in partnership with palangoy gospel church etwf church and training centre
TRANSCRIPT
In Partnership with Palangoy Gospel
Church
ETWF Church and Training Centre
REMITTANCE - TAYUMAN PROJECT (August 2011 – March 2012 )
Date Detail Sin $ Ph Pesos
15-Aug-11 Building Cost 85,964.89 3,000,000.00
22-Aug-11 Building Cost 86,087.90 3,000,000.00
4-Nov-11 Building Cost 88,893.89 3,000,000.00
20-Mar-12 Building Cost 59,612.52 2,000,000.00
Sub Total 320,559.20 11,000,000.00 EXPENSES - TAYUMAN PROJECT (August 2011 - March 2012 )
Date Detail Ph Pesos Balance
30-Aug-11 Building Permit Fees 43,572.20 10,956,427.80
1-Sep-11 Claim Form 1 100,000.00 10,856,427.80
7-Sep-11 Claim Form 2 300,000.00 10,556,427.80
12-Sep-11 Claim Form 3 800,000.00 9,756,427.80
20-Sep-11 Claim Form 4 800,000.00 8,956,427.80
29-Sep-11 Claim Form 5 800,000.00 8,156,427.80
30-Sep-11 Edgar's Salary - September 2011 11,000.00 8,145,427.80
7-Oct-11 Claim Form 6 800,000.00 7,345,427.80
20-Oct-11 Claim Form 7 1,400,000.00 5,945,427.80
30-Oct-11 Edgar's Salary - October 2011 13,750.00 5,931,677.80
30-Nov-11 Edgar's Salary - November 2011 12,000.00 5,919,677.80
10-Dec-11 Claim Form 8 1,000,000.00 4,919,677.80
2-Jan-12 Edgar's Salary - December 2011 12,000.00 4,907,677.80
6-Jan-12 Claim Form 9 1,000,000.00 3,907,677.80
1-Feb-12 Edgar's Salary - January 2012 12,000.00 3,895,677.80
20-Feb-12 Claim Form 10 1,000,000.00 2,895,677.80
1-Mar-12 Edgar's Salary - February 2012 12,000.00 2,883,677.80
Total 8,116,322.20 2,883,677.80
BUILDING FUND (April 2012 )Date Detail Sin $ Balance
14-Jan-12Philippines Building Fund (Target:
$350,000.00) 350,000.00
LESS REMITTANCES:
15-Aug-11 (1) Building Cost 85,964.89 264,035.11
22-Aug-11 (2) Building Cost 86,087.90 177,947.21
4-Nov-11 (3) Building Cost 88,893.89 89,053.32
20-Mar-12 (4) Building Cost 59,612.52 29,440.80
TBD (5) Furnishing Cost (PA System and Chairs) 29,440.80
PA System
$16,348.00
Chairs
$10,800.00
Total
$27,148.00
50% Building = Second Storey + Roof FrameStructure
80% Building = Roof + Tiles + PaintingStructure
100% Building = Fully Completed + TOPStructure
FRONT GATE
FRONT GARDEN
BACK PERIMETER
SIDE PERIMETER
CHAPEL AT DUSK
THE SANCTUARY - LEFT
THE SANCTUARY - CENTER
THE SANCTUARY - RIGHT
THE SANCTUARY - FRONT ENTRANCE
THE SANCTUARY - BACK ENTRANCE
FIRST FLOOR TOILETS OFFICE
ENTRANCE TO FRONT STAIRS
FRONT STAIRS
BEDROOM 3
MASTER ROOM KITCHEN
MASTER ROOM
SECOND FLOOR MEN TOILET
SECOND FLOOR WOMEN TOILET
IRENE IS STILL DECIDING ON THE PARTITION
THE ROOF DECK CANOPY
BEDROOM 2
BACK STAIRS
BACK DOOR
PRAYER Items:1.No Delay or Disruption,
2.Safety and Good Weather,3.Thanksgiving for providing
funds,4.Salvation of Construction
Workers ,5.Good Working Relationship,
6.PA System and Chairs,7. Built Within Budget,
8.Godspeed .