indian creek plant cim 6 21 13 - pentacles...

25
Indian Creek Plant Confidential Information Memorandum June 2013 June 21, 2013

Upload: dangtruc

Post on 07-Apr-2018

216 views

Category:

Documents


3 download

TRANSCRIPT

 Indian  Creek  Plant  

Confidential  Information  Memorandum    

June  2013  

 

June  21,  2013  

DISCLAIMER

This   Confidential   Investment  Memorandum   (“CIM”)   has   been  prepared  by   Pentacles   Electric,  LLLP   (“Pentacles”   or   “Seller”)   for   delivery,   on   a   confidential   basis,   to   a   limited   number   of  institutional   lenders   and   investors   (“Investor”)   solely   for   use   in   considering   whether   to  participate  in  the  development  and  ownership  (“Investment”)  of  a  simple  cycle  natural  gas  fired  power  generating  facility  located  in  Morgan  County,  TN.    

Neither   Seller   nor   any   affiliate   assumes   any   responsibility   for   and   none   make   any  representation  as  to  the  adequacy,  accuracy,  or  completeness  of  any  information  contained  in  this  CIM.  Each  expressly  disclaims  any  and  all   liability   for  such   information,   including,  without  limitation,   any   analysis,   forward   looking   statements   or   representations,   express   or   limited,  contained   herein   or   for   any   omission   from   such   information.   Nothing   in   this   CIM   should   be  construed  as  legal,  financial,  accounting,  or  tax  advice.  Each  prospective  Investor  should  consult  its   own   professional   advisors   as   to   legal,   investment,   tax,   accounting   and   related   matters  concerning  an  Investment.    

The  Investment  described  in  this  CIM  has  not  been  registered  under  the  Securities  Act  of  1933,  as  amended  (the  “Act”),  or  under  the  securities  laws  of  any  state,  in  reliance  upon  exemptions  from   the   registration   requirements   of   such   laws.   The   Investment   is   being   offered   only   to  accredited  investors  and  must  be  purchased  for  investment  purposes  only  and  not  with  a  view  to   further   distribution.   Furthermore,   the   Investment   may   not   be   sold   or   transferred   unless  subsequently   registered   under   the   Act   and   under   relevant   state   securities   laws,   unless  exemptions  from  registration  are  available.  It   is  not  anticipated  that  the  Investment  will  be  so  registered.  

By   accepting   delivery   of   this   CIM,   each   recipient   agrees   (a)   it   will   not   copy   or   otherwise  reproduce   it,   or   distribute   it   to   any   other   person   or   party   (including   any   employee   of   the  recipient  other  than  an  employee  directly  involved  in  reviewing  or  analyzing  the  Investment),  in  whole   or   in   part,   at   any   time   without   the   prior   written   consent   of   Seller,   (b)   it   will   keep  permanently  confidential  all  information  contained  herein  not  already  public  and  (c)  it  will  use  this  CIM  only  for  the  purpose  set  forth.  

Seller   requests   that   this   CIM,   as   well   as   all   authorized   copies,   be   returned   to   Seller   by   any  recipient  that  chooses  not  to  participate  in  the  proposed  transaction.  

Table  of  Contents    Executive  Summary  ......................................................................................................................................  1  

Project  Team  ................................................................................................................................................  3  

About  Pentacles  Electric,  LLLP  .....................................................................................................................  4  

Indian  Creek  Plant  Summary  .......................................................................................................................  6  

Site  Description  .........................................................................................................................................  6  

Equipment  and  Project  Operating  Information  ........................................................................................  7  

Permitting  Overview  .................................................................................................................................  7  

Electric  Transmission  Interconnection  ......................................................................................................  8  

Natural  Gas  Interconnection  &  Delivery  Optionality  ................................................................................  9  

Operations  and  Maintenance  Plan  .........................................................................................................  12  

Summary  of  Project  Benefits  ..................................................................................................................  12  

Target  Market  Status  .................................................................................................................................  13  

Overview  .................................................................................................................................................  13  

Change  in  Market  Dynamics  ...................................................................................................................  13  

Power  Contracting  Process  ........................................................................................................................  15  

Power  Purchase  Agreement  Transaction  Structures  ..............................................................................  15  

Power  Purchase  Agreement  Contracting  Timeline  .................................................................................  15  

Project  Schedule  ........................................................................................................................................  16  

Finance  and  Investment  Opportunity  .......................................................................................................  17  

Project  Pro-­‐forma  Financials  .....................................................................................................................  18  

Scenario  1  –  Phase  One:  (1)  Unit;  Phase  2:  (2)  Units  ..............................................................................  18  

TVA  –  Long  Term  Bilateral  Contract  ........................................................................................................  19  

 Table  of  Figures  

 1.  Pentacles  Companies  ................................................................................................................................  3  

2.  Indian  Creek  Project  –  Site  Map  ...............................................................................................................  6  

3.  Indian  Creek  Project  –  Geographic  Location  .............................................................................................  6  

4.  Indian  Creek  Project  –  Electric  Transmission  Interconnection  Point  ........................................................  8  

5.  Scheduled  Coal  Facility  Retirements  .......................................................................................................  14  

6.  Map  of  Scheduled  Coal  Facility  Retirements  ..........................................................................................  15  

7.  Indian  Creek  Project  Schedule  ................................................................................................................  16  

 List  of  Attachments  (Located  in  Data  Room)  

 A.  Pentacles  Experience  List  ...........................................................................................................................    

B.  Ecotek  Company  Information  .....................................................................................................................    

C.  Ecotek  Pre-­‐Feed  Engineering  Scope  ...........................................................................................................    

D.  NTE  Solutions  Qualifications  Package  ........................................................................................................    

E.  Wood  Group  Proposal  ................................................................................................................................    

F.  Wood  Group  Draft  O&M  Contract  ..............................................................................................................    

G.  Joseph  Dickey  CV  ........................................................................................................................................    

H.  Warranty  Deed  on  Site  ...............................................................................................................................    

I.  Rolls  Royce  Proposal  and  Draft  Contract  .....................................................................................................    

J.  Air  permit  and  Amendment  ........................................................................................................................    

K.  PWR  Solutions  Transmission  Report  ...........................................................................................................    

L.  TVA  Transmission  Interconnection  Application  ..........................................................................................    

M.  System  Impact  Study  Agreement  –  Full  Executed  .....................................................................................    

N.  TMD  Energy  Local  Gas  Production  Report  .................................................................................................    

O.  Citizens  Gas  Correspondence  .....................................................................................................................    

P.  Enrema  Correspondence  ............................................................................................................................    

Q.  Vineland  Energy/Ariana  Energy  Supply  and  Transportation  Correspondence  ..........................................    

R.  Local  Gas  Composition  ...............................................................................................................................    

S.  Citizens-­‐Pentacles  Lease  Agreement  ..........................................................................................................    

T.  Citizens-­‐Pentacles  LOI  to  Extend  Term  of  Lease  .........................................................................................    

U.  Pentacles  II  –  Pentacles  Electric  Assignment  Agreement  ...........................................................................    

V.  Draft  Natural  Gas  Purchase  Contract  .........................................................................................................    

W.  State  of  Tennessee  Grant  Award  for  Water  Infrastructure  .......................................................................    

X.  Power  Purchase  Agreement  Term  Sheets  ..................................................................................................    

Y.  Scenario  1  Pro-­‐forma  –  Phase  1:  1  Unit;  Phase  2:  3  Units  ..........................................................................    

Z:  Scenario  2  Pro-­‐forma  –  Phase  1:  2  Units;  Phase  2:  2  Units  ....................................................................    

 

1    

Executive  Summary:  

Pentacles   Electric,   LLLP   (“Pentacles”),   organized   in   the   state   of   Delaware   in   March   2011,   is  currently  developing  the  Indian  Creek  Project,  an  electric  generating  facility  directly  adjacent  to  the   Indian   Creek   Oil   &   Gas   Field   (the   “Project”).   The   Indian   Creek   Oil   and   Gas   Field   spans  Morgan,  Scott,  and  Fentress  Counties  in  Northeast  Tennessee.  Pentacles’  site  is  located  6  miles  NNW  of  Sunbright,  Tennessee  in  Morgan  County.    Pentacles  is  seeking  an  investment  partner  to  fund  further  development  and  equity  for  the  Project.  

The  Project  will  consist  of  four  (4)  gas  fired  Rolls  Royce  Trent  60  combustion  turbine  in  simple  cycle.    The  Project  will  be  completed  in  two  phases.    The  first  phase  of  the  Project  will  consist  of  one  or  two  Trent  60  turbines,  at  the  discretion  of  the  Investor,  with  a  total  nominal  capacity  of  60  or  120  MW  and  with  a  target  in-­‐service  date  of  early  2014.  The  second  phase  of  the  Project  will  include  the  addition  of  two  or  three  Trent  60  turbines  and  will  be  timed  to  provide  capacity  in  into  the  2017/2018  PJM  capacity  market.    The  Project  is  to  be  constructed  on  a  site  owned  by  Pentacles.    Development  of  the  Project  began  in  early  2011  and  has  been  funded  by  Pentacles.  Since  Project  inception,  Pentacles  has  acquired  ownership  of  the  site  and  filed  for  and  received  its   PSD   air   permit   from   the   Tennessee   Department   of   Environment   and   Conservation.   The  Project  has  filed  for  a  TVA  transmission  interconnection  in  January  2013  (Queue  13-­‐239).    TVA  is  currently   completing   the  System   Impact   Study.     Pentacles  expect   to   finalize  negotiations  and  execute  the  Interconnection  Agreement  with  TVA  in  the  third  quarter  2013.        

The   Project   provides   a   unique   commercial   contracting   structure   allowing   a   counterparty   to  purchase   capacity   and   associated  energy   from  an  efficient   natural   gas   fired   generator   fueled  with  low  cost,  high  btu  local  gas.  The  Project  is  situated  adjacent  to  the  Indian  Creek  Oil  and  Gas  Field,  which  has  the  capacity  to  store  2.3  bcf  of  natural  gas.  The  location  of  the  Project  provides  access  to  plentiful  low  cost,  high  Btu  fuel  supply  from  local  wells  located  in  Morgan,  Scott,  and  Fentress  Counties   in  Tennessee  and   in  wells   in   southern  Kentucky   (“Local  Gas”).     The  Project  will  purchase  Local  Gas  under  5  year  contracts,  containing  automatic  renewal  provisions,  with  local   suppliers.   The   Local   Gas   (heat   content   1.250   MMBtu/mcf)   is   within   the   operating  tolerances  of  the  Trent  60  engines  and  it  will  provide  substantial  cost  savings  as  compared  to  gas  purchased  from  interstate  pipelines.  The  Local  Gas  will  be  stored  in  the  Indian  Creek  Field  and  withdrawn  to  fuel  the  Project.    Currently  Pentacles  is  in  negotiations  with  suppliers  for  the  daily   supply   of   sufficient   Local   Gas   to   fuel   both   phases   of   the   Project   operating   at   a   ~45%  capacity  factor.    In  addition,  the  Project  has  accessibility  to  low  price  local  stripping  gas  (1.125  MMbtu/mcf)  and  interstate  pipeline  gas  to  provide  backup  sources  of  fuel,  if  necessary.    Local  Gas  production  is  expected  to  increase  over  time  as  the  Project  revitalizes  the  market  for  this  product.  Local  Gas  is  gathered  through  a  collection  system,  owned  and  operated  by  Citizens  Gas  Utility  District,  and  delivered  to  the  Indian  Creek  Oil  and  Gas  Field.  The  Local  Gas  is  blended  in  

2    

the  Indian  Creek  Oil  and  Gas  Field  with  other  gas  streams,  yielding  the  lowest  cost  delivered  gas  currently  found  in  the  TVA  region.    The  ability  of  the  field  to  store  up  to  2.3  bcf  of  gas  provides  operating   flexibility  and  a  significant  hedge  against  natural  gas  price  volatility  associated  with  sourcing  from  interstate  pipelines.    The  net  result  of  this  Local  Gas  benefit  is  a  large  supply  of  natural   gas   stored   locally,   under   control   of   Pentacles   and   dedicated   to   the   Project.     The  flexibility  associated  with  the  Project’s  gas  supply  will  provide  the  unique  opportunity  to  burn  natural   gas   at   prices   below  Henry  Hub  with   an   associated   “Natural   Gas   Re-­‐Supply  Option   to  Buyer”  arbitrage  against  periods  of  high  gas  price.  Please  refer  to  the  Natural  Gas  Availability,  Interconnection  &  Delivery  Optionality  section  herein  for  more  details  on  the  gas  supply.  

The   Project   Team   is   working   to   finalize   the   power   purchase   arrangements   with   a   focus   on  counterparties   participating   in   the   PJM   market.     The   first   phase   of   the   Project   will   rely   on  contracted  energy  revenues  and  revenues  from  the  PJM  incremental  capacity  auction  and  the  second  phase  will  relay  on  contracted  energy  revenues  and  PJM  base  residual  capacity  auction  revenues.    Term  Sheets  are  being  actively  negotiated  with  counterparties  for  a  minimum  of  four  years   on   nominal   energy   sales   from   the   Project,   beginning   in   January   2014.   Indicative   offers  have  been  received  offering  terms  of  up  to  8  years.  

It   is   anticipated   that   the   first   phase   of   the   Project,   at   the   discretion   of   the   Investor,   will   be  completed  with   100%   equity   and   that   the   second   phase  will   be   financed   under   a   traditional  project   finance   structure.     It   is   anticipated   that   the   project   debt   will   be   for   a   term   of   the  construction  period  plus  the  term  of  the  executed  power  purchase  agreements.    

Pentacles  is  seeking  an  investor  (“Investor”)  for  the  Project  that  will  participate  in  funding  the  development  costs  going   forward   (estimated  at  $4.0  mm;  Pentacles  has   invested  $7.3  mm  to  date)  and   in   funding  the  cash  equity  required  for  both  the  first  and  second  phases.  Pentacles  will   be   a   co-­‐owner   of   the   Project   and   remain   as   lead   project   developer   with   the   Investor  involved   in   the  key  decisions  going   forward.  Pentacles   is  prepared  to  entertain  any  proposals  that  may  better  fit  a  potential  investor’s  expertise  and  investment  criteria.  

Total   Project   costs   are   currently   estimated   to   be   approximately   $160   million,   including   EPC  costs,  development,   contingency  and   financing   fees.     Total  Project  Costs   are  estimated   to  be  $40  to  $80  million  for  the  first  phase  (one  or  two  units  respectively).  Construction  of  the  Project  is   targeted  to  begin   in   the  third   (3rd)  quarter  of  2013,  with  commercial  operation  of   the   first  phase  in  early  2014.    

It  is  estimated  that  the  Investor  will  make  a  total  cash  equity  investment  in  the  range  of  $40  to  $80  million  to  move  the  first  phase  forward,  depending  on  whether  the  first  phase  includes  one  or  two  units.    The  equity  in  the  first  phase  will  be  used  to  provide  equity  for  the  financing  of  the  second  phase.    The   financial  models   include  a   refinancing  at   the  end  of   the   initial  debt   term.    

3    

Over  a  20  year  Project  life  the  levered  return  is  in  the  18-­‐20%  range.      Please  refer  to  the  Project  Pro-­‐Forma  Financials   section   for  more  detailed  presentation  of   the  projected   financials.     The  Investor  will   receive   a   priority   distribution   from   the   Project   cash   flows   until   it   has   realized   a  minimum  return  on  its  investment,  after  which  the  cash  flows  from  the  Project  will  split  equally  between   the   Investor   and   Pentacles.   In   addition   to   the   cash   equity,   the   Investor   will   be  responsible  for  the  Letter  of  Credit  (“LC”)  requirements  under  each  PPA.    The  Project  will  enter  in   PPAs   to   support   each   phase   and   it   is   anticipated   that   approximately   $7mm  of   LCs  will   be  required  to  securitize  the  PPAs.    

Project  Team:    

Project  Developer  and  Owner  Pentacles   Electric,   LLLP,   a  Miami   based   development   company,   is   the   Project   developer   and  owner.     Pentacles   Electric,   LLLP,   although   it   has   a   similar   ownership   structure   to   Pentacles  Energy,  LLLP,  is  a  separate  entity  from  Pentacles  Electric,  LLLP.    Pentacles  Electric  and  Pentacles  Energy  have  a  contractual  relationship  through  Pentacles  II,  LLP,  as  shown  in  Figure  1  below,  for  certain   rights   to   gas   storage   and   transportation.     Pentacles’   principals   have   experience  developing  and  operating  energy  projects  internationally.  Please  refer  to  Attachment  A  for  the  Pentacles  Principals’  Experience  List.  

   

Pentacles  Companies  FIGURE  1  

 To  ensure  success  of  the  Project,  Pentacles  has  assembled  an  experienced  Project  Team.    Each  member  of  the  Project  Team  noted  below  has  a  proven  history  of  successful  power  generation  

4    

project   development,   engineering,   construction   and/or   operations   experience   in   their  respective  areas  of  expertise.    The  Project  Team  members  are  as  follows:  

Engineering  Contractor    Ecotek   Group   is   the   engineering   contractor   for   the   Project.   Ecotek   is   an   engineering   firm,  located  in  Panama,  which  has  significant  experience  in  designing  simple  cycle  power  generation  facilities.  Ecotek  has  a  joint-­‐venture  arrangement  with  CB&I  for  projects  in  the  U.S.    Please  refer  to  Attachment  B  for  more  information  on  Ecotek.    Ecotek  is  under  contract  to  complete  and  has  commenced  the  Pre-­‐Feed  (conceptual)  design  of  the  Project.    Upon  securing  the  Investor  and  moving   forward  on   the   first  phase,  Ecotek  will   complete   the  detailed  design.    Please   refer   to  Attachment  C  for  a  description  and  schedule  for  the  Pre-­‐Feed  Design  effort.  

Construction  Contractor    The  Wood  Group  will   provide   Construction  Management   Services.     Pentacles   and   the  Wood  Group  are   currently  engaged   in   contract  negotiations.    Under   this   contract,   the  Wood  Group  will   provide   construction   pricing   and   schedule   guarantees,   with   liquidated   damages   as  appropriate.    

Power  Contracting  and  Engineering  NTE   Solutions   is   providing   power   contracting   and   commercial   services.     NTE   Solutions   is   an  infrastructure  development  and  asset  management  services  provider,  with  headquarters  in  St.  Augustine,  FL.    Please  refer  to  Attachment  D  for  a  statement  of  NTE  Solutions  qualifications.  

Operating  and  Maintenance  Services  Wood  Group  GTS,  the  leading  of  provider  of  3rd  party  O&M  services  on  aero  derivative  gas  turbines  in  the  U.S.,  will  be  the  O&M  provider  for  the  Project.    Pentacles  and  the  Wood  Group  are  currently  engaged  in  contract  negotiations.    Please  refer  to  Attachment  E  for  the  Wood  Group  O&M  proposal  to  Pentacles.    Please  refer  to  Attachment  F  for  the  draft  O&M  Contract.  

Legal    Mark  Jendrek  is  providing  legal  representation,  via  his  Knoxville,  TN  office.  

About  Pentacles  Electric,  LLLP:    Pentacles  is  a  Miami-­‐based  power  development  firm.    

Alvaro  Campins  is  the  Chairman  of  the  Board  of  Pentacles  Electric.  Since  1983,  he  has  founded,  started  and  owned  several  companies  in  Venezuela,  USA,  Dominican  Republic,  Panama,  and  the  Bahamas;  covering  all  areas  of  the  energy  business  from  oil  production,  refining  and  trading  to  natural   gas   and   power   generation.   Mr.   Campins   has   a   degree   in   Economics   from   the  Universidad  Católica  Andres  Bello  in  Venezuela.    

5    

Luis  E.  Gutierrez   is  Pentacles  Electric’s  Chief  Financial  Officer.  Since  1996,  he  has  held  several  positions   in   the   financial   industry,  working   for   investment  and   commercial  banks  both   in   the  USA   and   Venezuela.   Mr.   Gutierrez   has   a   degree   in   Business   Administration   from   the  Universidad  Metropolitana  in  Caracas,  Venezuela.    

Carlos  Gamboa  is  Director  of  Pentacles  Electric.  He  is  the  founder  of  Carib  Petroleum  Inc.  and  Oilnet   Corporation.   His   international   business   experience   has   allowed   him   to   acquire   an   in-­‐depth  understanding  of  oil  marketing  and  trading,  financial  and  banking  negotiations,  as  well  as  superior  management   skills  while   living   and  working   in   several   different   locations   in   Europe,  North  and  South  America.  Mr.  Gamboa  studied  Economics  &  Business  Administration  at  Tulsa  University  in  Oklahoma.    

Joseph  Dickey  is  a  Partner  in  Pentacles  Electric’s  Indian  Creek  Project.    Joe,  a  former  executive  with  Florida  Power  and  Light  and  TVA,  leads  the  power  plant  portion  of  the  project.    Mr.  Dickey  has   considerable   experience   with   building,   operating   and   maintaining   power   plant   over   his  career.     Refer   to   Attachment   G   for   Mr.   Dickey’s   CV.   The   principals   of   Pentacles   Electric  conceptualized  and  developed  the  Indian  Creek  Project  to  utilize  the  plentiful  local  high  Btu  gas  and  gas  storage  advantages  that  they  control  under  contract  with  Pentacles  II,  LLC,  a  Tennessee  corporation,  and  a  wholly  owned  subsidiary  of  Pentacles  Energy,  LLLC,  which  owns  the  mineral  rights  to  the  Indian  Creek  Oil  and  Gas  Field.  

Based   on   their   experience   in   the   oil   and   gas   industry,   Pentacles   has   evaluated   the   fuel   cost  advantages   of   using   Local   Gas   and   determined   its   beneficial   use   for   power   generation,   thus  creating  a  market  for  the  Local  Gas.  

The  primary  contacts  for  Pentacles  are  Alvaro  Campins  and  Luis  E.  Gutierrez.  

Pentacles  Electric,  LLLP  

Alvaro  Campins  Chairman  of  the  Board  (786)  552-­‐9931  [email protected]      Luis  E.  Gutierrez  Chief  Financial  Officer  (786)  552-­‐9931  [email protected]    

 

 

6    

Indian  Creek  Project  Summary:    Site  Description  The  Project’s  20  acre  site,  Figure  2  below,  is  owned  by  Pentacles  Electric,  LLLP  and  is  located  in  Morgan   County,   TN,   approximately   5   miles   NNW   of   the   City   of   Sunbright.   Please   refer   to  Attachment  H  for  the  Deed  transferring  ownership  of  the  site  to  Pentacles  Electric.    Refer  to  the  map  Figure  3  below  for  site  location.    The  geographic  location  of  the  Project’s  site  enables  the  sale   of   capacity   and   energy   into   either   the   TVA   or   PJM  market.   In   addition,   the   site’s   close  proximity  to  gas  supply,  both   local  and  pipeline,  and  electric   transmission  provides  significant  capital  cost  savings  to  the  Project.    

 Indian  Creek  Project  –  Site  Map  

FIGURE  2  

 Indian  Creek  Project  –  Geographic  Location  

FIGURE  3  

7    

Equipment  and  Project  Operating  Information  The  first  phase  of  the  Project  will  utilize  one  or  two  Rolls  Royce  Trent  60  combustion  turbines,  generating  a  nominal  60  or  120  MW  of  gas  fired  electricity.  Commercial  operation  for  the  first  phase   is   targeted   for  early  2014.  The  second  phase  will  add   two  or   three  additional  Trent  60  turbines,   for  a  total  of  four  for  the  Project.    Each  high  efficiency  Trent  60  combustion  turbine  (“CT”)   will   allow   for   a   total   of   52  MW   (net   summer   95˚F)   and   63  MW   (net   winter   27˚F)   of  generation.     The   combustion   turbines,   generators   and   emissions   controls   equipment   will   be  supplied   by   Rolls   Royce   in   accordance  with   the   proposal   and   draft   contract   in   Attachment   I  hereto.     The   final   contract   with   Rolls   Royce   is   under   negotiation.     Under   the   terms   of   the  equipment   supply   contract,   Rolls   Royce   will   provide   industry   standard   performance   and  schedule  guarantees  and  equipment  warranties.     The  Project  will   also  enter   into  a   long   term  maintenance   agreement   with   Rolls   Royce   for   maintenance   and   operating   support   for   the  engines.    The  new  combustion  turbines  and  generators  are  currently  in  storage  with  Rolls  Royce  and  available  for  immediate  delivery.      

The  Project  has  the  following  key  features:    

207  MW  (net)  at  95⁰  F  /  251  MW  (net)  at  27⁰  F    (4)  Rolls  Royce  Trent  60  aero-­‐derivative  combustion  turbines   Simple  cycle  generating  technology     Efficient  aero-­‐derivative  CTs     Fast  startup,  under  10  minutes  –  qualifies  as  spinning  reserve   Utilizes  injection  of  water  in  the  combustion  system  to  reduce  emissions  and  increase  

output   Located  in  Morgan  County,  Tennessee   TVA  Interconnection  with  transmission  to  PJM   Commercial  Operations  –  First  phase  targeted  for  January  2014;  second  phase  targeted  

for  early  2017.     The  Project  has  received  its  PSD  Air  Permit  

 Permitting  Overview  The  Tennessee  Department  of  Environment  and  Conservation,  under  authority  delegated  from  the  US  EPA,  issued  a  PSD  Air  Permit,  number  964445P,  to  the  Project  on  June  1,  2011.    The  PSD  Air  Permit  was  amended  on  November  5,  2012  to  extend  the  date  to  commence  construction  to   November   30,   2013.     The   air   permit   includes   multiple   combustion   turbines   and  multiple  reciprocal  engines,  as  can  be  seen  in  Figure  4  in  the  upper  corner  of  the  Site,  construction  on  the  foundations  for  four  reciprocal  engines  has  commenced.    Please  refer  to  Attachment  J  for  the  Air  Permit  and  Amendment.      

 

8    

 Electric  Transmission  Interconnection    The  Project  is  located  adjacent  to  a  TVA  161  kV  transmission  line,  which  runs  east  to  west  from  the  TVA  Huntsville  substation  to  the  TVA  Jamestown  substation.  This  line  has  sufficient  capacity  (up   to   235   MW)   to   deliver   energy   generated   from   the   Project   without   triggering   any  transmission  system  upgrades  as  confirmed  in  an  injection  study  performed  by  PWR  Solutions,  Inc.  Please  refer  to  Attachment  K  for  the  PWR  Solutions   injection  study.    Pentacles  submitted  the  Transmission  Interconnection  Request  for  four  (4)  Rolls  Royce  Trent  60  machines  to  TVA  on  January   24,   2013,   queue   number   13-­‐239.     Please   refer   to   Attachment   L   for   the   TVA  Transmission   Interconnection   Application.     TVA   and   Pentacles   have   executed   the   System  Impact   Study   Agreement.     Please   refer   to   Attachment   M   for   the   System   Impact   Study  Agreement.     The   study   is   currently   under   way.     Pentacles   expects   finalize   and   execute   the  Interconnect  Agreement  with  TVA  in  the  third  quarter  2013.    Please  refer  to  the  map  in  Figure  4  for  Project  site  and  proximity  to  the  161  KV  TVA  transmission  lines.        

 

 

Indian  Creek  Project  –  Electric  Transmission  Interconnection  Point  FIGURE  4  

9    

 Natural  Gas  Interconnection  &  Delivery  Optionality    The  Project   is   located   in  an  area  containing  significant  quantities  of   locally  produced  high  Btu  natural   gas   (“Local   Gas”).     From   1970   through   2000,   Local   Gas   production   from   Fentress,  Morgan   and   Scott   counties   was   at   a   rate   of   between   2,000   and   5,000   mcf   per   day.     This  production  was  sold  through  Citizens  Gas  Utility  District  to  the  interstate  pipeline.    As  the  gas  prices  rose  in  the  early  2000s,  Tennessee’s  overall  production  grew  from  4,409,125  mcf  in  2000  to   41,313,582   mcf   in   2008.     In   2008,   the   Federal   Energy   Regulatory   Authority   imposed   a  maximum  1110  Btu/scf   limit  for  pipeline  gas.    This  effectively  shut  down  the  market  for  Local  Gas   and   caused   the   production   of   Local   Gas   to   drop   off   significantly,   as   the   gas   in   this   area  averaged  1250  Btu.    The  high  Btu  gas   fields  were  shut   in.  Citizens  has  worked  with   local  well  owners/operators  to  sell  a  small  amount  of  Local  Gas  locally  which  has  helped  producers  retain  their  leases.  

The  Local  Gas  is   located  in  the  southern  end  of  the  Appalachian  Basin.    Significant  volumes  of  this  high  btu  Local  Gas  are  located  in  close  proximity  to  the  Project,  in  northeastern  Tennessee  and  southeastern  Kentucky.    Pentacles  is  in  discussions  with  large,  medium  and  small  producers  for  the  supply  of  sufficient  Local  Gas  to  meet  100%  of  the  Project’s  fuel  requirements  for  both  phases.    (Each  Trent  60  will  require  approximately  4500  mcf/day  to  run  at  the  capacity  factors  used  in  the  models  discussed  in  the  Project  Pro-­‐forma  Financials  section  of  this  CIM.)  

TMD  Energy  prepared  a  report,  dated  April  25,  2013,  which  provides  a  local  production  outlook  for   Scott,   Fentress   and  Morgan   Counties.     Please   refer   the   Attachment   N   for   the   complete  report.    The  following  is  a  summary:  

• Wells   that  were  shut   in  producing  2,000  mcf/day  are  still   tied   into  gathering   lines  and  ready   to   be   turned   on   with   very   little   work.   In   addition,   there   are   some   3,000  abandoned  Mississippian  Lime  wells  that  have  Chattanooga  shale  potential.  As  the  gas  market  develops,  these  wells  can  be  deepened  less  than  100  feet  and  stimulated.    Early  tests  of  this  technique  showed  potential  of  sustained  production  of  30  mcf  per  day  from  each  of  these  once  abandoned  wells.  If  all  these  wells  were  stimulated,  this  area  could  produce   90,000  mcf   per   day.   Price  will   dictate   the   speed  with  which   these  wells   are  stimulated.  

• Nearly   every  well   now   producing   gas   in   the   area   is   producing   naturally,   as   there   has  been  little  or  no  financial  incentive  to  spend  funds  to  increase  production.  

• As   the   gas  market   develops,   operators  will   drill   horizontal   Chattanooga   Shale  wells   in  the  Fentress,  Morgan,  and  Scott  County  area.    The  horizontal  wells  drilled  in  the  shale  to  the   east   of   the   Project   area   were   the   major   factor   increasing   Tennessee   annual  production  in  the  2000’s.  

10    

• Many  of   the   shut   in  wells   had  been  producing   for   20-­‐30   years,  with   some   local  wells  producing   for  nearly  60  years.     Local  producers  believe,   that  with   the  development  of  the  market,  volumes  will  significantly  increase  as  only  a  small  portion  of  the  potentially  productive  area  has  been  drilled.  

 Refer  to  Attachments  O  and  P  for  correspondence  with  Citizens  Gas  and  Enrema,  respectively,  discussing   the  potential   for  additional  gas   supply  of  5500+mcf/day,  and   transportation   in   the  local  area.    In  addition,  Pentacles  is  in  discussion  with  Vineland  Energy/Ariana  Energy  regarding  additional  Local  Gas  supply  (~800  mcf/day)  and  transportation.    Please  refer  to  Attachment  Q  for  correspondence  with  Vineland/Ariana.    

The  Local  Gas   (heat  content  1.250  MMBtu/mcf  average)   is  within  the  operating  tolerances  of  the  Rolls  Royce  Trent  60  engines  and  will  be  burned  by  the  Project.    Please  refer  to  Attachment  R  for  the  gas  composition  of  the  Local  Gas.      

The  Local  Gas,  priced  at  a  discount  to  Henry  Hub  coupled  with  transportation  savings,  provides  substantial  natural  gas  cost  savings  compared  natural  gas  purchased  from  interstate  pipelines.  Local  Gas  production  is  expected  to  increase  over  time  as  the  Project  revitalizes  the  market  for  this  product.  This  Local  Gas  is  being  gathered  through  a  collection  system,  owned  and  operated  by  Citizens  Gas  Utility  District,  and  delivered  to  the  Indian  Creek  Oil  and  Gas  Field,  yielding  the  lowest  cost  delivered  gas  currently  found  in  the  TVA  region.  The  gas  field  has  a  storage  capacity  of  2.3  bcf.    The  net   result  of   this  process   is  a   large  supply  of  natural  gas  stored   locally  under  control  of  Pentacles  and  dedicated  to  the  Project.    The  ability  to  store  the  gas  locally  provides  a  valuable  flexibility  in  fuel  supply,  damping  fuel  price  volatility.    This  flexibility  is  included  in  the  power   purchase   agreements   currently   under   discussion.     The   flexibility   associated   with   the  Project’s   gas   supply  will   provide   the   unique   opportunity   to   burn   natural   gas   at   prices   below  Henry   Hub   with   an   associated   “Natural   Gas   Re-­‐Supply   Option   to   Buyer”   arbitrage   against  periods  of  high  gas  price.  This  arbitrage  opportunity  will  allow  the  Project  to  burn  natural  gas  from  the   Indian  Creek  Oil   and  Gas  Field  at   zero  cost  when  burned  and   replace  with   low  cost  equivalent  volumes  of  natural  gas  at  a  later  date  within  an  approved  time  period.  

Pentacles   II,   LLC   has   entered   into   a   10   year   agreement  with   Citizens   Gas   for:   i)   lease   of   the  storage   rights   to   the   field;   and   ii)   transportation   for   Local   Gas   delivered   to   the   Indian   Creek  Field   (the  “Citizens  Agreement”).    Please   refer   to  Attachment  S   for   the  Agreement.  Pentacles  and  Citizens  have  entered  into  an  LOI  to  extend  the  term  of  the  Agreement  for  a  20  year  period  commencing   on   and   contingent   upon   financial   closing   of   the   Project.     Please   refer   to  Attachment  T  for  the  LOI.    Pentacles  II,  LLC  has  assigned  the  benefits  of  the  Citizens  Agreement  to  Pentacles  Electric,  LLLP.    Please  refer  to  Attachment  U  for  the  Assignment  Agreement.  

11    

LOCAL  GAS:    Local  Gas  will  be  sourced  from  producers  in  Morgan,  Scott  and  Fentress  Counties  and  in  southern  Kentucky.    The  gas  will  be  transported  to  the  Indian  Creek  Field  by  Citizens  Gas  Utility   District   and,   potentially,   Vineland/Ariana.     Pentacles   is   currently   in   negotiations   with  several   publically   traded   energy   companies,   as   listed   below,   a   large   regional  production/transportation   company   (Vineland   Energy/Ariana   Energy),   and   local   well   owners,    for  the  supply  of  Local  Gas.    The  Project  will  enter  into  Natural  Gas  Purchase  Contracts  with  the  producers  for  supply  of  the  Local  Gas  commodity.    The  Natural  Gas  Purchase  Contracts  under  discussion  will  have  terms  of  5  years  with  automatic  renewal  and  provide  Pentacles  with  right  of   first   refusals   rights   to  all  of   the  gas  produced  by   the  producer  at  pricing   indexed   to  Henry  Hub.  Pentacles   is  also  discussion   the   requirement  of  a  minimum  quantity  guarantee  with   the  larger,  financially  secure,  suppliers,  which,  at  the  discretion  of  the  Investor,  can  be  included  in  the  gas  supply  contract  and  secured  by  a  parent  guarantee  or  LoC  from  the  Investor.  m  Please  refer  to  Attachment  V  for  the  draft  Natural  Gas  Purchase  Contract  currently  under  negotiation  with  local  producers.  

Pentacles  is  currently  in  negotiations  with  the  following  publically  traded  energy  companies  for  the  purchase  and  transportation  of  Local  Gas:  

• Atlas  Energy,  LP  –  www.atlasenergy.com  =  NYSE:  ATLS  • Consol  Energy  –  www.consolenergy.com  –  NYSE:  CNX  • Delta  Natural  Gas  Company  –  www.deltagas,com  –  NASDAQ:  DGAS  • Miller  Energy  Resources  –  www.millerenergyresources.com  –  NYSE:    MILL  

 Local  Gas:  

• Quantity:  9,000+  mcf/day  first  phase;  20,000+  mcf/day  second  phase.    Negotiations  are  currently  underway  to  secure  these  quantities.  

• Btu  Content:  1.250  MMBtu/mcf  average  • Commodity  Fuel  Cost  (on$/mcf  basis)  =  (Henry  Hub  $/mcf  *  85%)  • Commodity   Fuel   Price   (on  $/MMBtu  basis)   =   (Henry  Hub  $/mcf   *   85%)*(1.000/   1.250  

MMBtu/mcf)  • Transportation  Costs:    $0.15/mcf  +  2%  loss  • Commodity   Price   +   Transportation   Cost   yields   cost   of   gas   at   the   burner   tip   of   the  

Project,  at  a  price  significantly  less  than  the  price  of  delivered  interstate  pipeline  gas.      Local  Stripping  Gas  (if  needed):    

• Quantity:  7,000  mcf/day  currently  available  • Btu  Content:  1.125  MMBtu/mcf  average  • Commodity  Fuel  Cost  (on$/mcf  basis)  =  Henry  Hub  $/mcf    

12    

• Commodity  Fuel  Price  (on  $/MMBtu  basis):    (Henry  Hub  $/mcf)  /  1.125  MMBtu/mcf  • Transportation  Costs:    $0.15/mcf  +  2%  loss  • Commodity   Price   +   Transportation   Cost   yields   cost   of   gas   at   the   burner   tip   of   the  

Project,  at  a  price  significantly  less  than  the  price  of  delivered  interstate  pipeline  gas.      Pipeline  Gas  (if  needed):  

• Commodity  Fuel  Cost:  =  Henry  Hub    • Transportation   Costs:     $0.50/mcf   +   2%   loss.     Negotiations   with   Delta   may   provide  

pipeline   gas   with   a   discounted   transportation   charge,   representing   an   upside   to   the  Investor.    Negotiations  with  Delta  are  currently  under  way.  

• Commodity   Price   +   Transportation   Cost   yields   cost   of   gas   at   the   burner   tip   of   the  Project.    

• Pipeline:  East  Tennessee  Pipeline,  owned  by  Duke  Energy    Operations  and  Maintenance  Plan      Pentacles  intends  to  engage  the  Wood  Group  to  provide  operations  and  maintenance  (“O&M”)  services   for   the   Project.   Pentacles   and   the   Wood   Group   are   currently   engaged   in   contract  negotiations   for   the   O&M   Services.   The   Wood   Group   was   selected   to   provide   these   O&M  services  based  on  the  following:  

1. Their   significant   aero-­‐derivative   gas   turbine   O&M   capabilities   and   experience;  specifically  with  Rolls  Royce  Trent  60  machines.  

2. Their   experience   with   operation   of   new   technologies   and   management   of   OEM,  engineering  and  construction  activities  

3. Their   industry   leading   environmental,   health   and   safety,   regulatory   compliance   and  quality  management  systems.  

4. Their   track   record   of   integrating   and   implementing   construction   management,  commissioning  and  O&M  activities  successfully.    

Consistent   with   market   practice,   Pentacles,   as   Project   Owner,   will   continue   in   a   project  administration  role  to  monitor  the  work  performed  by  the  O&M  provider  and  perform  certain  other  administrative  services.    

Summary  of  Project  Benefits      • Commercial  Operation  Date:  first  phase:  Early  2014;  second  phase  –  early  2017.  

Short  construction    time   Site  Owned  by  Pentacles    

• Low  cost,  abundant,  high  Btu  Local  Gas  availability  

13    

On-­‐Site  Local  Gas  storage  capacity   Local  access  to  East  Tennessee  Gas  Pipeline  for  alternate/additional  gas  supply    

• Favorable  Heat  Rate  and  MW  Output   Latest  state-­‐of-­‐the-­‐art  aero-­‐derivative  CT  technology     Water  injection  for  increased  output  and  decreased  emissions   Low  power  production  cost  providing  dispatch  benefits  

• Access  to  both  PJM  and  TVA  markets   Independent  transmission  study  confirmed  transmission  capacity  exists  (no  additional  

$$)  • Low-­‐cost  161  kV  Transmission  Interconnection  

Property  adjacent  to  existing  161  kV  circuit   Connection  to  161  kV  Huntsville    to  Jamestown    

• Favorable  Air  Permit   PSD  Air  Permit  issued  (Air  Permit  No.    964445p)   Mode/method  of  Project  operations  will  not  be  restricted  by  Air  Permit  conditions  

• Favorable  Water  Services   The  site  is  permitted  for  wells  of  sufficient  capacity  to  meet  the  daily  operating  

requirement,  including  engine  cooling,  of  400  kgd.       In  addition,  Pentacles  has  received  a  Federal  Grant  for  $1,000,000  and  State  funding  for  

$200,000  to  build  an  additional  water  supply  system  to  the  property  and  storage  tank,  if  needed  or  beneficial  to  the  community.    Please  refer  to  Attachment  W  for  the  State  of  Tennessee  Grant  award.  

• Local  Benefits   Favorable  tax  environment     Labor  costs  reasonable   High  labor  productivity  

• Public  Benefit  Value   Economically  depressed  area  with  no  market  for  high  Btu  gas  (TN  to  provide  income  tax  

benefits  and  local  governments  to  provide  tax  benefits  to  stimulate  economic  development).  

Favorable  reputation  of  Project  in  local  and  regional  communities    

Target  Market  Status:    Overview    The   Project   provides   counterparties   (“Buyers”)  who   enter   into   a   power   purchase   agreement  with   a   number   of   long-­‐term   economic   and   commercial   advantages   not   found   in   other  development   projects.   These   advantages   include:   i)   abundant   low   priced   gas;   ii)   gas   storage  

14    

capability   and   iii)   overall   Project   design.     Uninterrupted   supply,   enabled   via   the   storage  capacity,  is  an  advantage  uniquely  inherent  to  the  Project  and  very  rare  in  this  particular  region.  The  term  sheets  issued  to  potential  Buyers  describe  the  “take  now/replace  later”  option  to  use  Project  gas  as  an  arbitrage  against  period  of  high  natural  gas  price.  This  feature  is  unique  to  the  Project  and  brings  significant  value  to  the  Buyer.   In  addition,   the  Project  will  have  one  of   the  lowest  dispatch  price  signals  among  natural  gas  fired  CT  generating  stations  in  the  area  due  to  favorable  heat  rate,  low  cost  operation,  and  the  least  expensive  fuel  in  its  market;  resulting  in  dispatch   costs   that   rival   combined   cycle   costs.   These   long-­‐term   economic   and   commercial  advantages  are   summarized  below.    Please   refer   to  Attachment  X   for   the  Term  Sheets  which  have  been  issued  to  potential  Buyers.    Change  in  Market  Dynamics  

The  TVA  and  PJM  markets  have  over  5  GW  of   coal   capacity   slated   for   retirement   in   the  next  three  to  five  years.  The  cessation  of  operation  of  these  facilities  creates  opportunities  for  new  generators,   such   as   the   Project,   to   the   fill   the   void   created   by   the   reduction   in   generating  capacity.   A   list   showing   scheduled   coal   retirements   for   facilities   serving   the   PJM   and   TVA  markets  is  provided  in  Figure  5  below.    Please  refer  to  Figure  6  for  a  map  showing  the  location  of  the  scheduled  coal  retirements  in  relation  to  the  location  of  the  Indian  Creek  Project.  

 

Plant  Name  &  Unit   Utility  or  TransZone  

Capacity  (MWs)  

Projected  Deactivation  

Date  PJM  

Big  Sandy  1   AEP   280   6/1/2015  Clinch  River  3   AEP   230   6/1/2015  Glen  Lyn  5   AEP   90   6/1/2015  Glen  Lyn  6   AEP   235   6/1/2015  Kanawha  River  1   AEP   200   6/1/2015  Kanawha  River  2   AEP   200   6/1/2015  Sporn  1   AEP   145   6/1/2015  Sporn  2   AEP   145   6/1/2015  Sporn  3   AEP   145   6/1/2015  Sporn  4   AEP   145   6/1/2015  Tanner  Creek  1   AEP   145   6/1/2015  Tanner  Creek  2   AEP   145   6/1/2015  Tanner  Creek  3   AEP   198   6/1/2015  Walter  C  Beckjord  2   DEOK   94   4/1/2015  Walter  C  Beckjord  3   DEOK   128   4/1/2015  

TVA  John  Sevier   TVA   800   2015  Johnsonville  1-­‐6  (7-­‐10)   TVA   1485  Total   2015  (2017)        

15    

Other  

Cane  Run   Louisville  Gas  &  Electric   645   2016  

Green  River  Kentucky  Utilities   189   2016  

 Scheduled  Coal  Facility  Retirements  

FIGURE  5  

 Map  of  Scheduled  Coal  Facility  Retirements  

FIGURE  6  

Power  Contracting  Process:    

 The   first   phase   of   the   Project   will   rely   on   contracted   energy   revenues   and   PJM   incremental  capacity  auction  revenues,  and  the  second  phase  will  relay  on  contracted  energy  revenues  and  PJM  base  residual  capacity  auction  revenues.    Pentacles  NTE  Solutions,  on  behalf  of  Pentacles,  is  conducting  the  power  contracting  process  and  will  continue  to  serve  as  the  commercial  team  Project  lead  throughout  the  contracting  process.  This  section  outlines  the  transaction  structures  solicited  through  the  RFP  and  the  timeframe  for  executing  offtake  agreements.      Power  Purchase  Agreement  Transaction  Structures:    Pentacles  has  solicited  bids  for  the  following  Power  Purchase  Agreement  (“PPA”)  transaction  structures  from  a  wide  variety  of  creditworthy  market  participants.  

16    

Physical  PPA     Unit  contingent  capacity  and/or  energy  supply  from  Project.   Associated  natural  gas  supply  provided  by  Project  with  cost  pass  through  to  Buyer.   “Take  now/Replace  Later”  capability.   Physical  delivery  at  TVA  /  PJM  South  Interface  or  at  Project  busbar  on  the  TVA  

Transmission  System.   Project  will  hold  firm  TVA  transmission  if  delivery  at  PJM  South  Interface  is  required.   Dispatch  parameters  commensurate  with  Project  operating  flexibility.   Term  7  to  10  years  from  Commercial  Operation  Date.    

Financially  Settled  Heat  Rate  Call  Option     Financially  settled  daily  Heat  Rate  Call  Option   Power  Settle  –  PJM  Day-­‐Ahead  index   Strike  –  Gas  Cost  *  Project  Heat  Rate  +  VOME  +  Start  Cost  +  Start  Fuel   “Take  now/Replace  Later”  capability  included  in  financial  provisions  of  gas  cost  settle.   Term  7  to  10  years  from  Commercial  Operation  Date.    

PJM  ICAP     PJM  ICAP  –  Anticipated  RTO  designation   Contract  quantity  will  include  full  output  of  the  Project  

 

Ancillary  Services   Buyer  retains  rights  to  all  applicable  ancillary  services    

 

Credit  Support   To  be  negotiated  between  the  parties    

 Power  Purchase  Agreement  Contracting  Timeline    The  power  contracting  portion  of  the  development  process  is  underway  with  the  execution  of  binding  power  purchase  agreements  to  support  the  first  phase  of  the  Project.    Detailed  discussions  are  underway  with  potential  Buyers  to  support  this  schedule.    Project  Schedule:    

The   Project   has   completed   a   number   of   major   milestones   and   is   on-­‐schedule   for   ground  breaking   in  2013,  and  thus  early  2014  Commercial  Operation.    The  Project  schedule   including  completed   and   anticipated   Project   milestones   is   shown   below   in   Figure   7.   Note   that   the  schedule  is  subject  to  change  during  development,  though  changes  are  expected  to  be  minor.      

17    

Indian  Creek  Project  Schedule  FIGURE  7  

Finance  and  Investment  Opportunity:    Pentacles  plans   to   finance   the  Project  by  bringing   in  an   Investor,   financing   the   first  phase  with  equity  and,  together,  seeking  one  or  more  third-­‐party  project  finance  lenders  to  provide  construction  and  term  financing   for   the   second  phase.     Pentacles   is   seeking  an   Investor   that  will  participate   in   funding  development   costs   going   forward   (estimated   at   $4.0  million),   and   in   funding   the   cash   equity  required   for   the   first   and   second  phases  of   the  Project.         It   is   assumed   that   the   total  equity  required   for   the   Project   (including   both   the   first   and   second   phases)   is   approximately   $60  million,  assuming  a  50:50  D/E  ratio.  Pentacles  will  be  a  co-­‐owner  in  the  Project  and  will  remain  as   lead   project   developer   with   the   Investor   involved   in   the   key   decisions   going   forward.  Pentacles   is   prepared   to   entertain   any   proposals   that   may   better   fit   a   potential   investor’s  expertise  and  investment  criteria.  

Total   Project   costs   are   currently   estimated   to   be   approximately   $160   million,   including  estimated   EPC   costs,   plus   development,   contingency   and   financing   fees.   Construction   of   the  first  phase  of  the  Project  is  targeted  to  begin  in  the  third  (3rd)  quarter  of  2013,  with  commercial  operation  in  early  2014.    

In   addition   to   an   equity   partner,   Pentacles   is   also   interested   in   exploring   partnering   with   a  strategic  investor  who  can  bring  skills  such  as  project  management,  power  plant  development,  engineering  or  industry  relations  to  the  Project.    

The  financial  model  for  the  Project  is  based  on  completing  the  first  phase  with  100%  equity  and  the  second  phase  with  third  party  construction  financing  that  rolls  over  to  8  year  term  financing  upon  commercial  operation  of  the  second  phase  of  the  Project,  with  a  50:50  D/E  ratio.  The  8  

18    

year   term   financing   is   anticipated   to   coincide   with   the   expected   term   of   Power   Purchase  Agreements   entered   into   by   the   Project.     Likewise,   revenue   included   in   the   financials   is  representative   of   expected   revenue   from   Power   Purchase   Agreements   currently   under  negotiation.  Pentacles  expects  to  extend  existing  or  enter  in  new  PPAs  to  support  a  refinancing  at   the  end  of   the  debt   term.    As   set   forth   in   the   financial  model,  Pentacles  projects  a  pretax  internal  rate  of  return  of  approximately  18%  to  20%  on  a  levered  basis.  The  Investor  will  receive  a  priority  distribution  from  the  Project  cash  flows  until  it  has  realized  a  minimum  return  on  its  investment,  after  which  the  cash  flows  from  the  Project  will  split  equally  between  the  Investor  and   Pentacles.     Actual   returns   will   depend,   amongst   other   things,   on   the   final   amount   of  leverage  utilized,  debt  cost  and  the  equity  split  agreed  upon  with  the  Investor.      

In  addition  to  participating  in  development  and  equity  funding,  the  Investor  will  be  responsible  for  the  Letter  of  Credit  (“LC”)  requirements  under  each  PPA.    The  Project  will  enter  in  PPAs  prior  to   financial   close   and   it   is   anticipated   that   approximately   $7mm   of   LCs   will   be   required   to  securitize  the  PPAs.    

Project  Pro-­‐forma  Financials:    Pentacles   has   modeled   the   Project   in   two   phases,   as   described   above,   under   two   different  scenarios.    Both  scenarios  are  based  on  power  purchase  agreement  transactions  sold  into  the  PJM  Capacity  and  Energy  markets.  Summaries  of  both  of  these  model  scenarios  are  provided  in  the  following  subsections.  

Scenario  1  –  Phase  One:  (1)  unit;  Phase  2:  (3)  units    This   scenario   assumes   the   two   phased   approach  with   the   first   phase   including   one   Trent   60  combustion   turbine   unit   and   the   second   phase   adding   an   additional   three   units.     Under   this  scenario  the  sale  of  capacity  and  energy  is  into  the  PJM  market.  The  sale  of  energy  is  assumed  to   with   a   PJM   market   participant   for   an   initial   eight   year   (8)   year   term   with   a   secondary  transaction   for   an   additional   (12)   year   period   following   expiration   of   the   first   contracts.   The  option  premium  shown  is  reflective  of  a  physical  or  financial  daily  heat  rate  call  option  with  firm  transmission  for  delivery  to  the  TVA/PJM  South  Interface.    It  also  assumes  the  sale  of  capacity  into   the   PJM   Incremental   Auctions   prior   to   the   Planning   Year   2017/2018,   after   which   the  capacity  will  be  bid  into  the  PJM  Base  Residual  Auction.      

The   model   incorporates   the   equipment,   construction,   and   financing   costs   required   for  commercial  operation  for  the  first  phase  of  the  Project  in  June  2014  and  second  phase  in  June  2017,   with   total   project   cost   equaling   approximately   $163   million.     Following   commercial  operation,   each  phase  of   the   Project   is   expected   to   have   a   load   factor   of   47%.     In   Year   1   of  

19    

operation,  Pentacles  is  projecting  an  option  premium  of  $5.71/kW-­‐mo.,  which,  when  combined  with   VOM   charges   and   fuel   charges,   results   in   $12.5   million   in   total   revenues.     A   snapshot  summary  of  the  revenues,  expenses,  and  cash  flows  associated  with  the  Project’s  first  ten  (10)  years   of   operation   under   this   type   of   market   transaction   are   presented   below.   For   a   more  detailed  version  of  this  model,  please  refer  for  Attachment  Y.    

    2014   2015   2016   2017   2018   2019   2020   2021   2022   2023  Revenue   $12.5   $13.3   $14.0   $66.6   $69.4   $78.1   $82.2   $83.2   $86.1   $88.8  Expenses   $11.2   $11.6   $11.8   $43.1   $44.7   $46.3   $48.3   $50.4   $52.7   $53.9  Cash  Flow   $1.3   $1.7   $2.2   $23.5   $24.7   $31.8   $33.9   $32.8   $33.4   $34.9  

   These  results  are  based  on  the  following  major  assumptions:    Financing:  

Phase  1:  all  equity;  Phase  2”  67:33  D:E  ratio;  Total  Project  50:50  D:E  ratio   6%  interest  rate  on  debt;  7  year  term   $16.1  million  refinancing  at  end  of  initial  debt  term  

 Capacity  Sale:  

Participation  in  the  PJM  Incremental  Auctions  prior  to  the  May/June  2017  PJM  Base  Residual  Auction  

Participation  in  the  PJM  Base  Residual  Auction  for  Planning  Year  2017/2018  and  beyond.  

 Energy  Sale:  

8  year  initial  PJM  Energy  Sale   12  year  secondary  PJM  Energy  Sale  

 Scenario  2  –  Phase  One:  (2)  units;  Phase  2:  (2)  units    This   scenario   assumes   the   two   phased   approach  with   the   first   phase   including   two   Trent   60  combustion   turbine   units   and   the   second   phase   adding   an   additional   two   units.     Under   this  scenario  the  sale  of  capacity  and  energy  is  into  the  PJM  market.  The  sale  of  energy  is  assumed  to   be  with   a   PJM  market   participant   for   an   initial   eight   year   (8)   year   term  with   a   secondary  transaction   for   an   additional   (12)   year   period   following   expiration   of   the   first   contracts.   The  option  premium  shown  is  reflective  of  a  physical  or  financial  daily  heat  rate  call  option  with  firm  transmission  for  delivery  to  the  TVA/PJM  South  Interface.    It  also  assumes  the  sale  of  capacity  into   the   PJM   Incremental   Auctions   prior   to   the   Planning   Year   2017/2018,   after   which   the  capacity  will  be  bid  into  the  PJM  Base  Residual  Auction.      

20    

 The   model   incorporates   the   equipment,   construction,   and   financing   costs   required   for  commercial  operation  for  the  first  phase  of  the  Project  in  June  2014  and  second  phase  in  June  2017,   with   total   project   cost   equaling   approximately   $163   million.     Following   commercial  operation,   each  phase  of   the   Project   is   expected   to   have   a   load   factor   of   47%.     In   Year   1   of  operation,  Pentacles  is  projecting  an  option  premium  of  $5.71/kW-­‐mo.,  which,  when  combined  with   VOM   charges   and   fuel   charges,   results   in   $25.0   million   in   total   revenues.     A   snapshot  summary  of  the  revenues,  expenses,  and  cash  flows  associated  with  the  Project’s  first  ten  (10)  years   of   operation   under   this   type   of   market   transaction   are   presented   below.   For   a   more  detailed  version  of  this  model,  please  refer  for  Attachment  Z.    

    2014   2015   2016   2017   2018   2019   2020   2021   2022   2023  Revenue   $25.0   $26.6   $28.0   $66.6   $69.4   $78.1   $82.2   $83.2   $86.1   $88.8  Expenses   $20.5   $21.2   $21.6   $43.1   $44.7   $46.3   $48.3   $50.4   $52.7   $53.9  Cash  Flow   $4.5   $5.4   $6.4   $23.5   $24.7   $31.8   $33.9   $32.8   $33.4   $34.9  

 These  results  are  based  on  the  following  major  assumptions:    Financing:  

Phase  1:  all  equity;  Phase  2”  100%  debt;  Total  Project  50:50  D:E  ratio   6%  interest  rate  on  debt;  7  year  term   $16.5  million  refinancing  at  end  of  initial  debt  term  

 Capacity  Sale:  

Participation  in  the  PJM  Incremental  Auctions  prior  to  the  May/June  2017  PJM  Base  Residual  Auction  

Participation  in  the  PJM  Auction  for  2017/2018  and  beyond.    Energy  Sale:  

8  year  initial  PJM  Energy  Sale   12  year  secondary  PJM  Energy  Sale