served for the construction of the El Centro Transfer Terminal at 7th and State Streets, the Brawley Transfer Terminal at 5th
and Plaza Streets, the Phase 2 Imperial Valley College (IVC) Transfer Terminal, and proposed in the City of Imperial. An-
other proposed but unfunded is the Calexico Intermodal Transportation Facility, however, a grant for feasibility study is
under consideration for funding by Caltrans.
With regards to specific revenues and expenditures, the following information is provided:
FEDERAL REVENUES AND FUND SOURCES
Federal Transportation Administration (FTA) Section 5307 Urban grant funds received in arrears ICTC totaling $4.4 million are
programmed to be utilized for the IVT and IVT- Blue/Green Lines, IVT Access transit systems, and the El Centro transfer termi-
nal. Actual apportionments for this fund are typically not available until October of each year. The numbers for FY
2010/2011are estimates based on apportionments from prior years.
Federal Transportation Administration (FTA) Section 5307 – ARRA Funds are budgeted for the improvement of the transfer
terminal in El Centro.
Federal Transportation Administration (FTA) Section 5311 Rural funds received in arrears totaling $363 K are programmed to
be utilized for the IVT fixed route transit system in the rural area. Actual apportionments for this fund are typically not available
until October of each year. The numbers for FY 2011/2012 are estimates based on apportionments from prior years.
Federal Transportation Administration (FTA) Section 5311 – ARRA Funds are budgeted for the right of way acquisition and
design of a bus transfer terminal in Brawley
Southern California Association of Governments Overall Work Program (SCAG – OWP) Funds are budgeted based on esti-
mates of funds available from the OWP for specific planning projects and related administrative expenses. In the SCAG OWP
there are funds identified for specific planning projects for Imperial Valley, such as, Imperial County Transportation Model Up-
date and Imperial County Border Crossing Study.
EXECUTIVE SUMMARY—FY 2011/2012 Overall Work Plan & Budget
5
STATE REVENUES AND FUND SOURCES
State Transportation Improvement Program Planning and Program Management (STIP-PPM) funds have been utilized for ex-
penses associated with planning and programming activities. The California Transportation Commission approved the use of
these funds in May 2010 based on the region’s request. The funds available in FY 2011-2012 are $300,000.
State Transit Assistance (STA) funds received quarterly which were withheld by the Governor are anticipated to be released by
the recent passage of ABX8 6 and ABX8 9. These funds are restricted to transit expenses only.
Local Transportation Funds (LTF): funds received monthly from the State Controllers offices based on the retail sales tax
collected locally totaling near $5 million for transit purposes.
Funds in excess of transit services, if any, are then available for bus stop maintenance and improvements, bicycle, pedes-
trian, street and road projects, etc. Available revenue received in the prior year, in excess of the previous year’s budgeted
amount is reprogrammed as “2011 reserve”.
Public Transportation Modernization Improvement and Service Enhancement Account (PTMISEA) Funds are expected to
be received annually, under the Bond Act Prop 1b approved by voters in November 2006. Funding has been frozen, how-
ever the State Controller’s office reports an anticipated bond sale that may provide revenues.
California Security and Transit Grant Program (CSTGP) Funds are budgeted for grants that will provide lighting, cameras
and security phones at the bus transfer facilities. Funds are expected to be received totaling approximately $133K in FY
2010, under the Bond Act Prop 1b approved by voters in November 2006. Funding has been frozen, however the State Con-
troller’s office reports an anticipated bond sale that may provide revenues.
LOCAL REVENUES AND FUND SOURCES
Fare Revenue funds to be received from passengers or affiliated agencies on their behalf, as a portion of a cost of the passen-
ger’s trip.
On Hand funds are programmed when there is a balance on account typically as a result of a cost savings from the prior year.
Local Transportation Authority (LTA 2%) these funds are listed due to language in the new LTA ordinance allowing for the use
of 2% of the funding for transit services for seniors. The Authority recently took action on May 26th, 2010 authorizing the use of
these funds for local transit services in FY 2011/2012.
Member Contributions this funding is received from member agencies based upon an adopted formula. The formula was
adopted by the Commission on April 28, 2010. See Appendix A on Page 37.
EXPENSES
Expenses in this report are summarized under the following categories:
Regional Transit Services Public transit serving multiple jurisdictions and multiple population groups
Local Transit Services Public transit serving individual jurisdictions and single population groups
Transit Capital Projects Projects with design and/or capital expenditures for fixed facilities
ICTC Administration and Planning These expenses are separated into three sub-elements: Transit Administration, Transit
Planning and Program Management; and, Transportation Planning (Regional Planning activities).
EXECUTIVE SUMMARY—FY 2011/2012 Overall Work Plan & Budget
6
Operating Reserve An operating reserve is established to provide flexibility.
Bikes and Peds Article 3 (Bicycle and Pedestrian Projects) An expense for 3% of the available LTF revenue has been
listed. A call for projects is scheduled on an annual basis and is scheduled in FY 2011/12 for September 2011.
Tables 1 and 2 on page 18 and 19 provide a summary of the FY 2011/2012 Budgets Fund Sources and Expenditures.
EXECUTIVE SUMMARY—FY 2011/2012 Overall Work Plan & Budget
7
This page is intentionally left blank.
8
Overview:
On May 11, 2011 ICTC board members, staff, agency personnel and media convened the first ever strategic planning proc-
ess for the organization. The group, aided by the assistance of a facilitator worked through a progression of exercises in-
tended to indentify, rank and reach consensus on issues relative to the organization’s focus, mission and priorities. Ulti-
mately, the group formulated a list of organization priorities and proposed mission statements for the agency.
The Process:
The strategic planning workshop gave consideration to both the long-term view and the short-term requirements in the con-
text of the organization’s overall charge. Elements included exercises in context setting, environmental scanning, current
focus, strengths and weaknesses, services and products prioritization, planning for action and the development of a mission
statement.
Strategic Planning Process Component Outcomes:
At the conclusion of each exercise, the group was asked to distill their input into a definitive list of parameters and goals.
Specifically, the group was asked to provide direction in four (4) key planning areas: priority setting criteria, priorities, a
plan for action and the development of a mission statement. Each component was designed to focus the discussion on an-
swering four results-based questions:
1) Who are we?
2) What do we have to work with?
3) Where do we want to be?
4) How do we get there?
The result was a consensus-based list of parameters that guided the development of the priorities, implementation action
plan and draft mission statement. Element outcomes are listed below.
a) Priority Setting Criteria The group agreed upon a list of criteria in which to evaluate and qualify priorities for the organization. The list considers
the relative capacity of the organization and seeks to focus efforts on issues in the context of the regional organization’s
original charge. The following should be considered when weighing the potential ICTC priority:
1) What impact would the ICTC product and/or service have on staff resources?
2) Do the ICTC products and or services have regional significance/impact?
3) Is there an economic benefit to the community; can it be quantifiably measured?
4) Consideration: Completion of existing projects; i.e. accommodating project timelines, schedules and
deadlines.
5) What are the ICTC products and services that impact the regional “quality of life?” (i.e. clean energy,
environmental impacts, etc.)
6) Prioritize activities (products/programs/projects) that generate revenue; explore available and eligible
revenue sources with the state and federal government while maintaining as well as developing new reve-
nue streams.
7) Prioritize products and services consistent with the ICTC’s “core mission”.
8) CTC activities should endeavor to collaborate with other entities to limit liability and share costs.
b) Priorities
Utilizing the criteria listed above, the group underwent a series of exercises and a voting process to winnow a large list of
initiatives to five (5) ICTC proposed priorities.
Proposed ICTC Priorities
1) Regional Transportation Planning Functions
2) Consolidation of Fractured Transportation Services
3) Advocacy and Exposure for ICTC and the Region
4) Development of a Council of Governments (COG)
5) Build ICTC’s Administrative Capacity
EXECUTIVE SUMMARY— Strategic Plan Report
9
c) Plan for Action
With the core priorities that were approved, the following action plan was established during the workshop and subse-
quently adopted by the Commission on July 27, 2011. As part of the budget development process, the costs associated with
staffing and support services are identified in the table below. These costs are incorporated in the FY 2011-2012 Overall
Work Plan and Budget.
*Total Sum of OWP Planning and Program Management Work Element
d) Mission Statement
Based on the core priorities and mandated responsibilities, participants were split up into subgroups and asked to formulate
a draft mission statement to capture the essence of the organization’s charge. Following the workshop , the draft mission
statements were reviewed by the Management Committee and the following Mission Statement was adopted by the Com-
mission on July 27, 2011:
“Our mission is to enhance the quality of life and regional economy of Imperial County by ensuring safe, responsive and
efficient transportation and transit solutions.”
What? Who? Timeframe Outcome Costs FY 2011-2012
1) Regional Transporta-
tion Planning ICTC Staff and Member Agencies together with
other outside agencies
Ongoing through
December 2011
Imperial County Long and Short Term Planning – SCAG RTP and
SCS Development; and Programming
– STIP, RTIP and FTIP
*$275,000
2) Consolidation of Ser-
vices ICTC Staff and other Mem-
ber Agencies Anticipated release of RFP
Oct 2011; Contract in place by
July 2012
Consolidated “Dial-a-Ride” Services
$28,000
3) Advocacy ICTC staff, Member Agencies and External Enti-
ties
Ongoing through the end of Fiscal Year
2011/2012
ICTC has memberships with Mobil-ity 21, Self-Help Counties, etc. Com-
pleted Community/Outreach & Edu-
cation
$22,000
4) COG Development CALCOG Membership, Mayor’s Roundtable,
CCMA Meetings, ICTC and County
Begin discussion in May 2011
through July 2012
Assist with the Development of an Action Plan for Implementing
the COG
$,5,000 5) Improve Administra-
tive Capacity (H.R.,
Accounting & Legal)
Expertise amongst both internal and
external agencies (e.g.
LAFCO), outside consultants ICTC Staff
Begin process July 2011 with additional staff person on board by the end of the
calendar year (July 1, 2011 to June 30, 2012).
Completion of Staffing Transition
(Human Resource support to com-
plete transition and hire 4th ICTC employee)
$40,000
Total
$369,000
Imperial County Transportation Commission
Strategic Plan Priorities and Associated Costs
10
This page is intentionally left blank.
11
THE ICTC AND ITS RESPONSIBILITIES
The ICTC or “Commission” was established under Senate Bill 607 (SB 607 - Ducheny) in
2009. As a county transportation commission, ICTC member agencies are enabled to exercise
basic initiative and leadership in the transportation planning and programming process. The
ICTC will act in accordance with all applicable laws and statutes for county transportation
commissions. ICTC body will guide the development of the Long Range Transportation Plan
for the Imperial region and its Regional, State and Federal transportation improvement pro-
grams (TIPs) and their updates, including, but not limited to: the distribution and oversight of
Local Transportation Fund monies; the preparation and submittal of applications for transpor-
tation related funds; approve the allocation of and claims for Transportation Development Act
funds; the planning, programming and administration of regional transit services; and, encour-
age active citizen participation in the development and implementation of various transporta-
tion-related plans and programs. The ICTC is responsible to carry out the above activities in
partnership with the California Department of Transportation (Caltrans) and the designated
Metropolitan Planning Organization (MPO) the Southern California Association of Govern-
ments (SCAG).
As established under SB 607 and ICTC Bylaws, the ICTC Board is currently composed of ten
voting members and one non-voting member consisting of two members of the Imperial
County Board of Supervisors; one member from each incorporated city (seven) within Imperial
County who shall be the mayor of the city or a member of its city council; one member of the
Board of Directors of the Imperial Irrigation District; and, one non-voting member appointed
by the Governor representing the California Department of Transportation (Caltrans). As
shown in the column to the left. In the future the governing Board of the commission may also
include the following ex-officio or non-voting members: one member representing the State of
Baja California, Mexico, who may be appointed by the governor of the state; one member rep-
resenting the municipality of Mexicali, Mexico, who may be the mayor or his or her designee;
one member representing the Consul of Mexico in Calexico, California, who may be the con-
sul or his or her designee; and, one member representing any federally recognized Native
American tribe in Imperial County.
In addition to the responsibilities described above, the Commission provides direct manage-
ment, administration and oversight for the following local and regional transportation pro-
grams:
Imperial Valley Transit (IVT) System and its Inner City Circulator Service (Blue and
Green Lines)
Med-Express (Non-Emergency Medical Demand Response Service to San Diego)
IVT Access (Americans with Disabilities Act - ADA Paratransit Service)
West Shores Dial-A-Ride (Local - Demand Response Transit Service)
Local Transportation Authority (Measure D Sales Tax Program)
Other regional responsibilities include the administration and oversight of other local demand
response or “Dial-A-Ride” services managed and operated by the City’s of Brawley, Calexico,
El Centro and Imperial.
“Our mission is to enhance the quality of life and regional economy of Imperial County by
ensuring safe, responsive and efficient transportation and transit solutions.”
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
Ryan E. Kelley, Council Member
City of Brawley
Hector Cervantes
Council Member,
City of Calipatria
John Moreno, Council Member
City of Calexico
Sedalia Sanders, Vice-Chair
Mayor Pro-Tem,
City of El Centro
David Bradshaw, Chair
Mayor, City of Holtville
Mark Gran, Mayor
City of Imperial
Larry Ritchie, Council Member
City of Westmorland
Jack Terrazas, Supervisor
County of Imperial
Mike Kelley, Supervisor
County of Imperial
John Pierre Menvielle, Director
Imperial Irrigation District
Laurie Berman, Director
California Department of Trans-
portation, District 11 (Ex-
Officio)
Mark Baza,
Executive Director
ICTC
Board and Executive Director
12
ORGANIZATIONAL STRUCTURE
REGIONAL COORDINATION
To encourage regional and public participation in the development of ICTC’s policies and priorities the ICTC
staff provides support to standing regional committees, described below. The Commission has the option of cre-
ating special purpose committees as the need arises.
Management Committee The purpose of the Management Committee is to serve as a policy advisory to the
Board. Membership of the Management Committee includes two members from the County of Imperial and one
member from each member city or agency, that include the City Managers, Chief Executive Officer, General
Manager or their designated representative.
Social Services Transportation Advisory Council (SSTAC) The SSTAC is statutorily (PUC 99238) created to
serve a broad representation of youth, students, elderly, disabled persons, persons of limited means, social service
agencies, the transit dependent, and transit providers. The three tenets of the Council are to participate in the
identification of transit needs; review and recommend action; and, provide advice and technical recommenda-
tions.
Technical Advisory Committee (TAC) The TAC is composed of Planning and Public Works Department repre-
sentatives from each member agency including advisory members of Caltrans, SCAG and ICTC. The purpose of
the TAC is to coordinate the plans and development of regional transportation improvement program of projects,
transportation planning programs, and transportation funding programs.
COMMITTEE STRUCTURE
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
13
ORGANIZATIONAL STRUCTURE (Continued)
ICTC STAFF
The Imperial County Transportation Commission’s greatest asset is its employees. As recognized in this budget
the ICTC staff serves the community through a variety of regional programs and services.
The FY 2011-2012 budget proposes minimal staffing of five full-time positions and one temporary office assistant
to manage the programs and services described in this budget. The full-time positions proposed, includes the Sec-
retary/Clerk to Commission, three transportation/transit planner positions from entry-level to senior-level in classi-
fications (responsible for: Regional Transportation Planning and Programming, and Transit Planning, Program-
ming and Administration), and the Executive Director’s position.
STAFF ORGANIZATIONAL STRUCTURE
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
14
COMMUNITY OVERVIEW AND INTRODUCTION
THE COMMUNITY WE SERVE
Originally part of San Diego County, the Imperial County or synonymously referred to as the “Imperial Valley” is a grow-
ing metropolitan community within a large agricultural area along California's border region. Imperial County expands for
4,597 square miles. The California Department of Finance’s January 2011 Population estimate indicates the County has a
population of 176,258. Surrounded by San Diego and Riverside Counties in California, the State of Arizona, and the Mu-
nicipality of Mexicali in the State of Baja California, Mexico. The Imperial Valley is rich in natural beauty, and a local his-
tory and economy based on agriculture, and the cross-border family and trade relationships with our neighbors in Mexico.
In 2010, there were an estimated 70,000 people that cross daily into the U.S. from Mexico through the U.S. Customs and
Border Protection Agency’s two busiest land ports of entry between Imperial County and Mexicali, Mexico at Calexico
West/Mexicali I, and Calexico East/Mexicali II (by cars and as pedestrians).
INTRODUCTION
The Imperial County Transportation Commission (ICTC) uses a modified accrual basis accounting for its governmental
funds. The Overall Work Plan and Budget is developed by ICTC staff and Executive Director. This process begins with a
review of the projected revenues from each source of federal, state and local funds together with a review of current and
future projects and programs. The Commission provides policy guidance and sets priorities. This process includes active
participation by the technical advisory committees and the recommendations provided by ICTC staff , the Executive Direc-
tor, and the ICTC Management Committee.
The Fiscal Year 2011-12 Overall Work Plan and Budget will be our second step toward implementation of a new compre-
hensive agency-wide budget that will thoroughly convey the work to be performed by the Commission. The budget is di-
vided into three sections: the Budget Summary and the core programs of Regional Transportation Planning and Program-
ming, and, Transit Planning and Program Management. The Main Budget contains the program overviews, and revenue
and expense projections and is intended to provide a general understanding of ICTC’s budgeted activities and programs for
the coming fiscal year. Within each of the other program sections, the work elements and services are also described.
After the budget is adopted, staff has the on-going responsibility to monitor actual revenues and expenditures of the budget.
A budget report comparing actual revenues and expenditures to budgeted amounts will be prepared mid-year and presented
to the Commission.
When it becomes necessary to modify the adopted budget, the amendment procedure will depend on the type of change that
is needed. It is proposed that administrative changes that do not result in an increase in the overall program budget, but
require line item transfers of costs and revenues within a work program budget will only require approval of the Executive
Director. Amendments that result in an increase to the total expenditures for a program would require Commission ap-
proval. These items would be brought to the Commission in a formal agenda item.
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
15
REVENUES AND FUNDING SOURCES
An essential role of ICTC is to allocate Federal, State and Local funds to transportation projects within the county. Al-
though many of these funds do not flow through the ICTC budget, the agency is the authority that allocates and administers
millions of dollars in transportation funds. Because of the significance of this responsibility, it is important to discuss this
role of the agency.
As projects are prioritized in the county in accordance with policy guidelines, ICTC allocates State and Federal funds and
designates a lead agency to administer the implementation of these projects. Once the Commission makes an allocation and
a project is programmed in the long-range Regional Transportation Plan (RTP) and the short-range Regional Transportation
Improvement Program (RTIP), the lead agency is responsible for applying for funds through ICTC, to the State or Federal
agencies as appropriate. These funds are then placed in the lead agency’s local budget. If ICTC is designated as the lead or
co-lead agency, these funds will appear in its budget. These funds include but are not limited to, Federal Transit Admini-
stration (FTA), Federal Surface Transportation Program (STP), Federal Congestion Mitigation and Air Quality (CMAQ),
Federal Transportation Enhancement (TE), Congressional Appropriations, State Transportation Improvement Program
(STIP) and Proposition 1B funds.
The revenues budgeted for ICTC in FY 2011/12 are estimated to $15,372,583 and include both new revenues and funds
carried-over from the previous fiscal year. As shown in the FY 2011-12 Overall Work Plan and Budget Summary, the sub-
total of the revenues are split by federal, state and local sources (Federal revenues total $6,393,869; State revenues total,
$7,932,870; and, Local revenues total $1,045,845).
The following are summary descriptions of the revenues and fund sources.
FEDERAL REVENUES AND FUND SOURCES
Federal Transportation Administration (FTA) Section 5307 Urban grant funds received in arrears ICTC totaling $4.4 million are
programmed to be utilized for the IVT transit system, IVT- Blue/Green Lines, IVT Access, and the El Centro transfer terminal.
Actual apportionments for this fund are typically not available until October of each year. The numbers for FY 2011-2012 are
estimates based on apportionments from prior years.
Federal Transportation Administration (FTA) Section 5307 – ARRA Funds are budgeted for the improvement of the transfer
terminal in El Centro.
Federal Transportation Administration (FTA) Section 5311 Rural funds received in arrears totaling $363 K are programmed to
be utilized for the IVT fixed route transit system in the rural area. Actual apportionments for this fund are typically not available
until October of each year. The numbers for FY 2011-2012 are estimates based on apportionments from prior years.
Federal Transportation Administration (FTA) Section 5311 – ARRA Funds are budgeted for the right of way acquisition and
design of a bus transfer terminal in Brawley
Southern California Association of Governments Overall Work Program (SCAG – OWP) Funds are budgeted based on esti-
mates of funds available from the OWP for specific planning projects and related administrative expenses. In the SCAG OWP
there are funds identified for specific planning projects for Imperial Valley, such as, Imperial County Transportation Model Up-
date and Imperial County Border Crossing Study.
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
16
STATE REVENUES AND FUND SOURCES
State Transportation Improvement Program Planning and Program Management (STIP-PPM) funds have been utilized for ex-
penses associated with planning and programming activities. The California Transportation Commission approved the use of
these funds in May 2010 based on the region’s request. The funds available in FY 2011-2012 are $300,000.
State Transit Assistance (STA) funds received quarterly which were withheld by the Governor are anticipated to be released by
the recent passage of ABX8 6 and ABX8 9. These funds are restricted to transit expenses only.
Local Transportation Funds (LTF): funds received monthly from the State Controllers offices based on the retail sales tax
collected locally totaling near $5 million for transit purposes.
Funds in excess of transit services, if any, are then available for bus stop maintenance and improvements, bicycle, pedes-
trian, street and road projects, etc. Available revenue received in the prior year, in excess of the previous year’s budgeted
amount is reprogrammed as “2011 reserve”.
Public Transportation Modernization Improvement and Service Enhancement Account (PTMISEA) Funds are expected to
be received annually, under the Bond Act Prop 1b approved by voters in November 2006. Funding has been frozen, how-
ever the State Controller’s office reports an anticipated bond sale that may provide revenues.
California Security and Transit Grant Program (CSTGP) Funds are budgeted for grants that will provide lighting, cameras
and security phones at the bus transfer facilities. Funds are expected to be received totaling approximately $133K for 2010-
11, under the Bond Act Prop 1b approved by voters in November 2006. Funding has been frozen, however the State Con-
troller’s office reports an anticipated bond sale that may provide revenues.
LOCAL REVENUES AND FUND SOURCES
Fare Revenue funds to be received from passengers or affiliated agencies on their behalf, as a portion of a cost of the passen-
ger’s trip.
On Hand funds are programmed when there is a balance on account typically as a result of a cost savings from the prior year.
Local Transportation Authority (LTA 2%) these funds are listed due to language in the new LTA ordinance allowing for the use
of 2% of the funding for transit services for seniors. The Authority recently took action on May 26th, 2010 authorizing the use of
these funds for local transit services in FY 2011-2012.
Member Contributions this funding is received from member agencies based upon an adopted formula. The formula was
adopted by the Commission on April 28, 2010.
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
17
EXPENDITURES
EXPENSES
Expenses in this report are summarized under the following categories:
Regional Transit Services Public transit serving multiple jurisdictions and multiple population groups
Local Transit Services Public transit serving individual jurisdictions and single population groups
Transit Capital Projects Projects with design and/or capital expenditures for fixed facilities
ICTC Administration and Planning These expenses are separated into three sub-elements: Transit Administration, Transit
Planning and Program Management; and, Transportation Planning (Regional Planning activities).
Operating Reserve An operating reserve is established to provide flexibility.
Bikes and Peds Article 3 (Bicycle and Pedestrian Projects) An expense for 3% of the available LTF revenue has been
listed. A call for projects is scheduled on an annual basis and is scheduled in FY 2011-2012 for September 2011.
Table 2 on page 18 provides a summary of the FY 2011-12 Budgets Fund Sources and Expenditures.
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
FY 2011/2012 OVERALL WORK PLAN AND BUDGET
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
18
TABLE 1
19
TA
BL
E 2
20
REGIONAL TRANSPORTATION PLANNING
Fiscal Year 2011/2012 will see an even greater emphasis in regional transportation planning than in previous years. With
the passage of SB 375 and the requirement to reduce Greenhouse Gas emissions, the relationship between land use and
transportation planning has been formalized and ICTC must be prepared to provide leadership in the development of Sus-
tainable Community Strategies (SCS) for Imperial County. In the upcoming year, ICTC and Southern California Associa-
tion of Governments (SCAG) will work in partnership with each of the Cities and the County’s planning agencies and our
regional planning partners to reach consensus on an approach to complete the multi-county SCS and Regional Transporta-
tion Plan (RTP). The SCS and RTP are scheduled for completion at the end of FY 2011-2012. Under ICTC this work began
for the first time in FY 2009/2010 with our regional partners at SCAG, together we reached out to the community at large to
gather the public’s input. While ICTC will not be alone in the SB 375 effort it will take a substantial amount of ICTC’s re-
sources to support this effort.
ICTC will continue efforts with SCAG and Caltrans District 11 to update the Imperial County Transportation Model. This
regional transportation model is a critical planning tool for evaluating and prioritizing major transportation improvements in
the County. Staff will also work to identify funding opportunities to pursue critical planning studies necessary for the For-
rester Road Corridor from I-8 to SR-78/86.
REGIONAL TRANSPORTATION PROGRAMMING
For Regional Transportation Programming, the ICTC efforts for Fiscal Year 2011/2012 will be focused on the Capital Pro-
jects Program and the Transportation Improvement Program.
Capital Projects The Capital Projects programs provide oversight, planning, project management and monitoring for on-
going roadway and highway improvement projects. One of the highest priorities in
this program in recent years has been to expedite the completion of the State Route 78 Brawley Bypass. Caltrans District 11
has completed construction of Stage 2 and began construction of Stage 3, the final stage of the project during FY 2010-
2011. Completion is scheduled for December 2012.
Other key regional projects include the, I-8/Dogwood Road Bridge Widening, I-8/Imperial Avenue Interchange, State Route
98 Widening (West of SR-111)/Cesar Chavez Blvd. Improvements, Proposed Widening of existing Forrester Road Corri-
dor, Phase 1 construction and expansion of the Calexico West Port of Entry, Proposed Expansion of the Calexico East Port
of Entry; and, other transit, pedestrian, and bicycle capital improvements referenced in the following sections.
Transportation Improvement Program (TIP) The Transportation Improvement Program activity encompasses development
and amendments to the State and Federal Transportation Improvement Programs (TIPs), including selection of projects to
provide the greatest benefit based on approved criteria. With on-going extensions of the previous federal transportation bill
the Safe, Accountable, Flexible, Efficient Transportation Equity Act – A Legacy for Users (SAFETEA-LU) and the poten-
tial authorizations of a “TIGER III” of the American Reinvestment and Recovery Act (ARRA), we anticipate submitting
projects previously identified for programming once the proposed funds are approved by the federal government. Staff will
also be finalizing development of the 2011 Federal TIP incorporating all federally funded transportation projects. ICTC has
also submitted project nominations to the California Transportation Commission (CTC) for inclusion in the State TIP
(STIP).
Local Transportation Authority (LTA) On March 24th, 2010, the ICTC Commission approved the LTA’s request to accept
the responsibilities of administration and oversight of the LTA program of Measure D sales tax transportation funds. Previ-
ously, these responsibilities were managed by the County of Imperial’s Public Works Department. Following the March
24th approval, County and ICTC staff were directed to initiate all necessary steps toward implementing this transfer of re-
sponsibilities to be effective July 1st, 2010. These responsibilities include but are not limited to providing staff support to
the LTA Board, and administration of the LTA funds.
ICTC REGIONAL TRANSPORTATION
PLANNING AND PROGRAM MANAGEMENT
ICTC IMPERIAL COUNTY
TRANSPORTATION COMMISSION
21
TABLE 3
22
This page is intentionally left blank.
23
The Transit Planning and Program Management work element provides the policy guidance
for the allocation of transit resources. In the development of this work element, staff receives
input from three primary sources; the general public through the mandated annual Unmet
Transit Needs Public Hearing process, a comprehensive review of revenue sources and the
receipt of budget requests from members agencies.
Approximately ninety five additional persons are employed indirectly through contracts with
transit operators and consultants in support of these programs and services. Funding is also
spent locally when and where possible for additional services including; fuel, tires, uniforms,
heavy duty mechanical, internet and marketing services.
The immediate future holds many opportunities as well as challenges. The state and federal
budget climate is still uncertain. The effort is designed to develop a broad based consensus
reflecting the values, needs and preferred solutions for as many transit passengers as possible.
The challenges of providing public transit continue. The Imperial Valley represents a true
crossroads of people, history, time and place. Each is unique but all share the same goal of a
better quality of life.
Striking a balance between public need and available funding is at the center of any public
transit project or program. The various sources and administrative requirements can be com-
plicated and challenging to understand. Tables 3 to 6 provides an overview of the revenue and
expenditure plan for FY 2011/12, along with the descriptions of the transit planning services
and projects.
OVERVIEW
THE PREVIOUS YEARS
Staff has also been empowered to turn innovative concepts into plans in prior years.
The most notable accomplishments include:
Intracity Circulators ICTC identified a need to provide increased access to public services
within the cities starting with the City of El Centro. The designs for a blue and a green line
were approved 2005. Service began on the IVT- Blue Line in October 2006. The service was
reconfigured for 2009/10 and the IVT-Green line began to operate July 2009. Conceptual dis-
cussions are under way for a Red line in Imperial, a Gold Line in Brawley and an Orange Line
in Calexico. The Circulator Lines provide continuing travel for passengers transferring from
the main line Imperial Valley Transit bus routes within the Cities.
Reduction of Headways ICTC directed the reduction of headways (the wait times for the next
approaching bus) from two hours to seventy minutes effective in July 2006. The response
from the passenger ridership has been very positive. Ridership has increased approximately
47% since the implementation in 2006/07.
Alternative Fuels The California Air Resources Board directed the region to convert the IM-
PERIAL VALLEY TRANSIT fleet to an alternative fuel. After a consultant prepared analysis
and significant discussions a policy decision was made in October 2004 incorporating ultra
low sulfur diesel into operations. The 40 ft. buses were completely retrofitted with emission
compliant engines. In January 2007, the smaller cutaway style bus fleet was replaced with new
emission compliant vehicles.
Transit Mission Statement:
The mission of the Imperial
County Transportation Com-
mission (ICTC) public transit
systems is to improve the
quality of life for the resi-
dents of the Imperial Valley
through a coordinated, acces-
sible, affordable and efficient
countywide transit system.
Transit Vision Statement:
The transit network provides
a safe, affordable and reliable
transit system that meets the
needs of the transit depend-
ent in communities within
the Imperial Valley, by pro-
viding access to health care,
education, public services,
employment, commercial and
recreational activities.
Source:
Imperial Valley Association
of Governments Short Range
Transit Plan (April 2004)
ICTC
IMPERIAL COUNTY
TRANSPORTATION COMMISSION
ICTC Transit Planning and
Program Management FY 2011/2012
24
TABLE 4
25
TA
BL
E 5
26
TABLE 7
TABLE 6
27
Regional Transit Planning will continue to be a significant part of the ICTC work program in FY 2011/12. The proposed prod-
ucts will provide valuable input and guidance to the future transit programs and priorities. The following are the major initia-
tives:
Updated Short Range Transit Plan The Short Range Transit Plan is under revision in 2011 and generally updated every 3-5
years. Its purpose is to evaluate all aspects of the provision of public transit within Imperial County and to make plans and
recommendations for future improvements including fixed route, demand response, Paratransit etc. It also evaluates and
makes recommendations concerning public outreach efforts, marketing plans, capital expenditures, financial management, etc.
Route Design for Local Circulator lines in Brawley, Calexico and Imperial, Currently, the Blue and Green lines in El Centro
provide local circulator service to a variety of destinations not serviced by other Imperial Valley Transit (IVT) bus routes.
The local routes have timed transfers with IVT buses at transfer terminals. A planning grant was approved and will allow the
ICTC to hire a consultant to assist in the development of conceptual plans that include routes and schedules for similar ser-
vices in Imperial (Red line), Brawley (Gold line), and Calexico (Orange line). The study will be underway in FY 2011/2012.
Feasibility Study of the Calexico Border Intermodal Transportation Center A grant for a proposed Calexico Border Intermo-
dal Transportation Center (ITC) study that will facilitate the movement of pedestrians and access with public and private tran-
sit services was submitted in FY 2010/2011 to Caltrans and was approved. The study will be underway in FY 2011/2012.
State Triennial Performance Audit State law requires that this audit be performed every three years by all agencies receiving
Transportation Development Act (TDA) funds. ICTC contracts with a private firm to perform this audit. Its purpose is to
ensure that ICTC is meeting all its obligations under the TDA and to evaluate ICTC’s organizational management and effi-
ciency as a Regional Transportation Planning Agency (RTPA). Audit results are useful for identifying areas for improvement
in ICTC’s future performance. This audit is not required or scheduled in FY 2011/2012.
Federal Triennial Performance Audit Federal law requires that this audit be performed every three years by all agencies re-
ceiving grant funding from the Federal Transit Agency (FTA). The FTA contracts with a private firm to perform this audit.
Its purpose is to ensure that ICTC is meeting all grant requirements established by the FTA. It is also used to identify areas
for improvement in ICTC’s future performance. This audit is not required or scheduled in FY 2011/2012.
Public Transit Statistical Sampling Project The Federal Transit Agency (FTA) requires that certain statistical information be
recorded in the National Transit Database (NTD) by all agencies receiving FTA funds on a monthly basis. Some of this infor-
mation requires the assistance of a consulting statistical research firm. Every three years ICTC contracts with such a firm to
conduct a year long study to collect the required information. The amount of financial assistance received from the FTA is
largely determined by the results of this study. This project is not required or scheduled in FY 2011/2012.
REGIONAL TRANSIT PLANNING
ICTC Transit Planning and Program Management
28
REGIONAL PUBLIC TRANSIT SERVICES
IMPERIAL VALLEY TRANSIT
(IVT) is an inter-city fixed route bus
system, subsidized by the ICTC, ad-
ministered by the County of Imperial
and operated by FIRST TRANSIT,
formerly known as LAIDLAW
TRANSIT SERVICE, INC. a private
for profit service. The service has ten
(10) wheelchair accessible 40 ft. transit
buses and four (4) wheelchair accessi-
ble minibuses.
Service is provided from 6:00 AM
until approximately 11:00 PM week-
days, and 6:00 AM to 5:00 PM on
Saturdays, within the areas classified
as the Primary Zone; a North-South
axis throughout Brawley, Imperial, El
Centro, Heber and Calexico, and from
6:00 AM until approximately
6:00 PM in the Secondary Zones;
outlying cities and communities of
Niland, Calipatria, Westmorland,
Seeley and Holtville. The outlying
Remote Zone communities including
the East and West sides of the Salton
Sea; Desert Shores, Salton City, Sal-
ton Sea Beach, Bombay Beach and
the far Eastern portion of the County
in Winterhaven are served once a
week, on a lifeline.
A website offers passenger schedule
information. For information please
call 760-482-2900, or visit
www.ivtransit.com.
This transit system is an extension
of IMPERIAL VALLEY TRAN-
SIT. The intra-city system operates
utilizing smaller buses and connects
to the public facilities and services
that are not currently served by the
larger bus system. There are timed
transfer points at 14th and State
Streets in El Centro for passengers
to transfer to and from both bus sys-
tems. A Transfer Terminal to facili-
tate synchronized transfers between
modes will be designed and con-
structed by the City of El Centro in
2011.
The service is subsidized and admin-
istered by the ICTC, and operated by
a private for-profit transportation
carrier.
A website offers passenger schedule
information. For information please
call 760-482-2900, or visit
www.ivtransit.com.
The Americans With Disabilities
Act (ADA) Comparable Comple-
mentary Paratransit Service is a fed-
erally mandated service requiring
equal access to the public fixed route
bus system for individuals with dis-
abilities. The service operates six (6)
wheelchair accessible, mini-buses as
a demand response service, in tan-
dem with the fixed route bus system.
The service is available to disabled
passengers who are certified as eligi-
ble.
The service area and hours are the
same as the fixed route bus system .
For trip information call 760-482-
2908 For eligibility information,
please call 760-592-4494. A website
offers passenger eligibility forms and
information at www.ivtaccess.com
The service is subsidized and admin-
istered by the ICTC, and operated
by a private non-profit transportation
carrier.
ICTC Transit Planning and Program Management
IMPERIAL VALLEY TRANSIT
IMPERIAL VALLEY TRANSIT - BLUE and GREEN LINES
IVT ACCESS
29
All the public services in the world are useless if people can not get to them. How do seniors
get to nutrition sites, if they can not drive? How do clients get to drug treatment programs
if their licenses are suspended?
INDIVIDUAL AGENCY PUBLIC TRANSIT SERVICES (TDA-LTF Article 8c)
The Brawley Dial-A-Ride is a
demand response transit ser-
vice within the City of Braw-
ley. Demand response service
is available to the general
public and provided six (6)
days a week. For information
please call 760-344-5377.
The service is subsidized by
the Imperial County Trans-
portat ion Commission
(ICTC), administered by the
City of Brawley and oper-
ated by a private for-profit
transportation carrier.
The Calexico Dial-A-Ride is
a demand response transit
service within the City of
Calexico. Demand response
service is available to seniors
and persons with disabilities
and provided seven (7) days a
week. For information please
call 760-482-0184.
The service is subsidized by
the Imperial County Trans-
por ta t ion Commiss ion
(ICTC), administered by the
City of Calexico and operated
by a private for-profit trans-
portation carrier
ICTC Transit Planning and Program Management
The Med-Express is a non-
emergency medical transporta-
tion service between communi-
ties in Imperial County and the
large hospitals and medical fa-
cilities in San Diego County.
Demand response service is
provided four (4) days a week,
with three (3) pick up spots in
Brawley, El Centro and Ca-
lexico. Pick up service is avail-
able on a limited basis from the
home for an additional fare. The
service is designed to provide
persons with disabilities, low in-
come and transit dependent persons
access to medical facilities and
services not available within
Imperial County, i.e. Children's
Hospital in San Diego. For infor-
mation please call 760-337-8002.
The service is subsidized and
administered by the Imperial
County Transportation Commis-
sion (ICTC) and operated by a
private non-profit transportation
carrier.
MEDEXPRESS
BRAWLEY Dial-A-Ride
CALEXICO Dial-A-Ride
30
In FY 2009/10, the various public transit services provided an average of 58,000 trips a
month, throughout the Imperial Valley.
The El Centro Dial-A-Ride is a
demand response transit service
within the City of El Centro. De-
mand response service is provided
five (5) days a week for seniors
and persons with disabilities. For
information please call 760-337-
8002.
The service is subsidized by the
ICTC, administered by the City of
El Centro and operated by a pri-
vate non-profit transportation
carrier.
The West Shores Roadrunner
Dial-A-Ride is a demand response
transit service within the County
of Imperial. The service operates
in the communities on the West
side of the Salton Sea. Demand
response service is available to the
general public and provided two
(2) days a week. For information
please call 760-337-8002.
The service is subsidized and ad-
ministered by the ICTC and oper-
ated by a private non-profit
transportation carrier .
The Imperial Dial-A-Ride is a
demand response transit service
within the City of Imperial. The
service also operates between the
City of Imperial and El Centro.
Demand response service is pro-
vided five (5) days a week to sen-
iors and persons with disabilities.
For information please call 760-
337-8002.
The service is subsidized by the
ICTC, administered by the
City of Imperial and operated
by a private non-profit trans-
portation carrier
Caption describing picture or graphic.
ICTC Transit Planning and Program Management
EL CENTRO Dial-A-Ride
WEST SHORES Dial-A-Ride
IMPERIAL Dial-A-Ride
31
Bicycle and Pedestrian Projects (TDA-LTF Article 3)
Streets and Roads (TDA-LTF Article 8a)
Local Bus Stop Benches and Shelters Program (TDA-LTF Article 8e)
On an annual basis three per-
cent (3%) of the Local Trans-
portation Fund (LTF) is set
aside for the development of
bicycle and pedestrian related
projects. Each year in the
month of September, the
member agencies submit can-
didate projects. These projects
are approved in a public proc-
ess by the Imperial County
Transportation Commission
(ICTC). Member agencies
then submit claim forms for
approved projects through
out the fiscal year. Typically
agencies submit projects to
create curb cuts for handicap
access where currently none
exists. In addition, all of the
member agencies have com-
pleted, or are in the process
of completing Master Bicy-
cle Plans. For further infor-
mation please contact the
specific public works depart-
ment in each community.
aesthetics desired as per lo-
cal requirements and values.
The ICTC created a bench
and shelter program to facili-
tate the installation and main-
tenance of bus stops for the
regional public transit ser-
vices. The program sets aside
funding annually for the
member agencies. This fund-
ing can be used for the instal-
lation of new bus stops, and
the upgrade and refinement of
existing stops. This includes
adding benches and shelters
and general maintenance i.e.
painting red curbs. Bus
stops are identified and lo-
cated by authorized agency
personnel according to ap-
proved industry standards.
At this time each agency is
responsible for the bus stop
locations in their respective
jurisdictions. Each agency
chooses the amenities and
The remaining LTF fund is
available to be spent on local
streets and roads projects
after meeting the transit
needs of the community.
The needs are identified
through the local annual
public hearing process.
Funding in excess of transit
expenses is then distributed
to agencies based upon a
population format. The LTF
fund is the only fund that can
be distributed for non-transit
projects. All other funding
sources are restricted to tran-
sit uses only.
Without a public
bus stop, what
good is a public
bus?
ICTC Transit Planning and Program Management
32
ICTC Transit Planning and Program Management
Imperial Valley College Transfer Terminal
Upon a request from the ICTC, the County and
Imperial Valley College (IVC) developed plans
and received approval for grant funding to im-
prove the transit transfer facility at IVC. There
are approximately 800 students embarking and
disembarking from transit buses daily; Monday
through Friday, Concurrent with the develop-
ment of a new technology and science center at
IVC, the project will include an enhanced wait-
ing area with benches, shelters and landscaping
on the North east section of the campus. Con-
struction is anticipated to be completed in De-
cember 2012 of Phase II. Phase I has been
completed.
This project is funded with the first two years
of proceeds from components of the State’s
Prop 1B Bond measure approved by voters in
November 2006 called the Public Transporta-
tion Modernization Improvement and Service
Enhancement Account (PTMISEA) program
and the California Transit System Security
Grant (CTSGP).
7th and State Streets Intermodal Transfer
Terminal—El Centro
The ICTC and the City of El Centro developed
plans and received grant funding to create a
unique transfer facility at 7th and State Streets in
El Centro. The facility will provide the opportu-
nity to transfer from the public intra city transit
system, the IVT Blue and Green Lines, to the
public intercity transit system Imperial Valley
Transit.
The City has selected the location and identified
specific amenities. The design process is under-
way. Construction is estimated to be completed
by December 2012.
This project is funded with the grant funds
through the Federal Transit Administration
(FTA) 5307 program, as well as economic
stimulus funding from the American Reinvest-
ment and Recovery Act (ARRA).
Capital Improvement Program
33
ICTC Transit Planning and Program Management
Brawley Transfer Transit Station – S. 5th St.
and S. Plaza Street, Brawley CA
The ICTC and the City of Brawley have re-
ceived state and federal funding to complete a
unique transfer facility at S. 5th Street and S.
Plaza Streets in Brawley. The facility will ini-
tially provide the opportunity to transfer from
different intercity transit systems currently pro-
vided by Imperial Valley Transit. This terminal
will also allow for the future creation and im-
plementation of Brawley’s intra-city transit
service to be known as the ―Gold Line.‖ Upon
implementation of the Gold Line, Brawley resi-
dents will be able to use this facility for both
intercity and intra-city transit trips and trans-
fers.
The City has completed design plans, selected
the location and identified specific amenities
(i.e., landscaping, benches, shelters, and rest-
rooms) and acquired the right-of-way. Con-
struction is scheduled to begin in November
2011 with an estimated completion date of June
2012.
The right-of-way and design for the project was
federally funded through the American Recov-
ery and Reinvestment Act of 2009 (ARRA).
Construction will be completed with state funds
through the Public Transportation Moderniza-
tion, Improvement, and Service Enhancement
Account (PTMISEA) of Proposition 1B Bond
Program. PTMISEA funds are set aside for
transit operators to use for transit rehabilitation,
safety or modernization improvements, capital
service enhancements or expansions, new capi-
tal projects, bus rapid transit improvements, or
rolling stock (buses and rail cars) procurement,
rehabilitation or replacement.
Capital Improvement Program (cont.)
34
ICTC Transit Planning and Program Management
ADMINISTRATION / OPERATIONS / PROGRAMS:
Staff will continue to coordinate the various subcommittees, administer the transit services contracts, monitor for compli-
ance issues, coordinate various consultant prepared technical documents, provide technical assistance to public and private
service providers and coordinate the disability eligibility certification process. There are several new planning projects
scheduled for this year. Staff time is dedicated to finalizing the projects and plans currently in progress and getting the new
projects under way.
The following list details the planning and technical studies or projects recently completed to date
1. Continuation of the El Centro Circulator Blue/Green Line Design Study—Implementation Phase
2. Continuation of the El Centro Transfer Terminal Analysis and Site Location– Implementation Phase
3. The FY 2008-2010 ICTC Performance and Management Audit
4. Rideshare Program for Imperial Valley College (IVC) - Phase I only, Phase II on hold per IVC request
5. Conversion of Bus route map to GIS format
6. Development of the ―Imperial Valley Transit‖ website (www.ivtransit.com)
7. Full implementation of retrofits and low emission diesel engines in fixed route transit buses
8. Relocation to newly leased facility to provide in house maintenance and achieve self sufficiency
9. Evaluation/Analysis of Public Transit Fare Pricing
10. Social Services Transportation Coordination Plan
11. Development of the ―IVT Access‖ website (www.IVTAccess.com)
12. 2011 update to the Short Range Transit Plan
13. Circulator design study for the IVT Gold, Orange and Red Lines
14. 2012 update to the IVtransit.com website
The following list details the formal planning studies scheduled in future years which are not included in these budget figures
1. Cost benefit analysis of a transfer to public agency owned vehicles/equipment versus contractor owned vehicles
2. Development of regional bus stop standards and designs handbook
3. Feasibility Review of Replacement of Colorized Bus Stop Signs
4. Update to the 1995 IVAG TDA Guidebook
Tables 8 and 9 provide a historical overview of the state and federal transit fund allocations and apportionments to the Impe-
rial Valley region.
35
TABLE 8
36
TABLE 9
37
TABLE 10
38
TABLE 11
39
AP
PE
ND
IX A
40
Imperial County Transportation Commission
Strategic Planning Workshop Report
Date Held: May 11, 2011
Time: 8:33 a.m. to 1:15 p.m.
The Imperial County Transportation Commission conducted a strategic planning workshop to identify, discuss and priori-
tize core activities of the newly formed organization. The planning process represents the first time that commission deci-
sion makers have been asked to provide direction for the overall focus of the organization. In order to facilitate that discus-
sion, the participants engaged in a number exercises designed to illuminate issues, stimulate discussion and gain consensus.
In the end, the commission agreed upon five (5) core priorities and developed a basis for constructing a core mission state-
ment for the organization to synthesize the agreed upon outcome.
The structured workshop program consisted of seven (7) key elements.
1.) Context Setting
2.) Environmental Scan
3.) Current Focus
4.) Strengths / Weaknesses Analysis
5.) Prioritizing Products and Services
6.) Plan for Action
7.) Mission Statement
Each element of the planning process served as a building block for the following segment. At the end of the session, the
group had agreed upon five (5) core priorities and established a ―plan for action‖ matrix that identified responsible parties,
timelines and desired outcomes. The final ICTC list of priorities was the following:
1.) Regional Transportation Planning Functions
2.) Consolidation of Fractured Transportation Services
3.) Advocacy and Exposure of ICTC and the Region
4.) Development of a Council of Governments (COG)
5.) Build ICTC’s Administrative Capacity
Criteria Developed for Establishing ICTC Priorities
In determining the priorities for the organization, the group with the help of a facilitator, developed a list of criteria that
would be used to evaluate and rank suggested priorities. Initially, participants recalled discussions and policies developed
at the time that the ICTC was created. Many of those in attendance had been involved in the creation of the ICTC and sug-
gested that the early discussions and decisions maintain relevance and should be considered as a starting point in developing
a strategic plan.
Evaluation Criteria developed for the workshop was:
1.) What impact would the ICTC product and/or services have on staff resources?
2.) Do the ICTC products and or services have regional significance/impact?
3.) Is there an economic benefit to the community; can it be quantifiably measured?
4.) Consideration: Completion of existing projects; i.e. accommodating project timelines, schedules and deadlines.
5.) What are the ICTC products and services that impact the regional ―quality of life?‖ (i.e. clean energy, environ
mental impacts, etc.)
6.) Prioritize activities (products/programs/projects) that generate revenue; explore available and eligible revenue
sources with the state and federal government while maintaining as well as developing new revenue streams.
7.) Prioritize products and services consistent with the ICTC’s ―core mission.‖
8.) ICTC activities should endeavor to collaborate with other entities to limit liability and share costs.
APPENDIX B
41
Workshop Element #1 ―Context Setting‖
This element focused the discussion on the state of the organization. Establishing the current and prevalent context allowed
the group to have a clear perspective of the challenges and demands on staff and the organization. Through this exercise,
the group gained a better understanding of the organization’s capacity and allowed for the development of realistic priorities
and the establishment of achievable goals for the organization.
ICTC Context:
Staffing Constraints: Currently in pipeline are the dental and health benefits proposal that is being considered;
The agency needs a Human Resources specialist to develop and review employment procedures and add expertise to the
agency;
Group Discussion:
It was suggested that there may be possible assistance from the County in the ICTC effort to address benefits; LAFCO was
also suggested as a source for assistance given savings brought on by economies of scale;
Participants anticipated contractual relationships given the H.R. function – ICTC to remain consistent with #37 ACT; utilize
County to staff ICTC; Mark Baza sees challenges with specific classification development that best meet the needs of
ICTC;
Members suggested that H.R. expertise may exist in other cities (organizations) to meet the needs or assist ICTC with its
future staffing needs.
Possibilities with collaborating with County, but gaps may exist as well; additional analysis and communication suggested
by members. Some suggested alternate sources for information: LAFCO and former consulting firm.
Legal services were also identified as another organizational component (function) for ICTC; it was suggested that the con-
cept of combining the two (H.R. & Legal) had some possibilities.
Workshop Element #2 ―Environmental Scan‖
The ―Environmental Scan‖ element was an opportunity for members of the group to share views on external issues that af-
fect ICTC. With input from staff, the group discussed the evolving state of transportation not only locally, but regionally
and nationally. During the discussion, the group explored the impacts that the economy, changes in government leadership
and shifting policy have and will have on the organization in preparation for establishing priorities and setting expectations.
The Environment:
CALTRANS staff present at the meeting confirmed that there was serious discussion on an initiative that would convert the
traditional six-year Federal Transportation Bill to a shorter term, possibly two years. The group discussed the potential
ramifications and impact on the planning process. Some in the group expressed concern that ICTC’s programmatic func-
tions could be adversely affected (predictability) particularly in the areas of long-term transit and transportation planning.
ICTC like all transportation/transit agencies, has experienced reduced revenue in the face of increasing demand for services.
The challenge for ICTC is to efficiently navigate through this economic environment while making progress in meeting the
needs of the region.
Workshop Element #3 ―Current Focus‖
The segment provided an opportunity for participants to identify and discuss areas where the organization has traditionally
focused its attention and resources. The discussion sought to answer questions such as: ―Who are we?‖, ―What do we have
to work with?‖, "Where do we want to be?" and "How do we get there?" The following items represent the consensus of
the group as to the existing areas of focus.
42
ICTC Member Voting to Establish ICTC Program & Service’s Priorities:
19 Votes: Regional Transportation Planning & Programs: (Regional Transit Planning Services)
13 Votes: Advocacy: Participation in Self-Help Counties Coalition, RCTC, SCAG, Ventura, Orange
County Transit, and Mobility 21.
10 Votes: Local Transportation Authority (LTA): Measure ―D‖ Sales Tax Program
9 Votes: Consolidation of ―Dial-a-Ride‖ Services: (Mark Baza: A priority, previously recognized by ICTC
board)
8 Votes: Human Resources and Support Services
8 Votes: Possible Structure for a Council of Governments (COG): Recognized by state and the federal govern-
ment; this entity would be complete with dues
6 Votes: Creation of Flexible RFP Process to foster efficiencies and cost reductions; would include an opt-out
provision for agencies.
5 Votes: Regional State & Federal Transportation Improvement Programs (TIP)
Workshop Element # 4 ―Strengths / Weaknesses Analysis‖
This exercise probed the capacity of the organization by identifying and analyzing the core strengths and weaknesses in an
effort to establish criteria for realistic and attainable goals. The group was asked to provide thoughts and perceptions about
challenges facing the organization and core competencies that position ICTC well for the future.
ICTC Strengths:
- Staff expertise and focus on strategic partnerships and technical support
- Recognition by the State: authorizing legislation gives the agency credibility and standing as a government entity. ―We
have a home (stability),‖ said one of the Members. This designation facilitates partnerships and collaboration that can assist
ICTC in meeting the transit/transportation needs of the region.
- Respect within the region due to ICTC’s staff expertise and relationships.
ICTC Weaknesses:
- Small staff; limited exposure: Regional Planning Project Management ICTC has visibility among local government lead-
ers and the Board, but not with the community.
- Statewide visibility is limited.
- Access to defined and secure revenue is limited which hampers efforts to pursue outstanding priorities included in the Ger-
mania Study.
Group discussion:
- Develop an ―ICTC Communication Plan‖ that would inform and educate the community. Presentations can be made to
local community groups including, Kiwanis, Rotary and Chamber of Commerce, etc.
- Develop a ―Sacramento‖ exposure for the agency and develop stronger working relationships.
- With the previous consultant study, there were examples of other similar agencies, case studies, but, there was no speci-
ficity as to staffing requirements, qualifications, revenue streams, etc. ICTC may get some assistance from SCAG.
Workshop Element #5 Prioritizing Products and Services
The content and range of priorities is dependent upon the abilities of the organization to succeed in the context of ICTC’s
core mission. To determine the appropriate criteria, the group was asked to engage in dialogue centered on honing down on
the organization’s needs to accomplish its core goals and achieve sustainability. The criteria developed by the group are
provided in no particular ranking.
43
a. Are project staffing requirements consistent with challenges?
b. What are the legal requirements or mandate for the proposed product or service?
c. Is the function of regional significance?
d. Are there economic development implications?
e. Can the function be measured quantitatively?
f. Does the function build upon existing work?
g. Can it accommodate timelines?
h. Can the function generate revenue?
i. Will the function, if accomplished, enhance the region’s quality of life?
j. Does the function generate more responsibility or liability for ICTC?
k. Will the function further consolidate services in the spirit of joint cooperation?
Workshop Element #6 Plan for Action
As a result of discussions and votes during the various elements of the strategic planning process, participants provided a
list of priorities for the group to discuss and evaluate through a voting process. The result was the following list (in ranked
order) of priorities that group agreed upon. The initial list of priorities contained seven (7) initiatives. They included:
1.) Regional Transportation Planning
2.) Consolidation of functions and services
3.) Advocacy and exposure of the Commission
4.) A focus on Measure ―D‖ programs
5.) Establishment of a comprehensive ―Council of Governments‖
6.) Build capacity of administrative capability
7.) Regional ―TIPs‖
Subsequent to the identification of the draft priorities, a vote was taken by all participants. The vote was tallied and ―like‖
priorities consolidated. The final priority rankings were as follows:
1.) Regional Transportation Planning Functions
2.) Consolidation of Fractured Transportation Services
3.) Advocacy and Exposure for ICTC and the Region
4.) Development of a Council of Governments (COG)
5.) Build ICTC’s Administrative Capacity
Once the priorities and correspondent ranking were set, the group was asked to establish goals and timelines for the priori-
ties. ICTC board members and staff discussed outstanding issues and generated the work plan matrix listed below.
What? Who? Timeframe Outcome Regional Transportation
Planning
ICTC Staff and Member Agen-cies together with other outside
agencies
Ongoing
through
December 2011
Long and Short Term
County Transportation Plan;
LTA audits, STIP Consolidation of Services ICTC Staff and other Member
Agencies Anticipated release of RFP
Oct 2011; Contract in place by July
2012
Consolidated ―Dial-a-Ride‖ Services
Advocacy ICTC Staff, Member
Agencies and external entities
(e.g. CalAct
and other groups
Ongoing through the
end of Fiscal Year
2011/2012
ICTC has memberships
with Mobility 21, Self-Help Coun-ties, etc. Completed Commu-
nity/Outreach & Education Plan
COG Development Mayor’s Roundtable,
CCMA Meetings, ICTC
and County
Begin discussion in
May 2011
through July 2012
Action Plan for
implementing
the COG Improve Administrative
Capacity (H.R., Accounting
& Legal)
Expertise amongst
both internal and
external agencies (e.g. LAFCO),
outside
consultants ICTC Staff
Begin process July 2011 with addi-
tional staff person on
board by the end of the
calendar year (July 1, 2011
to June 30, 2012).
Hiring the 4th ICTC employee; Hu-
man Resource staffing
plan, review and report
issues to Board (function analysis)
44
Workshop Element #7 Mission Statement
The final element of the workshop encompassed the group’s formulation of a formal mission statement for the ICTC. The partici-
pants were familiarized with the purpose and the intent of a statement and provided an instructive sheet that outlined pertinent ques-
tions that should be addressed by the statement. The group was then given a worksheet to aid in the development of draft statements.
Suggested Mission Statements:
―Our mission is to enhance the quality of life and regional economy of Imperial County by ensuring safe, responsive and efficient
transportation and transit solutions.‖
―ICTC will guide the development of the regional transportation plan for the Imperial region and its Regional, State and Federal
transportation improvement plans and updates.‖
―ICTC will take the lead in the provision of transportation facilities and services to provide mobility and support economic develop-
ment.‖
―ICTC will provide local and regional transportation services and programs to enhance the quality of life for the Imperial County.‖
The group agreed to revisit the adoption of a Mission Statement at a future meeting.
The workshop was adjourned at 1:15p.m.