infs 724 project and change management

59
INFS 724 Project and Change Management Amit Deokar, Ph.D.

Upload: samuel90

Post on 29-Oct-2014

4 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: INFS 724 Project and Change Management

INFS 724 Project and Change Management

Amit Deokar, Ph.D.

Page 2: INFS 724 Project and Change Management

Chapter 4

Project Integration Management

Page 3: INFS 724 Project and Change Management

3

Outline

Strategic planning and project selection What is project integration management? Preliminary scope statements Project management plans Project Execution Monitoring and controlling project work Integrated project control Closing projects

Page 4: INFS 724 Project and Change Management

Strategic Planning and Project Selection

Page 5: INFS 724 Project and Change Management

5

Strategic Planning and Project Selection The first step in initiating projects is to look at the big

picture or strategic plan of an organization Strategic planning involves determining long-term

objectives, predicting future trends, and projecting the need for new products and services.

Organizations often perform a SWOT analysis: Strengths, Weaknesses, Opportunities, and Threats

As part of strategic planning, organizations should: Identify potential projects. Select which projects to work on. Formalize project initiation by issuing a project

charter.

Page 6: INFS 724 Project and Change Management

6

Identifying Potential Projects

Many organizations follow a planning process for selecting IT projects.

It’s crucial to align IT projects with business strategy.

Research shows that: Supporting explicit business objectives is the

number one reason cited for investing in IT projects.

The consistent use of IT standards lowers application development costs by 41 percent per user.

Page 7: INFS 724 Project and Change Management

7

Why Firms Invest in Information Technology

Page 8: INFS 724 Project and Change Management

8

Information Technology Planning Process

Page 9: INFS 724 Project and Change Management

9

Business case – An example

Please refer to the JWD Consulting business case, p. 82

Page 10: INFS 724 Project and Change Management

10

Methods for Selecting Projects

There are usually more projects than available time and resources to implement them

It is important to follow a logical process for selecting IT projects to work on

Methods include: focusing on broad needs categorizing projects performing financial analyses using a weighted scoring model (multiple criteria)

Page 11: INFS 724 Project and Change Management

11

Focusing on BroadOrganizational Needs It is often difficult to provide strong

justification for many IT projects, but everyone agrees they have a high value

Three important criteria for projects: There is a need for the project There are funds available There’s a strong will to make the project

succeed

Page 12: INFS 724 Project and Change Management

12

Categorizing IT Projects

One categorization is whether the project addresses a problem an opportunity a directive

Another categorization is how long it will take (time) to do and when it is needed

Another is the overall priority of the project

Page 13: INFS 724 Project and Change Management

13

Financial Analysis of Projects

Financial considerations are often an important consideration in selecting projects

Three primary methods for determining the projected financial value of projects: Net present value (NPV) analysis Return on investment (ROI) Payback analysis

Page 14: INFS 724 Project and Change Management

14

Net Present Value Analysis

Net present value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time

Projects with a positive NPV should be considered if financial value is a key criterion

The higher the NPV, the better Internal rate of return (IRR) can by calculated

by setting the NPV to zero

Page 15: INFS 724 Project and Change Management

15

NPV Calculations

Determine estimated costs and benefits for the life of the project and the products it produces

Determine the discount rate (check with your organization on what to use)

Calculate the NPV Notes: Some organizations consider the

investment year as year 0, while others start in year 1.

Page 16: INFS 724 Project and Change Management

16

Net Present Value Example‘Resources’ page – Templates – Financial Analysis

Page 17: INFS 724 Project and Change Management

17

Return on Investment (ROI)

ROI = (total discounted benefits - total discounted costs) / discounted costs

The higher the ROI, the better Many organizations have a required rate of

return or minimum acceptable rate of return on an investment

Page 18: INFS 724 Project and Change Management

18

Payback Analysis

The payback period is the amount of time it will take to recoup, in the form of net cash inflows, the net dollars invested in a project

Payback occurs when the cumulative discounted net benefits are greater than zero

Many organizations want IT projects to have a fairly short payback period

Page 19: INFS 724 Project and Change Management

19

Charting the Payback Period

Payback period

$-

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

$3,000,000

Year 0 Year 1 Year 2 Year 3 Year 4

Year

Cumulative discounted benefits Cumulative discounted costs

Page 20: INFS 724 Project and Change Management

20

Weighted Scoring Model

A weighted scoring model is a tool that provides a systematic process for selecting projects based on many criteria First identify criteria important to the project selection

process Then assign weights (percentages) to each criterion so

they add up to 100% Then assign scores to each criterion for each project Multiply the scores by the weights and get the total

weighted scores The higher the weighted score, the better

Page 21: INFS 724 Project and Change Management

21

Sample Weighted Scoring Model for Project Selection‘Resources’ page – Templates – Weighted Decision Matrix

Page 22: INFS 724 Project and Change Management

22

Example of Management Criteria

Criteria

Explicit business objectives

Support decision making

Legal/government requirements

Implicit business objectives

Response to competition

Probability of achieving

Page 23: INFS 724 Project and Change Management

23

Example of Development Criteria

Criteria

Tech/system requirements

Intro./learning technology

Probability of completion

Page 24: INFS 724 Project and Change Management

24

Screening

Identify those factors that are important Establish a minimum level of importance Eliminate those projects that fail on any one

of the minimum standards

Page 25: INFS 724 Project and Change Management

25

Screening Example

Expected ROI Qualified project team

leadership Company has expertise

in area

Project completion time

At least 30% Available

Company is either experienced or desires to gain experience

Within 12 months

Page 26: INFS 724 Project and Change Management

What is project integration?

Page 27: INFS 724 Project and Change Management

27

Project integration is about…

Coordinating all of the other knowledge areas throughout a project’s life cycle

Coordinating people, plans, and work required to complete the project.

Steering the project team towards successful completion

Page 28: INFS 724 Project and Change Management

28

Project Integration Management Processes Develop the project charter: Work with stakeholders

to create the document that formally authorizes a project—the charter.

Develop the preliminary project scope statement: Work with stakeholders, especially users of the project’s products, services, or results, to develop the high-level scope requirements and create a preliminary project scope statement.

Develop the project management plan: Coordinate all planning efforts to create a consistent, coherent document—the project management plan.

Page 29: INFS 724 Project and Change Management

29

Project Integration Management Processes (cont’d) Direct and manage project execution: Carry out the

project management plan by performing the activities included in it.

Monitor and control the project work: Oversee project work to meet the performance objectives of the project.

Perform integrated change control: Coordinate changes that affect the project’s deliverables and organizational process assets.

Close the project: Finalize all project activities to formally close the project.

Page 30: INFS 724 Project and Change Management

30

Project Integration Management Overview

Page 31: INFS 724 Project and Change Management

Project charter

Page 32: INFS 724 Project and Change Management

32

Project Charters

A project charter is a document that formally: Recognizes the existence of a project Authorizes the project Provides direction on the project’s objectives and

management It is a roadmap that defines key questions or issues

to be addressed by the project as well as the high level project deliverables

Key project stakeholders should sign a project charter to acknowledge agreement on the need and intent of the project

Page 33: INFS 724 Project and Change Management

33

Project charter guidelines

There is no hard and fast rules. Brevity and clarity are highly valued. Suggested items include:

Project name Project sponsor (s) Project manager Statement of purpose (e.g., overarching goals, including the

need for the project in business terms) -WHY? Scope (high level product characteristics and requirements) -

WHAT? Approach – How?

Authorized project resources (people, budget) Roles and responsibilities Basic project timeline Project control Risk management

Page 34: INFS 724 Project and Change Management

34

Sample Project Charter (p. 86)

Page 35: INFS 724 Project and Change Management

Preliminary scope statements

Page 36: INFS 724 Project and Change Management

36

Preliminary scope statements

A scope statement is a document used to develop and confirm a common understanding of the project scope.

It is an important tool for preventing scope creep: The tendency for project scope to keep getting

bigger. A good practice is to develop a preliminary or

initial scope statement during project initiation and a more detailed scope statement as the project progresses.

Page 37: INFS 724 Project and Change Management

37

Contents of a Preliminary Scope Statement Project objectives Product or service

requirements and characteristics

Project boundaries Deliverables Product acceptance

criteria Project assumptions and

constraints Organizational structure

for the project

Initial list of defined risks Summary of schedule

milestones Rough order of

magnitude cost estimate Configuration

management requirements

Description of approval requirements

Page 38: INFS 724 Project and Change Management

Project management plans

Page 39: INFS 724 Project and Change Management

39

Project Plan Development

A project plan is a document used to coordinate all project planning documents

Its main purpose is to guide project execution Project plans assist the project manager in

leading the project team and assessing project status

Project performance should be measured against a baseline plan

Page 40: INFS 724 Project and Change Management

40

Attributes of Project Plans

Just as projects are unique, so are project plans

Plans should be dynamic and flexible Plans should be updated as changes occur Plans should first and foremost guide project

execution

Page 41: INFS 724 Project and Change Management

41

Common Elements of a Project Plan Introduction or overview of the project

Project name, brief description and sponsor Key team members Deliverables Key reference material Glossary

Description of how the project is organized (HR and communication) Organizational charts Project responsibilities

Management and technical processes Management objectives Project controls Risk management (Risk) Project staffing (HR) Technical processes including quality assurance

Work to be done, schedule, and budget information (Scope, Time, and Cost)

Page 42: INFS 724 Project and Change Management

42

Sample Outline for a Software Project Management Plan (SPMP)

Page 43: INFS 724 Project and Change Management

43

Stakeholder Analysis

A stakeholder analysis documents important (often sensitive) information about stakeholders such as stakeholders’ names and organizations roles on the project unique facts about stakeholders level of influence and interest in the project suggestions for managing relationships

Page 44: INFS 724 Project and Change Management

44

Sample Stakeholder Analysis (p. 144)

Page 45: INFS 724 Project and Change Management

Project execution

Page 46: INFS 724 Project and Change Management

46

Project Plan Execution

Project plan execution involves managing and performing the work described in the project plan

The majority of time and money is usually spent on execution (performing the work)

The application area of the project directly affects project execution because the products of the project are produced during execution

Page 47: INFS 724 Project and Change Management

47

What Went Wrong?

Many people have a poor view of plans based on past experiences. Senior managers often require a plan, but then no one follows up on whether the plan was followed.

For example, one project manager said he would meet with each project team leader within two months to review their plans. The project manager created a detailed schedule for these reviews. He cancelled the first meeting due to another business commitment. He rescheduled the next meeting for unexplained personal reasons. Two months later, the project manager had still not met with over half of the project team leaders.

Why should project members feel obligated to follow their own plans when the project manager obviously did not follow his?

Page 48: INFS 724 Project and Change Management

48

Important Skills for Project Execution General management skills like leadership,

communication, and political skills Product skills and knowledge (see example of

“What Went Right?” on p. 149) Application area/product vs. technical skills –

What do you think?

Page 49: INFS 724 Project and Change Management

49

Project Execution Tools and Techniques Project management methodology: Many

experienced project managers believe the most effective way to improve project management is to follow a methodology that describes not only what to do in managing a project, but how to do it.

Project management information systems: Hundreds of project management software products are available on the market today, and many organizations are moving toward powerful enterprise project management systems that are accessible via the Internet.

Page 50: INFS 724 Project and Change Management

Monitoring and Controlling

Project Work

Page 51: INFS 724 Project and Change Management

51

Monitoring and Controlling Project Work Monitoring project work includes collecting,

measuring, and disseminating performance information.

Important outputs of monitoring and controlling project work include: Recommended corrective Recommended preventive actions Recommended defect repair

Page 52: INFS 724 Project and Change Management

52

Monitoring and Controlling Project Work (cont.) According to PMBOK (2004), monitoring and

controlling is concerned with: Comparing actual project performance against the

project management plan Assessing performance to determine whether any

corrective/preventive measure is needed Analyze, track, and monitor project risks Maintain an accurate and timely information base

regarding project’s product (s) Provide information to support status reporting Monitor implementation of approved changes

Page 53: INFS 724 Project and Change Management

Integrated change control

Page 54: INFS 724 Project and Change Management

54

Integrated Change Control

Integrated change control involves identifying, evaluating, and managing changes throughout the project life cycle

Three main objectives of change control: Influence the factors that create changes to

ensure they are beneficial Determine that a change has occurred Manage actual changes when and as they

occur

Page 55: INFS 724 Project and Change Management

55

Change Control System

A formal, documented process that describes when and how official project documents and work may be changed

Describes who is authorized to make changes and how to make them

Often includes a change control board (CCB), configuration management, and a process for communicating changes

Page 56: INFS 724 Project and Change Management

56

Change Control Boards (CCBs)

A formal group of people responsible for approving or rejecting changes on a project

CCBs provide guidelines for preparing change requests, evaluate change requests, and manage the implementation of approved changes

Includes stakeholders from the entire organization

Page 57: INFS 724 Project and Change Management

57

Making Timely Changes

Some CCBs only meet occasionally, so it may take too long for changes to occur

Some organizations have policies in place for time-sensitive changes “48-hour policy” allows project team members

to make decisions, then they have 48 hours to reverse the decision pending senior management approval

Delegate changes to the lowest level possible, but keep everyone informed of changes

Page 58: INFS 724 Project and Change Management

58

Configuration Management

Ensures that the products and their descriptions are correct and complete

Concentrates on the management of technology by identifying and controlling the functional and physical design characteristics of products

Configuration management specialists identify and document configuration requirements, control changes, record and report changes, and audit the products to verify conformance to requirements

Page 59: INFS 724 Project and Change Management

59

Suggestions for Managing Integrated Change Control

View project management as a process of constant communications and negotiations

Plan for change Establish a formal change control system, including a

Change Control Board (CCB) Use good configuration management Define procedures for making timely decisions on

smaller changes Use written and oral performance reports to help

identify and manage change Use project management and other software to help

manage and communicate changes