improving sludge treatment whole life cost savings by way ...€¦ · we have considered the...
TRANSCRIPT
HUBER Technology UK – www.huber.co.uk
Improving sludge treatment whole
life cost savings by way of
dewatering on satellite sites
HUBER Technology UK – www.huber.co.uk
Slide 2
Present situation
• In order to optimise methane production and sludge quality for disposal, the
UK has seen a trend towards large, regional sludge reception facilities with
some form of Advanced Anaerobic Digestion (AAD) (e.g. with Enzymic or
Thermal Hydrolysis pre-treatment).
• These facilities involve significant CAPEX and it is more economically viable
to have only a few of these huge capacity sites and bring in sludge from
outlying satellite works.
• The transportation costs incurred by such sludge movement are significant
and obviously get higher if the sludge is thinner and if the satellite sites are a
long way from the AAD plant.
• Some water companies are already using satellite site sludge dewatering to
reduce volumes for transport followed by “re-wetting” at the AAD site to give
the required feed thickness.
HUBER Technology UK – www.huber.co.uk
Slide 3
Present situation
A cake reception area (as shown in these examples) and re-wetting facility are
an additional CAPEX required at the AAD plant.
United Utilities - Davyhulme WwTW
Northumbrian Water – Bran Sands WwTW Dwr Cymru - Afan WwTW
HUBER Technology UK – www.huber.co.uk
Slide 4
Drivers for dewatering at satellite sites
If practical and if the payback period is acceptable, upgrading satellite sites to
include some form of volumetric reduction of the sludge being produced:
• Can significantly reduce the whole life cost of the plant as a result of reduced
transportation costs,
• Can reduce the indirect carbon footprint of the AAD plant as a result of fewer
lorry movements (against which the increased power consumption etc. at the
satellite sites is insignificant),
• Can help the water company achieve it’s AMP6 goal to improve efficiency
(by reduced OPEX).
Dewatering is likely to only be favored over thickening or optimizing the existing
set-up if the overall whole life cost saving is significant and if the payback period
is sufficiently short (3-7yrs).
HUBER Technology UK – www.huber.co.uk
Slide 5
UKWIR report
This presentation makes use of data and findings in UKWIR report no.
13/SL/11/6 –
“Sustainable Sludge Thickening and Treatment at Small WwTWs”
Available from:
http://ukwir.forefront-library.com/reports/13-SL-11-6/96374
HUBER Technology UK – www.huber.co.uk
Slide 6
UKWIR report
Excellent info but suppliers’ sizing and process data (i.e. cake dryness)
limited by not wanting to promise too much based on general scenarios.
The disposal costs used in the report are higher than those used by at least
one water company (hereafter referred to as “Alternative Costs” when used)
so this presentation will use both for comparison.
The report also discusses using mobile kit for volumetric production that
would be moved from site to site as required but, in practice, we have found
that this concept can be limited by:
• Changes to management personnel
• Operators on subsequent sites not having the required training and
• Subsequent sites needing different polymers which may mean that the
poly kit should really be cleared out first.
HUBER Technology UK – www.huber.co.uk
Slide 7
Pertinent info from UKWIR report 13/SL/11/6
Of the 7 water companies who provided info:
• The no. of sites with a pop. smaller than 2,000 ranged from 191 to 1727 (58 –
89 % of all the sites in each area),
• The no. of sites with a pop. between 2,000 and 10,000 ranged from 32 to 197
(5 – 24 % of all the sites in each area) and
• The no. of sites with a pop. between 10,000 and 25,000 ranged from 12 to 61
(2 – 5 % of all the sites in each area).
• On all 2k, 10k and 25k sites, 60-65% sites co-settle Primary and Humus
sludges.
• 15%, 20% and 25% of 2k, 10k and 25k sites, respectively, produce separate
Primary and Activated sludges.
Sludge production rates varied from 60 to 85 g/head/d but the majority were in
the 60 – 65 g/h/d range.
HUBER Technology UK – www.huber.co.uk
Slide 8
Pertinent info from UKWIR report cont.
• 50-75% of 2k to 10k sites have at least consolidation tanks (i.e. with
decanting valves)
• 75-100% of 10k to 25k sites have at least consolidation tanks.
• <25% of 2k to 10k sites have more reliable sludge thickening than
consolidation tanks
• Only 25-50% of 10k to 25k sites have more reliable sludge thickening
than consolidation tanks.
<25% of 2k, 10k and 25k sites:
• Are manned permanently,
• Have sludge screening,
• Have dewatering facilities already
HUBER Technology UK – www.huber.co.uk
Slide 9
Potential limitations to upgrading
Infrequent attendance and the lack of sludge screening on many small to
medium sites mean that all process steps in any upgrade solution:
• Should be simple and not require regular attendance or operator
interaction.
• Should be robust against rags and process fluctuations without the need
for setting adjustments and not prone to spills (that won’t be immediately
cleared-up) should anything go wrong.
• Should be slow moving and physically robust so as to minimise the
likelihood of mechanical wear and failure (due to the potential delay in
maintenance staff being able to attend site to rectify the problem).
HUBER Technology UK – www.huber.co.uk
Slide 10
Potential limitations to upgrading
The physical size of small to medium sites and their potential remoteness
mean that all process steps in any upgrade solution:
• Should have a small footprint.
• Should require little power.
• Should require little or no water and should be able to make use of final
effluent rather than potable where water is needed.
• Should not add to the load at the inlet works by-way of a poor Solids Capture
Rate.
• Should have a relatively short-term payback period that justifies the site
upgrade when small sludge volumes are involved.
There may also be insufficient room for lorries to manoeuvre on the particularly
small sites.
HUBER Technology UK – www.huber.co.uk
Slide 11
Potential limitations to upgrading
Assuming that there is sufficient space, water and power for site
upgrading in the form a thickener and/or dewaterer:
• Some means of homogenizing the feed sludge and therefore preventing
stratification and “rat-holing” should be provided (so as to promote
efficient operation).
• In the case of upgrading to dewatering, some means of thickening the
raw sludge(s) should be provided so as to maximise cake dryness and
minimise the overall footprint.
• Cake storage facilities should have sufficient volume to cater for several
days without a lorry driver being able to get to site to remove the cake.
HUBER Technology UK – www.huber.co.uk
Slide 12
Huber solutions used for cost comparisons
These machines “tick the relevant boxes” on the previous slides.
Thickening for small to medium sites:
RoS2S Disc Thickener – Fully enclosed, very simple & slow moving, lowest
power demand, rigid screening medium with ragging-resistant ploughs, low
water demand and lowest poly consumption.
Dewatering for small to medium sites:
RoS3Q and RoS3 Screw Presses/Drum Dewaterers - Fully enclosed, very
simple & slow moving, low power demand, rigid screening medium, ragging
not an issue, low water and poly consumption.
RoS2S Disc
Thickener
RoS3Q Screw Press Dewaterer
(for smaller throughputs)
RoS3 Screw Press
Dewaterer
HUBER Technology UK – www.huber.co.uk
Slide 13
Cake handling solution used for comparisons
• Skips may not be the best solution (no means of evenly distributing cake if no
operator present, open to atmosphere, require specialist wagon for swapping
over and have limited volume).
• Agrivert’s cake silo and conveyor package is ideal if there is sufficient space
(for lorry movements as well). The smallest unit is for 60m3 BUT if the demand
is there they will look at including smaller units in their range (assumed costs
for 20 and 40 m3 units have been used in the comparisons).
Cake silo Lorry loading
HUBER Technology UK – www.huber.co.uk
Slide 14
Whole life cost comparison scenarios
We have considered the following scenarios for Co-settled sites:
• Leave the site as is (i.e. typically with a relatively inefficient consolidation
and inefficient tankering off-site) – this is the scenario that all other
Solutions will be compared against.
• Solution 1: Optimise the existing set-up (e.g. improve/install automatic
decanting and/or instal %DS monitoring on the PST de-sludging and
convert the consolidation tank to a mixing tank if possible.
• Solution 2: Solution 1 followed by Disc thickening and a mixed storage tank
(for ease of tanker pumping).
• Solution 3: Solution 1 followed by Screw Press dewatering and a cake
storage solution.
HUBER Technology UK – www.huber.co.uk
Slide 15
Whole life cost comparison scenarios
We have considered the following scenarios for Activated Sludge sites:
• Leave the site as is.
• Solution 1: Improve PST de-sludging & Disc thicken the SAS, pump both
thick sludges into a sufficiently large mixing buffer tank ready for removal
by tanker (it may be possible to use an existing consolidation tank if it is
large enough but we’ve assumed a new tank would be required as a worse
case).
• Solution 2: Improve PST de-sludging & Disc thicken the SAS, pump both
thick sludges into a sufficiently large mixing buffer tank (again, it may be
possible to use an existing consolidation tank but we’ve catered for a new
tank), dewater the mixed sludge by Screw Press followed by a cake
storage solution.
HUBER Technology UK – www.huber.co.uk
Slide 16
Scope of comparisons
Our whole life cost comparisons:
• Consider sites with Population Equivalents of 2,000, 10,000 and 25,000 so as
to tie-in with the UKWIR report.
• Consider Co-settling on 2,000 and 10,000 sites but consider both Co-settling
and an Activated Sludge process on 25,000 sites (as a result of the stats
provided in the UKWIR report).
• Have evaluated transport distances of 30, 40 and 50km.
• Have used both the disposal costs used in the UKWIR report and the
Alternative Costs provided by a water company.
• Have looked at the payback periods required to achieve savings when a cake
reception and re-wetting facility already exists and also how many sites would
need to be upgraded to achieve various payback periods if a new cake
reception and re-wetting facility had to be built (whilst considering the report
stats regarding how many sites are actually out there).
HUBER Technology UK – www.huber.co.uk
Slide 17
Assumptions and costs used
We have assumed:
• That as the site size increases, the effectiveness of the existing set-up (i.e.
consolidation tank) improves a little due to increased staff attendance (more
regular manual decanting/removal of blockages).
• That Huber kit have their 2 and 5 year spares replaced at those intervals.
• That overall sludge production is 65 gDS/PE/d in-line with the UKWIR report.
• That primary sludge production is 40 gDS/PE/d.
• That primary/co-settled sludge is typically at 1.25% DS and SAS is at 0.7%.
• That concrete hard standing and a building costs ~£100/m2
• That sludge storage tanks cost ~£100/m3
• That installing a mixer costs ~ £15k
• That a payback period of between 3 and 7 years would be required.
All CAPEX relating to proprietary equipment is obviously commercially sensitive
but has been based on actual order and quote prices for individual components
where possible.
HUBER Technology UK – www.huber.co.uk
Slide 18
Existing cake reception & re-wetting facility
Existing set-upOptimised
de-sludgingDisc thickening
Screw press
dewatering
Payback period
> 7 years
Payback period
≤ 7 years
Overall whole life
saving > 50%
Colour key for the following four tables:
HUBER Technology UK – www.huber.co.uk
Slide 19
Summary for 2,000 P.E. – Co-settled
Existing cake reception & re-wetting facility
Existing set-up: Partial thickening in
Consolidation tank
Solution 1: Transport after efficient
de-sludging (if viable)
Solution 2: All Disc thickened (to
5.5% DS max. for tankering) after
efficient de-sludging & mixer in
consolidation tank
Solution 3: Screw dewatering after
efficient de-sludging & mixer in
consolidation tank
Produced DS % 2 4.5 5.5 25
Weekly production rate m3/wk 46 20 17 4
OPEX £/yr £11,863 £5,272 £6,385 £3,309
Payback period Yrs NA 4 25 20
Expediture over 25 yrs £ £296,563 £131,806 £294,164 £245,315
Saving over 25 yrs % NA 56% 1% 17%
OPEX £/yr £14,804 £6,580 £5,369 £3,893
Payback period Yrs NA 4 14 15
Expediture over 25 yrs £ £370,110 £164,493 £317,183 £259,920
Saving over 25 yrs % NA 56% 14% 30%
OPEX £/yr £13,642 £6,063 £7,032 £3,451
Payback period Yrs NA 4 20 16
Expediture over 25 yrs £ £341,047 £151,576 £305,840 £248,874
Saving over 25 yrs % NA 56% 10% 27%
OPEX £/yr £17,651 £7,845 £6,401 £4,196
Payback period Yrs NA 3 12 13
Expediture over 25 yrs £ £441,285 £196,127 £343,002 £267,491
Saving over 25 yrs % NA 56% 22% 39%
OPEX £/yr £15,421 £6,854 £7,679 £3,593
Payback period Yrs NA 3 17 14
Expediture over 25 yrs £ £385,531 £171,347 £322,016 £252,433
Saving over 25 yrs % NA 56% 16% 35%
OPEX £/yr £20,498 £9,110 £7,434 £4,498
Payback period Yrs NA 3 11 11
Expediture over 25 yrs £ £512,460 £227,760 £368,808 £275,062
Saving over 25 yrs % NA 56% 28% 46%
UKWIR report costs
Alternative costs
UKWIR report costs
Alternative costs
30km transport distance
40km transport distance
50km transport distance
UKWIR report costs
Alternative costs
HUBER Technology UK – www.huber.co.uk
Slide 20
Summary for 10,000 P.E. – Co-settled
Existing cake reception & re-wetting facility
Existing set-up: Partial thickening in
Consolidation tank
Solution 1: Transport after efficient
de-sludging (if viable)
Solution 2: All Disc thickened (to
5.5% DS max. for tankering) after
efficient de-sludging & mixer in
consolidation tank
Solution 3: Screw dewatering after
efficient de-sludging & mixer in
consolidation tank
Produced DS % 2.5 4.5 5.5 25
Weekly production rate m3/wk 182 101 83 18
OPEX £/yr £47,450 £26,361 £25,551 £9,825
Payback period Yrs NA 2 8 6
Expediture over 25 yrs £ £1,186,250 £659,028 £800,902 £460,470
Saving over 25 yrs % NA 44% 32% 61%
OPEX £/yr £59,218 £32,899 £26,843 £12,746
Payback period Yrs NA 1 5 5
Expediture over 25 yrs £ £1,480,440 £822,467 £928,554 £533,491
Saving over 25 yrs % NA 44% 37% 64%
OPEX £/yr £54,568 £30,315 £28,786 £10,537
Payback period Yrs NA 2 6 5
Expediture over 25 yrs £ £1,364,188 £757,882 £871,282 £478,264
Saving over 25 yrs % NA 44% 36% 65%
OPEX £/yr £70,606 £39,225 £32,006 £14,260
Payback period Yrs NA 1 5 4
Expediture over 25 yrs £ £1,765,140 £980,633 £1,057,608 £571,347
Saving over 25 yrs % NA 44% 40% 68%
OPEX £/yr £61,685 £34,269 £32,022 £11,248
Payback period Yrs NA 1 6 5
Expediture over 25 yrs £ £1,542,125 £856,736 £952,163 £496,057
Saving over 25 yrs % NA 44% 38% 68%
OPEX £/yr £81,994 £45,552 £37,168 £15,774
Payback period Yrs NA 1 4 4
Expediture over 25 yrs £ £2,049,840 £1,138,800 £1,186,663 £609,203
Saving over 25 yrs % NA 44% 42% 70%
40km transport distance
UKWIR report costs
Alternative costs
50km transport distance
UKWIR report costs
Alternative costs
30km transport distance
UKWIR report costs
Alternative costs
HUBER Technology UK – www.huber.co.uk
Slide 21
Summary for 25,000 P.E. – Co-settled
Existing cake reception & re-wetting facility
Existing set-up: Partial thickening in
Consolidation tank
Solution 1: Transport after efficient
de-sludging (if viable)
Solution 2: All Disc thickened (to
5.5% DS max. for tankering) after
efficient de-sludging & mixer in
consolidation tank
Solution 3: Dewatering by Screw
Press after efficient de-sludging and
mixer installed in existing
consolidation tank
Produced DS % 3 4.5 5.5 25
Weekly production rate m3/wk 379 253 207 46
OPEX £/yr £98,854 £65,903 £61,507 £21,091
Payback period Yrs NA 1 5 4
Expediture over 25 yrs £ £2,471,354 £1,647,569 £1,708,311 £797,126
Saving over 25 yrs % NA 33% 31% 68%
OPEX £/yr £123,370 £82,247 £74,695 £28,393
Payback period Yrs NA 1 4 2
Expediture over 25 yrs £ £3,084,250 £2,056,167 £1,962,995 £979,678
Saving over 25 yrs % NA 33% 36% 68%
OPEX £/yr £113,682 £75,788 £69,596 £22,870
Payback period Yrs NA 1 4 3
Expediture over 25 yrs £ £2,842,057 £1,894,705 £1,893,513 £841,610
Saving over 25 yrs % NA 33% 33% 70%
OPEX £/yr £147,095 £98,063 £87,601 £32,179
Payback period Yrs NA 1 3 3
Expediture over 25 yrs £ £3,677,375 £2,451,583 £2,365,327 £1,074,318
Saving over 25 yrs % NA 33% 36% 71%
OPEX £/yr £128,510 £85,674 £77,684 £24,650
Payback period Yrs NA 1 3-4 3
Expediture over 25 yrs £ £3,212,760 £2,141,840 £2,095,715 £886,095
Saving over 25 yrs % NA 33% 35% 72%
OPEX £/yr £170,820 £113,880 £100,506 £35,964
Payback period Yrs NA 1 3 3
Expediture over 25 yrs £ £4,270,500 £2,847,000 £2,687,963 £1,168,958
Saving over 25 yrs % NA 33% 37% 73%
Alternative costs
UKWIR report costs
30km transport distance
Alternative costs
UKWIR report costs
50km transport distance
Alternative costs
UKWIR report costs
40km transport distance
HUBER Technology UK – www.huber.co.uk
Slide 22
Summary for 25,000 P.E. – Mixed
Existing cake reception & re-wetting facility
Existing set-up: Partial thickening in
Consolidation tank
Solution 1: Transport after efficient
Primary de-sludging and Disc
thickening of SAS
Solution 2: Screw dewatering after
efficient Primary de-sludging & Disc
thickening of SAS
Produced DS % 3 4.98 27
Weekly production rate m3/wk 379 228 42
OPEX £/yr £98,854 £63,927 £22,601
Payback period Yrs NA 5 6
Expediture over 25 yrs £ £2,471,354 £1,756,225 £1,061,946
Saving over 25 yrs % NA 29% 57%
OPEX £/yr £123,370 £78,699 £29,362
Payback period Yrs NA 4 5
Expediture over 25 yrs £ £3,084,250 £1,967,484 £1,230,976
Saving over 25 yrs % NA 36% 60%
OPEX £/yr £113,682 £72,862 £24,248
Payback period Yrs NA 4 5
Expediture over 25 yrs £ £2,842,057 £1,979,597 £1,103,135
Saving over 25 yrs % NA 30% 61%
OPEX £/yr £147,095 £92,995 £32,867
Payback period Yrs NA 3 4
Expediture over 25 yrs £ £3,677,375 £2,324,879 £1,318,605
Saving over 25 yrs % NA 37% 64%
OPEX £/yr £128,510 £81,797 £25,896
Payback period Yrs NA 4 5
Expediture over 25 yrs £ £3,212,760 £2,202,969 £1,144,324
Saving over 25 yrs % NA 31% 64%
OPEX £/yr £170,820 £107,291 £36,372
Payback period Yrs NA 3 4
Expediture over 25 yrs £ £4,270,500 £2,682,275 £1,406,235
Saving over 25 yrs % NA 37% 67%
UKWIR report costs
Alternative costs
30km transport distance
UKWIR report costs
Alternative costs
40km transport distance
UKWIR report costs
Alternative costs
50km transport distance
HUBER Technology UK – www.huber.co.uk
Slide 23
No. of 10k P.E. Co-settled satellite sites requiring installation of
dewaterers in order to provide an acceptable payback period.*
•Assuming the cake reception and re-wetting facility are built on a 30,000 tDS/annum sludge facility.
** Not feasible as in significantly more than 50 sites would require upgrading to having dewaterers.
UKWIR
disposal
costs
30km
Alt.
disposal
costs
30km
UKWIR
disposal
costs
40km
Alt.
disposal
costs
40km
UKWIR
disposal
costs
50km
Alt.
disposal
costs
50km
No. of plants to
give 7 yrs
payback
36 16 19 10 13 7
No. of plants to
give 6 yrs
payback
Not
feasible**27 35 14 20 10
No. of plants to
give 5 yrs
payback
Not
feasible**
Not
feasible**
Not
feasible**26 46 15
No. of plants to
give 4 yrs
payback
Not
feasible**
Not
feasible**
Not
feasible**
Not
feasible**
Not
feasible**34
No. of plants to
give 3 yrs
payback
Not
feasible **
Not
feasible **
Not
feasible **
Not
feasible **
Not
feasible **
Not
feasible **
No existing cake reception & re-wetting facility
HUBER Technology UK – www.huber.co.uk
Slide 24
No. of 25k P.E. Co-settled satellite sites requiring installation of
dewaterers in order to provide an acceptable payback period.*
•Assuming the cake reception and re-wetting facility are built on a 30,000 tDS/annum sludge facility.
** Not feasible as in significantly more than 50 sites would require upgrading to having dewaterers.
UKWIR
disposal
costs
30km
Alt.
disposal
costs
30km
UKWIR
disposal
costs
40km
Alt.
disposal
costs
40km
UKWIR
disposal
costs
50km
Alt.
disposal
costs
50km
No. of plants to
give 7 yrs
payback
7 5 5 4 4 3
No. of plants to
give 6 yrs
payback
9 6 7 5 5 4
No. of plants to
give 5 yrs
payback
15 9 10 6 7 5
No. of plants to
give 4 yrs
payback
42 16 19 9 12 7
No. of plants to
give 3 yrs
payback
Not
feasible **
Not
feasible **
Not
feasible **23 41 13
No existing cake reception & re-wetting facility
HUBER Technology UK – www.huber.co.uk
Slide 25
No. of 25k P.E. Primary & SAS satellite sites requiring installation
of dewaterers in order to provide an acceptable payback period.*
•Assuming the cake reception and re-wetting facility are built on a 30,000 tDS/annum sludge facility.
** Not feasible as in significantly more than 50 sites would require upgrading to having dewaterers.
UKWIR
disposal
costs
30km
Alt.
disposal
costs
30km
UKWIR
disposal
costs
40km
Alt.
disposal
costs
40km
UKWIR
disposal
costs
50km
Alt.
disposal
costs
50km
No. of plants to
give 7 yrs
payback
6 5 5 4 4 3
No. of plants to
give 6 yrs
payback
8 6 6 4 5 4
No. of plants to
give 5 yrs
payback
13 8 9 6 7 4
No. of plants to
give 4 yrs
payback
29 13 16 9 11 6
No. of plants to
give 3 yrs
payback
Not
feasible **46
Not
feasible **18 27 11
No existing cake reception & re-wetting facility
HUBER Technology UK – www.huber.co.uk
Slide 26
Conclusions
Thickening or dewatering on 2k P.E. sites is not viable – customers should aim at
improving PST de-sludging and/or consolidation tank decanting instead (where
feasible).
Where the regional sludge reception/AAD plant already has a cake reception and
re-wetting facility:
• Disc thickening on 10,000 P.E. satellite sites (40+km) and 25,000 P.E. satellite
sites (30+km) is viable, having a payback period of ≤ 6 years and an overall
whole life cost saving of ≥ 31%.
• Screw Press dewatering on 10,000+ P.E. satellite sites is viable with a payback
period of ≤ 5-6 years for 30+km transport distances and ≤ 4-5 years for 40+km.
The overall whole life cost saving is ≥ 61%.
HUBER Technology UK – www.huber.co.uk
Slide 27
Conclusions cont.
Where a new cake reception and re-wetting facility is required to be built at the
regional sludge reception/AAD plant:
• A payback period of ≤ 7 years is possible providing a sufficient number of
10,000+ P.E. sites are upgraded to include Screw Press dewatering.
• A payback period of ≤ 4 years is possible providing a sufficient number of
25,000+ P.E. sites are upgraded to include Screw Press dewatering.
In all instances, the payback period reduces and the overall saving increases
as transport distance and P.E. increase. Actual payback periods and savings
may vary depending on the customer’s own disposal costs.
HUBER Technology UK – www.huber.co.uk
Slide 28
Acknowledgements
Martin Jolly
Richard Murray
David Robson
HUBER Technology UK – www.huber.co.uk
Slide 29
References
1) Chapman, K., Newton, J. And Van de Moortel, J., Sustainable sludge
thickening and treatment at small WwTWs, UKWIR
2) Jolly, M. and Knight, G., Commissioning Of Davyhulme Thermal Hydrolysis
Plant, 17th European Biosolids & Organic resource Conference Proceedings
3) Rawlinson, D. and Oliver. B., New Thermal Advanced Digestion plant at
Northumbrian Water’s Howdon works, 17th European Biosolids & Organic
resource Conference Proceedings
4) Wilson, S., Brown, R., Oliver, B. and Merry, J., Operational experience with
Thermal Advanced Digestion in Dwr Cymru Welsh Water, 17th European
Biosolids & Organic resource Conference Proceedings
5) Skelton, H. and Depala, P., Controlling the thickness of sludge at source,
17th European Biosolids & Organic resource Conference Proceedings
6) Tchobanoglous, G. and Burton,. F., Wastewater Engineering: Treatment,
Disposal, and Reuse, Metcalf and Eddy, Inc., 3rd Edition, McGraw Hill, Inc.
Metcalf and Eddy
HUBER Technology UK – www.huber.co.uk
Slide 30
Any questions?
Jason Sims: [email protected]
Huber Technology UK
Units C&D Brunel Park
Bumpers Farm Industrial Estate
Chippenham
Wiltshire - SN14 6NQ
Tel. +44 (0)1249 765000
Fax +44 (0)1249 449076
E-mail: [email protected]
Website: www.huber.co.uk
Thank you for your attention