installation – accelerator systems
DESCRIPTION
Installation – Accelerator Systems. Installation Planning & Schedules Install org chart & planning 2007 Installations BTH -> FEH “2008” Installation. * Denotes IMT member. Installation Planning. 2007 SLAC Shutdown SLAC downtime – September, October, November 2007 - PowerPoint PPT PresentationTRANSCRIPT
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 1
Installation – Accelerator Systems
•Installation Planning & Schedules– Install org chart & planning– 2007 Installations– BTH -> FEH “2008” Installation
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 2
* Denotes IMT member
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 3
Installation Planning• 2007 SLAC Shutdown
–SLAC downtime – September, October, November 2007• 2007 Installation Planning
– Installation through BC2 & all cable plant; including cables through the BSY into the BTH West– Using SLAC Schedule process for SLAC resource loading
• 2008 Installation Planning– LCLS installations begin at Early Occupancy dates defined by TCCo & LCLS– 2008 Installation schedule developed to begin detailed planning & integration process – refined by the rebaseline
• Early Co-Occupancy dates being defined• Will follow on 2007 Installation learning curve and use P3 for detailed install schedule (shift work, multiple calendars, etc)• Schedule shows Metrology work starting as early as December 2007
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 4
2007 Installation ScheduleLCLS 2007 Installation schedule includes:
Facilities WorkSector 21 – 30 electricalBTH West MEP & LCW
Cable PlantSector 24 – 30
I&C and DC cables for BC2
BSY WorkCables from B005, B105, B106, B136 into BTH West
BPM S21 to BSY
Mechanical/VacuumSector 24 – 29 removal and installations of BC2 & L3
ControlsBCS; BC2 Magnet controls; Vacuum System; BC2 Timing System; BC2 MPS; BC2 Networks; BC2 Motion Control System
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 5
2007 Installation Schedule (cont)
LCLS 2007 Installation schedule, as of 10/19/07, contains 550 task linesShift work and multiple crews being used for Mech/Vac; shift work in schedule for Cable Plant work during PPS no access periodsCritical Path
As of 10/19/07, CP runs through BC2Removal of hardware - Cable plant and component install – cable terminations – cable testing; complete 11/23/07Magnet testing & checkouts need to interleave and follow cable completion through end of downtimeFurther testing may need ROD periods
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 6
2007 Installation Schedule (cont)
LCLS 2007 Installation schedule 6/22/07 BSY Work (for example)
Cable Plant from B005, B105, B106, B136 into BTH West
Requires Downtime (obviously) to install cables, therefore needed in 2007 down. Magnet loads not installed until ~March 2008, but need to checkout & commission before next downtime
Cable plant (Controls) install needs to be coordinated with BTH West MEP (LCLS CF)
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 7
BSY Work – B005 to BTH West
Cable run from B005 through the BSY, into BTH West via ~12 small penetrations
B005
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 8
2007 LCLS Installation Schedule 0 of 4
Started integrating schedules in July
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 9
2007 LCLS Installation Schedule 1 of 4
Status as of 10/19/07
Completed items removed
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 10
2007 LCLS Installation Schedule 2 of 4
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 11
2007 LCLS Installation Schedule 3 of 4
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 12
2007 LCLS Installation Schedule 4 of 4
Several Controls Systems schedules included: PPS, BCS, Magnet, Vacuum,
MPS, etc.
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 13
2007 Installation Schedule (cont)
Installation checks & balancesRSWCF for linac & cable way penetrations
ES&H review of Statement Of Work’s (SOWs)Subcontractor installations
Appropriate training
Work authorization forms (WAF)AD & LCLS forms
Radiation Work Permit (RWP)
Electrical safety for cable plant install & connection to PS
PO lockdown procedure being used
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 14
Shutdown Planning & Installation Schedule
• Installation Planning & Schedules– BTH -> FEH 2008 Installation
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 15
2008 Installation Planning• 2008 Installation Planning
– LCLS installations begin at Early Occupancy dates defined by TCCo
• BTH, Undulator Hall & Service Buildings available as early as December 5, 2007; NEH 12/21/07; X-ray tunnel 1/8/08; FEH 3/24/08; SB 2.3 late December• TCCo has priority over co-occupied space until B.O.
– BTH-NEH B.O. 3/21/08; X-ray tunnel – FEH B.O. 6/23/08– NEH elevator not available until ~March 2008, will limit early equipment installation
• Subcontract SOWs are being prepared• Need to ensure this work does not impact the 2007 installation effort, but stay on schedule (cable plant already slipped into February 2008)
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 16
2008 LCLS Installation Schedule 1 of 7
2008 Schedule• Co-Occupancy dates defined•Major subcontracts used for installations• First activity is Metrology network installation
LTU components connect to cables installed through BSY in 2007 downtime
2007 Downtime
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 17
LTU Hardware contained inside BTH West and BTHEntry areas are East & West mazes, and openings at headhouseWill plan access areas to limit interferences with Undulator and LTU installation phases
Undulator Hall
BTH West tunnel
East Maze – Undulator entry point
West Maze entry pointHeadhouse entry
SB 2.1
SB 2.2
SB 2.3
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 18
2008 LCLS Installation Schedule 2 of 7
Undulator girder installation
LTU components installed in BTH
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 19
LCLS UNDULATOR SYSTEM
33 Undulators33 Quadrupoles/Correctors
EM air-cooled10 Long breaks22 Short BreaksSupports with movers
5 DOF plus horizontal sliderVacuum System interconnects
33 rf Beam Position Monitors33 Beam Finder WiresWire Position MonitorHydro static level system
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 20
Undulator Elevation
Egress space between aisle and back of undulators
(cleared with Fire Marshal)
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 21
Integration also means knowing what the facility looks like prior
to installing equipment
~430’ long
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 22
SB 2.3 SB 3.1Undulator Hall
Beam dump/Fee area
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 23
2008 LCLS Installation Schedule 3 of 7
FEE installation
E- Dump components installed
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 24
LCLS 2008 Installation scheduleFEE systems are well along in the planning stages
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 25
2008 LCLS Installation Schedule 4 of 7
NEH Installations; most of which are delayed into FY09
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 26
LCLS 2008 Installation scheduleNEH overview
NEH Hutches
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 27
2008 LCLS Installation Schedule 5 of 7
X-Ray tunnel and FEH installation delayed until FY2009
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 28
2008 LCLS Installation Schedule 6 of 7
LTU ready – 8/11/08Und ready – 10/15/08FEE ready – 4/30/09
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 29
2008 LCLS Installation Schedule 7 of 7
Commissioning activities
leading to CD-4
2009 Downtime
Systems ready for first electron beam into LTU & dump by 10/22/08
2008 Downtime
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 30
Summary•2008 Installation Planning
– Early occupancy of Conventional Facilities will begin the installation process for technical systems
• Working to understand definition of early occupancy for each area
– Does not require Linac/PEPII down for LCLS installations
• BTH West installation puts some limits on beam operation to other areas like ESA
– Need to coordinate several subcontracts (~3-4?) to install mechanical systems and cable plant simultaneously– Detailed Installation planning in process by coordinators
Richard M. Boyce
FAC Review – Accelerator Installation [email protected]
October 29-31, 2007 31
End of Presentation