implementation report
TRANSCRIPT
~ 0 ~
HELP DAVAO – DOST XI
Vertical Helophyte Filter system construction report The implementation, quotation and maintenance of a vertical helophyte filter system in Davao City
Sean Ligtvoet 1/24/2013
~ 1 ~
Vertical Helophyte Filter system
construction report The implementation, quotation and maintenance of a vertical helophyte filter system in
Davao City
HELP Davao
Corner Dumanlas and Friendship, Davao 8000 Philippines
0031 181 404 900
Version 1
24 January 2013 Davao City
Author:
Ligtvoet, S.
~ 2 ~
1. Preface
The treatment of wastewater coming from households is an effective way to create a more
sustainable environment and therefore a better world. With the Vertical Helophyte Filter System
manual for Davao City my attentions were to make more understanding about the wastewater
treatment in Davao City. This manual was a project of the HELP Davao Network. This report can be
seen as an extension of the manual as it was used as base for the construction.
With this report I wish to make a clear sight on how the implementation of the first Vertical
Helophyte Filter system in Davao City was accomplished.
This report is produced during a third year Water Management internship of Rotterdam University of
Applied Science, at the HELP Davao Network in Davao City.
The construction of the Vertical Helophyte Filter System wouldn’t be possible without the help and
support I received from several individuals and organizations within the HELP Davao Network and the
Rotterdam University of Applied Science. The next chapter is devoted to those who I’d like to thank
for their support and help during the construction.
Sean Ligtvoet, 24 January 2013
~ 3 ~
2. Acknowledgements This report is made to function as an example for future implementation of a Vertical Helophyte Filter
System. The construction is funded by the HELP Davao Network. HELP Davao is the local network of
the UNESCO HELP1 program. Therefore I would like to extend my sincere thanks and appreciation to
Hon. Marissa-Salvador Abella chairperson of the HELP Davao Network and the following
organizations within the organization:
DOST XI (Department of Science and Technology Region XI)
The help of the DOST XI was my biggest asset during the construction of the filter system. They
arranged an office to work on my report and their assistance was their when it was needed.
Therefore I want to thank; Dr. Anthony Sales for the opportunity he gave me to build the filter
system for the new laboratory of the DOST XI; Ma’m M. Domingo who was the who coordinated the
preparation and course of our internship; Sr. Adonis M. Traje who provided equipment; Ma’am
Marife Anunciado who made the cash advantages possible, controlled and registered the payments
and arranged transportation and contracts; The rest of my colleges at DOST XI who were providing
me lots of help and a comfortable working environment.
Professor T.H. Heikoop Rotterdam University of Applied Science
Mr. Heikoop was my internship supervisor and provided me the contact with the HELP Davao
Network. He gave asset on my proposal, surveyed my stay and gave me a good preparation before
going to Davao City.
Ms. Hydie Maspiñas DCWD (Davao City Water District)
Ms. Hydie, working for the DCWD, gave me 20,000 peso cash advantage. Therefor I’d like to thank
her for her generosity.
My most sincere thanks to you all
1 Hydrology for Environment, Life and Policy (HELP)
~ 4 ~
Table of Contents 1. Preface ............................................................................................................................................. 2
2. Acknowledgements ......................................................................................................................... 3
3. Introduction ..................................................................................................................................... 5
4. Proposal ........................................................................................................................................... 7
4.1. VHFS manual for Davao City ......................................................................................................... 7
4.1.2. Technical design made by KIWA ............................................................................................ 7
4.1.2. Cross section of the implemented filter system ................................................................. 10
....................................................................................................................................................... 10
4.1.3. Location ............................................................................................................................... 11
4.1.4. Scale ..................................................................................................................................... 12
4.1.5. Construction ........................................................................................................................ 13
4.2. Quotation ................................................................................................................................... 16
4.3. Funding by HELP Davao network .......................................................................................... 17
5. Preparation phase ......................................................................................................................... 18
5.1. Workers ...................................................................................................................................... 22
5.2. Supplies ................................................................................................................................. 22
5.3. Working schedule .................................................................................................................. 23
5.4. Designs .................................................................................................................................. 27
6. Implementation ............................................................................................................................. 32
7. Finances ......................................................................................................................................... 43
8. Conclusion ..................................................................................................................................... 44
Appendix ................................................................................................................................................ 45
~ 5 ~
3. Introduction Context Davao City is the biggest city on the Island Mindanao in the Philippines, with a population of 1 449
296 people in 2010 the second city in the Philippines and with 244 000 hectare of land one of the
largest cities in the world based on surface area (City Planning and Development coordinator, 2010).
The name Davao might be derived from the Davao river, however impossible to trace the origin of
the name, it is certain that Davao is a delta city under influence of eight watersheds, of which the
largest and near the highest populated area is the Davao River (HELP Davao Network, 2011).
Davao City is a growing city where the society has enormous differences in incomings and lifestyles.
Brand new shopping malls are lying next to informal settlements were the houses are made from
wood and wave plates. The city is developing with new businesses from America, Korea and Australia
that are settling there.
The wastewater drainage of the city is designed to drain mainly the rainwater and wastewater
coming from the kitchen, shower and sinks. The toilet water is generally discharging in septic tanks
that are, in some cases, poorly maintained and in worst cases are overflowing. Some of the poorest
areas drain all their wastewaters direct to the surface water.
The cities drainage channels are in sometimes overflowing when the rainfall intensity and the tides
are high. When this occurs, the wastewater of households, local businesses and even hospitals are
flowing through the streets creating health risks and lots of environmental pollution due to the
damage full substances that are used in households, local businesses and even hospitals.
Main goal The main goal of this project is the implementation of a Vertical Helophyte Filter System (VHFS) for
wastewater treatment of the new laboratory building of the DOST XI office.
Target group The target of this project is primarily the (non-)governmental organizations within or outside the
HELP Davao network that have or feel the responsibility of establishing a cleaner way of discharging
wastewater within Davao city. These (non-)governmental organizations are:
- The City Government of Davao City
- Department of Science & Technology Region XI
- Davao City Water District
- Department of Environment & Natural Resources
- Department of Highways and public structures
- PCEEM People Collaborating for Environmental and Economic Management in Davao
foundation
- University of the Philippines Mindanao
- University Ateneo de Davao
- University of South Philippines
~ 6 ~
Secondary are (non-)governmental organizations, businesses, households and community based
households that are settled inside or outside Davao City that feel or have the responsibility of
establishing a cleaner way of wastewater discharge within or outside Davao city. These target groups
can be:
- City governments
- Research or educational organizations
- Consultancies
- Suppliers of wastewater treatment facilities or components of it
- Environmental organizations
- Residents of Davao City or other city’s/ villages
- Local businesses in- or outside Davao City
- Water quality administrators
Delimitation of the manual This Vertical Helophyte Filter System construction report is written to be used as a guideline with
recommendations. The construction of the filter system is done by using the VHFS manual for Davao
City.
Used programs - Microsoft Word 2012
- Microsoft Excel 2012
- Adobe Illustrator CS5
- Google Sketch up 8 Pro
~ 7 ~
4. Proposal This chapter describes how the funding was obtained from the HELP Davao Network. In this phase a
quotation and a proposal was made with help of the Vertical Helophyte Filter System (VHFS) Manual.
4.1. VHFS manual for Davao City The actual implementation of the VHFS at the Department of Science & Technology was an action
after releasing the ‘’VHFS manual for Davao City’’. In this manual the need for a wastewater
treatment facility in Davao City was described and a full design was already made for the new
laboratory building in the DOST XI building complex. A few chapters of this manual where fully used in
the implementation phase and used for the proposal. In this paragraph these chapters are copied.
4.1.2. Technical design made by KIWA
Dimensioning The hydraulic design load at average domestic wastewater depending on the dirt load is not allowed
to be more than 60 liters/ m²/ day.
- The guideline for the surface determination of the helophyte filter must be 4m²/p.e.
(population equivalent = 1 person a day)
- The helophyte filter must be irrigated at least two times a day
Pump installation - The pump installation must be installed that, with normal flow of wastewater, the helophyte
filter is irrigated twice in 24 hour
- The pump and the structure of the supply drainage line must be constructed in a way that
the wastewater is evenly distributed over the helophyte filter and the pump cycle doesn’t
take more than five minutes
- The pomp must connected conform NEN 1010 (Only in the Netherlands)
- The pump must have a high and low level alarm, visually or acoustically
- The pump must be suitable for long lasting pumping of wastewater
Wastewater well
- The wastewater well must be watertight and properly build
- The wastewater well must still be able to retain 50% of the average daily flow above the
maximum content level. So when failures on the pump occur there is 12 hours to fix the
problem
Supply pipes - The structure of the supply pipes must be constructed in a way that the wastewater is evenly
distributed over the helophyte filter
~ 8 ~
- The main supply line to that transports the wastewater to the perforated supply lines must
be big enough so there is no higher internal resistance possible than the pump system can
take. The main supply line must have a diameter that’s twice the size of the perforated lines
and must be connected with the same connection parts as the perforated pipes
- The perforated supply lines must have a diameter of 32 to 40 mm
- The supply lines must be made from PVC, HDPE, PP (with KOMO or KIWA validation (Only in
the Netherlands))
- There must be at least two perforated supply lines
- The distance between the perforated pipelines have to be between 70 and 100 cm for a
elegant irrigation
- The links between the supply pipes have to be removable to perform maintenance,
inspection and possible ground settlement
- The links have to be made from PP with fixmanchet connection (waterproof)
- The perforated supply lines have to be perforated in longitude direction and in one straight
line
- The perforation diameter have to be between 6 and 10 mm with regards to internal system
pressure
- The perforations have to be free from burrs
- For the prevention of jammed supply lines it’s possible to make taps in the perforations
- The distance between the perforations must be within 1 meter
- The perforated supply lines have to lay in a top layer that’s not sensitive for jamming. The
layer is a barrier against smell
- The perforated supply lines must be isolated good by the top layer to prevent craters in the
sand bed
- The top layer must be made from shells or gravel with no residences of clay in it
- The thickness of the top layer must be at least 10cm
Drainage discharge pipes - The drainage discharge pipes must have a minimum diameter of 80mm for filters until 10
p.e. and 100mm for filters until 50 p.e.
- The drainage discharge pipes must be made developed with Pp-fiber class 450 µm or
equivalent pipes
- Between and on the drainage pipes there must be gravel to seal the pipes
- There must be an imperforated pipe attached to the perforated drainage pipes so they can
be removed for cleaning. These pipes must be closed so no rainwater can enter
- The drainage discharge pipes must be installed on a maximum depth of 100cm under the
sand filter
- The discharge of the filter must be constructed on a higher level so it’s always inside water so
oxidation can’t occur
Clean water well - After the filtering but before the discharge of the water to the surface water there must be a
small well to make it able to get samples of treated water
- The well must be constructed in a way that sampling is possible
~ 9 ~
- This well must contain 5 liters and must be constructed in such a way that the water can flow
without resistance
- The well must be watertight and properly constructed
Gravel layer - The drainage discharge pipes must be sealed with gravel. This layer must be at least 20cm of
which 5 cm is above the pipes
- The grain size of the gravel has to be between 8 and16 mm thick
Root cloth - For the dividing of the sand filter bed and the gravel layer, where the drainage discharge
pipes are, a root cloth must be placed
- The material quality must be PP and it must have a minimum weight of 100 gram/m²
- The minimum water permeability must be 20 liter/m²s by 1000mm water column
- Tensile strength chain 3 X 600 dlex-woof 40 X 1200 dlex
Sand filter bed - The sand filter must be at least 80 cm
- The grain size of the filter sand must be between 100 to 500µm with a median of 200 to
250µm, with less than 1% of its weight through the 100µm sieve
- The sand must be free from contamination by organic, toxic or clogging ground
- The sand must be free from loam
- For the binding of phosphate (oil free) iron filings can be added to the sand. This must be
15kg/m³
- The adding of iron can only be done in the upper layer of the sand filter because otherwise
iron oxidation will drain to the drainage discharge pipes. Also the binding of phosphate only
occurs in the upper layer of the sand filter bed (During the oxidation from ferrous to ferric
ions)
Sealing - The helophyte filter must be separated from the ground with a waterproof layer
- For the waterproof layer PE, HDPE or EPDM rubber foil can be used with a minimum
thickness of 1mm
Plants - Within the helophyte filter only apply one kind of plant
- The best plant to use is reed (Phragmites australis)
- The planting density for seedlings amounts to 4 to 6 plants/m² and for cuttings 6 to 10
plants/m² depending on the root herb so that an acceptable amount of plants is realized fast
- To prevent preferred path lines the plants must not be planted in straight lines
~ 10 ~
Micro-organism
- Add 20kg of straw per 10m³ sand. This will be an attachment site and carbon source for
microorganisms for the first years. Later the roots of the reed will take it over
Limestone - Limestone has a high capacity on phosphorus removal. This is why it’s recommended to add
lime stone to the under part of the sand filter bed. This part is from the root cloth up to 80cm
in the sand filter bed. The good amount of limestone is 10% of the sand filter (Blom, 2003)
Duckweed - By adding duckweed at the discharge side of the helophyte filter lots of phosphorus and
nitrogen gets removed from the water
4.1.2. Cross section of the implemented filter system
This cross section is used as an aid to explain the working of the VHFS.
Figure 1: cross section
~ 11 ~
4.1.3. Location
The compound of the DOST XI is
located at the corner of
Dumanlas- Friendship Road that
lays in Bajada, Davao City. On the
chart to the right you can see the
exact location.
On the chart on the right the project
side is shown. The helophyte
filter will be realized at the
North-Eastside of the compound
next to the Northern building. It
will catch the wastewater of the
RSTL (Regional Science and
Technology laboratory) and
TIPDC (Technology Innovation
Packaging Development Center)
buildings.
Figure 2: location 1
Figure 3: Location 2
~ 12 ~
4.1.4. Scale
The Helophyte filter next to the building will be a triangle. The slope will be 1.4m by 0.3m. That’s why
the inside surface area is different. The measurements of the filter are shown in the tables below.
The left table shows the maximum space that is available on the left of the new DOST building. The
right table shows the available space deducted with the space that the construction and the slope
takes away.
Table 1
Available space at DOST
Measurements
length adjacent side 5.2 m
length opposite side 5.6 m
length oblique side 7.64198927 m
height 1.4 m
Surface 14.56 m²
Volume 20.384 m³ Table 2
The filter system will be designed for a capacity of 5 persons. According to the results from the tables
above and the estimations of water consumption two different scales are established. The results are
shown in the tables below. There were two water consumptions made in the VHFS manual for Davao
City which are used to establish the scale.
Table 3
Table 4
Dimension of filter based on leakage
Normal filter 4 m²/l/p.e. Normal amount l/p.e. 121
l/p.e.
Amount of l/p.e. 106 l/p.e.
Percentage of normal 87.6033 %
New dimension filter 3.50413 m²/p.e.
Amount of staff 5 persons
Size of filter 17.5207 m²
Available space at DOST with constr.
Measurements : 10 cm of all edges
length adjacent side 4.87 m
length opposite side 5.25 m
length oblique side 7.160963622 m
height 1.4 m
Surface 12.78375 m²
Volume 17.89725 m³
Dimension of filter based on research
Normal filter 4 m²/l/p.e. Normal amount l/p.e. 121
l/p.e.
Amount of l/p.e. 74.5428 l/p.e.
Percentage of normal 61.6056 %
New dimension filter 2.46423 m²/p.e.
Amount of staff 5 persons
Size of filter 12.3211 m²
~ 13 ~
Table 5
The different results from the tables of
the previous page are combined into one
and an average of the two is established.
See table on the right.
But because there is only 10m² space available , although this isn’t enough according to the
calculations it the assumption is made that it will be big enough to manage the capacity since the
measurement are based on Dutch principles and the waste load will not be as much as common
households in the Netherlands. The occupation of the new building will differ from 3 to 5 persons
that will work from 7am to 5pm and the therefore the waste load is less.
4.1.5. Construction
This sub-paragraph shows the dimensions of the
helophyte filter system in 3D pictures. The
pictures below and on the right show the exact
sizes of the walls inside the wall construction.
Dimension of filter based on compensation
Normal filter 4 m²/l/p.e.
Normal amount l/p.e. 121 l/p.e.
Amount of l/p.e. 90.27141 l/p.e.
Percentage of normal 74.60447 %
New dimension filter 2.984179 m²/p.e.
Amount of staff 5 persons
Size of filter 14.92089 m²
Figure 5: Basin size Figure 4: Wall size
~ 14 ~
The walls will be constructed on a concrete under layer. For this layer steel pipes will be used for a
stronger and more sustainable construction. The picture below shows the construction of the steel to
support the construction of the filter basin. In the table below the right amount of steel is calculated.
Table 6
Amount of steel
Part Q Length (m)
Total (m)
A 2 5.45 10.9
B 2 5.05 10.1
C 2 7.5 15
D 1 0.75 0.75
E 1 0.5 0.5
F 1 0.6 0.6
G 10 0.8 8
H 10 1.4 14
Total (m) 59.85
To make a strong basis for the wall
it’s important to let the concrete
penetrate the ground. In the pictures below is shown how the steel will be put into the ground. The
depth of the grooves will be 30 cm and the liquid concrete will fill half of the grooves. The width of
the groves will be 20cm and 10cm in the corners. The amount of liquid concrete that is needed for
this is 3.63m² X 15cm = 0.55m³.
Figure 6: steel construction
Figure 7: steel construction 2 Figure 8: steel construction 3
~ 15 ~
After filling the gloves hollow concrete blocks will be used to build the walls. Every 40cm a steel pipe
will be horizontally placed for extra strength, except the first layer because that one will be 55cm in
between. In the picture bellow the first layers are shown with the horizontal steel pipes. There will
be 3 extra layers of horizontal pipes as shown in the picture below. This will increase the amount of
steel the amount of extra steel is shown in the table below. So the total amount of steel will be
167.85m.
Table 7
Amount of
extra steel
Part Q Lenght (m)
Total (m)
A 6 5.45 32.7
B 6 5.05 30.3
C 6 7.5 45
Total (m) 108
Figure 9: steel construction 4
~ 16 ~
4.2. Quotation In this paragraph the final sum of the quotation is shown. The full quotation can be found in the
appendix.
Total price
Hollow block = Php: 3,480,- Steel= Php: 2,478. 10 Sand= Php: 3,550,- Pump= Php: 3,000,- Roof= Php: 3,819.31 Sealing= Php: 1000,- Tools= Php: 2,472.50 Gravel= Php: 2,175,- Pipes = Php: 3,946.75 Pipe fittings= Php: 1,632,- Lime stone= Php: 600,- Plants= Php: -- Iron fillings= Php: 100,- Concrete= Php: 2,430,- Root control fabric= Php: 2,130,- +
Total Price equipment: Php: 36,813.66
Workers costs
Amount= 3
Costs= (2*350 p/d, 1*200 p/d)
Days working= 5
Total price workers= Php: 4,500,-
Total price: Php: 41,313.66
To have a flexible funding the DOST XI advised me to increase the quotation to 50,000 peso.
~ 17 ~
4.3. Funding by HELP Davao network The project is funded by the HELP Davao Network which gave 50,000 peso for the construction of the
filter system. To apply for the budget a proposal was made. An exact copy of the preposal is shown in
this paragraph.
~ 18 ~
~ 19 ~
~ 20 ~
~ 21 ~
~ 22 ~
5. Preparation phase Before a project starts preparations have to be made This chapter tells all the preparations that
have been made before the starting the constructing the VHFS. After approval for a funding of
50,000 peso by the HELP Davao Network workers had to be hired, a working schedule had to be
made, supplies were purchased and designs were used to build the VHFS.
5.1. Workers
For the constructing four carpenters were hired to work on the VHFS. These workers were all hired
by S. Ligtvoet and paid a equal amount of 350 peso for a 8 hour working day. The carpenters were:
Jouboy Munion Deca Homes, Cabantian 09 46 989 6 106 Lorddycan D. Carin Bajada, Agno Riverstreet 8 09 09 341 7 751 Joel Notarte Barangay 31-D Roxas 09 10 726 9 234 Arman Arevalo Barangay 31-D Roxas Contact Joel Notarte
Be aware that these are Pilipino cellphone numbers, dial +63 before dialing the number. The
contracts of the workers can be found in Appendix C ‘Contracts’
5.2. Supplies
All the supplies that are purchased during the project are registered and can be viewed in
Appendix A ‘Payroll’. Because of a delay in de funding the supplies couldn’t have been purchased
at ones as planned. For instance: instead of buying the full amount of sand at ones, the sand was
delivered in 3 phases.
Some of the supplies weren’t available In Davao Ciy. The weed control fabric, used to divide the
sand from the gravel, was purchased online from Pasig City. Also the drainage pipes weren’t
available. For drainage pipes 90mm PVC pipes that are manually treated and converted into
drainage pipes were used,
Because of the delay in the project the expenses were rising to a maximum of 50,000 peso. To
accomplish the project, with the available budget, new suppliers were used to minimize the
expenses. TLCO hardware shop became the new supplier for cement, PVC pipes and fittings.
~ 23 ~
5.3. Working schedule The exact copy of working schedule, made to construct the VHFS is shown in this paragraph. The
schedule was presented to the workers and used in the funding proposal for the HELP Davao Network.
Working schedule
Preparation Phase
- Prepare transport for collecting the supplies (1 day)
- Buy/ order equipment from the suppliers mentioned in the Quotation Report (2-3 days) - Contact the workers for their availability (1 day)
- Inform the workers on the work that is expected from them (1 day)
- Hiring the concrete mixer for the first working day (1 day)
Construction
Figure A
Figure 10: cross section
~ 24 ~
Day 1 (Preparing the ground)
- Making a flat working area (morning) - Dig out & preparing the groves for the concrete - figure 1 (morning)
- Preparing/ constructing the steel – figure 2 (morning) - Filling the groves half way with concrete (afternoon)
- Placing the steel (afternoon)
- Filling up the groves with the 2nd layer of concrete – figure 3 (afternoon)
Figure 1 Figure 2 Figure 3
Day 2 (Building the walls)
- Building the walls – figure 4 (whole day)
- Shaping the walls – figure 5 (afternoon)
F Figure 4
~ 25 ~
Figure 5
Day 3 (placing the sealing, 1st layer, drainage pipes and weed control fabric)
- Placing the sealing (morning) - Filling the walls with sand (morning)
- 5-10cm Layer of thick gravel – figure A (morning)
- Placing the drainage pipes + maintenance pipes – figure 6 (afternoon) - Placing the resisting amount of thick gravel (afternoon)
- Placing the weed control fabric – figure A (afternoon)
Figure 6
Day 4 (Placing the different sand layers + pump system)
- Filling up the Helophyte filter system with different sand layers (morning)
- By first mixing them with the ads before placing it
Important: The layers must not get mixed!
- Figure A
- Preparing the irrigation pipes – figure 7 (whole day)
- Placing the irrigation pipes – figure 7 (afternoon)
Figure 7
~ 26 ~
Day 5 (Planting the plants & connecting the pumping system)
- Planting the plants – table 1/ figure 8 (whole day)
- Connecting the supply pipes and pump system – figure 8 (whole day) - Adding the final gravel layer – figure A (afternoon)
Table 1
Figure 8
Day 6 (Extra day)
- If things are not finished yet they can be done in the extra day Note: This will increase the quotation!
Plants Surface filter: 12,78375 m²
Amount/m² Amount Price
Cuttings 6 to 10 102.27
Seedlings 4 to 6 63.91875
~ 27 ~
5.4. Designs The official design of the VHFS is made with Google Sketchup. In the VHFS manual for Davao City the
design was already made. In this paragraph the exact design out of the manual are shown. To build
an effective and sustainable helophyte filter system the construction of the pipes are of most
important. They must be constructed according to the requirements of chapter IV.
Supply pipes The supply pipes have to be twice the size of the irrigation pipes. In figure 2 the supply pipes (yellow)
are shown. It runs from the septic tank to the pump (Orange) and from the pump to the irrigation
pipes. The pump sucks the water from the clear water well inside the septic tank (North side). The
blue print of this septic tank can be found in the appendix (paragraph 3). This septic tank has 3
chambers in which the grey and black water are combined.
In this case the septic tank is a combined tank where the grey and black wastewaters are both
discharged into. This will created the opportunity to leave the settling tank out of the design because
this unit is already integrated in the septic tank.
Irrigation pipes The irrigation pipes must be
constructed according to the
requirements of chapter 6. In
the figure on the right the
construction of the irrigation
pipes is illustrated (Bleu). The
pipes have a distance from
1m from each other and
50cm from the wall.
Figure 11: irrigation
Figure 12: Irrigation 2
~ 28 ~
Drainage pipes & discharge pipes To have an efficient drainage system three drainage pipes (Figure 24, Red) will be laid in the gravel
layer of the basin. The pipes will be placed on a small slope (5cm difference from beginning to end).
Than the pipes will be connected to another drainage pipe (Also red), that also is laid with the same
small slope with the lowest point at the discharge pipe (Figure 25, Purple). The discharge pipe will
discharge the treated wastewater to a freshwater well (black) where inspections can be made. From
the freshwater well the water will drain to the drainage well nearby the filter system.
The effluent of the filter system shall be analyzed and with good results the effluent can be re-used
for purposes as irrigating plants or flushing the toilet. The designs of this will be made when a
sufficient effluent is recorded for at least six months. Based on the water consumption, that is
calculated in phargraph 2 of this chapter, the volume of the effluent will be
((90.2l*5pers*5days)/1000=) 2.255m³ a week. This will save around 9.5m³ of water a month.
For qualifying the effluent the following reports can be used; Water Quality Guidelines and General
Effluent Standards of 2008, Revising DAO 34 and 35, Series of 1990 by the DENR; Philippine
Regulations on Sanitation and Wastewater Systems (INTERNATIONAL EDITION) by Bonifacio B.
Magtibay; and Global Effluent Guidelines by Levi Strauss & Co .
Maintenance pipes To make maintenance on the discharge pipes
possible it’s important to build maintenance pipes
(Figure 26, Brown) that are connected with the
drainage pipes. The drainage pipes can be jammed
so by flushing the pipes out via the maintenance
pipes with water this problem can be prevented.
The maintenance pipes have to be closed after
cleaning with a cap so dirt can’t enter the drainage
pipes. In the figure on the right is illustrated how
these pipes will be constructed.
Figure 14: drainage Figure 13: fresh water well
Figure 15: maintenance pipes
~ 29 ~
Expansion pipe
To ensure that the helophyte filter basin doesn’t overflow a few interventions have been made to
the design. The height of basin will be increased with 10 cm to increase the capacity of the filter bed
and an expansion pipe (Dark red) will be constructed on the edge of the extra 10cm. If the filter basin
is overflowing the water will be drained back to the septic tank so that no wastewater will spill over
the basin. The figure bellows shows the extra 10 cm and the expansion pipe. The pipe will be
constructed 4cm lower than the supply pipe (Yellow) so a back flush is not possible. Without this
intervention the pump system would be vulnerable for overflow.
Figure 16: expansion pipe
Reset pipe In case the effluent of the filter system isn’t sufficient the water in the fresh water well will drain
back to the septic tank (clear water chamber). This will be done by adding a reset pipe (Orange). This
pipe can be shut with a valve so, when the effluent is good, the water will drain out of the other side
of the fresh water well. The water will than drain to a nearby drainage well.
Figure 17: back flush pipe
~ 30 ~
Full design The figures below show the full design of the helophyte filter system pipe lines and the different compartments of sand.
Figure 19: Full design
Figure 18: full design 2
~ 31 ~
For the 1mm PP sealing an individual design was made which is shown below.
Figure 20: Sealing
~ 32 ~
6. Implementation The implementation of the filter system started 7 January 2013 when the budget wasn’t available jet.
To make the implementation possible on time 10,000 peso was given as cash advantage to start the
project. Later in the project more of this cash came available until the 15 of January when the real
funding money was available. At that time 37,000 peso was already given. These budgets were given
in stages and therefore it wasn’t possible to purchase all the equipment at ones. This caused a lot of
delay in the construction, because some days there wasn’t any money available. The quotation
became bigger because the transport of the equipment became more expensive. The working
schedule became a guideline and workers didn’t show up because it was unsure if they had work on a
particular day.
Day 1 ‘Preparing the construction site’
Date: 01/03/2013 Workers: 2 Supplies: Gloves, Shovel, buckets, masonry tools, tire wire, cutter Remarks: On the first day the goal was to dig out the groves for the concrete, make the steal construction and filling the groves with concrete. The first problem in the project came already in the first activity ‘making the groves’. The soil consists out of sticky (wet) clay and pieces of concrete. Therefore it was nearly impossible to dig in the ground. Due to this unfortunate soil composition the preparation of the wholes was finished on the first day. This was causing a half day delay. Also one of the workers didn’t show up. Therefore an insufficient amount of manpower was available on this day. The picture below shows the construction site after 1 day work.
Figure 21: picture 1
~ 33 ~
Day 2 ‘Concrete base’
Date: 01/04/2013 Workers: 3 Supplies: Sand, Gravel, Hollow block, Cement, Nails, Steel Grinder Remarks: On the second day the goal was to make the walls. But because of the delay on day one the goal was re-established to only make the wall half way. The first problem of the day occurred when the supplier of the sand didn’t show up. When they were contacted via the phone they informed that there was no more sand available (while the order was given a day before). After two hours another supplier brought the sand (picture below). Because of the limited amount of budget I could only purchase half of the needed amount of sand. The hollow blocks and steel was delivered two hours after negotiated time (see pictures below)
Figure 23: Picture 2 Figure 22: picture 3
Figure 24: Picture 4
~ 34 ~
After all the delays caused by
the suppliers the actual
construction of the basin
began. The picture on the
right shows the steel
construction. Underneath
sand with gravel was added
as an under layer. This would
ensure the construction to
sink less in the clay.
At the end of the day the day
the concrete base was poured
into the groves, the first layer
of hollow blocks were laid and
the steel construction was
finished. The picture on the
right shows the first hollow
blocks that are laid.
Because of all the delays with
the suppliers the project was
delayed with one day after the
second day already.
Figure 25: Picture 5
Figure 26: picture 6
~ 35 ~
Day 3 ‘Constructing the walls’
Date: 01/05/2013 Workers: 3 Supplies: none Remarks: On the third day the goal was to apply the 1mm PP sealing, put in the first gravel layer, install the drainage pipes and apply the weed control fabric. But because of the delay on day one and two the goal was re-established to further construct the walls. The first problem of the day occurred when one of the workers didn’t show up and didn’t call himself absent. Another worker was needed so Mr. Notarte (carpenter) was instructed to get another worker who began working at 11 am. This caused almost one working day for one constructor. On this day the walls were halfway constructed. The picture on the right shows the masons working on the walls.
Day 4 ‘Constructing the walls’
Date: 01/07/2013 Workers: 2.5 Supplies: cement Remarks: On the fourth day the goal was to fill up the basin with different layers of sand and apply the
irrigation pipes. Because of the earlier delays in the past days the goal was re-established to further
construct the walls.The problem of the day was that 1 carpenter didn’t show up again. Therefore
another carpenter was hired and worked a half day.
Day 5 ‘Constructing the walls’
Date: 01/08/2013 Workers: 1 Supplies: cement Remarks: On the fifth day the goal was to finish the project. Because of the earlier delays in the past days the
goal was re-established to further construct the walls.
On this day there was no budget so only one carpenter was working.
Figure 27: picture 7
~ 36 ~
Day 6 ‘Constructing the walls’
Date: 01/09/2013 Workers: 2 Supplies: cement Remarks: On this day the project was half way finished and one day delayed.
On this day there was no budget so 2 carpenters were working. The next day more money was
promised to be available so more carpenters could work.
This day the walls were constructed and the sealing was ordered from Jacinto canvas store. The
picture below shows the construction of the walls fully finished.
Figure 28: Picture 8
~ 37 ~
Day 7 ‘Filling up the basin’
Date: 01/11/2013 Workers: 2 Supplies: PVC pipes & fittings, Sealing,
plumbing materials Remarks: The goal of the day was to apply the first gravel
layer and install the drainage pipes was
accomplished.
The problems of the day were; one carpenter who
didn’t show up and the budget wasn’t available jet.
The payments were done with another cash
advantage.
The picture on the right shows the installed drainage
pipes, the installed sealing and the gravel. The
picture below shows how the pipes were treated to
let them function as drainage pipes. This was done
by carving drainage lines into the PVC pipes. The
picture below on the right shows the drainage pipes
covered with gravel.
Figure 29: Picture 9
Figure 31: picture 10 Figure 30: picture 11
~ 38 ~
Day 8 ‘Filling up the basin’
Date: 01/12/2013 Workers: 2 Supplies: PVC pipes & fittings, Sealing, plumbing
materials Remarks: On this day the project was half way finished and two
days delayed.
The problem of the day was that there wasn’t any
budget and the limestone for the filter system couldn’t
be delivered. This is why two carpenters where hired to
construct a well.
The constructing of the well is shown in the picture on
the right. Also the feed control fabric was applied,
picture below.
Figure 32: picture 12
Figure 33: picture 13
~ 39 ~
Day 9 ‘Filling up the basin’
Date: 01/14/2013 Workers: 4 Supplies: limestone Remarks: On this day limestone had to be purchased from a supplier. The limestone had to be manually dogged from a mountain and transported to the DOST. This activity took a half day. The rest of the day 30cm of the 90cm soil was filled into the filter system. The picture on the right shows the limestone that was manually purchased from the supplier.
The picture on the right shows the
VHFS that is filled with the first
two layers of soil.
Figure 34: Picture 14
Figure 35: picture 15
~ 40 ~
Day 10 ‘Filling up the basin’
Date: 01/15/2013 Workers: 3 Supplies: sand Remarks: On this day the filter system was filled up further. There were 3 stages:
- 60cm limestone with sand
- 20cm limestone with sand and hay
- 20cm sand with iron fillings
Day 11 ‘Installing the system
Date: 01/16/2013 Workers: 3 Supplies: plants, PVC pipes & fittings Remarks: On this day the plants were purchased and
planted in the basin. After planting the reed
the last layer of gavel was poured into the
basin and the construction of the irrigation
pipes was measured and cut.
The problem of the day was that one
carpenter didn’t show up again.
The picture on the right shows the filter
system with the plants that were just
planted.
Figure 36: Picture 16
~ 41 ~
Day 12 ‘Installing the irrigation and outlet pipes’
Date: 01/17/2013 Workers: 1 Supplies: PVC pipes & fittings, pump Remarks: On this day the project was almost finished and the
fully amount of 50,000 peso was almost spended
completely because of the big delay. Therefore only
one carpenter was assigned to help with the final
stage of the project.
At the end of the day all the pipes were installed
but the pump wasn’t connected jet. The picture on
the right shows the back flush pipes and the pump
box.
The picture below shows the irrigation pipes that
were installed.
Figure 37: Picture 17
Figure 38: Picture 18
~ 42 ~
Day 12 ‘Installing the irrigation and outlet pipes’
Date: 01/18/2013 Workers: 1 Supplies: PVC pipes & fittings, Remarks: On this day the project the pump system had to
be installed. The Picture on the right shows the
pump that was installed.
The problem of the day was that the first pump
unit didn’t work and a check valve had to be
installed. Therefore the project was delayed
again.
At 5 pm the pump system was working and the
VHFS functioned for the first time. The pump ran
for 10 minutes and after 30 minutes clear effluent
was draining to the fresh water well. See picture
on the right.
Because of all the delays during the project there
wasn’t time left to construct the roof for the filter
system. This will be done without personal
authorization. The picture below shows the first
Vertical Helophyte Filter System of Davao City that
was built in 12 days.
Figure 39: picture 19
Figure 40: pictre 20
Figure 41: picture 21
~ 43 ~
7. Finances
The funding for the project came from the HELP Davao Network who gave 50,000 peso for the
implementation of the Vertical Helophyte Filter System. The proposal for the funding was made
December 2012 and available January 15th 2013. Because of the time limit for the project, January
20th 2013, the project started earlier.
Budget The start of the project, on January the third 2013, was funded with a cash advantage of 2 X 5,000
peso.
Before the 9th of January 2013 7,000 peso was given already as cash advantage.
On the 9th of January 2013 20,000 peso was given as cash advantage.
On the 14th of January 2013 another 5,000 was given as cash advantage.
On the 15th of January the budget was available. The budget was still 8,000 peso of the 50,000 peso.
Due to the late availability of the funding these cash advantages where given by:
- DOST XI 17,000 peso
- Dr. Sales 5,000 peso
- Ms. Maspiñas 20,000 peso +
42,000 peso
Because the budget wasn’t available on time the project had days when supplies and workers
couldn’t be paid. This caused 4 days delay in the project based on the absence of supplies or workers.
The transport costs were also increasing because of the late funding.
Workers payroll The carpenters that worked on the VHFS construction project where all given 350 peso for an 8 hour
working day. All of the workers needed to sign a working contract provided by the DOST XI office.
The payments were given every working day after signing the payroll.
Payments In the appendix the full Microsoft Excel sheet of all payments is shown. All payments of the project
are registered for approval of the HELP Davao Network. The registration is only done with official
receipts of the suppliers, transporters and shops.
~ 44 ~
8. Conclusion
The construction of the Vertical Helophyte Filter System (VHFS) for the new laboratory building was
started on the third of January 2013. On the 18th of January the filter system became operational.
The VHFS is a pilot project, of the HELP Davao Network, to treat the wastewater of households,
offices and small companies.
The effectiveness of the VHFS is clear a 1-3 months after the first day of operation. After this period
the VHFS must drain clear effluent. The success of the project lies within the effectiveness of the
filtration capacity and the further implementation of more VHFS’s in Davao City. When this
understanding of wastewater treatment is integrated in Davao City the project can be seen as step
towards a community based sewage system where all the wastewater of Davao City is treated on an
environmental responsible way.
The individuality, small scale and relatively low costs & maintenance of the VHFS make this filter the
most applicable wastewater treatment facility for Davao City. Although the project was delayed by
different obstacles, the project is capable to be finished in a time period of 8 days or less instead of
12 days. The budget was fully spent and the filter system was operational on time.
~ 45 ~
Appendix
~ 46 ~
Appendix A ’Payroll’
As of
January
11, 2012
Expense
Code Date Payee Description Civil works
Supplies and
Materials
Re-
presentation
Travel
Transporation Total
192121 2-jan Davao Citihardware equipment 802,00 802,00
22190 2-jan Maligaya Taxi taxi 208,00 208,00
10601 2-jan Midvalley taxi 323,50 323,50
89301 2-jan Roso Hardware cement 1440,00 1440,00
216371 3-jan-13 Davao Citihardware equipment 575,00 575,00
3-jan-13 gravel 1125,00 1125,00
942 3-jan-13 El-Zed Concrete Products steel 2520,00 2520,00
5519 3-jan-13 Edong's Lechon Manok meals 251,00 251,00
216596 4-jan-13 Davao Citihardware nails 34,75 34,75
188576 4-jan-13 Davao Citihardware tie wire 110,00 110,00
29146 4-jan-13 Penong's meals 420,00 420,00
27496 4-jan-13 Midvalley taxi 47,00 47,00
21711 4-jan-13 Maligaya Taxi taxi 57,50 57,50
54843 4-jan-13 JR Concrete Products hollow blocks 3200,00 3200,00
54843 5-jan-13 JR Concrete Products gravel 2100,00 2100,00
89333 5-jan-13 Roso Hardware cement 720,00 720,00
5542 5-jan-13 Edong's Lechon Manok meals 272,00 272,00
4983 5-jan-13 Siycha Transport taxi 99,50 99,50
7-jan-13 MKNETTE Trading weed fabric 380,00 245,00 625,00
5557 7-jan-13 Edong's Lechon Manok meals 251,00 251,00
966 7-jan-13 El-Zed Concrete Products cement 920,00 920,00
~ 47 ~
21786 9-jan-13 Siycha Transport taxi 47,00 47,00
111037 9-jan-13 Davao TLCO General Merchandise cement 693,00 693,00
1239 9-jan-13 Penong's meals 205,00 205,00
166396 8-jan-13 Jolibee meals 158,00 158,00
5600 11-jan-13 Edong's Lechon Manok meals 269,00 269,00
189399 11-jan-13 Davao Citihardware supplies 276,15 276,15
4170 10-jan-13 Jacinto Canvass Supply supplies 4000,00 4000,00
119451 10-jan-13 Davao TLCO General Merchandise supplies 462,00 462,00
111122 10-jan-13 Davao TLCO General Merchandise supplies 3860,00 3860,00
119511 12-jan-13 Davao TLCO General Merchandise supplies 368,00 368,00
9143 12-jan-13 Davao PSG Foods Corp. meals 315,00 315,00
RER 14-jan-13 Eric Goc-ong materials 400,00 400,00
RER 14-jan-13 Eric Goc-ong materials 200,00 200,00
4-jan-13 Bebelin Diaz hollow blocks 0,00
5-jan-13 Bebelin Diaz gravel 2100,00 2100,00
14-jan JR Concrete Products rental 900,00 900,00
5629 14-jan Edong's Lechon Manok meals 417,00 417,00
15-jan Bebelin Diaz sand 2300,00 2300,00
8-jan Bebelin Diaz sand 2300,00 2300,00
5629 14-jan edong's meals 417,00
5635 15-jan edong's meals 320,00
34 15-jan Antonieto Diaz Sand & Gravel sand/gravel
35 16-jan Antonieto Diaz Sand & Gravel sand/gravel 1200,00
193745 16-jan davao citihardware supplies 660,95
166868 16-jan Superstandard Plumbing Supply Inc. pvc elbow 302,00
119678 16-jan Davao TLCO General Merchandise pipes 400,00
~ 48 ~
218853 16-jan davao citihardware pipes 327,50
218952 17-jan davao citihardware outlet 79,75
80287 17-jan Superstandard Plumbing Supply Inc. pvc adapter 16,00
106065 17-jan Nyco Sales Corp pvc adapter 20,00
219056 17-jan davao citihardware pipes 118,85
190214 17-jan davao citihardware seal 58,50
219190 18-jan davao citihardware steel brace 111,75
89431 18-jan roso hardware foot valve 163,00
Total 10325,00 39566,70 2878,00
TOTAL 49891,70
pending:
625
mknette
1500
harbin
900
jr trucking
~ 49 ~
Appendix B
Quotation of the
vertical helophyte
filter system DOST XI
Sean Ligtvoet
11/26/2012
~ 50 ~
Quotation - Helophyte filter system 11/26/2012
Sean Ligtvoet
DOST XI
Equipment prices
Hollow blocks J.R. Concrete Products (221-9794)
Hollow block = 4’’ 8’’ 16’’ = 10.16cm * 20.32cm * 40.64cm
Surface = 825,8048cm² = (/10.000) 0,08256m²
Surface filter system = 11, 85 + 8, 06+8, 68= 28,59m²
Surface area + fresh water well= 32,59
Blocks needed = (32,59/0,08256) 395
+10% material losses= 435
Price per block= 8,-
Total price = (8* 435) = Php: 3,480,-
Steel
J.R. Concrete Products (221-9794)
Steel= 8mm X 20 feet/ 90,-
Price= 90,-/6,096m= 14, 76378/m
Amount= 167,85m
Total price (14, 76378*167, 85) = Php: 2,478. 10
~ 51 ~
Sand J.R. Concrete Products (221-9794)
Amount= 7,91m³
Price= Php: 500,-/ m³
Total Price= (500 * 9, 91) Php: 3,550,-
Pump Local shops
M. Aqua
Total price: Php: 3,000,-
Roof
City Hardware (J.P. Laurel Ave.)
Wood= (2*2,20m +1*2) 6,40m
Price = (520/2,4m) 217,- /m
Wood price= (3 * 520) Pph: 1.560,-
Wave plate= 16m²
Price= (210,-/ 2*8ft) 141,21,-/m²
Roof price= (16* 141,21) Php: 2.259,31 +
Total price: (1.560+2.259,31) Php: 3,819.31
~ 52 ~
Sealing Suison Canvas (247-B Juan Dela Cruz Street, tell: 224-1742/ 286-3261)
Amount= 40m²
Price= 25,-/m²
Total price: (25 * 40) Php: 1000,-
Tools City Hardware (J.P. Laurel Ave.)
Masonry tools: 395,-
Watertight glue: 438,-
Duck-tape: 62,-
Plastic saw: 60,-
Concrete saw: 58,75
Screws with plugs : (34,75/ 8* 5) 173,75
Concrete mixer (0063-922-5233-6440): 1,200,-
Measuring lint: 85,- +
Total price: Php: 2,472.50
http://davaocity.olx.com.ph/tools-and-equipment-rental-iid-321116351
Gravel
J.R. Concrete Products (221-9794)
Amount fine gravel: 1.5m³
Price fine gravel: 750,-
~ 53 ~
Amount thick gravel: 1.5 m³
Price thick gravel: 700,-
Total price: (1.5*700+1.5*750) Php: 2,175,-
Pipes City Hardware (J.P. Laurel Ave.)
PVC 32mm:
Price: 98,75
Amount: 5
Total price: (98,75*4) Php: 493.75
PVC 63mm:
Price: 255,-
Amount: 3
Total price: (3*255) Php: 765,-
PVC 90mm:
Price: 384,-
Amount: 7
Total price: (7*384) Php: 2688,-
Total price: (1.5*700+1.5*750) Php: 3,946.75
~ 54 ~
Pipe fittings
Super standard plumbing (Juan Dela Cruz Street, tell: 222-5437)
amount Diameter (mm) Angle (°) type price Total
price
2 63 45 Equal elbow 370 740
1 63X63X63 - TEE Crossing 370 370
4 65X65X32 - TEE Reducer 480 1920
1 63>32 - Straight Reducer
235 235
3 63 90 Equal elbow 320 960
3 90 45 Equal elbow 52 156
4 90 - TEE Crossing 94 376
3 90 - Cap 100 300
5 63 - Cap 35 175
1 63 - valve 200 200
1 90 - valve 200 200
Total price: Php: 1,632,-
Lime stone
Max (0063-923- 428-8940)
Amount needed: 3m³
Price per/ m3: 200,-
Total price= Php: 600,-
Plants
No costs
~ 55 ~
Iron fillings
Don Traje DOST XI ([email protected])
Amount: 34 kg
Total Price: Php: 100,-
Liquid concrete
J.R. Concrete Products (Tell: 221-9794)
Starlight at Magsaysay
Cement for walls
Surface of the wall= 32,59m²
Ratio cement kg/liter= 25kg /12 liter
Liters cement needed= (33*25) 284 liter
Kg cement needed = ((825/12)*25=) 71kg
Price/ kg= 220,-/40kg
M³ sand= 0.15
Price 1m³ sand= 500,-
http://www.eclecticsite.be/bouw/muur.htm
Total price= 75,-
Bags cement needed= 2
Total price: (2*220+75 =) 515,-
~ 56 ~
Cement for concrete basis
Ratio cement kg/liter= 25kg /12 liter
Ratio concrete= 1 cement : 2 sand : 3 gravel
http://www.metselen.net/beton%20maken.html
Mass density ring cement= 2500 kg/m³
Mass density ring sand= 1500 kg/m³
Mass density ring gravel= 1500 kg/m³
http://www.gwwmaterialen.nl/soortelijk-gewicht-materialen/
Amount concrete needed= 0.70m³
Amount needed for 1m3 concrete: 325 kg cement
750 kg sand
1200 kg gravel
Bags of cement needed: (325/40) 8
Bags really needed: 6
Price of 1 bag (40kg): 220,-
Total cement price: 1320,-
M3 sand needed: 0.5m³
M3 really needed: 0.35
Price 1 m3 sand: 500,-
Total sand price: 175,-
M3 gravel needed: 0,8m³
~ 57 ~
M3 really needed: 0.56m³
Price 1m3 gravel: 750,-
Total gravel price: 420,-
Total Price: (3960+880+125+300=) Php: 2,430,-
Root control fabric
Earthonomic ([email protected])
Amount needed: 1
Price per unit: 380,-
Shipping costs: 1750,-
http://www.sulit.com.ph/index.php/view+classifieds/id/5903122/Weed+Control+Fabric
Total price: Php: 2,130,-
~ 58 ~
Total price
Hollow block = Php: 3,480,- Steel= Php: 2,478. 10 Sand= Php: 3,550,- Pump= Php: 3,000,- Roof= Php: 3,819.31 Sealing= Php: 1000,- Tools= Php: 2,472.50 Gravel= Php: 2,175,- Pipes = Php: 3,946.75 Pipe fittings= Php: 1,632,- Lime stone= Php: 600,- Plants= Php: -- Iron fillings= Php: 100,- Concrete= Php: 2,430,- Root control fabric= Php: 2,130,- +
Total Price equipment: Php: 36,813.66
Workers costs
Amount= 3
Costs= (2*350 p/d, 1*200 p/d)
Days working= 5
Total price workers= Php: 4,500,-
Total price: Php: 41,313.66
~ 59 ~
Appendix C ‘Contracts’
JOEBOY MUNION
~ 60 ~
JOEL NOTARTE
~ 61 ~
LORDDYCAN D. CARIN
~ 62 ~
ARMAN AREVALO
~ 63 ~
~ 64 ~