incident analysis simple (edc
TRANSCRIPT
-
8/3/2019 Incident Analysis Simple (EDC
1/21
-
8/3/2019 Incident Analysis Simple (EDC
2/21
Over All leakage Trend
EDC/VCM (Jan-June)
0
10
20
30
40
50
60
70
JanFeb
MarApr
May
Jun
51
4240
46
69
25
Overall Half yearly Incident bar chart
Jan
FebMar
Apr
May
Jun
Incidents in
months , 25
0
10
20
30
40
50
60
70
80
Jan Feb Mar Apr May Jun
NoofIncidents
Trend of Incidents over last 06 months
Jan 51
Feb 42
Mar 40
Apr 46May 69
Jun 25
Total 273
Months No Of Leakages
Most vulnerable month
Reason (Continuous
shutdown from Jan to may
summary pasted below till
may)
Shutdowns Summary
3 - 18 Jan (Fur / Oxy) (16 days)
1 - 30 Mar (Fur / Oxy) (30 days)
1 - 5 Apr (Fur / Oxy) (5 days)
6 - 10 Apr (Fur / Oxy) (5 days)
15 - 17 Apr (Fur / Oxy) (3 days)
28 - 30 Apr (Fur / Oxy) (3 days)
4 - 6 May (FurA) (3 days)
4 May - 19 Jun (Fur B) (15 days)
Total65days shutdown prior to the month of MAY which lead to fatigue and other
factors leading to incidents and if may shut down also included it goes to more then
100 days of shutdown
In next slide we will see the break down of theses incidents which will give a better
insight of the problems
-
8/3/2019 Incident Analysis Simple (EDC
3/21
EDC-VCM Incidents Monthly TrendJan Feb Mar Apr May JunNear misses 47 38 37 41 64 23
FAC 1 1 1
MTC 1
Process release 1 1
Operational upset 1 1 1
Process Incident 4 2 2 2 1
Fire 2
Env release 1
Total 51 42 40 46 69 24
0
10
20
30
40
50
60
70
Jan Feb Mar AprMay Jun
51
4240 46
69
25
No
ofIncidents
No of month
0
10
20
30
40
50
60
70
JanFeb
MarApr
May
Jun
47
38
3741
64
23
1
11
11
1
1
1
1
4
2
2
2
1
2
1
No
ofIncide
nts
Months
Incident Monthly break down To Types
near misses
FAC
MTC
Process release
operational upset
Process Incident
Fire
Envc release
Incidents Trend
High no of near misses are due to higher no
of leakages in the plant
May has highest no incidents then any other
months due high leakages in this month also for
reference see section of leakages latter
There are 03 operational upset in last six
months 01 cause shut down which was in April
rest of the 02 were in startup phase
-
8/3/2019 Incident Analysis Simple (EDC
4/21
45
46
47
48
49
50
51
Jan
47
1
1
1
1
operation
al upset
Process
release
MTC
FAC
near
misses
35
36
37
38
39
40
Mar
37
1
2
process
incident
operation
al upset
Nearmiss
38
39
40
41
42
43
44
45
46
Apr
41
1
2
1
1 FAC
process
release
process
incident
operational
upset
near miss
61
62
63
64
65
66
67
68
69
May
64
2
2
1
FAC
Fire
Pricess
Incident
Near miss
22
22.5
23
23.5
24
24.5
25
Jun
23
1
1
Env
Process Incident
Near miss
36
37
38
39
40
41
42
Feb
38
4
Process
Incident
near
misses
Incidents break down per month
-
8/3/2019 Incident Analysis Simple (EDC
5/21
0
10
20
30
40
50
60
70
80
90
Ops Maint Inspection I&E Others sharedresponsibilites
18
37
78
52
88
NoofIncidents
Incidents distribution on basis of dept responsible
6%13%
29%
19%
33%
Incidents distribution
w.r.t departments
Ops
Maint
Inspection
I&E
Others(multiple
discpline)
06 % of the total incidents that
were purely operation related
(which has 03 operational
upsets 01 process incident)
Most of the incidents are based on leakages at different points which led to a higher no of incidents in inspection department which has 78 no of
incidents (29%)
Rest others include shared responsibilities of misc group
2nd most vulnerable department in case of incidents is I&E which shares 19% of all incidents that took place at EDC/VCM plant
Pure operational related incidents are fewer then any other department but are critical as well room of improvement is there
-
8/3/2019 Incident Analysis Simple (EDC
6/21
1%
1%
1%
4%
1%
Nearmiss;
92%
Distribution of incidents type
Env Incident FAC
Fire MTC
Operational upset Process Incident
1, 4%
3, 13%
2, 9%
1, 4%3, 13%
11, 48%
2, 9%
Percentage of Incidents excluding Nearmiss
Env Incident
FAC
Fire
MTC
Operational upset
Process Incident
Process release
0
2
4
6
8
10
12
1
3
2
1
3
11
2
Env Incident FAC Fire MTCOperational
upset
Process
Incident
Process
release
No of leakags 1 3 2 1 3 11 2
Incidents bar graph as per type
Distribution of Process w.r.t
dept responsible
Near misses accounts for almost 92 percent of all incidents which lead to
other critical incidents needs to be control in future to a lesser extent
If we exclude Near misses largest no of incidents that took place are Processincidents total 11 (48%) out of which 08 are related to I&E and 03 to
operations
8
3
I&E Ops
-
8/3/2019 Incident Analysis Simple (EDC
7/21
Inadequate , 4
Proceduer not
followed, 17
Not available , 21
4
10
2
4
6
8
10
12
14
16
18
Inadequate Proceduer not followed Not available
No
ofIncidents
Category
Total (alldept.)Ops related
0
5
10
15
20
25
Inadequate Proceduer
not followed
Not available
4
17
2
1
4
1
Ops related
Total (alldept.)
4, 17%
Proceduer not
followed, 74%
2, 9%
Inadequate
Proceduer not followed
Not available
Procedure related Incidents
16%
Proceduer not
followed, 67%
17%
Procedure related incidents distribution(Operation )
inadequate
Proceduer not
followed
Not available
Procedure related incidents distribution
On analysis its shown that training on procedures and its ease of availability
is required to over come the not following part and already emphasis on internal
grooming is being taken care at EDC/VCM Plant
74% are the incidents related to procedures which are not being followedsimilarly 67% is the share in ops distribution of these incidents
Procedure not followed has a
huge share both in ops and all
other departments forincidents related
No of incidents comparison of
ops vs other departments
-
8/3/2019 Incident Analysis Simple (EDC
8/21
11-20% 20-36% 50-65% 70-85% 90-100% 105-120% 125-135%
27
11
161
48
10 7 3
Incidents distribution on the basis of score
allotted
11-20% 20-36% 50-65% 70-85% 90-100% 105-120% 125-135%
10%
4%
60%
18%
4% 3% 1%
Pie chart showing percentage of most
incidents as per rated score
11-20%
20-36%
50-65%
70-85%
90-100%
105-120%
125-135%
Almost of all the total score given to all incident lies in
the category of 50-60% and 70-85% which contributes
almost 78% of the all the incidents that occur during
last 06 months
High percentage of
incidents score lies in the
middle to top score
category which is alarming
as 88 % of all the whole
incidents lies in category in
between50-100%
Above charts indicate to have strong analysis of all those incidents lying in this score and formulating a way to minimize them and
their reoccurrence should not occur at any stage
Need to focus on major part of these incidents which is the middle portion also safety department to give feedback on these
-
8/3/2019 Incident Analysis Simple (EDC
9/21
0
2
4
6
8
10
12
14
16
Careless act Judgement Lack of
communication
16
11
13
2
3 3
Chart Title
All dept. Ops
0
10
20
30
40
50
60
70
80
90
100
normal
Operation
Plant start up Plant shutdown Commissioning
100
13
31
1
7
16
1
Events at which incidents occur most
Misc dept Ops
Incidents distribution on personnel behavior
Personnel issue(requirestraining)
Carless act
Judgment error
Lack ofcommunication
Most of the incidents that are
related to plant shutdown are
indicative of physical and mental
tirdness which includes slipping of
blind, injuries etc
Normal operation has high no
of incidents due to leakages
involved thats why score of
other dept is high as compared
to ops
-
8/3/2019 Incident Analysis Simple (EDC
10/21
0
10
20
30
40
50
60
70
PSI PHA O&MP SWP PSSR MI QA PT&P E&RP auditing
5
10
55
38
7
68
33
21
1 12 1
8 8
0 0
6
1 1 1
Total (all dept)
Ops
PSI2%
PHA
4%O&MP
23%
SWP16%
PSSR3% MI
29%
QA
14%
PT&P
9%
E&RP
0%auditing
0%
PSRM basis distribution of incidents (All dept)
PSI
7%
PHA
3%O&MP29%
SWP
29%
PSSR
0%
MI
0%QA
21%
PT&P3% E&RP
4% auditing4%
Are high due to high
number leakages on
the plant and
Safe work practices are align with
operation and maintenance
procedure both PSRM violations
are high and critical also
operation related incidents
major contributor s
Ops distribution of incidents indicating
area of concern is procedures and safe
work practices
Ops distribution of Incidents on PSRM violation
PSRM wise distribution of incidents
-
8/3/2019 Incident Analysis Simple (EDC
11/21
0
20
40
60
80
100
120
140
Fire in
furnace B
Gr-301
Tripping
Gr-301
Tripping
Partial power
faliuer
Oxy leakage
inlet line
Gr-301
Tripping
Steam gasket
rupture Lp
header
High
Acetylene in
MS-304
High moisture
in MS-403
Partial power
faliuer
(Transformer
1 Tripping)Incident 135 125 125 120 120 110 105 105 105 105
135125
125
120
120
110
105
105 105
105
Incidentscore
Area 300
Cause
MI
Resp
ALL
Area 300
Electrical
Issue
Resp
I&E
Top 10 Incidents at EDC/VCM Plant on basis of Score
Oxyinletleakagecausing
shutdownofpla
nt
Area 300
Electrical
Issue
Resp
I&E
Area
300
Electric
al
Issue
Resp
I&E
Area 300
Ops Upset
TT-306B
MI issue
tube
failure
Resp Ops
Sub station
Electrical
Issue
Resp
I&E
Sub Station
Electrical
Issue
Resp
I&E
Area 200
Process
release
MI issue
Resp
ME /INSP
Area 400
Ops
Upset
At start
up of
Area 200
Resp Ops
Area
400
Ops
Upset
LT issue
Resp
Ops/I&E
-
8/3/2019 Incident Analysis Simple (EDC
12/21
54, 77%
15, 21%
1, 2%
Distribution Of Leakages As Per Identity
MECHNICAL
INSTRUMENT
MACHINERY
1. Total no of leakages 70 in last 04 months till 2nd June
2. Average leak per months 18
3. 77% (54) of leakages occur on mechanical part of the plant that is 54 out of 70
4. 21% are leakages are due instrumentation of plant that is 15 leakages out of 70
-
8/3/2019 Incident Analysis Simple (EDC
13/21
1% 1% 1% 1% 1%3%
3%3%
3%
4%
4%
4%
CONNECTOR , 6%
tubing , 7%FLANGES, 11%
VALVES, 15%
Piping, 30%
seal
RD holder
PG
vessel
Purge point
FT mainifold
Burner assembly
GLG
Switches
GASKIT
BELLOW
Head cover (Exchanger)
CONNECTOR
tubing
FLANGES
VALVES
Piping
Vulnerable parts prone to leakages:-
The most prone part where leakages occur is process piping including fitting T-joints elbows etc which accounts for 30% of the total
leakages
Second most vulnerable area are Valves where leakages report goes to 15% and subsequently flanges has 11% and instrument
tubing connector 7% of the total leakages that occur during past four months
Parts prone to leakages
Distribution of leak points
-
8/3/2019 Incident Analysis Simple (EDC
14/21
Service where most of the leakages occur during last 04 month are
1. EDC
2. HCL &
3. Mix of EDC/HCL/VCM
0
5
10
15
20
25
1 1 1 23 3 4 4
6
10
13
22
No
ofleakages
Chemical Released
No of leakages due to serviceMost leaking services
-
8/3/2019 Incident Analysis Simple (EDC
15/21
2% 1% 1%3%
4%
4%
6%
6%
9%
Mix of EDC HCL VCM
, 14%
HCL, 19%
EDC , 31%
CL2
waste water EDC
carbon material
VCM
HeaviesVCM HCL
Cautic NaOH
10% HCL
Low Ph water
Mix of EDC HCL VCM
HCL
EDC
Break of leakages as per
Service released1. EDC accounts for more then
30% of the leakages that
occurred during last 04 months
out of total 70 leakages 22
leakages occurred at EDC
service then most highly leaking
service is pure HCL which has a
share of19% of the total
leakages that is 13 leakages out
of 70
2. In addition both HCL and EDC
accounts for 50% leakages that
occurred in EDC/VCM plant
and if mix ofEDC/HCL ANDVCM is taken in account it goes
to 60%
Distribution of leakages as per service leak
Area of
concern
hl k d
-
8/3/2019 Incident Analysis Simple (EDC
16/21
Monthly Leakages Trend
Shut down
Period Furnace A/B&oxy both
(Thats why ratio of
leakages are
minimum)
Reasons for High no Of leakages in MAY:-
MAY has the most no of leakages and June has also potential for high no of leakages month,
May apart from furnace incident has been running normal there are 3 major reason for high no of leakages in MAY
1. Plant was running no major shutdown apart from furnace fire
2. April has seen no of shutdown startups which resultantly effect the operation of MAY and increase leakages
3. 11th may high CL2 after which 05 Leakages occur at wash train before that only 01 leakage was reported
4. June also saw an equal amount of leakages including area 100/200 and area 900 as bulk of it
Shutdowns Summary
3 - 18 Jan (Fur / Oxy)
1 - 30 Mar (Fur / Oxy)1 - 5 Apr (Fur / Oxy)
6 - 10 Apr (Fur / Oxy)
15 - 17 Apr (Fur / Oxy)
28 - 30 Apr (Fur / Oxy)
4 - 6 May (FurA)
4 May - 19 Jun (Furnace B)
0
5
10
15
20
25
FEB MARCH APRIL MAY JUNE
0
5
10
15
20
25
JANFEB
MARCHAPRIL
MAYJUNE
20
16
9
16
21 21
Months 2011
-
8/3/2019 Incident Analysis Simple (EDC
17/21
Area -800
3%
Area -4004%
Area -200
12%
Area -600
11%Area -300
19%
Area -900
20%
Area -100
31%
Leakages distribution area wise
050 2281338214
14
8
Area 100 leakages break up
LTCA/B
periphery
wash train circuit
which contains
highest no of
leakages
AREAS HAVING HIGH RATE OF LEAKGES :-
1. A-100 is the most gray area where leakages has occurred time to time andparticularly wash train circuit which accounts for 63% of area100 leakages
2. Second most vulnerable areas include A-900 and A-300 which accounts for
20% and 19% of the total leakages combining these areas70% of the leakages
occur in A-100/300/900
-
8/3/2019 Incident Analysis Simple (EDC
18/21
0
5
10
15
20
25
Area -
100
Area -
200
Area -
300
Area -
400
Area -
600
Area -
800
Area -
900
22
8
13
3
8
2
14
Total
no of
leakages
Leakages at
AS-302 and its circuitLeakage on
overhead
circuit
13 7 (out of 0704 on Reflux circuit of
PP-302)
4 are on
over head
circuit
Total At Ko pots At backend
14 06
at ko-pots
06
backend area
Break up of Area-900 leakages
Break up of Area-300 leakages
(remaining 02 leakages at furnace side)
Remaining 02 leakages at burner assembly
2nd and 3rd most vulnerable areas are A-900 and A-300 respectively
Areas Most Prone to leakages and their break down
Top 03 most leakage
vulnerable areas
1. Area 100
2. Area 900
3. Area 300
-
8/3/2019 Incident Analysis Simple (EDC
19/21
0
1
2
3
4
5
6
7
8
9
10
HCL feed line toOxy Reactor tie in
leakage from PP101 B suction and
PP 101 A/B
common
discharge lines
and valve body
Heavy causticleakage gaskit
rupture
PP-302 A seal oilpot level grass
breaks
Bullet C SV upstream spool
clamped
leakage
Priming valve PP-302A (gland
leakage)
02 pin holes at PP101 A/B
circulation
line isolation
valve to MS 103
10m
8m
6.25m
5m
4m 4m
3m
Heavy leakages but
control without any
abnormality
Top Seven heavy leakages in EDC/VCM Plant
(last 04 months on the basis of extent of leakage)
Extentofleakage
Meter(m)
Description Of Leakage
A-200
A-100
A-100
A-300A-600
A-300
A-800
-
8/3/2019 Incident Analysis Simple (EDC
20/21
Recommendation of Analysis
Incidents that occur repeatedly should have high score then previously allotted for example
GR-301 Tripping on the same cause (control power issue) was scored 125 on all the three occasion
it occurred
1. 3-Feb -11
2. 7-Mar -11
3. 14-Jun -11 For such incidents Quality of B-report should also be check by Safety Department
(Resp Safety)
On the basis of these Incidents analysis Training on procedures and their availability to be ensured
(Resp All interfaces)
Refresher of SWP , OMP, MI and other high violated PSRM to be conducted
(Resp Safety, relevant dept)
PM plans and Inspection plan of all equipment to be shared and should address chronic and
problematic areas like A-100/800-900/300
(Resp Inspection)
-
8/3/2019 Incident Analysis Simple (EDC
21/21
Physical tiredness long shutdowns and continuous duties in these runs should be dealt with care in order to minimize the fatigueand mental tiredness of a employee esp. Maintenance person who works on 6 duty 1 rest Rota
On normal plant run leakages have been most choronic issue which led to high no of incidents where as shutdowns and start upseems to have process related issue as well as injuries issue
Most
21 TR done out of 70 leakages that is 30% of the total it is recommended to keep a close look at each TR done as in bullet C case atemporary repair was done on 11th April and after 8days a heavy leakage occur on bullet C same point from clamp, it is highlyrecommended to check integrity of such clamps and TR
Bullet C inlet manifold has 03 leakages during last 04 months which has a high probability of exposure to corrosive material asquench filters are deacon here all such circuits to be marked and highlighted and Inspection to be done
30% of leaks has occurred in process piping along with that other major 02 leak points are VALVES AND FLANGES there PM
plan to be revised and its effectiveness to be checked thoroughly as its is causing 26% of the total leaky points
THE END