NAME / LOCATION OF PROJECT APPROPRIATION : P 7,978,070.43 2-STOREY OFFICE BUILDING SOURCE OF FUND: TAGBILARAN CITY, BOHOL ISSUED OBLIGATED AUTHORITY: RELEASED: CALENDAR DAYS TO COMPLETE : 90 CD PROJECT CATEGORY : Provincial Office DESIRABLE STARTING DATE: PROJECT DESCRIPTION : 2-Storey Office Building DESCRIPTION NO. Dump Truck, (cap. 10-11 cu.m.) 2 One Bagger Concrete Mixer 2 Construction Foremen 1 Concrete Cutter 3 Skilled Laborer 18 Grinder 3 Concrete Vibrator 2 Bar Bender 2 Welding Machine 3 Item No. Description Unit Qty Direct Cost Unit Cost I General Requirements 575,000.00 575,000.00 II Health & Safety Requirements 180,000.00 180,000.00 III Furnish & Installed Billboard 20,000.00 20,000.00 IV Site Works 112,333.00 112,333.00 V Structural Works 2,154,656.39 2,154,656.39 VI Architecturak Works 2,759,431.51 2,759,431.51 VII Watering & Sanitary Works 156,523.12 156,523.12 VIII Electrical Works 130,327.07 130,327.07 6,088,271.08 1.85 35.39 45.32 2.57 2.14 100.00 % of Total 9.44 2.96 0.33 Item Cost ESTIMATED COST OF PROPOSED WORK INDIVIDUAL PROGRAM OF WORK TECHNICAL PERSONNEL REQUIRED DESCRIPTION QUANTITY MINIMUM EQUIPMENT REQUIREMENT

Upload: rhejo-orioque

Post on 22-Jan-2016

221 views

Category:

Documents


0 download

DESCRIPTION

seminarhandout

TRANSCRIPT

Page 1: Individual Program of Work

NAME / LOCATION OF PROJECT APPROPRIATION : P 7,978,070.43

2-STOREY OFFICE BUILDING SOURCE OF FUND:

TAGBILARAN CITY, BOHOL ISSUED OBLIGATED AUTHORITY:

RELEASED:

CALENDAR DAYS TO COMPLETE : 90 CD

PROJECT CATEGORY : Provincial Office DESIRABLE STARTING DATE:

PROJECT DESCRIPTION : 2-Storey Office Building

DESCRIPTION NO.

Dump Truck, (cap. 10-11 cu.m.) 2

One Bagger Concrete Mixer 2 Construction Foremen 1

Concrete Cutter 3 Skilled Laborer 18

Grinder 3

Concrete Vibrator 2

Bar Bender 2

Welding Machine 3

Item

No. Description Unit Qty Direct Cost Unit Cost

I General Requirements 575,000.00 575,000.00

II Health & Safety Requirements 180,000.00 180,000.00

III Furnish & Installed Billboard 20,000.00 20,000.00

IV Site Works 112,333.00 112,333.00

V Structural Works 2,154,656.39 2,154,656.39

VI Architecturak Works 2,759,431.51 2,759,431.51

VII Watering & Sanitary Works 156,523.12 156,523.12

VIII Electrical Works 130,327.07 130,327.07

6,088,271.08

1.85

35.39

45.32

2.57

2.14

100.00

% of Total

9.44

2.96

0.33

Item Cost

ESTIMATED COST OF PROPOSED WORK

INDIVIDUAL PROGRAM OF WORK

TECHNICAL PERSONNEL REQUIRED

DESCRIPTION QUANTITY

MINIMUM EQUIPMENT REQUIREMENT