infra presentation aft may-2014 - economic community of ... · regional broadband infrastructure...
TRANSCRIPT
![Page 1: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/1.jpg)
01/08/2014
1
ECOWAS TRADE & DEVELOPMENT WORKING GROUP MEETINGAID for Trade Related Infrastructure Programmes
ECOWAS Commission, 20th May, 2014
Presentation OutlinePresentation Outline
General Introduction
ECOWAS Infrastructure Development Strategy
Programme/Project UpdatePPDU
FODETE
Transport
Telecoms
Conclusion
General Introduction
ECOWAS Infrastructure Development Strategy
Programme/Project UpdatePPDU
FODETE
Transport
Telecoms
Conclusion
![Page 2: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/2.jpg)
01/08/2014
2
Introduction 1/2Introduction 1/2
The Infrastructure Sector is guided by Goal 2 of theregional strategic plan, “To facilitate thedevelopment of infrastructure for the attainmentof a Competitive Business Environment andInvestment Capacities”
Programs, projects and activities are tailored towardspromoting integration and supporting growth inregional TRADE and free movement.
TRADE must be positioned to take advantage ofinfrastructure development and provision……
The Infrastructure Sector is guided by Goal 2 of theregional strategic plan, “To facilitate thedevelopment of infrastructure for the attainmentof a Competitive Business Environment andInvestment Capacities”
Programs, projects and activities are tailored towardspromoting integration and supporting growth inregional TRADE and free movement.
TRADE must be positioned to take advantage ofinfrastructure development and provision……
Introduction 2/2Introduction 2/2
Infrastructure Sectors currently under 3Departments namely:
Department of Infrastructure
Department of Telecommunications & IT
Department of Energy & Mines
Infrastructure Sectors currently under 3Departments namely:
Department of Infrastructure
Department of Telecommunications & IT
Department of Energy & Mines
![Page 3: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/3.jpg)
01/08/2014
3
Infrastructure challenges affect competitiveness of the region and presents major impediments to economic growth due to high production cost
– ECOWAS Strategic Plan 2011-2015
Key Issues & ChallengesKey Issues & Challenges
Key Issues & Challenges:Key Issues & Challenges:
Finance & Resource Mobilization
Inadequate investment finance for infrastructure development especially transport and energy sub-sectors
Limited mobilization of potential investment financing from the vast regional natural resource base
Institutional & Capacity
Management Structures and Discordant Frameworks
Technical human resources for infrastructure development
Limited regional dimensions to national infrastructure development strategies
Project preparation and development
Finance & Resource Mobilization
Inadequate investment finance for infrastructure development especially transport and energy sub-sectors
Limited mobilization of potential investment financing from the vast regional natural resource base
Institutional & Capacity
Management Structures and Discordant Frameworks
Technical human resources for infrastructure development
Limited regional dimensions to national infrastructure development strategies
Project preparation and development
![Page 4: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/4.jpg)
01/08/2014
4
5-year ECOWAS Strategic Plan: Infrastructure Development5-year ECOWAS Strategic Plan: Infrastructure Development
Reduce cost and enhance provision of infrastructure services Increase involvement of the private sector and public-private-partnerships in infrastructure developmentSecure adequate funding for infrastructure projects - facilitate member states access to funds, secure foreign capital and expertiseImprove rural access to infrastructure services esp. energy, transport & ICTFocus on multimodal transportation systems to improve connectivity between member states
Reduce cost and enhance provision of infrastructure services Increase involvement of the private sector and public-private-partnerships in infrastructure developmentSecure adequate funding for infrastructure projects - facilitate member states access to funds, secure foreign capital and expertiseImprove rural access to infrastructure services esp. energy, transport & ICTFocus on multimodal transportation systems to improve connectivity between member states
ESTABLISHMENT OF THE FUND FOR THE DEVELOPMENT OF THE
TRANSPORT AND ENERGY SECTORS(FODETE)
ESTABLISHMENT OF THE FUND FOR THE DEVELOPMENT OF THE
TRANSPORT AND ENERGY SECTORS(FODETE)
ECOWAS Donors Coordination Infrastructure Thematic Group Meeting
Abuja, April 10, 2014
ECOWAS Donors Coordination Infrastructure Thematic Group Meeting
Abuja, April 10, 2014
![Page 5: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/5.jpg)
01/08/2014
5
ECOWAS Heads of State and Government at the 37th Summit in Abuja on 22nd June, 2009 decided to create a fund for the development and financing of the transport and Energy Sectors expected to be fed from a levy on the key export resources within the region.
A consultant consortium was recruited, with funding from AfDB and EBID, to conduct a feasibility study for the establishment of the fund.
The Consultant’s assignment includes examining the effect on the economy (national and regional) of establishing the FODETE and propose mitigating measures. Specifically, to:
Conduct the economic, financial and legal feasibility analysis relating to the creation of the FODETEDefine the conditions for set up of the fundsDefine the modalities for resourcing the fundElaborate the governance and operational modalities
From preliminary analysis of 2012 data and the proposed taxation scheme for all products (agriculture, mining, oil, gas), an estimate of US$310million is expected from FODETE based on
ECOWAS Heads of State and Government at the 37th Summit in Abuja on 22nd June, 2009 decided to create a fund for the development and financing of the transport and Energy Sectors expected to be fed from a levy on the key export resources within the region.
A consultant consortium was recruited, with funding from AfDB and EBID, to conduct a feasibility study for the establishment of the fund.
The Consultant’s assignment includes examining the effect on the economy (national and regional) of establishing the FODETE and propose mitigating measures. Specifically, to:
Conduct the economic, financial and legal feasibility analysis relating to the creation of the FODETEDefine the conditions for set up of the fundsDefine the modalities for resourcing the fundElaborate the governance and operational modalities
From preliminary analysis of 2012 data and the proposed taxation scheme for all products (agriculture, mining, oil, gas), an estimate of US$310million is expected from FODETE based on
Background and introduction 2/2Background and introduction 2/2
OutlookOutlook
Main stages of the feasibility studyLaunch of the study
Inception Study Report Data collection mission in Member States Interim Study Report Validation Seminar Draft Final Report – May 2014Validation Seminar – June 2014Submission of Final report – July 2014
The conclusions of the final report will be presented in a memorandum to the Summit of Heads of State for decision
Preparation and adoption of the legal and institutional documentsDecision of the Heads of State concerning the findings of the studyImplementation of the FODETE
Main stages of the feasibility studyLaunch of the study
Inception Study Report Data collection mission in Member States Interim Study Report Validation Seminar Draft Final Report – May 2014Validation Seminar – June 2014Submission of Final report – July 2014
The conclusions of the final report will be presented in a memorandum to the Summit of Heads of State for decision
Preparation and adoption of the legal and institutional documentsDecision of the Heads of State concerning the findings of the studyImplementation of the FODETE 10
![Page 6: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/6.jpg)
01/08/2014
6
ECOWAS Project Preparation and
Development Unit (PPDU)
ECOWAS Project Preparation and
Development Unit (PPDU)
ECOWAS Project Preparation and Development Unit (PPDU)ECOWAS Project Preparation
and Development Unit (PPDU)
The objective of the PPDU is to equip
ECOWAS with the required capacity
to quickly prepare bankable
infrastructure investment projects
which will attract private and public
sector financing
The objective of the PPDU is to equip
ECOWAS with the required capacity
to quickly prepare bankable
infrastructure investment projects
which will attract private and public
sector financing
“Closing Africa’s infrastructure financing gap is critical to the region’s prosperity” –
AICD study
• Africa's infrastructure services are twice as expensive as elsewhere –YET Infrastructure contributed over half of Africa's improved growth performance
• Project financing is scarce and in high demand – YET alarge share of Africa's infrastructure is domestically financed
• We have deficit Infrastructure BUT it can be increased by creating the right institutional, regulatory, and administrative environment for investment (public/private)
![Page 7: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/7.jpg)
01/08/2014
7
PPDU Operation and ManagementPPDU Operation and Management
A ‘Honest Broker’ unit supported by a Fund for project preparation to be split into two windows;
One to be used to stimulate private sector led Infrastructure initiatives (IDCF), whilst the other used to support public sector projects (AF)
A governance structure consisting of a Board (composed by ECOWAS, MS, Dev’t Partners and Private Sector representatives) and a Management team
In order to respond adequately to public and private sector demands/requirements.
A ‘Honest Broker’ unit supported by a Fund for project preparation to be split into two windows;
One to be used to stimulate private sector led Infrastructure initiatives (IDCF), whilst the other used to support public sector projects (AF)
A governance structure consisting of a Board (composed by ECOWAS, MS, Dev’t Partners and Private Sector representatives) and a Management team
In order to respond adequately to public and private sector demands/requirements.
PPDU scopePPDU scope
•Undertake project prioritization, preparation and development activities including studies
•Transaction support to Member States (project owners)
Identification, selection and prioritization of
projects
• Inform the creation of appropriate enabling environment/ policies
• Increase private sector participation in funding
Resources mobilization and
funding
•Building Technical support for projects preparation and development
•Capacity building for Member States MDAs responsible for project implementation
Partnerships and Cooperation
![Page 8: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/8.jpg)
01/08/2014
8
PPDU – MilestonesPPDU – MilestonesJan 2005: C/REG/18/01/05
ECOWAS Council of Ministers in 2005 approved the creation of the PDIU with the required skills and funding as well as the establishment of a regional infrastructure fund
Nov 2008: C/REG.18/11/08ECOWAS Council of Ministers approved US$ 8.684M for at least the first 5 years of PPDU Operations and $10 Million to the Infrastructure Fund for project preparation
Sept 2010Headquarters Agreement signed with the Togolese Republic
Aug 2011ECOWAS Council of Ministers approved the the regulation defining the PPDU, its mission and mode of operations (REG.C/REG.R/08/11 of 19/08/2011)
2011Received first tranche of 5Miliion Euro’s of the Spanish Government 15million Euro support to PPDU
December 2013/ Year 2014Interview for PPDU Staff conducted, staff to resume shortlyPPDU Manuals of operations and procedures: draft elaborated and on comments
Jan 2005: C/REG/18/01/05 ECOWAS Council of Ministers in 2005 approved the creation of the PDIU with the required skills and funding as well as the establishment of a regional infrastructure fund
Nov 2008: C/REG.18/11/08ECOWAS Council of Ministers approved US$ 8.684M for at least the first 5 years of PPDU Operations and $10 Million to the Infrastructure Fund for project preparation
Sept 2010Headquarters Agreement signed with the Togolese Republic
Aug 2011ECOWAS Council of Ministers approved the the regulation defining the PPDU, its mission and mode of operations (REG.C/REG.R/08/11 of 19/08/2011)
2011Received first tranche of 5Miliion Euro’s of the Spanish Government 15million Euro support to PPDU
December 2013/ Year 2014Interview for PPDU Staff conducted, staff to resume shortlyPPDU Manuals of operations and procedures: draft elaborated and on comments
Project Preparation & Development:Priority Studies for 2014
Project Preparation & Development:Priority Studies for 2014
Contract signing1. ECOWAN market analysis and business model – ICT
Procurement process ongoing (RFP launched – deadline 27th
MARCH, 2014)2. ECOWAS Regional Infrastructure Development Master Plan – ALL
SECTORS3. Lagos-Dakar Corridor missing links – INFRASTRUCTURE/
TRANSPORT4. Development of airport infrastructure in West Africa –
INFRASTRUCTURE/ TRANSPORT5. Development of rural and peri-urban electrification in West Africa
– ENERGY6. Development of a postal service Master Plan in West Africa – ICT7. Feasibility Studies for Railways master plan new links –
INFRASTRUCTURE/ TRANSPORT
Contract signing1. ECOWAN market analysis and business model – ICT
Procurement process ongoing (RFP launched – deadline 27th
MARCH, 2014)2. ECOWAS Regional Infrastructure Development Master Plan – ALL
SECTORS3. Lagos-Dakar Corridor missing links – INFRASTRUCTURE/
TRANSPORT4. Development of airport infrastructure in West Africa –
INFRASTRUCTURE/ TRANSPORT5. Development of rural and peri-urban electrification in West Africa
– ENERGY6. Development of a postal service Master Plan in West Africa – ICT7. Feasibility Studies for Railways master plan new links –
INFRASTRUCTURE/ TRANSPORT
![Page 9: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/9.jpg)
01/08/2014
9
Procurement process ongoing ( EOI evaluation completed)8. Study for the Extension of the West Africa gas pipeline project –
ENERGY
Procurement – pipeline9. Procurement of Construction Works: Joint Border Post between
Ghana and Cote d’Ivoire – INFRASTRUCTURE/ TRANSPORT10. Regional broadband infrastructure development – ICT11. Development of the ECOWAS maritime master plan –
INFRASTRUCTURE/ TRANSPORT
Special Projects12. Abidjan-Lagos Highway Development project – INFRASTRUCTURE/
TRANSPORT13. Action Plan for the implementation of the UN Decade of Action for
Road Safety – INFRASTRUCTURE/ TRANSPORT14. Feasibility Study for new Joint border posts construction –
INFRASTRUCTURE/ TRANSPORT
Procurement process ongoing ( EOI evaluation completed)8. Study for the Extension of the West Africa gas pipeline project –
ENERGY
Procurement – pipeline9. Procurement of Construction Works: Joint Border Post between
Ghana and Cote d’Ivoire – INFRASTRUCTURE/ TRANSPORT10. Regional broadband infrastructure development – ICT11. Development of the ECOWAS maritime master plan –
INFRASTRUCTURE/ TRANSPORT
Special Projects12. Abidjan-Lagos Highway Development project – INFRASTRUCTURE/
TRANSPORT13. Action Plan for the implementation of the UN Decade of Action for
Road Safety – INFRASTRUCTURE/ TRANSPORT14. Feasibility Study for new Joint border posts construction –
INFRASTRUCTURE/ TRANSPORT
Project Preparation & Development:Priority Studies for 2014
Project Preparation & Development:Priority Studies for 2014
LAND TRANSPORTLAND TRANSPORT
![Page 10: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/10.jpg)
01/08/2014
10
Joint Border Posts, Axle Load Control, etc
Reduce cost of transport in intra-community tradeReduce cost of transport in intra-community trade
Objective 2.1: Economic and business infrastructure development
Objective 2.2: Private sector and public-private-partnership development
Goal 2: Facilitate the development of infrastructure for the attainment of a competitive business environment
ECOWAS 5-YR STRATEGIC PLAN: STRATEGIC CONTEXT (Transport)
ECOWAS 5-YR STRATEGIC PLAN: STRATEGIC CONTEXT (Transport)
Promote the Development of Economic and Technological InfrastructurePromote Regional transport and transit facilitation in the ECOWAS RegionEstablish Common Operational Rules for Infrastructure and Services in the Region
ISRT & Inter-state
Transport Industry Reforms
Harmonization of Interstate Transport Procedures
Observatories of Abnormal Practices
Abidjan-Lagos Highway Development ProgrammeAbidjan-Lagos Highway Development Programme
o Description o Presidents of Cote d’lvoire, Ghana, Togo, Benin and Nigeria
proposed the construction of a 6-lane dual carriage Abidjan-Lagos Highway, 28th February, 2013.
o Steering Committee made up of Infrastructure/ Works/ Roads Ministers from the five Member States (Chair, Nigeria). Coordination by ECOWAS Commission.
o Scopeo Design, Construction and Supervision of the 6-Lane Highway
o Project Treaty by the beneficiary Member States
o Transaction, Technical Advisory and project management advisers
o Corridor Management
o Description o Presidents of Cote d’lvoire, Ghana, Togo, Benin and Nigeria
proposed the construction of a 6-lane dual carriage Abidjan-Lagos Highway, 28th February, 2013.
o Steering Committee made up of Infrastructure/ Works/ Roads Ministers from the five Member States (Chair, Nigeria). Coordination by ECOWAS Commission.
o Scopeo Design, Construction and Supervision of the 6-Lane Highway
o Project Treaty by the beneficiary Member States
o Transaction, Technical Advisory and project management advisers
o Corridor Management
![Page 11: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/11.jpg)
01/08/2014
11
Abidjan-Lagos Highway Dev’tProgramme – Achieved Milestones Abidjan-Lagos Highway Dev’tProgramme – Achieved Milestones
Steering Committee of Infrastructure/Works
Ministers established by Heads of States and
functional
4 Ministerial and Presidential consultation
meetings held on proposed Highway
Terms of Reference for Feasibility and Detailed design Study completed
Fully Signed Project Treaty
Request for Proposals finalised and sent for
Technical and Transaction Advisory
Services
Discussion ongoing with the African Union
Commission, GIZ and African Development
Bank for project preparation support and
capacity building.
Dakar-Abidjan Highway Development ProjectDakar-Abidjan Highway Development Project
Proposed construction of Multi-Lane Dual Carriage Highway from Dakar-AbidjanInitial High Level Consultation Planned for early June, 2014Components:
Road constructionCorridor ManagementJoint Border PostReservation for Railway connectionSpatial Development Initiatives
Proposed construction of Multi-Lane Dual Carriage Highway from Dakar-AbidjanInitial High Level Consultation Planned for early June, 2014Components:
Road constructionCorridor ManagementJoint Border PostReservation for Railway connectionSpatial Development Initiatives
![Page 12: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/12.jpg)
01/08/2014
12
Dakar-Lagos Coastal Corridor Development – Existing InterventionsDakar-Lagos Coastal Corridor Development – Existing Interventions
Connects Eleven (11) Coastal Countries from Nigeria to Senegal covering a total distance of over 4500km.
Dakar-Abidjan CorridorAn amount of €62.245 million was secured under the European Union 10th EDF for the rehabilitation the 103km Bandajuma (Sierra Leone) -Liberia Border road including the construction of three bridges.
Trans-Gambia BridgePhase I includes the funding of the bridge and connecting roads = UA 67.36 million, (AfDB 99.07%, Government The Gambia 0.24% and Government of Senegal 0.69%) and will be executed over a five year period (2012-2017)
ECOWAS-China Consultations ongoing with Government of China on missing links on the Dakar-Lagos Corridor
Appraisal & Data Collection Mission to all 11 Coastal Countries on-going (Team of 10 Chinese Engineers on Mission)
Connects Eleven (11) Coastal Countries from Nigeria to Senegal covering a total distance of over 4500km.
Dakar-Abidjan CorridorAn amount of €62.245 million was secured under the European Union 10th EDF for the rehabilitation the 103km Bandajuma (Sierra Leone) -Liberia Border road including the construction of three bridges.
Trans-Gambia BridgePhase I includes the funding of the bridge and connecting roads = UA 67.36 million, (AfDB 99.07%, Government The Gambia 0.24% and Government of Senegal 0.69%) and will be executed over a five year period (2012-2017)
ECOWAS-China Consultations ongoing with Government of China on missing links on the Dakar-Lagos Corridor
Appraisal & Data Collection Mission to all 11 Coastal Countries on-going (Team of 10 Chinese Engineers on Mission)
Regional Missing Road Link ImprovementsRegional Missing Road Link Improvements
o Construction of bad sections on the Abidjan-Lagos Section – World Banko Phase I - Ghana 110km; Benin 17km; Togo 8km. Supervision, Technical
Assistance & Road Safety
o Rehabilitation of the Cotonou-Lome road – AfDBo Construction of the Trans-Gambia Bridge – AfDB
o Construction of two roads in Senegal
o Construction of two Joint Border Posts (Senegal & Gambia)
o European Union – 10th EDF Regional Indicative Programme
o Construction of Zinder- Nigeria Border Road (Niger-Nigeria)
o Koupela Piega-Fada Gourma-Niger Border (Burkina Faso-Niger)
o Construction of bad sections on the Abidjan-Lagos Section – World Banko Phase I - Ghana 110km; Benin 17km; Togo 8km. Supervision, Technical
Assistance & Road Safety
o Rehabilitation of the Cotonou-Lome road – AfDBo Construction of the Trans-Gambia Bridge – AfDB
o Construction of two roads in Senegal
o Construction of two Joint Border Posts (Senegal & Gambia)
o European Union – 10th EDF Regional Indicative Programme
o Construction of Zinder- Nigeria Border Road (Niger-Nigeria)
o Koupela Piega-Fada Gourma-Niger Border (Burkina Faso-Niger)
![Page 13: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/13.jpg)
01/08/2014
13
Nigeria-Cameroon Multinational Highway & Transport facilitation Program – ECOWAS ComponentNigeria-Cameroon Multinational Highway & Transport facilitation Program – ECOWAS Component
o Review /Engineering design of JBP at Mfum.
o Detailed design of the Mfum JBP on going.
o Duration of design expected for four (4) and half months.
o Initial site investigations, topographical studies &
o Soil investigation and Survey Work are to commence in One week time.
o Harmonization of norms, standards, vehicle size, axle load & JBP legal Framework Studies
o Contract Signed with Messrs Consultant is Corridor Development Consultants (Pty) Limited from Namibia for a period of 6 months
o Outputs:o Bilateral agreement on the harmonization of axle Load control policies and strategies between
Nigeria and Cameroon
o Compendium of Operation procedure manuals for border agencies at the Mfum Joint Border Post
o Expected Completion date is 8th August, 2014 (JBP Legal Framework) & 15th August, 2014 (Axle Load)
o Review /Engineering design of JBP at Mfum.
o Detailed design of the Mfum JBP on going.
o Duration of design expected for four (4) and half months.
o Initial site investigations, topographical studies &
o Soil investigation and Survey Work are to commence in One week time.
o Harmonization of norms, standards, vehicle size, axle load & JBP legal Framework Studies
o Contract Signed with Messrs Consultant is Corridor Development Consultants (Pty) Limited from Namibia for a period of 6 months
o Outputs:o Bilateral agreement on the harmonization of axle Load control policies and strategies between
Nigeria and Cameroon
o Compendium of Operation procedure manuals for border agencies at the Mfum Joint Border Post
o Expected Completion date is 8th August, 2014 (JBP Legal Framework) & 15th August, 2014 (Axle Load)
ECOWAS Joint Border Post (JBP) ProgrammeECOWAS Joint Border Post (JBP) Programme
Borders key Bottleneck to cross-border Trade:
o To enhance movement of persons, vehicles and goods within the Community joint controls in a single location
JBP Concept & Components
o Infrastructure configuration
o Reforms in Documentation & Processes
o Sensitization and Education.
o Pre-clearance possible through information & equipment sharing
Borders key Bottleneck to cross-border Trade:
o To enhance movement of persons, vehicles and goods within the Community joint controls in a single location
JBP Concept & Components
o Infrastructure configuration
o Reforms in Documentation & Processes
o Sensitization and Education.
o Pre-clearance possible through information & equipment sharing
![Page 14: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/14.jpg)
01/08/2014
14
Update on the construction of the JBPsUpdate on the construction of the JBPsProject Update
Architectural and engineering designscompleted for Seven JBPsConstruction ongoing on Four (4) sites:
SEME (Nigeria/Benin)Noepe (Togo/Ghana) andMalanville (Benin – Niger borderMfum (Nigeria-Cameroon) – AfDB Grant
Next Steps - ECOWAS Internal funds being considered for
Ghana-Côte d’Ivoire Ghana-Burkina Faso
Secure funding for remaining JBPs
Bénin-Togo Guinée-Mali
o Intervention at some Borders may only bereforms of crossing procedures anddocumentation
Soft Components
ECOWAS Supplementary Act for JBPs fullySigned by HoSG and in force
Equipment Needs assessment Study andOperational Procedure manuals underway(World Bank)
Procurement of Equipment to followimmediately afterwards
Undertake detailed training programmes forborder control officials on the JBP scheme
Project UpdateArchitectural and engineering designscompleted for Seven JBPsConstruction ongoing on Four (4) sites:
SEME (Nigeria/Benin)Noepe (Togo/Ghana) andMalanville (Benin – Niger borderMfum (Nigeria-Cameroon) – AfDB Grant
Next Steps - ECOWAS Internal funds being considered for
Ghana-Côte d’Ivoire Ghana-Burkina Faso
Secure funding for remaining JBPs
Bénin-Togo Guinée-Mali
o Intervention at some Borders may only bereforms of crossing procedures anddocumentation
Soft Components
ECOWAS Supplementary Act for JBPs fullySigned by HoSG and in force
Equipment Needs assessment Study andOperational Procedure manuals underway(World Bank)
Procurement of Equipment to followimmediately afterwards
Undertake detailed training programmes forborder control officials on the JBP scheme
ECOWAS RAILWAY MASTER PLANECOWAS RAILWAY MASTER PLAN
OBJECTIVETo enhance competitiveness of economy in the region by providing affordable transport costs for agriculture and mining products and goods.
Master plan detailsECOWAS Railway Master Plan developed in 2009, identifying 17 priority links
Rehabilitation of 3,300 km existing railways
Construction of 6,700 KM of new lines
OBJECTIVETo enhance competitiveness of economy in the region by providing affordable transport costs for agriculture and mining products and goods.
Master plan detailsECOWAS Railway Master Plan developed in 2009, identifying 17 priority links
Rehabilitation of 3,300 km existing railways
Construction of 6,700 KM of new lines
![Page 15: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/15.jpg)
01/08/2014
15
MaritimeMaritimeo “Support to African Maritime Transport Sector” – 10th EDF
Intra-ACP Programo Development of Port database interchange mechanism, marine Environment
Protection & emergency response performance
o Support to Flag State Implementation and port State Control (PSC) in Africa
o Improvement of port Safety and Port Efficiency
o Kick-of in March, 2014
o Proposed Regional Shipping Company in West and Central Africa (Sealink Project)
o FNB Capital appointed as Financial Advisers and Issuing House to capital raise for Sealink Promotional Company Limited
o Key partners Nigeria Export – Import (NEXIM) Bank, the Federation of West Africa Chambers of Commerce and Industry (FEWACCI) and TransimexCameroun
o Entirely Private Sector Driven
o Regional Maritime Strategy – Study being procured for Port capacity assessment – ECOWAS Commission
o Development of maritime service and link from Praia to the West African Coast Line - PIDA
o “Support to African Maritime Transport Sector” – 10th EDF Intra-ACP Program
o Development of Port database interchange mechanism, marine Environment Protection & emergency response performance
o Support to Flag State Implementation and port State Control (PSC) in Africa
o Improvement of port Safety and Port Efficiency
o Kick-of in March, 2014
o Proposed Regional Shipping Company in West and Central Africa (Sealink Project)
o FNB Capital appointed as Financial Advisers and Issuing House to capital raise for Sealink Promotional Company Limited
o Key partners Nigeria Export – Import (NEXIM) Bank, the Federation of West Africa Chambers of Commerce and Industry (FEWACCI) and TransimexCameroun
o Entirely Private Sector Driven
o Regional Maritime Strategy – Study being procured for Port capacity assessment – ECOWAS Commission
o Development of maritime service and link from Praia to the West African Coast Line - PIDA
Air TransportAir Transport
![Page 16: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/16.jpg)
01/08/2014
16
SYNOPSIS OF THE AIR TRANSPORT SUB SECTOR
SYNOPSIS OF THE AIR TRANSPORT SUB SECTOR
The Air Transport Subsector is guided by:Goal 2 of the regional strategic plan, “To facilitate thedevelopment of infrastructure for the attainment of aCompetitive Business Environment and InvestmentCapacities”...and Yamoussoukro Decision of 1999 relating to theimplementation of the Yamoussoukro Declaration concerning theliberalization of Access to Air Transport Markets in Africaadopted on the 14th of November 1999 by the African Ministersin charge of civil aviation; and endorsed by the OAU Heads ofState in Lome, Togo, in July 2000Air Transport Programmes seek “to develop a sound and seamlessregional air transport system with safe, secure, efficient andaffordable air services, well connected within West Africa andintegrated with the global network”
The Air Transport Subsector is guided by:Goal 2 of the regional strategic plan, “To facilitate thedevelopment of infrastructure for the attainment of aCompetitive Business Environment and InvestmentCapacities”...and Yamoussoukro Decision of 1999 relating to theimplementation of the Yamoussoukro Declaration concerning theliberalization of Access to Air Transport Markets in Africaadopted on the 14th of November 1999 by the African Ministersin charge of civil aviation; and endorsed by the OAU Heads ofState in Lome, Togo, in July 2000Air Transport Programmes seek “to develop a sound and seamlessregional air transport system with safe, secure, efficient andaffordable air services, well connected within West Africa andintegrated with the global network”
WEST AFRICAN AVIATION MARKETWEST AFRICAN AVIATION MARKET
o Inter-continental: the most lucrative market, dominated by foreign carriers (42% of total market of roughly 8 to 10 million passengers annually)
o Intra-Africa: market dominated by South African, Ethiopian and Kenya Airways
oDomestic: small market, except for Nigeria (around 10 million domestic passengers per year in Nigeria).
o Inter-continental: the most lucrative market, dominated by foreign carriers (42% of total market of roughly 8 to 10 million passengers annually)
o Intra-Africa: market dominated by South African, Ethiopian and Kenya Airways
oDomestic: small market, except for Nigeria (around 10 million domestic passengers per year in Nigeria).
Market shares (seats) of ECOWAS-registeredairlines on intra-ECOWAS flights withoutdomestic Nigerian market, Jan. 2013.Source: SRSAnalyser
![Page 17: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/17.jpg)
01/08/2014
17
CHALLENGESCHALLENGES
Political
• Political unrest in the region affected Air Carriers, damaged airport infrastructure, facilities & equipment and undermined the confidence of users.
• National protectionist attitudes affects the granting of air traffic rights contradicting the YD Liberalization
Economicand Social
• Market size: ECOWAS Member States are faced with economic and social crises (health, education, poverty, famine)
• High operating cost of airlines: airport taxes and fees, fuel, insurance, maintenance, training of personnel
• Lack of cooperation between ECOWAS Air carriers: flight schedules, interline agreements, join venture, alliances ....
• Inadequate skilled manpower and capacity• GDP Size and stable political climate facilitate hub development (LOS,ACC,DKR)
Legal
• Shortcomings of the Implementation of the YD: lack of Executing Agency, Rules of Competition, Settlement of Disputes, Consumer Rights protection
ECOWAS Air Transport Program UpdateECOWAS Air Transport Program Update
1. Coordination and development of Air Transport Liberalization inMember StatesImplementation of the Yamoussoukro Decision for Air Transport Liberalizationin West Africa
o Developed 9 Air Transport Supplementary Acts that have been adopted by theAuthority on 17 February 2012, Next Steps: Publish, conduct awarenesscampaign and follow up on the implementation of the Air TransportSupplementary Acts to establish and maintain a Liberalized Community AirTransport Market
o Established the Air Transport Committee (DGCA of Member States) and inOctober, 2013, updated the Air transport action Plan 2009-2015 and approved a new AirTransport Action Plan 2014-2020
o AIR TRANSPORT CHAMPIONSHIP: H.E. Alassane Ouattara, President of theRepublic of Cote d’Ivoire entrusted by his peers to Encourage pursuit of air transportliberalization measures, and urge Member States to ensure their effectiveimplementation;
o 1st Meeting of the Air Transport Steering Committee, held on 11-12 February2014, Abidjan, Cote d’Ivoire, Prepared a Draft Roadmap for the implementation ofthe Action Plan for approval by Authority of HoSG
1. Coordination and development of Air Transport Liberalization inMember StatesImplementation of the Yamoussoukro Decision for Air Transport Liberalizationin West Africa
o Developed 9 Air Transport Supplementary Acts that have been adopted by theAuthority on 17 February 2012, Next Steps: Publish, conduct awarenesscampaign and follow up on the implementation of the Air TransportSupplementary Acts to establish and maintain a Liberalized Community AirTransport Market
o Established the Air Transport Committee (DGCA of Member States) and inOctober, 2013, updated the Air transport action Plan 2009-2015 and approved a new AirTransport Action Plan 2014-2020
o AIR TRANSPORT CHAMPIONSHIP: H.E. Alassane Ouattara, President of theRepublic of Cote d’Ivoire entrusted by his peers to Encourage pursuit of air transportliberalization measures, and urge Member States to ensure their effectiveimplementation;
o 1st Meeting of the Air Transport Steering Committee, held on 11-12 February2014, Abidjan, Cote d’Ivoire, Prepared a Draft Roadmap for the implementation ofthe Action Plan for approval by Authority of HoSG
![Page 18: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/18.jpg)
01/08/2014
18
2. Enhancing Civil Aviation Safety and Securityo Enhance pooling of resources for Civil Aviation Authorities (CAA)
o Support Regional Aviation Safety Oversight Organizations (RSOO) and establish a pool of Regional Aviation Security Experts in ECOWAS region
o Currently finalizing the drafting of a Regulation on Aviation Security to operationalize the Supplementary Act on Aviation Security.
o Regional Seminar on Man Portable Air Defence Systems (MANPADS) was jointly organized by ECOWAS and ICAO in Niamey, from 27-29 August 2013 to create awareness and to mitigate the persistent terrorist threats to civil aviation in West Africa.
o A Roadmap to prevent illegal use of MANPADS in ECOWAS region was adopted. NEXT STEPS- assist States in implementing the Roadmap and engage partners for support
o AfDB Support to ECOWAS – Finalization and closure of the Phase 1 of COSCAP Programme for Aviation Safety Oversight in West Africa funded by the AfDB and preparation of the Phase 2 grant to ECOWAS Air transport Unit;
2. Enhancing Civil Aviation Safety and Securityo Enhance pooling of resources for Civil Aviation Authorities (CAA)
o Support Regional Aviation Safety Oversight Organizations (RSOO) and establish a pool of Regional Aviation Security Experts in ECOWAS region
o Currently finalizing the drafting of a Regulation on Aviation Security to operationalize the Supplementary Act on Aviation Security.
o Regional Seminar on Man Portable Air Defence Systems (MANPADS) was jointly organized by ECOWAS and ICAO in Niamey, from 27-29 August 2013 to create awareness and to mitigate the persistent terrorist threats to civil aviation in West Africa.
o A Roadmap to prevent illegal use of MANPADS in ECOWAS region was adopted. NEXT STEPS- assist States in implementing the Roadmap and engage partners for support
o AfDB Support to ECOWAS – Finalization and closure of the Phase 1 of COSCAP Programme for Aviation Safety Oversight in West Africa funded by the AfDB and preparation of the Phase 2 grant to ECOWAS Air transport Unit;
ECOWAS Air Transport Program UpdateECOWAS Air Transport Program Update
ECOWAS Air Transport Program UpdateECOWAS Air Transport Program Update
3. Regional Aircraft Maintenance Centreo to establish a world class Aircraft Maintenance Facility in the region to reduce the cost and
delay incurred by airlines in sending their aircraft to maintenance centers outside the region thereby enhance economic viability and sustainability of the airline industry.
o Preliminary studies have been carried out.
4. Regional Aircraft Leasing Companyo Create a Joint Venture lessor grouping of investors for leased aircraft acquisition, including
purchase/leaseback, leasing of engine to reduce operating costs of ECOWAS’s airlines and consequently increase the competitiveness and profitability of the said airlines. This will facilitate airlines access to new and modern fleet.
o TOR for the Feasibility study on the establishment of Regional Aircraft Leasing Company prepared
5. Study on the Development of airport infrastructure in West Africa o This project is meant to address deficiencies identified by ICAO‘s Safety Oversight Audit
reports on the international airport infrastructure, equipment and facilities of the ECOWAS member States. The Procurement process in progress for hiring the consultant to conduct this study.
3. Regional Aircraft Maintenance Centreo to establish a world class Aircraft Maintenance Facility in the region to reduce the cost and
delay incurred by airlines in sending their aircraft to maintenance centers outside the region thereby enhance economic viability and sustainability of the airline industry.
o Preliminary studies have been carried out.
4. Regional Aircraft Leasing Companyo Create a Joint Venture lessor grouping of investors for leased aircraft acquisition, including
purchase/leaseback, leasing of engine to reduce operating costs of ECOWAS’s airlines and consequently increase the competitiveness and profitability of the said airlines. This will facilitate airlines access to new and modern fleet.
o TOR for the Feasibility study on the establishment of Regional Aircraft Leasing Company prepared
5. Study on the Development of airport infrastructure in West Africa o This project is meant to address deficiencies identified by ICAO‘s Safety Oversight Audit
reports on the international airport infrastructure, equipment and facilities of the ECOWAS member States. The Procurement process in progress for hiring the consultant to conduct this study.
![Page 19: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/19.jpg)
01/08/2014
19
6. REGIONAL AIR TRANSPORT DATABASEDesign and implementation of a Database/information system to provide useful and up to date data for regional planning and development and / or monitoring of progress in the different areas of the Air transport industry.
November 2012: Pre-Feasibility study on Regional Air Transport Data Base financed by the AfDB, validated in December 2012. AfDB and World Bank have indicated interest to fund the study
7. Capacity building in Civil Aviation and Climate ChangeTrain adequate and appropriate personnel in relevant aviation fields as needed by States including collaboration with the renowned aeronautical Universities / training centers
8. Promote Viable Airline Industry: Coordinate meetings of the CEOs of ECOWAS Airlines with a view to foster cooperation (interline/commercial/technical agreements, joint venture, alliances, mergers, etc.) amongst airlines in the region. NEXT STEP: Hire a consultant to conduct study on airline cooperation
6. REGIONAL AIR TRANSPORT DATABASEDesign and implementation of a Database/information system to provide useful and up to date data for regional planning and development and / or monitoring of progress in the different areas of the Air transport industry.
November 2012: Pre-Feasibility study on Regional Air Transport Data Base financed by the AfDB, validated in December 2012. AfDB and World Bank have indicated interest to fund the study
7. Capacity building in Civil Aviation and Climate ChangeTrain adequate and appropriate personnel in relevant aviation fields as needed by States including collaboration with the renowned aeronautical Universities / training centers
8. Promote Viable Airline Industry: Coordinate meetings of the CEOs of ECOWAS Airlines with a view to foster cooperation (interline/commercial/technical agreements, joint venture, alliances, mergers, etc.) amongst airlines in the region. NEXT STEP: Hire a consultant to conduct study on airline cooperation
ECOWAS Air Transport Program UpdateECOWAS Air Transport Program Update
Information & Communication Technology (ICT)
Information & Communication Technology (ICT)
![Page 20: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/20.jpg)
01/08/2014
20
Some major ProjectsSome major Projects
ICT Terrestrial connectivity
ECOWAN
Cybersecurity
Internet Exchange Point – IXP
Telecoms/ICT Database - SIGTEL
ICT Terrestrial connectivity
ECOWAN
Cybersecurity
Internet Exchange Point – IXP
Telecoms/ICT Database - SIGTEL
ICT TERRESTRIAL CONNECTIVITYICT TERRESTRIAL CONNECTIVITY
ObjectiveEnsure each country has direct broadband infrastructure connections to all its neighbouring countries
ensure the access to submarine cables to all landlocked countries
Cost US$320 MillionNext Steps
The following should be implemented as a priority:
Ensure submarine landing
stations in Guinea Bissau and a second landing point in Benin Republic
Link Mali - Niger - Nigeria
Links Burkina Faso - Benin and Burkina Faso - Ghana
Terrestrial broadband Links between Mano-River Countries (Cote d’Ivoire, Liberia, Sierra Leone and Guinea) and neighbouring countries (Mali, Senegal and Guinea Bissau).
ObjectiveEnsure each country has direct broadband infrastructure connections to all its neighbouring countries
ensure the access to submarine cables to all landlocked countries
Cost US$320 MillionNext Steps
The following should be implemented as a priority:
Ensure submarine landing
stations in Guinea Bissau and a second landing point in Benin Republic
Link Mali - Niger - Nigeria
Links Burkina Faso - Benin and Burkina Faso - Ghana
Terrestrial broadband Links between Mano-River Countries (Cote d’Ivoire, Liberia, Sierra Leone and Guinea) and neighbouring countries (Mali, Senegal and Guinea Bissau).
![Page 21: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/21.jpg)
01/08/2014
21
ICT - ECOWAN ProjectICT - ECOWAN ProjectECOWAS WIDE AREA NETWORK(ECOWAN) - public sector e-governancecomputer network, connecting all ECOWASinstitutions, Governments and affiliatedorganizations. Cost - US$130m
Benefits to ECOWASEnhance knowledge sharing and regionalintegrationSecure communication, administration and financial transactions portal.
The Project comprises:Fibre-optic connectivity within a country (Middle Mile connectivity)Cross-border connectivityLast Mile (end-user) connectivityCapacity building banks enabling real-time financial transaction support
Core Applications to be deployed:The Regional Control, Commandand Communication (R3C) – Theconnectivity of the Heads of State andGovernment, Foreign Affairs ministries,ECOWAS Institutions
and fee paying applicationsALISA – Customs connectivity and transaction supportRVAIS – Regional Vehicle Administration Information systemWAMI – connectivity for national central
UpdateThe Gambia and Sierra Leone have bothsigned loan agreements with the IslamicDevelopment Bank (IsDB) for theimplementation of the project .
IsDB has also indicated interest tofinance the implementation project inother IsDB member countries
ECOWAS WIDE AREA NETWORK(ECOWAN) - public sector e-governancecomputer network, connecting all ECOWASinstitutions, Governments and affiliatedorganizations. Cost - US$130m
Benefits to ECOWASEnhance knowledge sharing and regionalintegrationSecure communication, administration and financial transactions portal.
The Project comprises:Fibre-optic connectivity within a country (Middle Mile connectivity)Cross-border connectivityLast Mile (end-user) connectivityCapacity building banks enabling real-time financial transaction support
Core Applications to be deployed:The Regional Control, Commandand Communication (R3C) – Theconnectivity of the Heads of State andGovernment, Foreign Affairs ministries,ECOWAS Institutions
and fee paying applicationsALISA – Customs connectivity and transaction supportRVAIS – Regional Vehicle Administration Information systemWAMI – connectivity for national central
UpdateThe Gambia and Sierra Leone have bothsigned loan agreements with the IslamicDevelopment Bank (IsDB) for theimplementation of the project .
IsDB has also indicated interest tofinance the implementation project inother IsDB member countries
ECOWAN Project Implementation plan
ECOWAN Project Implementation plan
Individual country
Coastal corridor
CV-Senegal-Mali-Cote d’Ivoire link
Senegal-Mali-B/Faso-Togo link
Niger-Benin link
![Page 22: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/22.jpg)
01/08/2014
22
CybersecurityCybersecurity
ObjectivesTo provide a secure cyber space in ECOWAS region to promote and facilitate the use of ICT services and Applications
Cost US$ 15 Million
ObjectivesTo provide a secure cyber space in ECOWAS region to promote and facilitate the use of ICT services and Applications
Cost US$ 15 Million
Next StepsSet up Computer Incidence Response Team/Computer Emergency Response Team (CIRT/CERT) in all the Member States and ECOWAS Centre of Cybersecurity
Capacity Building
Next StepsSet up Computer Incidence Response Team/Computer Emergency Response Team (CIRT/CERT) in all the Member States and ECOWAS Centre of Cybersecurity
Capacity Building
Internet Exchange Points -IXPs
Internet Exchange Points -IXPs
ObjectivesTo provide the region with adequate internet node exchange to maximise internal traffic
Cost US$ 15 Million
ObjectivesTo provide the region with adequate internet node exchange to maximise internal traffic
Cost US$ 15 Million
Next StepsSetup Internet Exchange Points in all the ECOWAS Members States
Setup Regional Exchange Points
Transition from IPv4 to IPv6
Next StepsSetup Internet Exchange Points in all the ECOWAS Members States
Setup Regional Exchange Points
Transition from IPv4 to IPv6
![Page 23: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/23.jpg)
01/08/2014
23
TELECOMS/ICT DATABASE - SIGTELTELECOMS/ICT DATABASE - SIGTEL
Objective
To provide information on the use and the level of Telecommunications/ ICT market development in the ECOWAS Region
Cost US$10 Million
Expected Results
A tool to keep track of developments in the Telecoms/ ICT sector for decision making
Next Steps
Finalize the development of the SIGTEL
Production of accurate indicators and maps for the Telecoms/ICT markets
Dissemination of information for stakeholders
Objective
To provide information on the use and the level of Telecommunications/ ICT market development in the ECOWAS Region
Cost US$10 Million
Expected Results
A tool to keep track of developments in the Telecoms/ ICT sector for decision making
Next Steps
Finalize the development of the SIGTEL
Production of accurate indicators and maps for the Telecoms/ICT markets
Dissemination of information for stakeholders
Conclusion(Critical Success Factors)
Conclusion(Critical Success Factors)
![Page 24: Infra Presentation AfT May-2014 - Economic Community of ... · Regional broadband infrastructure development – ICT 11. Development of the ECOWAS maritime master plan – INFRASTRUCTURE](https://reader033.vdocument.in/reader033/viewer/2022042318/5f076dea7e708231d41cf0b5/html5/thumbnails/24.jpg)
01/08/2014
24
MUITO OBRIGADO MUITO OBRIGADO
JE VOUS REMERCIE
THANK YOU