indoor site cut over guidance-v1.0
DESCRIPTION
it is a kmowledge base this material is meant for gsm engineers for BTS cut overthiaTRANSCRIPT
![Page 1: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/1.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Guidance for Cut over and External Alarm
Termination of Indoor sites
For MTNN Hybrid Project
V1.0
![Page 2: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/2.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Contents
1. Key points for Indoor sites installation ............................................................................................ 3
2. 24V Ericsson indoor sites & 48V Huawei Indoor sites ................................................................... 3
3. 24V Huawei Indoor site ..................................................................................................................... 3
3.1. Before Cutover ........................................................................................................................... 3
3.2. Cutover preparation .................................................................................................................. 4
3.3. Transmission cutover ................................................................................................................ 4
3.4. BTS cutover and remove the old PSU modules ...................................................................... 6
4. 48V Ericsson indoor RBS .................................................................................................................. 6
5. Alarm Termination for indoor site ................................................................................................... 7
![Page 3: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/3.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
1. Key points for Indoor sites installation
Indoor sites cannot be cut over before MTN install DC cooling system, either DC
air conditioner or DC extractor fans for shelter cooling;
Both the hybrid cabinet and battery cabinet should be installed outside shelter on
available plinth;
DCDB should be installed close to the existing rectifier, in order to reuse the
load cables from the rectifier output;
Three pairs of input should be connected for DCDB input, two for LLVD and
one for BLVD
DCDB can be powered either from rectifier or converter, depending on the input
power needed for BTS;
Inverter can be installed either indoor or outdoor to power the AC load including
shelter light, aviation light and etc;
Be sure to cut over all the DC loads from existing rectifier, including but not
limited to BTS, transmission, DC cooling system, DC sensors and etc.
Figure 1. DCDB to be installed on the wall of the shelter
2. 24V Ericsson indoor sites & 48V Huawei Indoor sites
For these two types of sites, all the new connections from hybrid rectifier is the
same as old existing rectifier, so the cut over is easy to identify and is omitted in
this document.
3. 24V Huawei Indoor site
Scenario description: this is applicable for indoor site with 24V output rectifier
system and Huawei indoor BTS. Converter is not really necessary for this type
of sites.
3.1. Before Cutover
Input from rectifier/converter
Output to DC load
![Page 4: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/4.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Figure 2. Connection structure before cut over
3.2. Cutover preparation
Figure 3. Cut over preparation and cut over point
3.3. Transmission cutover
Please be noted that all transmission cut over should be done before BTS cut over.
Pay attention to the Positive and Negative difference for 24V and 48V.
Cut over point
![Page 5: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/5.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Figure 4. Cut over of transmission equipments
24V :Red-Positive; Black-Negative
48V:Black-Positive; Blue-Negative
![Page 6: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/6.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
3.4. BTS cutover and remove the old PSU modules
Transmission
Huawei
Indoor BTS
24V input
Top
Bottom
PSU PSU PSU
48V
output
24V Input
24V to 48V Converter
24V~60V input.Can support
both 24V and 48V input
24V rectifier
48V rectifier DCDB
Figure 5. connections after cut over
4. 48V Ericsson indoor RBS
Scenario description: this is applicable for indoor site with 48V output rectifier
system and Ericsson indoor RBS.
24V :Red-Positive; Black-Negative
48V:Black-Positive; Blue-Negative
![Page 7: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/7.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Figure 6. connections after cut over
5. Alarm Termination for indoor site
Figure 7. DDF rack for indoor site
Input from DCDB to RBS converter module.
![Page 8: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/8.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
Figure 8. Alarm termination
Table 1 shows the alarm configuration existing on site while column “hybrid alarm”
shows the alarm we are going to terminate from hybrid side. Subcontractor shall
follow this standard unless the regional customer have different requirements.
Table 2 shows the alarms from hybrid equipments, by which you should know how
to terminate the alarms on hybrid side.
Table 1. Existing alarm definition for indoor sites
No. Port Alarm
ID Redefined Alarm ID
Alarm Name Redefined Alarm
Name Hybrid Alarm
Signal Ground
1 8 2262 65401 Extended 4B
alarm
Harris dehydrator low pressure alarm
EAC1-PIN10 EAC1-PIN11
2 1 2246 65402 Extended 43
alarm Free High Temp EAC1-PIN28 EAC1-PIN29
3 2 2248 65403 Extended 44
alarm Free DC Aircon EAC1-PIN9 EAC1-PIN1
4 3 2250 65404 Extended 45
alarm
Harris high temperature
alarm EAC1-PIN27 EAC1-PIN20
5 4 2252 65405 Extended 46
alarm Harris main supply alarm
EAC1-PIN8 EAC1-PIN30
6 5 2254 65406 Extended 47
alarm
Harris dehydrator
excess run alarm EAC1-PIN26 EAC1-PIN12
7 6 2256 65407 Extended 48
alarm Free Shut Alarm EAC1-PIN7 EAC1-PIN12
8 7 2258 65408 Extended 49
alarm Free
Emergency Fan
EAC1-PIN25 EAC1-PIN12
9 15 2602 65409 Extended F5
alarm Free EAC1-PIN6 EAC1-PIN1
10 9 2268 65410 Extended 4E
alarm Intrusion alarm EAC2-PIN14 EAC2-PIN22
![Page 9: Indoor Site Cut Over Guidance-V1.0](https://reader036.vdocument.in/reader036/viewer/2022062404/552a2c714a79593b778b46a6/html5/thumbnails/9.jpg)
Guidance for Cut over and Alarm termination of MTNN Hybrid Project
11 24 2620 65411 Extended FE
alarm
High Temperature
alarm EAC2-PIN15 EAC2-PIN22
12 23 2618 65412 Extended FD
alarm Smoke/Fire
alarm EAC2-PIN16 EAC2-PIN22
13 22 2616 65413 Extended FC
alarm Smoke detector
failure alarm EAC2-PIN17 EAC2-PIN22
14 13 2598 65414 Extended F3
alarm Mains supply
alarm EAC2-PIN18 EAC2-PIN22
15 12 2596 65415 Extended F2
alarm Surge protection
failure alarm EAC2-PIN19 EAC2-PIN22
16 11 2594 65416 Extended F1
alarm Common genset
1 alarm D.G. Fail EAC2-PIN20 EAC2-PIN22
17 10 2592 65417 Extended F0
alarm Common genset
2 alarm EAC2-PIN1 EAC2-PIN21
18 20 2612 65418 Extended FA
alarm Low fuel alarm EAC2-PIN2 EAC2-PIN21
19 18 2608 65419 Extended F8
alarm Battery
discharge alarm Bat Load EAC2-PIN3 EAC2-PIN21
20 16 2604 65420 Extended F6
alarm Low voltage
alarm DC Under
Voltage EAC2-PIN4 EAC2-PIN21
21 14 2600 65421 Extended F4
alarm Exchange over voltage alarm
EAC2-PIN5 EAC2-PIN21
22 21 2614 65422 Extended FB
alarm Mains failure
alarm EAC2-PIN6 EAC2-PIN21
23 19 2610 65423 Extended F9
alarm System fault
alarm EAC2-PIN7 EAC2-PIN21
24 17 2606 65424 Extended F7
alarm Module fail
alarm PSU Alarm EAC2-PIN8 EAC2-PIN21
Table 2. hybrid alarms ports on hybrid equipments
Alarm port
(PSU Alarm) Alarm 3
Rectifier (Alarm cable 1) (High Temp) Alarm 5
(Emergency Fan) Alarm 6
(DC Under Voltage) Alarm 9
Bat Load SAU (Alarm cable 2)
Shut Alarm
D.G. Fail ATS (Alarm cable 2)
DC Aircon Battery Cabinet (Alarm cable 3)