Innovative Contracting

Construction Management Association of America Seminar

May 17, 2013

           

California Department of Transportation

Traditional Project Delivery

Design-Bid-Build (DBB) Specified by Public Contract Code Design must be complete Awarded to the lowest responsible bidder

Why Use Innovative Methods?

Faster Delivery Cost Certainty Constructability Better Partnering Risk Transfer Innovation

Innovative Contracting Effort

Hired Trauner Consulting Services, Inc. to: Identify methods used by others Identify the pros and cons of each method Assist in developing policy, procedures, and

processes for selected methods Assist in developing training

Innovative Contracting Report

Identified 27 methods divided into the following categories:Project Delivery SystemsProcurement PracticesContract Management Methods

Project Delivery Systems

Caltrans Experience Design-Bid-Build Design-Sequencing

Additional Methods Indef. Delivery/

Indef.Quantity Agency-CM CM at-Risk Design-Build Early Contractor

Involvement Project Alliancing Contract Maintenance

Procurement Practices

Caltrans Experience Cost-Plus-Time (A+B)

Bidding Low Bid Lump Sum Bidding

Additional Methods Multi-Parameter

(A+B+C) Bidding Alternate Design Alternate Bid Additive Alternates Best-Value Reverse Auction Bid Averaging

Contract Management Methods

Caltrans Experience Incentive/Disincentive Lane Rental Flexible Notice to

Proceed Warranties

Additional Methods Liquidated Savings Active Management

Payment Mechanism No Excuse Incentives Shared-Risk

Contingency Fund

Design-Build

Design-Build

A delivery method where a contract for both the design and construction of a project is awarded to a single entity.

Design-Build

30% Design

RFQ

RFP

Design

RFC RFC

Construct Construct Construct

RFC

Award

Legislation – Senate Bill 4

Allows 15 design-build projects 10 Caltrans 5 Local

California Transportation Commission must authorize

Prequalification versus shortlisting

Allows “Low Bid” or “Best Value” awards

Sunsets January 1, 2014

Authorized Projects

Awarded Projects LA 10/110 – Express Lanes $ 72 million Mad 99 – Rehabilitate Roadway $ 23 million SM 101 – Install Ramp Metering System $ 11 million Fre 180 – Construct Braided Ramps $ 41 million LA 10/605 – Construct EB 10/SB 605 Connector $ 46 million SD 805 – I-805 North HOV/BRT $ 72 million LA 710 – Gerald Desmond Bridge $650 million SBd 15/215 – Devore Interchange $208 million Riv 91 – HOV Lanes $633 million

Projects Currently in Procurement Cajon Pass $140 million North Region Bridge Deck Rehabilitation $ 58 million

Why Use Design-Build?

Faster Delivery Cost Certainty Constructability Risk Transfer Innovation

Alternative Technical Concepts

Alternative Technical Concepts (ATC) are proposed changes to the Department’s supplied basic configurations, design criteria, or construction criteria which provide a solution that is equal to or better to the requirements in the Request for Proposals.

Alternative Technical Concepts (ATCs)

ATCs submitted – 206Value of ATCs submitted – $967 million

ATCs approved – 109Value of ATCs approved – $502 million

ATCs incorporated – 29

Value of ATCs incorporated – $142 million

Devore Interchange Project

Deliver project 18 months earlier Secured $108 M SHOPP funding for the

project Improved design, I-15 NB continuity Reduced right of way take (10 parcels) Reduced environmental impacts $40 M savings

Construction Manager-General Contractor

Construction Manager /

General Contractor (CM/GC)

A delivery method that allows an owner to engage a construction manager to provide input during the design process. At an agreed upon point, the owner and construction manager negotiate a price for construction of the project and the construction manager becomes the general contractor.

CM/GC Process

30% Design

RFQ

Award (Construction

Services)

Design

Negotiate Price

Construct

Award(Preconstruction

Services)

Preconstruction Services

Constructability Reviews Verify Quantities Estimate Alternatives Value Analysis Risk Analysis Construction Phasing Project Scheduling

Authority

Assembly Bill 2498 (Gordon) Signed September 2012 Added Section 6700 to Public Contract Code Authorizes up to 6 projects by Caltrans Must be administered by Caltrans 5 projects greater than $10 million Effective January 1, 2013 No sunset date

Why Use CM/GC?

Faster Delivery Cost Certainty Constructability Risk Mitigation Innovation

Next Steps

Develop processes and contract templates

Industry outreach

Project selection

Begin procurements

Useful Links

Innovative Procurement Practices Report:

http://www.dot.ca.gov/hq/oppd/contracting/InnovativeProcurementPractices.pdf

Alternative Procurement Guide:

http://www.dot.ca.gov/hq/oppd/contracting/AlternativeProcurementGuide.pdf

Useful Links

Design-Build Demonstration website:

http://www.dot.ca.gov/hq/oppd/designbuild/db.htm

FHWA’s Design-Build Effectiveness Study

http://www.fhwa.dot.gov/reports/designbuild/designbuild.pdf

Useful Links

CMGC Pilot Program website:

http://www.dot.ca.gov/hq/oppd/cmgc/

NCHRP Synthesis 402: Construction Manager-at-Risk Project Delivery for Highway Programs

http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_syn_402.pdf

For More Information Contact:

Raymond S. Tritt

Chief, Office of Special Projects

California Department of Transportation

(916) 653-3348

[email protected]

[email protected]

[email protected]