Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771 [email protected]

Upload: others

Post on 10-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Implementing Systems Engineering in a

Sustainment Environment

25 Sept 06

Jim MillerChief Engineer727 ACSG/ENPhone: [email protected]

Page 2: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

So What is the Problem?So What is the Problem?

• High-level policy is a good and necessary first step, however, more detailed direction is essential to turn the policy into a workable, grass-roots program

• Sustainment different than acquisition• Our organization had insufficient direction,

documentation, and procedures to begin implementing an effective, comprehensive Systems Engineering program

Page 3: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

So What Are Doing About It?So What Are Doing About It?

• Instigated a step-by-step approach to begin implementing systems engineering throughout the sustainment organization

• Tangible approach that is:– Aimed at the working level– Affects all phases of a program’s lifecycle– Applicable throughout entire organization– Accounts for organization’s progress through metrics

Page 4: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Systems Engineering Implementation PhasesSystems Engineering Implementation Phases

• Phase 1: Awareness of Need• Phase 2: Workforce Training• Phase 3: Identify Applicable Programs/Orgs• Phase 4: Identify and Define Processes• Phase 5: Incentivize Contractors/Partners• Phase 6: Develop Library of Tools• Phase 7: Track Progress via Metrics

Page 5: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 1: Awareness of NeedPhase 1: Awareness of Need

Brief senior leadership and got documented buy-inIdentify focal point for organizationPrepare SE re-invigoration briefingPresent briefing to all:

Supervisors (Squadron Commanders/Directors)Program Manager’sLogisticiansEngineersEquipment SpecialistsTelecommunication Specialists

Page 6: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 2: Workforce TrainingPhase 2: Workforce Training

Determine appropriate amount/level of training by working with:

Internal engineering managementCenter-level functional officesHigher headquarters (HQ AFMC)Senior Program Managers

Ensure training consistent with other ALC, AFMC and DoD effortsDetermine training plan robust enough to make a difference yet realistic based on workload

Train Workforce

Page 7: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Who: All PM’s, Equipment Specialists and EngineersWhen: Complete in 12 monthsWho: All PM’s, Equipment Specialists and EngineersWhen: Complete in 12 months

Courses Selected (All CBT):

• SYS 182 Intro to Systems Engineering ~ 3 hrs

• SYS 155 Operational Safety, Suitability & Effectiveness ~ 9 hrs

• SYS 028 Intro to Configuration Management ~ 16 hrs

• SYS 165 Intro to Risk Management ~ 21 hrs

• SYS 172 Modification Management Process ~ 6 hrs

Phase 2: Workforce TrainingPhase 2: Workforce Training

Page 8: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Org A Training Progress (45 People)

0102030405060708090

100

SYS 182

SYS 028

SYS 165

SYS 155

PercentageComplete

SYS 172

1st Qtr Goal

2nd Qtr Goal

3rd Qtr Goal

4th Qtr Goal

Phase 2: Workforce TrainingPhase 2: Workforce Training

Page 9: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 3: Identify Applicable Programs/OrgsPhase 3: Identify Applicable Programs/Orgs

Determine Applicable Programs Criteria:

All OSS&E Programs* C-9 * C-12* C-20 * C-21* C-21 * C-26* C-38 * E-9* KC-10 * KDC-10* Peace Lotus * T-43* Academy Fleet * E-4B* VC-25 * HFGCS

Page 10: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 4: Identify and Define ProcessesPhase 4: Identify and Define Processes

Ensure processes incorporate systems engineering

Jumpstarted SE revamp with 3 Key Processes:Requirement Management OIRisk Management OITest Management OI

Will springboard into otherorganizational processesGoal to standardize and shareBest Practices across organization

Page 11: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Basic Systems Engineering ProcessBasic Systems Engineering Process

RequirementsAnalysis

INPUTSINPUTS

FunctionalAnalysis/Allocation

DesignSynthesis

Analysis &ControlVerificationVerification

LoopLoop

RequirementsRequirementsLoopLoop

DesignDesignLoopLoop

OUTPUTSOUTPUTS

Phase 4: Identify and Define ProcessesPhase 4: Identify and Define Processes

Page 12: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

• Break requirements down in a Requirements Correlation Matrix (RCM):

• Spreadsheet with following columns:– Requirement– Requirement Source– Derived Requirements– Quantification– Initial Risk Assessment– Operational Conditions

• Give RCM to – Test Team for their planning– Risk Mngt Team for their planning

Phase 4: Identify and Define ProcessesPhase 4: Identify and Define Processes

Page 13: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

RCMRCM

Risk(R/Y/G)

Op CasesQuantification

ReqDefinition

Derived Req

ReqSource

ReqTitle

Program Manager

User

Entire Team

ProjectEngineer(s)

(Gov & Contr.)

Page 14: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

0102030405060708090

Phase 4: Identify and Define ProcessesPhase 4: Identify and Define Processes

Low

Low

Med.

Med.

High

High

42 210

61 10 43

324231

Meas.

Lean

Current

Doc.

Requirements

RiskProcesses

Qua

ntifi

edRev

iew

ed

Tota

l Req

uire

men

ts

Page 15: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 5: Incentivize Contractors/PartnersPhase 5: Incentivize Contractors/Partners

Ensure Systems Engineering is an incentivized factor in all applicable contractsList all Contracts

Determine which should have SEDetermine appropriate SE wording Develop plan, so as contractsrenewed, incorporate SE incentivization

Work with contractor/partner to improve implementation of systems engineering

Already incorporated in two major contracts!Already incorporated in two major contracts!

Contracts

Goal

Page 16: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 6: Develop Library of ToolsPhase 6: Develop Library of Tools

Need good SE “toolbox”– Templates– Metrics– How-to’s (fishbone, 5-whys, paredo, …)– Lessons Learned– Explanations– Best Practices– Peer Review– Case Studies– Life Cycle Cost consideration– Contractual language– Etc…

Functional Office to Develop/Obtain….Not Started Yet

Page 17: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 7: Track Progress via MetricsPhase 7: Track Progress via Metrics

Metrics developed to track progressMetrics shown regularly to upper management

1st staff meeting of monthQuarterly Weapon System ReviewsMetrics must be able to roll up

Metrics will track:Systems Engineering Implementation RequirementsRiskProcessesTrainingContracts

Page 18: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Phase 7

Phase 5

Phase 4

Phase 3

Phase 2

Phase 1

Phase 6Goal

1QFY06

4QFY06

3QFY06

3QFY07

2QFY06

1QFY08

4QFY07

2QFY08

1QFY07

2QFY07

4QFY08

3QFY08

2QFY09

3QFY09

1QFY09

4QFY09

4QFY05

1QFY05

3QFY05

2QFY05

Org AOrg B

Sys Eng Implementation Progress

Still Refining Goal DatesStill Refining Goal Dates

Phase 7: Track Progress via MetricsPhase 7: Track Progress via Metrics

Page 19: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

0102030405060708090

Sample Program Sys Eng “Dashboard”Sample Program Sys Eng “Dashboard”

Low

Low

Med.

Med.

High

High

42 210

61 10 43

324231

Meas.

Curr.

Lean

Doc.

Requirements Training

RiskProcesses

Contracts

Qua

ntifi

edRev

iew

ed

Tota

l Req

uire

men

ts

0102030405060708090

SYS

028SY

S 05

5

SYS

182

SYS

165

Page 20: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

0102030405060708090

Low

Low

Med.

Med.

High

High

40 8020

5 50 60

40510

Meas.

Curr.

Lean

Doc.

Requirements (%)

Risk (%)Processes (%)

Sample Organization Sys Eng “Dashboard”Sample Organization Sys Eng “Dashboard”

Contracts100%50%

Tota

l

Rev

iew

ed

Qua

ntifi

ed

%

0102030405060708090

100

Training (%)

Page 21: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

What’s Next What’s Next

• Continue implementation throughout organization

• Measure/Track results• Increase and standardize systems

engineering presentation in quarterly Weapon System Reviews and Staff Mtgs

• Start configuration management Process Improvement Team

Systems Engineering can be implemented, applied AND make a difference

Page 22: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

SummarySummary

• Recent high-level policy issued• 727th ACSG developed grass-roots means to

implement SE in Sustainment Environment• Clear-cut, tangible processes steps for the

working-level; metrics to measure progress for management

•In Place and In Use Now

Page 23: Implementing Systems Engineering in a Sustainment ... · Implementing Systems Engineering in a Sustainment Environment 25 Sept 06 Jim Miller Chief Engineer 727 ACSG/EN Phone: 736-5771

Questions ?Questions ?