inspection_tank.docx

27
TABLE OF CONTENTS 1. Scope 2. Applicable Code, Standard And Specification 3. General 4. Material Inspection 4.1 Material Receiving Inspection 5. Material Traceability Control 5.1 Extent of Traceability Control 6. Dimensional Inspection 6.1 Foundation Receiving Inspection 6.2 Location Mark Check 6.3 Fit-up Inspection 6.4 Roundness 6.5 Plumbness 6.6 Local Deviation 7. Nondestructive Examination 7.1 Visual Inspection 7.2 NDE Procedure 7.3 Radiographic Examination (RT) 7.4 Liquid Penetrant Examination (PT) 7.5 Vacuum Box Test (VBT) 7.6 Pneumatic Leak Test (LT) 7.7 Repair and Re-examination 8. Hydrostatic Test 8.1 Pre-test Check 8.2 Water Filling 8.3 Settlement Monitoring 8.4 Hydrostatic Test 8.5 Cleaning 8.6 Hydrostatic Test for Heating Coil 9. Fixed Roof Test 10. Paint Inspection 11. Tank Calibration 12. Final Inspection 13. Witness Inspection 14. Manufacturer’s Data Report 1. Scope This document covers the inspection and test requirements of storage tanks at the construction site specified for the Two (2) nos additional PSR-2 Crude storage tank at Petronas Penapisan Melaka. (PPM) 2. Applicable Code, Standard And Specification The following standards, code, and specifications have been used as a source of information in the preparation of this document. API Standard API 650-9th Ed. 1995 : Welded Steel Tanks for Oil Storage ASME CODE ASME SEC. VIII DIV.1 : Rules for Construction of Pressure Vessels ASME SEC.V : Nondestructive Examination

Upload: sbmmla

Post on 29-Oct-2015

108 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: INSPECTION_TANK.docx

TABLE OF CONTENTS

1. Scope2. Applicable Code, Standard And Specification3. General4. Material Inspection4.1 Material Receiving Inspection5. Material Traceability Control5.1 Extent of Traceability Control6. Dimensional Inspection6.1 Foundation Receiving Inspection6.2 Location Mark Check6.3 Fit-up Inspection6.4 Roundness6.5 Plumbness6.6 Local Deviation7. Nondestructive Examination7.1 Visual Inspection7.2 NDE Procedure7.3 Radiographic Examination (RT)7.4 Liquid Penetrant Examination (PT)7.5 Vacuum Box Test (VBT)7.6 Pneumatic Leak Test (LT)7.7 Repair and Re-examination8. Hydrostatic Test8.1 Pre-test Check8.2 Water Filling8.3 Settlement Monitoring8.4 Hydrostatic Test8.5 Cleaning8.6 Hydrostatic Test for Heating Coil9. Fixed Roof Test10. Paint Inspection11. Tank Calibration12. Final Inspection13. Witness Inspection14. Manufacturer’s Data Report

1. Scope This document covers the inspection and test requirements of storage tanks at the construction site specified for the Two (2) nos additional PSR-2 Crude storage tank at Petronas Penapisan Melaka. (PPM)

2. Applicable Code, Standard And SpecificationThe following standards, code, and specifications have been used as a source of information in the preparation of this document.API StandardAPI 650-9th Ed. 1995 : Welded Steel Tanks for Oil StorageASME CODEASME SEC. VIII DIV.1 : Rules for Construction of Pressure VesselsASME SEC.V : Nondestructive ExaminationASME SEC.IX : Welding and Brazing QualificationsWH’S SPECIFICATION: Construction (Erection) Procedure Specicification: NDT (Non Destructive Procedure): Scheme for Water Filling Test and Settlement Measurement: Quality Plan

3. General

Page 2: INSPECTION_TANK.docx

(1) Unless otherwise specified in this specification, inspection and testing shall be performed in accordance with WH’s Quality Plan and applicable codes, standards and PTS.

(2) Field QC personnel shall carefully follow the construction and testing of tanks, and shall make sure that it complies in all details with design, construction, inspection and tests specified by the applicable codes, standards and specification.

4. Material Inspection4.1 Material Receiving InspectionVisual inspection of incoming material including the fabricated tank material sent from the shop, shall be made by the field QC personnel to ensure that there is no injurious defect on the surface and cut edges. Check on the identification number of raw material shall be made against material certificates. Check on the erection mark of fabricated tank material shall be made against the corresponding drawings.

5. Material Traceability Control5.1 Extent of Traceability ControlThe following tank components are required to be traceable against the material certificate. The As-built Sketch shall be prepared upon completion of the erection.a. Shell PlateCoded marking made at shop can be used to identify the material and be recorded in As-built Sketch. As-build Sketch may be supported by the related material identification records sent from shop.

6. Dimensional Inspection

6.1 Foundation Receiving InspectionAll the stage of receiving tank foundation, the field QC personnel shall review the foundation inspection report. Spot check of actual dimension and bench mark shall be made against the report.

6.2 Location Mark CheckPrior to the primary laying-down or erection of Bottom Plate, Bottom Sketch Plate, Shell Plate, Roof Structures and Roof Plate, the field QC personnel shall check the location marking in accordance with the related orientation drawings. Similarly, prior to make the Nozzle/Manhole opening, the location marking of opening shall be ensured.

6.3 Fit-up InspectionWeld preparation and dimensional accuracy shall be checked prior to start welding. Butt welds of Shell joints shall be matched accurately and retained in position during welding operation.Misalignment of Shell weld joint shall not exceed the following tolerance.a. In completed shell vertical jointShell Plate 15.8 mm thk : 1.6 mmb. In completed shell horizonttal jointUpper Plate 15.8 mm thk : 1.6 mmFor Bottom Annular butt weld, the tolerances of vertical joints shall be applied.

6.4 RoundnessPrior to commencement of shell to Bottom Sketch plate weld, the tank internal radius shall be measured. The horizontally measured tank radius at 300 mm above the bottom corner weld shall not exceed the following tolerances.Tank < 12 m diameter : + 13 mm 6.5 Plumbness The first course shell plate shall be checked for plumbness, level and roundness before welding in accordance with WH’s construction procedure to ensure that the tank will be completed within the specified dimensional tolerances. Plumbness of Shell shall be inspected after completion of all Shell welds. The out-of plumbness shall not exceed 1/200 of the total tank height. 6.6 Local Deviation Local deviation shall be inspected, if there is any noticeable distortion after completion of shell weld. The Local deviation shall not exceed the tolerance of 13 mm. 6.7 All nozzle and couplings directly connected with piping shall be at the correct elevations from the surface of bottom plate and radial positions after completion of welding and erection and remain at the following tolerance. Elevation of nozzle : + 10 mm Radial position of nozzle : + 15 mm Nozzle projection : + 10 mm Inclination of flange face : + 0.5°

Page 3: INSPECTION_TANK.docx

7. Nondestructive Examination

7.1 Visual InspectionRegardless any other nondestructive inspection method applied, all the site welds shall be subjected to visual inspection, and meet the requirements of API 650 Sec. 6 para 6.5.

7.2 NDE ProcedureGeneral requirements, examiner’s qualification, equipment and operation procedure of nondestructive examination shall be in accordance with WH Specification : Nondestructive Test Procedure.

7.3 Radiographic Examination (RT)The following RT shall be performed.a. Shell vertical / horizontal joints and bottom annular radial joints shall be radiographed in accordance with the requirement of API 650 Sec. 6 para 6.1.Heating coil butt joints shall be radiographed on spot basis. Minimum 5% butt joints of heating coil welded by each welder shall be fully radiographed.b. Radiographs shall be judged in accordance with API 650 Sec. 6 para 6.1.5.c. When a spot radiograph fail to comply with the acceptance standard, additional radiographs shall be taken in accordance with the requirement of API 650 Sec. 6 para 6.1.6.

7.4 Liquid Penetrant Examination (PT)

The following PT shall be performed.a. The attachment welds of nozzle / manhole welded to shell at site shall be examined by PT.b. The acceptance standard shall be in accordance with API 650 sec. 6 para 6.4.4.

7.5 Vacuum Box Test (VBT)

The following vacuum box test shall be performed.a. All Bottom welds, i.e. Bottom-to-Bottom, Sketch Bottom Sketch-to-Bottom Sketch, Bottom Sketch-to-Shell joints, shall be inspected.b. Any leakage observed by VBT is unacceptable.

7.6 Pneumatic Leak Test (LT)

The following pneumatic leak test shall be performed.All attachment weld of reinforcement plate on each shell opening welded at site shall be inspected in accordance with API 650 Sec. 5 para 5.3.5. Any leakage observed by LT is unacceptable.

7.7 Repair and Re-examination

When an imperfection is judged to be repaired by welding, repair welding shall be make in accordance with the applicable welding procedure. Repaired are shall be re-examined by the same method originally used.

8. Hydrostatic Test

8.1 Pre-test Checka. Before filling water into the tank, it shall be ensured that all inspection on Bottom, Shell and Roof including attachment welds shall be completed.b. Any foreign articles shall not be left in the tank.

8.2 Water Fillinga. The water filling rate shall be decided with consideration given to tank size, pump facilities, water supply available, stability of foundation settlement, and other matter relating to safety.b. When foundation settlements are negligible or significantly greater than expected settlement, water filling rate may be changed.c. During the entire filling and emptying operation, roof manhole and/or other openings shall be kept open.

Page 4: INSPECTION_TANK.docx

d. During the water filling, the floating roof shall be checked frequently for leaks.

8.3 Settlement Monitoringa. Settlement reading shall be take at a minimum of 4 points around the base of tank.b. Settlement reading shall be taken and reported to Contractor at least once a day while the tank is being filled with water and emptied.

8.4 Hydrostatic Testa. Water shall be filled to the specified test level as WH Spec.b. After the tank filled to test water level, all welds in the shell, including shell to bottom Sketch Plate welds, shall be visually inspected for water tightness.c. Water shall be maintained at the test level for minimum of 24 hours after which water may be discharged.d. Prior to starting the water discharging, ensure that the roof openings are opened.

8.5 Cleaninga. During and after the tank is emptied, the inside of tank shall be cleaned.b. All sand, sludge and rubbish on the tank bottom shall be removed.

8.6 Hydrostatic Test for Heating CoilHeating coil shall be tested hydrostatically at a pressure specified in applicable drawing.

9. Fixed Roof TestWhile the tank is maintained at the test water level, welds on the fixed roof shall be pneumatically leak tested. Non-pressure tank roofs shall be tested to pressure not exceeding the weight of the roof plates with compressed air and low-pressure tank roofs shall be tested to a pressure equal to the maximum internal pressure rating. The inaccessible are during hydrostatic test shall be inspected in advance by vacuum box.

10. Paint InspectionPaint inspection shall cover the following items.a. paint material checkb. surface preparation checkc. paint application checkd. dry film thickness (DFT) checke. visual inspection of completed surfacef. pinhole test for tank internal lining

The magnetic pull-off type gauge or fixed probe magnetic flux type gauge shall be used for DFT readings. For each coat of paint, the DFT shall be taken at a frequency of one measurement of every 10 square meters area. Each measurement consists of an average of three gauge readings next to one another. All spot measurements shall not be less that 100% of the specified DFT.After the final coating has been completed, the field QC personnel shall ensure that the appropriate clean-up is done, and that any abrasions, nicks or scrapes are repaired as required.

11. Tank CalibrationTank calibration and preparation of gauge table shall be performed by a specialized firm in accordance with internationally accepted method and with local statutory requirements.

12. Final InspectionPrior to tank box-up, the inside of tank shall be thoroughly ensured clean. Flange surfaces of Nozzle/Manhole shall be carefully inspected for defects which may caused and leakage.It shall be also ensured that all works required by drawings, specifications and the related inspection and test plan have been thoroughly completed.

13. Witness InspectionThe scope of inspection by Vendor, CONTRACTOR, and OWNER is indicated in Scope of Inspection. The Inspection and Test Plan shall be progressively followed by the inspector throughout site construction.

Page 5: INSPECTION_TANK.docx

14. Manufacture’s Data Report (MDR)The site portion of MDR shall be compiled at site as the construction is progressing. The completed site MDR shall be submitted to CONTRACTOR, while a original copy will be sent to WH home office for retaining. As a minimum, the following inspection records shall be included in the site MDR as per Quality Plan.a. Inspection Certificateb. As-built Sketch of Shell Platec. Welders Map of Shell and Bottom Plate/WPS & PQR/Welder’s Qualification Recordsd. NDE Record of RT, PT, VBT and LTe. Dimensional Inspection Record of Tank Foundation, Roundness and Plumbnessf. Hydrostatic Test Record including settlement datag. Roof Test Recordh. Paint Inspection Record

Thursday, December 17, 2009

TANK ERECTION PROCEDURE *note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS

1. SCOPE2. APPLICABLE CODE3. FOUNDATION4. CONSTRUCTION PROCEDURE4.1. BOTTOM PLATE4.2. SHELL PLATE4.3. ROOF STRUCTURE4.4. ROOF PLATE4.5. OUTER RAFTER ERECTION PROCEDURE4.6. WIND PROTECTION OF SHELL PLATE AND ROOF STRUCTURE4.7. TEST4.8. CALIBRATION4.9. ATTACHMENT

1. SCOPEThis specification covers construction (erection) procedure for field erection of Two (2) nos additional crude Storage Tanks.

2. APPLICABLE CODEa. ASME IX: : Welding & Brazing Qualification

b. B31.3 : Chemical Plant, Petroleum and Refinery piping.

c. ASME V : Non Destructive Testing

d. API650 : Welded Steel Tank for Oil Storage.

e. BS 2654 : Vertical Steel Welded Non-refrigerated Storage Tank with Butt welds for the Petroleum Industry.

f. Client Technical Standard

Page 6: INSPECTION_TANK.docx

PTS-20.156A :Standard Tank Vol. 1 – Part 1PTS-20.156B :Standard Tank Vol. 1 – Part 2PTS-20.156C :Standard Tank Vol. 2 – Part 3

g. Contractor Specification: Field Inspection Procedure Specification: Water Filling Test: Quality Plan

3. FOUNDATIONThe following item of the foundation shall be confirmed and accepted by warga Hikmat QC and Client rep (PPMSB) prior to erection of the tanks.(Refer to PTS-20.156A – 09.00.00- Foundation)

i. Level and Direction of the foundationii. Camber and flatness of foundation surface

4. CONSTRUCTION PROCEDURE(Refer to PTS-20.156B – 10.00.00 Erection & 10.02.00 Erection Procedure)

4.1 BOTTOM PLATE

(1) Arrangement and welding of the Bottom plate shall conducted as per Bottom Plate Welding Sequence in Attachment 1 and detail procedure as follow;i. Marking of centre line.ii. Bottom plate arrangement as per welding sequence and applicable drawing.iii. Fitting between shell and bottom plate.

(2) Bottom plate shall be welded by back step or skip welding method.

(3) To prevent welding distortion, restraint jigs or reinforcing beams shall be used.

4.2 SHELL PLATE

(1) Prior to erection of shell plate, following marking shall be performed on the bottom plate as shown in Fig. 1 & Fig. 2

i. Marking of radius for shell erection. (The marking shall be larger than the diameter shown in the drawing, considering weld shrinkage of shell plate).ii. Radius for checking the roundness of shell plate shall be marked.iii. The marking allotment of 1st course of shell plate shall be carried out.(2) Level, roundness and verticality shall be inspected after completion of erection of 1st course of shell plate.

(3) Shell plate from second to fifth course and top angle shall be erected.

(4) Welding of shell plate shall be performed from lower course, and vertical joint shall be welded prior to the horizontal joint.

4.2.1 DETAIL ERECTION PROCEDURE OF SHELL PLATE.The sequence of erection and welding are as follow:

1) Erection of 1st course.

2) Check level, verticality and roundness of 1st course.

3) I) Erection of 2nd course. After completion of erection of second course, the vertical joint of 1st course shall be welded.

Page 7: INSPECTION_TANK.docx

ii) Vertical joint of 2nd course shall be aligned.iii) Local departure, tolerance cut horizontal and vertical shell seams shall be checked.

4) i) Erection of 3rd course. After completion of erection of third course, the vertical joint of 2nd course shall be welded follow by horizontal joint between 1st course and 2nd course.ii) Local departure, tolerance cut horizontal and vertical shell seams shall be checked.

5) i) Erection of 4th course. After completion of erection of fourth course, the vertical joint of 3rd course shall be welded follow by horizontal joint between 2nd course and 3rd course.ii) Joint between shell plate and bottom plate shall be welded.iii) Local departure, tolerance cut horizontal and vertical shell seams shall be checked.

6) i) Erection of 5th course. After completion of erection of fifth course, the vertical joint of 4th and 5th course shall be welded follow by horizontal joint between 3rd and 4th course, and between 4th course to fifth course.ii) Local departure, tolerance cut horizontal and vertical shell seams shall be checked.

7) i) Installation of top angle. Dimensional shall be checked prior welding the top angle to the top (last) course.ii) Local departure, tolerance cut horizontal and vertical shell seams shall be checked.

4.3 ROOF STRUCTURE

i. Roof structure shall be assemble on the ground in section or completed depending on size and weight.

ii. Assembled roof structure shall be erected inside the tank after completion of bottom plate and annular plate.

4.4 ROOF PLATERoof plate shall be arranged on the roof structure and welding to be carried out according to welding sequence considering the distortion or warping of plates.

4.5 OUTER RAFTER ERECTION PROCEDURERoof of outer rafter shall be assemble on the ground in section or completed depending on size and weight. The sequence of assembly are as follow;

1. Assemble the roof plate on the temporary support.

2. Assemble and welding the center ring and center plate complete with stiffener and rib plate.

3. Fit the ring on the roof plate.

4. Install the rafter and girder on the roof plate.

5. Erect the outer rafter on the temporary support after completion of bottom plate and annular plate.

4.6 WIND PROTECTION OF SHELL PLATE AND ROOF STRUCTUREShell plate and roof structures shall be protected by heavy wind during the erection using guy wire rope method. A detailed execution procedure and/ or plan including the detailed dimensions of the device shall be prepared and submitted to CLIENT site for approval, prior to commencement of shell construction work.

4.7 TESTAfter completion of the entire tank, test shall be performed in accordance with WH FIELD INSPECTION & TEST PROCEDURE SPECIFICATION.

4.8 CALIBRATIONAfter completion of the required test, the tank shall be calibrated in accordance to WH FIELD INSPECTION & TEST PROCEDURE SPECIFICATION.

Page 8: INSPECTION_TANK.docx

4.9 ATTACHMENT:

1. Fig 1 AND Fig 2.2. Welding Sequence For Bottom Plate.

Page 9: INSPECTION_TANK.docx

Thursday, December 17, 2009

SHOP FABRICATION PROCEDURE *note: this is the sample document for the related job only*author: [email protected]

Page 10: INSPECTION_TANK.docx

TABLE OF CONTENTS

1.0 GENERAL1.1 Scope1.2 Drawing1.3 Material1.4 Welding1.5 Inspection1.6 Post Weld Heat Treatment1.7 Painting

2.0 SHOP FABRICATION2.1 Shell Plate2.2 Roof Plate2.3 Roof Structure2.4 Top Angle and Stiffener2.5 Manhole & Nozzle (Unit Fabrication)2.6 Reinforcing Plate2.7 Stairway, Ladder & Platform2.8 Heater piping. (if any)2.9 Other Accessories

3.0 Dimensional Tolerance3.1 Shell Plate3.2 Roof Plate3.3 Roof Structure3.4 Top Angle. Stiffener and top Birder3.5 Nozzle and Manhole

1. GENERAL

1.1 ScopeThis specification covers the requirement for shop fabrication of the EPCC of Two (2) nos additional crude Storage Tanks.

1.2 DrawingAll shop fabrication shall be carried out in accordance with WH fabrication drawings.

1.3 MaterialAll material shall comply with WH drawing and applicable CLIENT specification.

1.4 WeldingTo submit all WPS and WQT for review and approved by 3rd Party Inspector (Dosh approved NDT)All welding shall be carried out in accordance with approved Welding Procedure Specification. (Shop/Site)

1.5 InspectionInspection shall be carried out in accordance with Shop Inspection Procedure Specification.

1.6 Post Weld Heat TreatmentPost weld heat treatment shall not be required for this project.

1.7 PaintingPainting at shop shall be carried out in accordance with Painting specification.

2 SHOP FABRICATION

2.1 Shell Plate

Page 11: INSPECTION_TANK.docx

Cutting and/or edge preparation shall be done with flame planer or automatic gas cutting and/or automatic beveling machine.All damage such as pop-outs, deep burn serrations shall be repaired by grinding.After edge preparation, shell plates shall be cold rolled to the curvature in accordance with fabrication drawings.The weld edges shall free from oil, dust, scale, water and other foreign materials, then shall be coated with weld able paint.

2.2 Roof PlateRoof plate shall be marked off in accordance with fabrication drawing and the edge shall be cut with automatic gas cutting for shop fabrication.

2.3 Roof StructureRafter, girder and column shall be prefabricated to be ready for erection.

2.4 Top Angle and StiffenerTop angle and stiffener shall be rolled to suit the curvature of the tank with bending roll machine, then both ends shall be cut and edge prepared.

2.5 Manhole & Nozzle (Unit Fabrication)Neck plate of manhole shall be cut with automatic gas cutting machine according to the drawing and be cold rolled.Seam joint shall be welded and then Flange shall be welded to manhole neck.Nozzle pipe shall be beveled end with pipe cutter or gas cutting machine, and flange shall be welded to nozzle pipe.

2.6 Reinforcing PlateReinforcing plate shall be outer periphery cut, opened and beveled with automatic gas cutting machine after marking off then pressed or rolled to suit the tank curvature.

2.7 Stairway, Ladder & PlatformHandrails shall be shaped to the specified curvature with bender.Treads and platform shall be fabricated to be ready for site erection.

2.8 Heater piping. (if any)Cutting of pipes may be done either by mechanical or thermal (flame, arch or plasma) means.For carbon steel, thermal cutting and beveling may be used only if the cut is reasonably smooth and all oxides are removed from the surface.

2.9 Other AccessoriesOther accessories shall be fabricated completely in accordance with drawings.

Page 15: INSPECTION_TANK.docx

WELDING MATERIAL CONTROL PROCEDURE *note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS

1. SCOPE 2. REFERENCE 3. RESPONSIBILITIES3.1 SITE MANAGER 3.2 QC MANAGER3.3 QA ENGINEER3.4 QC INSPECTOR4. WELDING MATERIAL CONTROL

Page 16: INSPECTION_TANK.docx

1.0 SCOPE This procedure shall outline the control of welding materials in welding works for the EPCC of Two (2)Nos crude Storage Tank

2.0 REFERENCE1) PTS 64.51.01.31 - STANDARD VERTICAL TANKS ERECTION & TESTING (Section 6.5 –Welding Consumables)2) IS/D-322 - FIELD INSPECTION & TESTING PROCEDURE3) IS/D-310 - MATERIAL CONTROL PROCEDURE4) KOBE / ESAB - MANUFACTURE RECOMENDATION

3.0 RESPONSIBILITIES3.1 Site ManagerShall be responsible for the full implementation of this procedure. He shall assign knowledgeableMaterial Controllers / Welding Foreman who will be able to distinguish all types welding consumables.3.2 QC ManagerShall be responsible for ensuring that all personnel involved are indoctrinated and shall assignpersonnel to conduct monitoring and audits for compliance to this procedure.3.3 QA EngineerShall be responsible for Supervision of Inspection activities, monitoring and documentinginspection / monitoring activities.

3.4 QC InspectorShall inspect welding material control on daily basis and document any deviation from this procedure.

4.0 WELDING MATERIAL CONTROL4.1 All welding materials shall be received by the Material Controller / Welding Foreman. He shall checkwelding material condition, damage, material identification and batch / lot / heat / number. All weldingmaterials received shall be accompanied by an Inspection Certification form manufacturer or supplier. The QA Engineer shall review the manufacturers inspection certificates for compliance to thespecifications and if acceptable sign and stamp “Issued For Construction”. The certificate shall besubmitted to contractor for review

4.2 The Material Controller / Welding Foreman shall check that sufficient quantity is stored in baking /holding oven for daily use. The Material Controller / Welding Foreman shall issue as follows:1. Issue electrodes by priority,a. re-baked electrodesb. first baked electrodesc. new electrodes2. Check size and type of welding material to be issued3. Issued maximum quantity of 5kg for each portable oven4. For GTAW rods, original containers shall be issued. For stainless steels the container or welders quiver shall be clearly marked by paint or colored tape with the same color identification asgiven by the consumable manufacturer. 5. Issue of portable oven marked with Welders no only to respective welders.6. Issues of consumables are to be recorded on Consumable Issue Report.

4.3 The Material Controller / Welding Foreman shall monitor / check his welder’s portable oven (quivers)are plugged to power source all the time. At the end of the day, he shall gather all quivers and take tothe welding material control room.

4.4 After receiving all portable ovens the Material Controller / Welding Foreman shall place all segregatedelectrodes and place at top portion of baling oven and shall be issued first on the next day. Returnedelectrodes shall be re baked only once. There after they shall disposed of as scrap.

Page 17: INSPECTION_TANK.docx

Sunday, December 20, 2009

PRESSURE TEST PROCEDURE FOR PIPING SYSTEM *note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS

1. SCOPE 2. REFERENCES 3. GENERAL REQUIREMENTS 4. PNEUMATIC TEST 5. EQUIPMENT FOR HYDROSTATIC TEST 6. PREPARATION OF THE TEST PACKAGE7. LIMITATION, EXCEPTIONS AND EXCLUSIONS8. FIELD PREPARATION9. PERFORMANCE OF PRESSURE TEST10. EVALUATION OF TEST RESULTS11. REPORT / DOCUMENTATION12. REINSTATEMENT13. ATTACHMENT 1 (TEST MANIFOLD)

1.0 SCOPE 1.1 This procedure covers the minimum requirements and plans for field pressure test of piping system forThe EPCC of Two (2) nos additional crude Storage Tanks.

2.0 REFERENCE2.1 ANSI / ASME B31.3 - Chemical Plant and Petroleum Refinery Piping

3.0 GENERAL REQUIREMENT3.1 All piping lines shall be hydrostatic tested, but however, lines which where indicated in the line list maybe service test.3.2 All lines which were indicated as a tie-in joint need to do 100% NDT such as RT, MPI or DPT andcarry out the service test.3.3 The minimum test pressure shall be as specified in each piping Iso drawing or pressure test flowdiagram based on ANSI / ASME B31-3 requirement.3.4 Test medium shall be fresh water, which clean and free from silt or un dissolved solids of anydescription.3.5 Test medium for austenitic stainless steel piping the water shall not contain more than 30 ppm chloride10N.3.6 All the equipment and lines, which are to be tested along with the piping, shall be blanked off orreplaced with temporary spool pieces. Any test along the said item shall be approved by Contractor.3.7 All pressure gauge and pressure recorder used for the test shall be calibrated and registered inaccordance with Calibration of Test/ Inspection Tools Control Procedure. Each certificate shall bevalid for a period of three (3) months. Pressure gauge shall be selected so that the test pressure of thesystem falls between 30% and 75% of the gauge scale range. The following in line items will not besubjected to Field Pressure Testing:-1) Elements of strainers and filters2) Pressure relieving devices such as rupture disc, pressure valves etc.3) Locally mounted pressure gauge.4) Pressure measuring and regulating items such as flow control valves, turbine meters etc.5) Equipment like pumps, hose reels etc.6) Lines directly open to the atmosphere such as vents drains, safety valves, discharge etc. (conformationis required from Contractor)

Page 18: INSPECTION_TANK.docx

4.0 PNEUMATIC TESTS4.1 Pneumatic test may be applied for certain lines and test pressure shall be 110% of design pressure asspecified in each piping Iso drawing and / or pressure test flow diagram as per ANSI / ASME B.31-3requirement 345.5.4.4.2 The pressure shall be increased gradually until a gauge pressure which is the lesser of ½ the testpressure or 25 psi (170kpa) is attained and held for 10 minutes, at which time a preliminary leak checkshall be made with soap solution on all joint. The pressure shall be increased in steps of 25%, 50%and 75% of the test pressure. At each step the pressure shall be held for sufficient time to allow thepiping to equalize strains. After holding at test pressure for 10 minutes, the pressure shall be reducedto the design pressure for leakage examination. Leak testing of joints shall be done with soapy water.Safety precautions shall be taken by placing a safety relief valve on the system under test.4.3 The set pressure of the relief valve shall be set at a pressure not higher than the test pressure plus thelesser of 50 psi (340kpa) or 10% of the test pressure

5.0 EQUIPMENT FOR HYDROSTATIC TEST5.1 Equipment for hydrostatic test shall be properly designed and in good working order and shall becompatible with the pressure and capacity required during the test.5.2 The following equipment will be provided in order to conduct the hydrostatic test but not necessarily belimited to the following:-1) One high volume pump2) One portable tank to provide a source of pressurizing water3) One hand pump for pressurizing4) Pressure gauges and temperature gauges5) Pressure recorder6) Safety relief valve (only for pneumatic test)7) Test manifolds (if required)

6.0 PREPARATION OF TEST PACKAGE6.1 Prior to commencement the Field Hydrostatic Test the piping test package shall be prepared andsubmitted to the Client Inspector for review / approval.6.2 The following documents will be included in the test package:-1) Piping test package certificate2) Test block diagrams3) Signed off punch list4) Signed off Q.C check sheet5) Q.C Iso drawing6) Pressure Gauge calibration Records (calibration certificates)6.3 When the documents in test package are proper and approved by the Contractor. Line check shall bemade in accordance with approved procedure prior to the test.6.4 All welds to be pressure tested shall be free of paint, thermal insulation coating and wrapping.

7.0 LIMITATION, EXCEPTIONS AND EXCLUSIONS7.1 Where the test pressure of piping attached to a vessel is the same as or less then the test pressure for the vessel, the piping may be tested with the vessel at the test pressure of the piping.7.2 Where the test pressure at the piping exceeds the vessel test pressure and it is not consideredpracticable to isolate the piping from vessels, the piping and the vessels may be tested together at thetest pressure of the vessels, when approved by the owner, and provided the test pressure is not less77% of the piping test pressure. (ASME B 31.3)(337.4.2)7.3 The equipment or piping which is not subjected to the test shall be blinded off from the piping to betested.

8.0 FIELD PREPARATION8.1 When the whole length of system to be tested is completely installed and boundaries are checked by

Page 19: INSPECTION_TANK.docx

Subcontractor Q.C8.2 Test manifold shall be provided in order to supply water to the system, install pressure gauge,temperature gauge and safety relief valve.8.3 Pressure gauge shall be provided at two points where one is to be located at highest location in thesystem and the other at the manifold. 8.4 All test blanks required for pressure test shall have sufficient thickness to ensure safety during test orpermanent blinds may be used for the field pressure testing.8.5 Prior to commencement of the hydrotest, all hot works shall be completed.

9.0 PERFORMANCE OF HYDROSTATIC9.1 All vents and other connections which can serve as pressure test vents, shall be open during filling sothat air can be vented prior to applying test pressure to the system.9.2 The system shall be filled with fresh water by use of electrical or hand pressurizing pump until theintended pressure, slowly and gradually.9.3 While the system is being pressured all weld joints will be visually inspected for any leakage.9.4 Once attained, the intended test pressure shall be held for a period of 30 minutes minimum or suchtime as required for full visual inspection of the system.9.5 Any joints found leaking during the pressure test shall be retested to the specified test pressure afterrepair have been made.9.6 After hydrostatic testing of the system is completed, all lines and equipment shall be drainedcompletely. The system shall be vented while draining to avoid vacuum.9.7 All pressure test must be witness and report to be endorsed by Client rep.

10 EVALUATION OF TEST RESULTS10.1 If there is no leakage during the test it will be considered as accepted and test report to beendorsed by Client.

11 REPORT / DOCUMENTATION11.1 After pressure test, the pressure test records and the post-test punch items shall be signed off bySubcontractor approved by Contractor and endorsed by PPM’s rep. All this documents shall becompiled into the Test package.

12 REINSTATEMENT12.1 After completion of hydrostatic test, all the system shall be reinstated as per the approved drawings.

REPAIR PROCEDURE FOR TANK *note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS1. INTRODUCTION2. PURPOSE3. SPECIFICATION4. APPLICABLE CODE / STANDADR5. METHOD AND INSPECTION6. SAFETY7. REFERENCES & OTHER SUPPORTIVES DOCUMENT - LIST OF WPS & PQR - LIST OF WQT ( WELDER LIST )

REPAIR PROCEDURE 1. INTRODUCTIONThis repair procedure is required for grind off and / or perform weld repair on minor defect such as Cluster Porosity, Slug, Under Cut, Arc Strike, Spartter and etc. which have been found during visual inspection and / or found by NDE.

Page 20: INSPECTION_TANK.docx

2. PURPOSEThe purpose of this work is as follow: To grind off all the defect, at the defect area base on the report and / or marking area and carry out visual inspection and follow by NDE, examination such as MPI / DPT To perform welding at the defect area after grinding ( surface preparation ) and carry out NDE such as MPI, DPT or RT 3. SPECIFICATIONAs per Owner / Client requiment or NDE report.

4. APPLICABLE CODE / STANDARDThe welding and NTD works are to be carried out and in accordance with the following:i) ASME VIII DIV 1 - UW 42 “Surface Weld Metal Build Up” - Appendix 6 “Method For Magnetic particle Testing” - Appendix 8 “Method For Liquid penetrating Testing”ii) ASME IX - Welding And Brazing Qualification iii) ASME V - Nondestructive Examination

5. METHOD & INSPECTION5.1) Mark the defect area to grind off accordingly by appointed inspector and base on NDE (RT, MPI or DPT) report.5.2) Grind off the defect until meet the sound metal and perform NDE to confirm the has been removed from the respective shell area for welding surface preparation.5.3) Perform surface preparation before performing weld build up.5.4) Ensure that area is free from Oil, Grease, Water or any other foreign material5.5) Proceed weld build up by qualified welder, WPS No as per requiment refer to Welding Qualification. 5.6) Perform NDT upon completion of weld build up on the defect / marking area.5.7) If the result of NDE is unacceptable remove the defect by grinding and repeat NDE to ensure it is completely removed.5.8) If the result of NDE is acceptable, carry out the Visual Inspection and request for RT to confirm the weldment are free from and indication / defect.

6. SAFETY6.1) All condition stated on job safety analysis (JSA) must complied with permit to work (PTW).6.2) All personal working at job site shall be informed to the safety awareness by attending the safety induction or safety tools box meeting conducted by safety prior to commencing of work.6.3) Full PPE is ensured whilst working at site.6.4) Refer to safety requirement.

7. REFERENCES & OTHER SUPPORTIVE DOCUMENT7.1) WPS & PQR – To be Advice7.2) WQT List or Welder list – To be Advice

This BlogLinked From HereThe WebThursday, December 24, 2009

CALIBRATION OF TEST INSPECTION TOOL CONTROL PROCEDURE *note: this is the sample document for the related job only*author: [email protected]

TABLE OF CONTENTS

1.SCOPE2.REFERENCES3.RESPONSIBILITIES4.PROCEDURE4.1 CALIBRATION4.2 REGISTRATION4.3 DOCUMENTATION

Page 21: INSPECTION_TANK.docx

1.0 SCOPE To provide procedure guidelines for controlling calibration test and inspection tools to be used for inspection at the construction of The EPCC of Two (2) nos. of Storage Tanks.

2.0 REFERENCES Field Inspection Procedure QA/QC Requirements for Subcontractors Control of Measuring and Test Equipment Specification for Pressure Testing of Piping.

3.0 RESPONSIBILITIES

3.1 Site Manager Shall be responsible for the full implementation and administration of this procedure3.2 QC Manager Shall be responsible for ensuring that all personnel involve are indoctrinated about this procedure.3.3 QA Engineer Shall Check and monitor the calibration and registration of testing tools and equipment necessary for the conduct of inspections in accordance with this procedure. Shall record and file all documents pertaining to the calibration certificate and registration of Testing / Inspection Tools.

4.0 PROCEDURE

4.1 Calibration 1) Equipment that needs to be calibrated shall be sent to a calibration Agent equipped with laboratory facilities for conduction calibration of inspection and test equipment except for equipment that can be calibrated on site.2) All equipment tests shall be designated with a controlled serial number which shall be engraved on the equipment. A calibration label shall be attached to the equipment which shall contain the serial no, registration no. frequency of calibration and date of calibration3) Calibration frequency of each equipment shall be subject to change according to the manufacturer’s instruction, frequency of use and adjustments mode during calibration.4) The control of deficient measuring and test equipment shall be controlled in accordance with Client requirement.4.2 Registration All equipment for measuring and testing to be used shall be submitted to the Contractor for registration. The ‘Equipment Calibration Registration Record’ shall be filled up and registry of the necessary information made before submission together with the calibration certificate.4.3 Documentation Registration of equipment in accordance with the Contractor’s procedure shall be documented using the ‘Equipment Calibration and Registration Record’. The record shall be filed together with calibration certificates and manufacturer’s instructions in a manner for easy filling and retrieval.

Tuesday, December 29, 2009

MATERIAL IDENTIFICATION AND MARKING PROCEDURE 1.1 SCOPE

This specification describes the requirement of material identification and marking procedure.

2.0 MATERIAL IDENTIFICATION AND MARKING

2.1 The material identification shall be carried out in order to :-i) Confirm that the material to be used shall comply with the Mill Certificate.ii) Identify the individual primary component (i.e. shell plate, roof plate and bottom plate) so that it can be traced back to the Mill Certificate later after shop fabrication. This shall be documented in the Inspection Record.

2.2 The following identification mark shall be used :-

Page 22: INSPECTION_TANK.docx

i) Mill marking which consists of heat number, size, plate number, etc. This marking shall be stenciled or stamped on the material by the Mill.ii) Code marking which consists of tank number, drawing number, part number and serial piece number. The code marking shall correspond to the Mill Certificate as documented in the Inspection Record.