infrastructure projects initial proposals for sjws #5 entsog offices – brussels stakeholder joint...
TRANSCRIPT
![Page 1: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/1.jpg)
Infrastructure projectsInitial proposals for SJWS #5
ENTSOG offices – BrusselsStakeholder Joint Working Session – 20 April 2012
![Page 2: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/2.jpg)
Online questionnaire
Streamlined process> For every project submitted to ENTSOG for TYNDP 2011-2020, online
questionnaire will be set with previous values as a default setting> Even if answer will remain the same, promoter will have to click-submit the
questionnaire> Online form will ease the data process and make it more robust
Updated questionnaire> Given past experience, questionnaire will be fine-tuned in order to avoid
misunderstanding and lack of clarity
2
Microsoft Word 97 - 2003 Document
![Page 3: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/3.jpg)
Main evolution
3
Project capacity for modelling purpose> Key information required for modelling purpose> Intermediate entry/exit capacity is a requirement for long-haul projects> In case of different options, project promoter should identify the one to be
modeled by ENTSOG
Project benefits> Questions could be based on Annex IV of the EIP proposal> Promoters could be asked if they will apply for PCI status
Project timeline> Mode detailed questions in order to help reader to monitor the evolution of
projects from one edition to the other
![Page 4: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/4.jpg)
Project stage outlook
4
Synthetic information on project timeframe> As there is no single timeline for projects and challenging steps often differ, a robust clustering can only be based
on FID status> Additional proposal is to provide a synthetic outlook of project steps highlighting:• Last completed step• Main challenge (is it possible to anticipate such difficulty?)• Remaining steps
Step 1 Step 2 Step 3 Step 4 Step 5 Step 6 Step 7
Project A Planned FEED Permitting Market test FID Construction
Project B Planned FEED Permitting Market test FID Construction
Project C Planned FEED Permitting FID Construction
Project D Planned FEED Permitting Supply contract FID Construction
Project E Planned FEED Supply contract FID Permitting Construction
![Page 5: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/5.jpg)
Expected construction load
5
Graphical representation of the effort> Aggregated figures on a 10-year range are not sufficient to express the expected
load in term of works> Using the same data as Annex A (Infra. Projects) it is possible to give more
visibility based on the construction phase of transmission lines, UGS and LNG
Equivalent km
![Page 6: Infrastructure projects Initial proposals for SJWS #5 ENTSOG offices – Brussels Stakeholder Joint Working Session – 20 April 2012](https://reader035.vdocument.in/reader035/viewer/2022062421/56649d8d5503460f94a75532/html5/thumbnails/6.jpg)
6
Thank You for Your AttentionOlivier Lebois, Adviser, System DevelopmentENTSOG -- European Network of Transmission System Operators for GasAvenue de Cortenbergh 100, B-1000 Brussels
EML: [email protected]: + 32 2 894 5105WWW: www.entsog.eu