independent office of evaluation the gambia country programme evaluation 2015: main findings and...
TRANSCRIPT
Independent Office of Evaluation
The Gambia Country Programme Evaluation 2015:Main Findings and Recommendations
National Roundtable WorkshopBanjul, 3 December 2015
Independent Office of Evaluation
Total number of approved loans: 10 (since 1982)
Total value of portfolio: US$ 196.8 million
IFAD contribution: US$ 73.1 million; counterpart funding (contribution from Government and beneficiaries): US$ 24.1 million
Co-financing: US$ 99.5 million
On-going projects: 6
CPE covers IFAD – The Gambia partnership from 2004-2014, and looked at 5 projects, the COSOP 2003, and country programme management
IFAD – The Gambia cooperation highlights
- 2 -
Independent Office of Evaluation
Objectives
Assess the performance and impact of IFAD-supported operations in The Gambia
Generate conclusions and recommendations to enhance the effectiveness, rural poverty impact and sustainability and inform the preparation of the next COSOP for The Gambia
MethodologyCPE assesses: (i) project portfolio; (ii) non-lending activities including grants and SSTC; (iii) performance of the COSOP
A variety of data collection methods used and triangulation; pre-planned field visits to purposively selected sites
Evaluation objectives/methodology
- 3 -
Independent Office of Evaluation
Preparatory phase (December 2014): approach paper and preparatory mission
Desk review (January-March): preparation of desk review notes, identification of hypotheses and issues to explored in the course of the evaluation
CPE main mission (April 2015): a multidisciplinary team of experts visited all current projects and held a wrap up mission in Banjul
Analysis, report writing and peer review (May-September)
CPE national roundtable workshop (December 2015)
Evaluation process
- 4 -
Independent Office of Evaluation
General
IFAD-Government partnership has been highly valued, reflecting mutual trust and cordial relations
IFAD supported interventions demonstrated a moderate performance, caused by among others lack of varied partnerships and unexpected staff turnover
Main findings
- 5 -
Independent Office of Evaluation
The country strategy The COSOP 2003 had provided a strategic framework, defining the context in which project designs were undertaken was clear, and highlighting the existing challenges.
The COSOP 2003 had been unofficially revised but never been approved or adopted (by IFAD or Government); after 12 years it was probably outdated
The COSOP did not comprise a detailed target strategy, taking into account characteristics of target groups and unequal distribution of poverty
Main findings (cont.)
- 6 -
Independent Office of Evaluation
The project portfolio
The interventions were all found relevant, on water management, crop production and rural finance. An additional focus on climate change is already planned
A large number of outputs was achieved, but an integrated approach was lacking. Support to value chain development was planned but hardly implemented
The introduction of the CPA enhanced understanding, but linkage between projects was virtually absent
.
Main findings (cont.)
- 7 -
Independent Office of Evaluation
The project portfolio The interventions helped women to increase their
economic empowerment, but no effort was made to decrease drudgery
Rural poverty impact was varying and better in upland than in lowland areas
Though there has been increasing focus on sustainability over the years, it was still found compromised in all projects
Main findings (cont.)
- 8 -
Independent Office of Evaluation
Non-lending activities In policy dialogue, IFAD focused on microfinance policy,
integrated watershed management and master plan for the lowlands
Knowledge management was sub-optimal
Partnership was with a limited number of Ministries and NGOs were seen as service providers (although rarely used)
Though focus of grants was relevant, they had very little linkage with the project portfolio
Main findings (cont.)
- 9 -
Independent Office of Evaluation
Programme management
Establishing CPCU brought improvement to coordination and implementation, but lack of full engagement of donors hampered its effectiveness
Staff turnover decreased effectiveness and efficiency and deleted institutional memory
Though slow improvement seem, still challenges in setting up M&E systems and application of RIMS – particularly for outcome and impact
Main findings (cont.)
- 10 -
Independent Office of Evaluation
The selected targeting approach led to some better off villages being covered whilst poorer remote villages did not receive support in any of the projects
The type of infrastructure provided by PIWAMP did not encourage ownership for the hard work needed and short life span. Nema infrastructure is more sturdy but too sophisticated for communities to maintain and costly for maintenance
Sustainability in rural finance was compromised; only few VISACAs are stable and the V-Apex needs support to become a viable institution
Five main conclusions
- 11 -
Independent Office of Evaluation
Major focus on rice as crop and lack of value chain development support hindered beneficiaries to achieve full profitability or sustainability
If IFAD had consider a wider and more diversified partner group, this could have positively contributed to the quality of implementation
Five main conclusions (cont.)
- 12 -
Independent Office of Evaluation
Three strategic recommendations
- 13 -
1
2
3
Independent Office of Evaluation
Agreement at Completion Point 2015
Final CPE report published 2016
Discussion in IFAD Evaluation Committee 2016
Discussion in IFAD Executive Board 2016
Next steps in the CPE
- 14 -
Independent Office of Evaluation
Thank you very much for your attention
- 15 -