installation guide-2015 edition

Upload: nilanka-shyaminda-abayagunarathna

Post on 07-Jul-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Installation Guide-2015 Edition

    1/79

     DIALOG AXIATA PLC

    Installation GuideBSS/MW/Power

    Dialog Network Services - 2015

  • 8/18/2019 Installation Guide-2015 Edition

    2/79

    1

    DNS Installation Guide-2015 Edition

    Table of Contents

    INTRODUCTION…………………………………………………………………………………………………………………………………..5

    1  BSS INSTALLATION  ............................................................................................................................... 6

    1.1  Cellular Antenna Installation  ....................................................................................................... 6

    1.1.1  Cellular Antenna Brackets  .................................................................................................... 6

    1.1.2  Cellular Antenna positioning  ............................................................................................... 7

    1.2  TMA Installation  ........................................................................................................................... 8

    1.3  RRU Installation  ............................................................................................................................ 9

    1.4  Fiber Cable Installation  .............................................................................................................. 16

    1.5  Fiber Cable Installation Categories  ............................................................................................ 19

    1.5.1  CAT A  ................................................................................................................................... 20

    1.5.2  CAT B  ................................................................................................................................... 20

    1.5.3  CAT C  ................................................................................................................................... 21

    1.5.4  CAT D  ................................................................................................................................... 22

    1.5.5  CAT E  ................................................................................................................................... 23

    1.5.6  Covering bends using GI Flexible  ....................................................................................... 23

    1.6  RF Cable Installation  ................................................................................................................... 24

    1.7  RF Cable Grounding.  ................................................................................................................... 25

    1.8  Jumper Cables Installation  ......................................................................................................... 26

    1.8.1  Jumper Length &Bending Radius  ....................................................................................... 26

    1.9  RRU Power/Earth cable installation  .......................................................................................... 26

    1.10  BTS Installation  ........................................................................................................................... 28

    1.11  BSS Equipment Power  ................................................................................................................ 29

    1.11.1  Method of selecting correct load side for BSS equipment ............................................... 29

    1.12  EMUA  .......................................................................................................................................... 30

    1.13  BSS Equipment Grounding  ......................................................................................................... 31

    1.13.1  Making grounding cables  ................................................................................................... 31

    1.13.2  Outdoor cabinet BSS equipment grounding...................................................................... 32

    1.13.3  Indoor cabinet BSS equipment grounding......................................................................... 32

    1.14  Things to do Before Power up BSS Equipment .......................................................................... 33

    2  MICROWAVE INSTALLATION  .............................................................................................................. 34

  • 8/18/2019 Installation Guide-2015 Edition

    3/79

    2

    DNS Installation Guide-2015 Edition

    2.1  MW Antenna Installation  ........................................................................................................... 34

    2.2  Wind braces Installation  ............................................................................................................ 36

    2.3  ODU Installation  ......................................................................................................................... 37

    2.4  IF Cable Installation  .................................................................................................................... 37

    2.5  IF Cable Grounding  ..................................................................................................................... 38

    2.6  IF Cable Routing  .......................................................................................................................... 39

    2.7  Surge Arresters Installation  ....................................................................................................... 41

    2.7.1  Surge Arresters Near ODU  ................................................................................................. 41

    2.7.2  Surge arresters Near MW rack ........................................................................................... 42

    2.8  INU/IDU Installation  ................................................................................................................... 43

    2.9  INU Power Connections  ............................................................................................................. 45

    2.10  MW Tributary Cable/DDF Installations  ..................................................................................... 45

    2.11  Things to do Before Power up TX Equipment  ........................................................................... 47

    3  RECTIFIER INSTALLATION  ................................................................................................................... 48

    3.1  Indoor Cabin Rectifier Installation ............................................................................................. 48

    3.1.1  Placing and Mounting the Rectifier(ID) ............................................................................. 48

    3.1.2  1P & 3P Power Connections (DB/SPD) (ID)  ....................................................................... 49

    3.1.3  Number of Rectifier Modules(ID)  ...................................................................................... 50

    3.1.4  Battery Strings Connections(ID) ......................................................................................... 51

    3.1.5  Rectifier Grounding(ID)  ...................................................................................................... 51

    3.1.6  Indoor Casings for Cable installations(ID)  ......................................................................... 51

    3.1.7  Alarms Cable Installation(ID)  ............................................................................................. 52

    3.1.8  BSS/TX/Other DC Load Connecting to the rectifier(ID) .................................................... 52

    3.1.9  General Settings(ID)  ........................................................................................................... 53

    3.1.10  Things to do Before Power up Rectifier(ID) ....................................................................... 53

    3.2  Outdoor Cabin Rectifier Installation .......................................................................................... 54

    3.2.1  Placing and Mounting the Rectifier(OD)  ........................................................................... 54

    3.2.2  1P & 3P Power Connections to the Rectifier (DB/SPD) (OD) ............................................ 54

    3.2.3  Number of power modules(OD)  ........................................................................................ 55

    3.2.4  Battery Strings Connections(OD)  ....................................................................................... 55

    3.2.5  Rectifier Grounding(OD)  .................................................................................................... 56

    3.2.6  Alarm Cable Installation(OD)  ............................................................................................. 56

  • 8/18/2019 Installation Guide-2015 Edition

    4/79

    3

    DNS Installation Guide-2015 Edition

    3.2.7  BSS/TX/Other DC Power Supply(OD)  ................................................................................ 56

    3.2.8  General Settings(OD) .......................................................................................................... 57

    3.2.9  Things to do Before Power up Rectifier(OD) ..................................................................... 57

    4  BATTERY BANKS INSTALLATION  ........................................................................................................ 59

    4.1  Indoor Cabin battery bank Installation  ..................................................................................... 59

    4.1.1  Battery Rack Mounting & Placing(ID) ................................................................................ 59

    4.1.2  Battery placing and inter connections(ID) ......................................................................... 60

    4.1.3  Casings for Battery Strings/cables(ID) ............................................................................... 60

    4.1.4  Battery Strings connections(ID)  ......................................................................................... 60

    4.1.5  Rack Grounding(ID)  ............................................................................................................ 61

    4.1.6  Things to do before connecting to rectifier(ID) ................................................................. 61

    4.2  Outdoor Cabin battery bank Installation  .................................................................................. 61

    4.2.1  Battery placing and inter connections(OD) ....................................................................... 61

    4.2.2  Battery Cable Laying from OD battery cabinet to equipment cabin. (OD) ...................... 62

    4.2.3  Battery Strings connections(OD)  ....................................................................................... 62

    4.2.4  Things to do before connecting to the rectifier(OD) ......................................................... 62

    5  WATERPROOFING/WEATHERPROOFING  .......................................................................................... 63

    5.1  Why Waterproofing/Weatherproofing.  .................................................................................... 63

    5.2  Common procedure for outdoor RF/IF connector water proofing. ......................................... 63

    5.3  Cellular Antenna/RRU unused ports waterproofing ................................................................. 64

    5.4  TX Waveguides waterproofing  .................................................................................................. 64

    5.5  RF/IF Connectors waterproofing  ............................................................................................... 66

    5.6  RF/IF Cable Grounding points waterproofing  ........................................................................... 66

    5.7  PVC/flexible conduit joints  ........................................................................................................ 67

    5.8  Water draining methods for fiber cable installation via PVC ................................................... 67

    5.9  Bulkhead Sealing  ........................................................................................................................ 67

    5.10  Cable inlets/outlets sealing methods for outdoor cabinet cable inlets. .................................. 68

    5.11  Unused cable entry points Sealing(Outdoor cabinets) ............................................................. 68

    6  MAINTAINING THE CABLE LADDER/GANTRY & THE BULKHEAD ...................................................... 69

    6.1  Outdoor Cable Ladder  ................................................................................................................ 69

    6.2  Indoor Cable Gantry Installation Procedure.............................................................................. 69

    6.3  Bulk Head  .................................................................................................................................... 70

  • 8/18/2019 Installation Guide-2015 Edition

    5/79

    4

    DNS Installation Guide-2015 Edition

    6.4  Outdoor Cabin inlets & Outlets  ................................................................................................. 71

    6.5  Using correct conduit type & fastening method ....................................................................... 71

    7  EQUIPMENT LABELING  ....................................................................................................................... 72

    7.1  Examples for labeling positions  ................................................................................................. 74

    7.1.1  BSS outdoor  ........................................................................................................................ 74

    7.1.2  Rectifier  ............................................................................................................................... 74

    7.1.3  MW antenna/ODU Labeling ............................................................................................... 75

    7.1.4  19” rack labeling  ................................................................................................................. 75

    8  GENARAL SAFETY PROCEDURES  ........................................................................................................ 76

    9  ABBREVIATIONS  ................................................................................................................................. 77

  • 8/18/2019 Installation Guide-2015 Edition

    6/79

    5

    DNS Installation Guide-2015 Edition

    INTRODUCTION

    Dialog Axiata PLC, a subsidiary of Axiata Group Berhad (Axiata), operates Sri Lanka’s largest and fastest

    growing mobile telecommunications network. Company mobile network consists 3000+live base station

    sites scattered throughout the country and over 2200 of those sites are owned by DAP while the resthas been shared from other telecom operators infrastructure. DAP network is geographically divided in

    to ten (10) regions managed by Dialog Network Services(DNS) by which all operation & maintenance and

    project activities are coordinated & executed from regional offices and dispersed depots within the

    region.

    DNS maintains the base station infrastructure in well-coordinated manner compliance to the Dialog

    standards with 99.99% network up time to provide seamless network services to our valued customers.

    Therefore DNS expects to strictly follow Installation Guide document for any installation works at DAP

    owned and shared infrastructure sites to continuously maintain the above goals.

    Apart from equipment supplier’s manuals, this Installation Guide document gives the idea for all

    installers on how to install/label telecommunication equipment and accessories on towers and cabins as

    per DAP standards. Installation Guide document basically covered three main areas including Base

    Station Subsystem (BSS), Microwave Transmission (MW) and Power (PWR) installations. All installers

    (contractors) shall follow the document guidelines for all the BSS/MW/PW installations to be completed

    at DAP owned, shared infrastructure sites. DNS strictly advices all contractors to consult respective

    regional in charge for any deviations to the Installation Guide document.

    This is 2015 edition of Installation Guide and DNS has the responsibility to amend the document yearly if

    and only if there is a requirement for any amendment or addendum.

  • 8/18/2019 Installation Guide-2015 Edition

    7/79

    6

    DNS Installation Guide-2015 Edition

    BSS INSTALLATION

    1.1 

    Cellular Antenna Installation

    1.1.1 

    Cellular Antenna Brackets

      Antenna pole should be Heavy Duty GI made pole, 3m in length & 2.5” in diameter & painted

    with standard color using the same paint type used for the structure. Clamps too should be

    fabricated using the same material & paints.

    Picture 1.1.1: 3m antenna pole

      Antenna pole should be adjusted to fix vertically every time before beginning any equipment

    installation.

      Antenna bracket should be fixed as per WO azimuth setting such a way that orientation of the

    antenna bracket should be allowed maximum possible antenna rotation in either.

      All the nuts & bolts should be tightened firmly & secure with check nuts.

    Picture 1.1.2: antenna installation directions

  • 8/18/2019 Installation Guide-2015 Edition

    8/79

    7

    DNS Installation Guide-2015 Edition

    1.1.2 

    Cellular Antenna positioning

      Cellular antennas should be able to rotate within +/-150 from the WO azimuth to enable future

    optimizations. If it is not possible with available bracket arrangement, need to rearrange the

    brackets/antenna poles or relocate the antenna to other available pole to ensure the

    requirement.

    Picture 1.1.3: Antenna Rotating Tolerance +/- 15 degrees

      Original clamp set provided by the antenna fabricator must be used to install any antenna.

    Mechanical down tilt should be set to zero as per the current practice unless mentioned in the

    WO.

    Picture 1.1.4: Down tilt Clamps 

      Antennas should not be fixed near to the bottom end of the antenna poles, so that reaching the

    antenna ports shall be much easier for operational activities. Also this will allow the lower

    antenna clamp to be fixed above the lower arm/clamp of the antenna bracket, which will add

    some extra protection when adjusting or dismantling the antenna in the future.

  • 8/18/2019 Installation Guide-2015 Edition

    9/79

    8

    DNS Installation Guide-2015 Edition

    Picture 1.1.5: Antenna mounting on towers to easy access for works

      Azimuth and tilt error should be +/- 0.5 degrees from the WO specifications.

      Unused antenna ports should be sealed with PVC tape and 3M rubber tape as per the DAP guide

    lines on chapter 5.2 of this document.

      All the antennas should be labeled according to the DAP labeling standards described on chapter

    7. 

    1.2 

    TMA Installation

     Steel tie wraps should be used to mount TMA on the antenna pole just at the back of theantenna.

      Height from the bottom of the antenna should be ~0.5 m & should be able to connect the

    antenna side using =

  • 8/18/2019 Installation Guide-2015 Edition

    10/79

    9

    DNS Installation Guide-2015 Edition

    Picture 1.2.1: TMA installation on antenna pole 

    1.3 

    RRU Installation

      RRUs should Installed such a way that it should not block cellular antenna main lobe.

      RRUs installation should be installed to facilitate the easy operations and maintenance. Hence

    adequate space around RRU should be maintained for human operations.

      All the RRUs should be positioned in a way that the maintenance cavity of the RRU facing the

    tower side to facilitate easy operation.

      RRUs must be installed as far as possible from the lightning arrester/down conductor of the

    tower.

      Orientation of the RRU should allow the antenna to be adjusted within +/-150  for the future

    optimizations.  If the recommended clearance not available, contractor must contact regional PM & get

    directions before proceed the Installation with minimum clearance possible.

      Clearance between RRUs should always adhere to the vendor specifications & should

    accommodate the heat dissipation requirement and easy O&M. RRU clearance requirement can

    be vary from vendor to vendor and based on RRU model. Need to align with the RRU

    manufacturer specification as much as possible. Following is the general practice.

  • 8/18/2019 Installation Guide-2015 Edition

    11/79

    10

    DNS Installation Guide-2015 Edition

    Picture 1.3.1 (a): Recommended /Minimum Clearance for a Single RRU

    Picture 1.3.2 (b): Recommended /Minimum vertical space between RRUs

      To ensure the proper heat dissipation of the RRU and ensure waterproofing of the ports at the

    bottom of the RRU, the tilt of the RRU must be less than or equal to 10 degrees in general.

    Picture 1.3.3: Correct RRU positioning

      All the RRUs should be installed vertically as per above requirement. Any deviation due to

    exceptional case should be acknowledged & get approval from the regional PM.

  • 8/18/2019 Installation Guide-2015 Edition

    12/79

    11

    DNS Installation Guide-2015 Edition

    Picture 1.3.4: RRU Installed in Vertical Mode 

      At RT Pole site, a minimum of 1200mm ~ 1600mm distance should be kept between the tower

    base level and bottom of the RRU.

      RRUs must be installed within the arms of the antenna bracket (cross bars for double bracket).

    That will provide extra protection when adjusting or replacing.

    Picture 1.3.5: RRU mounting on pole and between supporting bars to tower

     

    If enough space not available to mount the RRU on the same antenna pole, then special bracket

    approved/issued by DAP must be used.

      Maximum number of RRU installed on single cellular pole should be limited to 2. Any deviation

    should get approval from the regional PM.

  • 8/18/2019 Installation Guide-2015 Edition

    13/79

    12

    DNS Installation Guide-2015 Edition

    Picture 1.3.6: Wrong Installation (more than two RRU on single pole)

      RRU must be fixed firmly to the pole. All clamps should be installed according to the product

    specification. Booklet of the quick installation guidance provided by the manufacturer must bereferred or get the instructions from regional PM at any difficulty.

    Picture 1.3.7: RRU Fixed without any loose connection

      A torque wrench should be used when tightening the nuts according to the product

    specifications. A mark should be made to confirm all nuts are tightened to the correct value.

  • 8/18/2019 Installation Guide-2015 Edition

    14/79

    13

    DNS Installation Guide-2015 Edition

    Picture 1.3.8: a mark made for identifying the nut is tightened to the correct torque setting. 

      All check nuts, spring washers, flat washers must be installed without neglecting any, according

    to the product specifications.

      If the extra length of the RRU bracket bolts block the expected azimuth tolerance of the installed

    antennas (+/- 15 degrees) then the bolt/bolts must be cut off and proper protection for avoiding

    any corrosion should be applied. Bonding and Insulation tapes can be used for this purpose.

      Cover plates of the RRU’s maintenance cavity should be fixed firmly ensuring the water seal in

    place to avoid water leakages into the cavity.

    Picture 1.3.9: Cover Plate of RRU maintenance cavity  

     

    Do not remove dust proof caps of the vacant RF ports on the RRUs or antennas. Water proofingshould be done as per the common guide lines on chapter 5-waterproofing on this document for

    unused ports.

  • 8/18/2019 Installation Guide-2015 Edition

    15/79

    14

    DNS Installation Guide-2015 Edition

    Picture 1.3.10: Dust Proof Caps of an RRU

      Unused ports of the RRU’s maintenance cavity should be blocked using original rubber bushes

    only provided with the RRU by the manufacturer.

    Picture 1.3.11: Closed maintenance cavity of the RRU (left) & blocked unused ports of maintenance cavity (right)

      Stripped part of the RRU power cable should not exposed out of the maintenance cavity. Good

    installation shown on below picture.

    Picture 1.3.12: Correct installation of RRU power cable 

  • 8/18/2019 Installation Guide-2015 Edition

    16/79

    15

    DNS Installation Guide-2015 Edition

      RRU should be grounded to the structure with good electrical contact by using a C clamp. Tower

    paint should be removed on minimum area required for C clamp only & must not damage zinc

    layer when removing the paint which will lead to structure corrosion.

    Picture 1.3.13: RRU Grounding with C-Clamp 

     

    Refer to the below picture for correct way of connecting earth cable to the RRU.

    Picture 1.3.14: Correct and incorrect ways of fixing earth cables 

      All the RRUs should be labeled as per the DAP standard described on chapter 7-labeling section

    on latter part of this document.

      The surface of all equipment should be cleaned after the installation.

  • 8/18/2019 Installation Guide-2015 Edition

    17/79

    16

    DNS Installation Guide-2015 Edition

    1.4 

    Fiber Cable Installation

      Minimum bending radius for average fiber cables in general is 20 times the diameter of the

    cable. So need to prevent any sharp bends at any point.

      Should follow all the safety precautions defined by the manufacturer & it is a must to use fiber

    hooks provided for hoisting RRU fiber cables one by one, avoiding any damage.

    Picture 1.4.1: Incorrect Binding of RRU Fiber Cable

      RRU power cable, RRU fiber cable and Grounding cables should not be bundled together.

     

    Cable coiling near the RRU must be avoided if not instructed to do so.  Extra care should be taken when tightening the fiber cable close to the maintenance cavity of

    the RRU to avoid the cable being damaged.

      Connectors of fiber cables must be covered with dust proof caps throughout the installation

    period.

      Need to keep the dust proof caps installed for all unused SFP/fiber ports.

    Picture 1.4.2: SFP ports covered with dust proof caps 

  • 8/18/2019 Installation Guide-2015 Edition

    18/79

    17

    DNS Installation Guide-2015 Edition

      Clamps used for installing RRU cables should comply with the fiber cable sizes. Eg. Clamps used

    for Huawei fiber cables do not match with Ericsson fiber cables which are thinner than Huawei

    fiber cables.

    Picture 1.4.3: fiber cables installed using correct & incorrect cable clamps. clamp diameter>fiber on incorrect 

      In the instance of unable to cover fiber cables with PVC pipes (bends in irregular shape)

    according to the fiber cable installation category described on the next chapter, need to use GI

    flexible or UV protected conduits. Plastic conduits without UV protection will be rejected.

    Picture 1.4.4: GI flexibles used at bending points of fiber cable installation

      SLS certified PVC pipe must be used for the installation.

      Fiber/power cables used for the same technology or same BTS must be installed in the same

    cluster.

  • 8/18/2019 Installation Guide-2015 Edition

    19/79

    18

    DNS Installation Guide-2015 Edition

      Cables should have enough free length near RRU/Antenna [between last tie wrap point and

    RRU/Antenna] for allowing RRU & antenna movements /removals [for maintenance work]

    without changing current cable installation.

    Picture 1.4.5: free length of cables for easy operation 

      Excess fiber cables must be kept rolled, not less than 1 feet diameter. This zag of fiber cables

    must be kept on the tray below the BBUs if it is an outdoor cabinet. If it is indoor, the zag must

    be kept on the most distant place from busy area of the cable tray.

    Picture 1.4.6: Fiber cable zag kept away from frequently used area of the cable gantry

  • 8/18/2019 Installation Guide-2015 Edition

    20/79

    19

    DNS Installation Guide-2015 Edition

      All the fiber cables must be labeled according to the DAP standards described on chapter 7 of

    this document.

    Picture 1.4.7: All power/fiber cables must be labeled

    1.5 

    Fiber Cable Installation Categories

      Refer to the below table for fiber cable installation categories. Detail description will follow the

    table.

    Category

    Optical Fiber Cable Power Cable

    Optical Fiber &

    Power Cable in one

    conduitJunction

    BoxCable Clamps

    PVC(1/2") PVC(1/2") PVC(1")

    V-

    Ladder

    H-

    Ladder

    V-

    Ladder

    H-

    Ladder

    V-

    Ladder

    H-

    Ladder

    CAT-A     Optional V-Ladder Only(2m)

    CAT-B     Optional V-Ladder Only(2m)

    CAT-C   V-Ladder Only(1m)

    CAT-D   V-Ladder Only(1m)

    CAT-E         Optional V-Ladder Only(8m)

    Table: 1.5.1 PVC conduit installation Categories 

  • 8/18/2019 Installation Guide-2015 Edition

    21/79

    20

    DNS Installation Guide-2015 Edition

    1.5.1 

    CAT A

      ½” PVC conduit only for fiber cable V and H. 

      Using junction box upon the preference

      For V ladder need to use clamps in every 2m interval

      For H cable tray, no clamps will be used.

     

    T joints near the bulk head and the 900

     bend.  No PVC for power cable, need to install via clamps in the V ladder and need to be routed using

    cable ties in H cable tray.

      Need to cover fiber cable using ½” insulated steel flexible conduits at 900 bend, near bulk head

    and V ladder to RRU.

      In this category fiber cable should not be exposed to outside at any point

    Picture 1.5.1: Category A Fiber/power cable installation

    1.5.2 

    CAT B

     

    1” PVC conduit for both fiber and power cable on V and H ladders.  Using junction box upon the preference

      For V ladder, need to use clamps in every 2m interval

      For H cable tray, no clamps will be used.

      T joints near the bulk head and the 90 bend.

      Fiber and power cables need to be routed through clamps on the V ladder and need to be

    routed using cable ties in H cable tray.

  • 8/18/2019 Installation Guide-2015 Edition

    22/79

    21

    DNS Installation Guide-2015 Edition

      Need to cover fiber cable using 1” insulated steel flexible conduit at 90 bend, near bulk head and

    V ladder to RRU

      In this category fiber and power cables should not be exposed to outside at any point

    Picture 1.5.2: Category B Fiber/power cable installation, both fiber & power cables in 1” PVC & 1” GI flexible

    1.5.3 

    CAT C

      ½ “PVC conduit only for fiber cable in H cable tray. 

      For V ladder need to use clamps in every 1m interval

      For H cable tray, no clamps will be used.

      T joints near the bulk head and the 900 bend.

      GI flexible @ bulk head & 900bend.

      Fiber and power cables need to be routed through clamps on the V ladder and must use cable

    ties on H cable ladder.

  • 8/18/2019 Installation Guide-2015 Edition

    23/79

    22

    DNS Installation Guide-2015 Edition

    Picture 1.5.3: Category C Fiber/power cable installation, ½” PVC up to 900

    bend with T joints for draining water.

    1.5.4  CAT D

      1 “PVC conduit for both fiber and power cables in H cable tray only.

      For H cable tray, tie wraps instead of clamps.

      For V ladder need to use clamps in every 1m interval for both fiber & power cables.

      T joints near the bulk head and the 90 bend.

      Fiber and power cables need to be routed through clamps in the V ladder and must use cable

    ties on H cable ladder.

    Picture 1.5.4: Category D Fiber/power cable installation, 1” PVC for fiber & power cable on H ladder only  

  • 8/18/2019 Installation Guide-2015 Edition

    24/79

    23

    DNS Installation Guide-2015 Edition

    1.5.5 

    CAT E

      ½ “PVC conduit separately for both fiber and power cables in V and H cable tray. 

      Using junction box upon the preference

      For V ladder need to use clamps in every 8m interval

      For H cable tray, use tie wraps for fastening.

     

    T joints near the bulk head and the 90 bend for draining water.  Fiber and power cables need to be routed through clamps on V ladder and must use tie wraps

    on H cable tray.

      Need to cover fiber and power cables using ½” insulated GI flexible conduit at 900 bend, Bulk

    head and V ladder to RRU.

      In this category fiber and power cables should not be exposed to outside at any point

    Picture 1.5.5: Category E Fiber/power cable installation, both power cables & fiber cables inside ½” PVC 

    1.5.6  Covering bends using GI Flexible

      Need to cover irregular shapes of fiber path near bulk head & 900  bend using insulated GI

    flexible conduits with same diameter as the PVC conduits. 

    Picture 1.5.6: GI flexible @ bends

  • 8/18/2019 Installation Guide-2015 Edition

    25/79

    24

    DNS Installation Guide-2015 Edition

      PVC to GI flexible joints should be sealed using same mastic sandwich method used for

    waterproofing outdoor connectors.(chapter 5.2) 

    Picture 1.5.7: PVC to GI Flexible joints waterproofed.

     

    Interface between GI flexible & bulk head must be weatherproofed using silicon/masticsandwich as per the chapter 5.9 guidelines.

      Using PVC T junctions at 2 ends of horizontal ladder is a must for any PVC conduit installation for

    fibers.

    1.6  RF Cable Installation

      The minimum bending radius of an RF cable should be 20 times the diameter of the RF cable.

    Minimize the bending points and Maximize the bending radius while installing RF cable.

      Use the same brand or recommended RF connector and cable clamps for each RF cable brand.

    Picture 1.6.1: Uniformly installed RF clamps & 7/8” RF connectors.  

      Do not use scratched or outer damaged RF cables for any installation. Cables should be clean

    and clear all along after the completion of installation. Any scratched cable will be rejected.

  • 8/18/2019 Installation Guide-2015 Edition

    26/79

    25

    DNS Installation Guide-2015 Edition

    1.7 

    RF Cable Grounding.

      All the installation teams need to refer the installation manual provided with the grounding kit

    to avoid unwanted stripping of the RF cable.

    Picture 1.7.1: RF grounding kit fixed before waterproofing

      Each RF cable should be grounded using proper grounding kits at below points.

      Near the bulkhead. Grounding cable should be connected to bulk head ECB.

      1m distance above (90 bend) from horizontal ladder. Grounding cables to V ladder ECB @

    cable bend.

      1m below the top RF connector. Grounding cables to ECB on V ladder. ECB should be

    electrically connected to the structure using C clamp method.

      If the cable distance is more than 50m, install middle grounding point as well.

    Picture 1.7.2: RF groundings near bulk head & vertical cable ladder 

      All the RF connectors and grounding points should be properly waterproofed according to the

    DAP standards. (Refer the water proofing methods on chapter 5.2 of this document).

  • 8/18/2019 Installation Guide-2015 Edition

    27/79

    26

    DNS Installation Guide-2015 Edition

    1.8 

    Jumper Cables Installation

    1.8.1  Jumper Length &Bending Radius

      In general bending radius should not be less than 150mm for ½” RF Jumper cables. 

     

    The bending radius of the 1/4'' jumper, super-flexible 1/2'' jumper and ordinary 1/2'' jumpermust be according to the product specifications.

      Jumpers should be neat up using UV protected outdoor cable ties.

      Must use jumper cables with appropriate length (neither short nor longer than required) as per

    the situation to avoid any zag.

    Picture 1.8.1: correct & incorrect Jumper Cable Installation 

      Need to route outdoor RF Jumpers underneath the platform to avoid any damages when

    working on the platform, (jumpers used between antenna & RF cable).

      Crossings of jumper cables on the cable ladder/structure should be zero. Any jumper cable

    should be able to remove without disturbing any other cable.

      Must use ½” cable clamp or UV protected cable ties as jumper aids.

      Both ends of all the jumper cables should be labeled according to the  labeling guide lines  on

    latter part of this document.

    1.9 RRU Power/Earth cable installation

      Avoid cable joints of any method on RRU power/Earth cables.

    Picture 1.9.1: Cable Joints

  • 8/18/2019 Installation Guide-2015 Edition

    28/79

    27

    DNS Installation Guide-2015 Edition

      RRU power cables should not hang freely close to the RRU. The bending radius of the power

    cable or Earth cable must be at least three times the diameter of the cable.

      Power cables should meet the RRU vendor specifications.

    Picture 1.9.2: correctly installed RRU power cable

      Power rating of the breaker to the RRU must be selected according to the maximum power

    rating of the unit defined by the RRU manufacturer.

      Do not lay RRU power cables near to the tower down conductor.

      The space between power cable/ground cable and fiber cables outside the RRU should be more

    than 3 cm.

      Black UV-resistant cable ties (UV protected 14.5” black tie wraps)  must be used for outdoor

    cable fastening.

      RRU power cable shield must be grounded using a proper grounding kit at the cabin entry point

    (inside the cabin), or on the DCDU.

    Picture 1.9.3: RRU Sheath Grounding

  • 8/18/2019 Installation Guide-2015 Edition

    29/79

    28

    DNS Installation Guide-2015 Edition

      Sheath should be covered with heat sleeve and proper cable lug should be applied before

    connecting to the grounding point.

    Picture 1.9.4: DCDU point for grounding RRU power cables (Left) & RRU power cables grounded @ bulk head (right) 

    1.10 

    BTS Installation  Rack mount BBU - The minimum space between two units should be (top & bottom) 1U space.

    Picture 1.10.1: minimum free space between two equipment must be 1 U

      Should be able to observe indicators easily.

      Install the BBU in a way that it could be removed without disturbing any other node.

      No cross cables should be laid from side to side of the rack to avoid any disturbance for card

    removals/addition.

    Picture 1.10.2: incorrectly routed cables, across the RBS.

  • 8/18/2019 Installation Guide-2015 Edition

    30/79

    29

    DNS Installation Guide-2015 Edition

      All the vacant slots should be covered with dummy plates.

    Picture 1.10.3: all the unused slots must be covered with dummy plates.

      All the unused dummy plates should be handed over to DNS regional staff.

      BH/E1 paths should be installed through proper lighting arresters if they are routed outside the

    equipment cabin. (UELP/SLPU for Huawei)

    Picture 1.10.4: E1s through surge protecting device

    1.11 

    BSS Equipment Power

    1.11.1 

    Method of selecting correct load side for BSS equipment

      Technology vise DC power connectivity requirement is below.

      2G (900/DCS) - Need to connect to non-critical load

      3G - Need to connect to non-critical load

     

    LTE FDD - Need to connect to non-critical load

      LTE TDD - Need to connect to critical load

      Other broadband - Need to connect to critical load

    Picture 1.11.1: Critical & Non critical sides are separated & labeled in the rectifier 

  • 8/18/2019 Installation Guide-2015 Edition

    31/79

    30

    DNS Installation Guide-2015 Edition

      Power cable diameter should comply with the power rating of the equipment on manufacturer

    specifications.

      Use the shortest path possible separately for the power cables & grounding cables

      Each DC power cable should be labeled as per given standard at both ends. Labeling guide is on

    chapter 7 of this doc.

    Picture 1.11.2: Power cables are properly labeled. In the rectifier (left), at the DCDU (right)

      Cabling from the DCDU/PDU to other equipment should adopt a common orderly pattern

      (Ex: - Right hand-side cables and left-hand side cables can be routed separately in two routes)

    Picture 1.11.3: Power neatly installed near PDU

      Power connection main breaker of the DCDU/PDU should facilitate future expansions.

    Hence 50A DC breaker from rectifier should be used for each & every technology/base station.

      When connecting RRU & BBU power to DCDU, suitable/recommended breaker capacity must be

    used as per the equipment manufacturer guide lines.

    1.12 

    EMUA

      Should be installed above the BBU in the reserved 19-inch space. It is only for outdoor cabinets

    according to Huawei guideline.

  • 8/18/2019 Installation Guide-2015 Edition

    32/79

    31

    DNS Installation Guide-2015 Edition

    1.13 

    BSS Equipment Grounding

      For BBU grounding, use 10/16mm2 Earth wires.

      Earth cable should be routed separately from all other cables, inside duct lines/cable casings or

    on the cable tray using the shortest path possible.

    1.13.1  Making grounding cables

      Lug crimping tool of exact size of the lug should be used when making power/Earth cables.

    Using hammers/plier or any other inappropriate method for tightening lugs should be avoided &

    will be rejected on PAT.

    Picture 1.13.1: a lug fixed to the cable using a plier/Hammer

      Selected lug dimensions should be according to the cable size. Removing strands of the cable to

    match with lower size lugs must be avoided.

      The lug handle and any part of cable core exposed should be wrapped with the heat shrink

    sleeve.

    Picture 1.13.2: cable lug made correctly (left) & uncompleted cable lug (right)

      Usage of insulation tape instead of heat sleeves should be avoided as much as possible.

  • 8/18/2019 Installation Guide-2015 Edition

    33/79

    32

    DNS Installation Guide-2015 Edition

    1.13.2 

    Outdoor cabinet BSS equipment grounding

      BBU chassis should be grounded to the nearest earth plate. Ex. Left side of Huawei cabinet

    Picture 1.13.3: Earth plate at the left side of the outdoor cabinet is the nearest to BBU

    1.13.3  Indoor cabinet BSS equipment grounding

      If BBU is mounted on 19’ rack at indoor site, its chass is to be grounded to the ECB of the

    particular rack. Earth cable should be tightly laid along back side of the rack using the shortestpath possible.

    Picture 1.13.4: ECB on top of 19” MW rack 

    Picture 1.13.5: Earth cables on back of the mw rack. Other cables not install near them.

      If it is macro BTS, should be connected to the ECB near the bulk head using 25mm2 Earth cables.

      All other base stations should be connected to the nearest common grounding point using

    16mm2 or higher earth cables.

      BBUs in outdoor sites should be grounded to the earth plates provided inside the outdoor

    cabinets.

      Crone block (metal case) should ground to the earth plate inside the outdoor cabinet.

  • 8/18/2019 Installation Guide-2015 Edition

    34/79

    33

    DNS Installation Guide-2015 Edition

    1.14 

    Things to do Before Power up BSS Equipment

      Check and take all safety measures for yourself and then equipment’s

      Compare all installation work is done as per given WO or Project Proposal Document/s. All the

    equipment must be placed as per WO/CPR.

      Clean the site (Indoor+ out Door) & collect all the garbage. Ensure they are not left inside the

    site/roof top when leaving.  Check antennas are installed correctly as per manufacturer specifications & all the clamps are

    properly tightened.

      Check Antenna orientation (azimuth and Tilt) is set to WO specs. If not adjust until they meet

    the required.

      Check outdoor RF/IF/Fiber/Power cable installed according to the DAP guide lines.

      Check all OD grounding points are well connected to ECB/Tower.

      Check water proofing is done according to the DAP standard given on this document.

      Check Bulkhead is properly used & Sealed according to the guide lines on this document.

      Measure VSWR (Only for RF cable available sites). Rectify before turning on if there are

    unexpected values.

      Check Fiber Cable/SFP/RF cables are properly connected & if any of them are defected during

    the installation. SFP units must be removable easily and reinstall them after checking any slot

    damages.

      Check all indoor grounding points are tightly connected at both ends of grounding cables.

      Check E1 cable is properly laid up to the crone tag & neaten up.

      Check External alarm cable is neatly laid up to the rectifier.

      Check DC power cables for end to end connectivity, correct polarity +/- & physical damages to

    the cable.

      Check DC Breaker capacity. Must exceed the maximum current rating of the RBS.

      Check DC power taken from correct side of the rectifier(Critical/Non Critical)

      Measure DC/AC voltage levels & note down the values before turning on the new equipment, so

    we can communicate to DTBU if they (voltages) drop after new load/loads are added.

     

    Check all available cards with WOs & are inserted in to correct slots.  Check whether all accessories available in the BTS. (Fan Cards, Dummy cards etc.)

      Check tightness of all installed nuts/bolts of power and BSS equipment’s 

      Check the labeling for all installed equipment.

      Switch on the BTS.

  • 8/18/2019 Installation Guide-2015 Edition

    35/79

    34

    DNS Installation Guide-2015 Edition

    MICROWAVE INSTALLATION

    2.1 

    MW Antenna Installation

      Need to adhere to the manufacturer guidelines strictly. Installation manual provided by the

    antenna manufacturer should be referred by the installation teams & must take regional PM

    consent before proceeding in difficult situations.

     

    The installation paste has to be applied to all threads of bolts and fine adjustment spindles. It isprovided with the installation kit, which is a corrosion preventing and lubricating liquid

    especially for all threads of stainless steel bolts, U-bolts, spindles. After this, keep the lubricated

    threads free of dust and dirt. Manufacturers define fastener torque settings only for bolts

    lubricated with this installation paste.

    Picture 2.1.1: installation paste applied on the balt.

      If there is planer radome available need to follow manufacturer guide lines and install it without

    any kinking. Kinking will destroy the radome which is non repairable or replaceable on live

    antenna.

      All safety precautions should be taken to avoid any damage to the antenna/existing equipment

    on the tower during the installation, need to align with manufacturer guide lines when hoisting

    the antenna to the tower top.

  • 8/18/2019 Installation Guide-2015 Edition

    36/79

    35

    DNS Installation Guide-2015 Edition

    Picture 2.1.2: Hoisting the MW antenna.

      Default polarization for any single polarized antenna is vertical if not specified on the WO.

    Picture 2.1.3: antenna polarization can be observed from the orientation of the antenna feeder point  

  • 8/18/2019 Installation Guide-2015 Edition

    37/79

  • 8/18/2019 Installation Guide-2015 Edition

    38/79

    37

    DNS Installation Guide-2015 Edition

    2.3 

    ODU Installation

      Need to adhere to the manufacturer guidelines strictly during installation.

      Unpacking the installation kit must be done carefully for avoiding any particles being missing.

    Neglecting any item in the installation kit or any instruction by the radio manufacturer will lead

    to a total destruction of the unit or QOS issues, sooner or later.

     Need to select/locate the MW bracket & position the MW antenna in a way that the radio unitscan be reached easily, at any cost. That is, the radio units must be installed nearest side of the

    antenna to the tower. It will ease up the O&M.

    Picture 2.3.1: ODU installed away from the tower will make O&M hard

    2.4 IF Cable Installation

      IF connectors for deferent brands/models of MW links vary from one to another. So need to

    follow the instruction set provided by the IF connector manufacturer for each type. Using the

    correct tools (Eg. Crimping tools) is a must.  During the cable installation, IF cable connectors may be damaged & the connectivity may also

    broke up. Therefore need to test the connectivity of the cables after the cable is fully installed

      We can proceed with short circuit test using a multi meter to check the cable connectivity.

    Picture 2.4.1: Testing Cable Connectivity using multi meter 

  • 8/18/2019 Installation Guide-2015 Edition

    39/79

    38

    DNS Installation Guide-2015 Edition

      Do not perform short-circuit test when one side of the IF cable connected with either ODU side

    or IDU side

      Must avoid joints on IF cables at any cost. Need to check whole cable for damages after cable

    laying is completed.

      Before connecting/disconnecting the IF cable at any point, ODU and IDU power switches should

    be turned off to void damages due to short circuiting.

     

    IF cable should be connected to the IDU through the IF jumper from the indoor IF arrestor.

      IDU must be connected to the common ground before connecting the IF cable to IDU.

      ODU Earth cables must be installed before connecting IF cable to ODU. 

    2.5 

    IF Cable Grounding

    Picture 2.5.1: Grounding points for IF cable

      The point of about 1 m away from the IF interface of the ODU should be grounded. – point 01

      The place about 0.5 to 1 meter away from the cable entry point of equipment cabin or outdoor

    cabinet is required to be grounded. -point 02

      The point about one meter away from the Cable bend between Horizontal and vertical cable

    ladders should be grounded. -point 03.

      Additionally, below points of IF cable should be grounded according to the length of considered

    part

     

    The middle point of the cable when the cable is longer than 60 meters-point 04 on the

    picture 2.5.1:

      The middle point of the horizontal portion of the cable if the portion is longer than 60m.

      IF cable grounding should be electrically connected to the structure using C-clamps in the

    absence of ECB. Paint on the tower should be removed as per the minimum requirement

    without damaging the zinc layer if GI member, to avoid any corrosion.

      Picture 2.5.2 describes how to make grounding on IF cable using grounding clips.

  • 8/18/2019 Installation Guide-2015 Edition

    40/79

    39

    DNS Installation Guide-2015 Edition

    Picture 2.5.2: Grounding kit installation for IF cable

      The grounding wire of any grounding point should be routed to the ground direction as much as

    possible.

    Picture 2.5.3 orientation of the grounding wire of IF grounding

    2.6 IF Cable Routing

      IF cable neat up should begin from the top end. I.e. from the ODU end.

      The IF cable should be curved as shown on below pictures for making the waterproofing more

    effective, near the ODU & near the bulk head.

  • 8/18/2019 Installation Guide-2015 Edition

    41/79

    40

    DNS Installation Guide-2015 Edition

    Picture 2.6.1: cable bends near ODU & just outside bulk head

     

    The bending radius of the IF cable should be larger than 30 cm.  The IF cable should be bound to the cable ladder using UV protected outdoor cable ties or

    suitable clamps, at every one meter interval.

      Orientation of all cable ties/clamps should be in the same direction for keeping the neatness of

    the installation.

    Picture 2.6.2: fastening method should be uniform & cable should not cross each other. 

      Both ends of the IF cable should be applied with temporary labels before installation.

    Permanent labels should be pasted after the completion of the installation as per the labelingguide on chapter 7 of this document.

      IF cable should not be crossed with any other cable on the cable ladder. Take permission from

    regional PM in exceptional case.

      IF cables should be taken through separate slot of bulk head, they should not mix with RF/RRU

    power cable clusters. Does not matter new cable is routed in existing IF cable cluster. After the

    IF cable routing, the bulk head should be sealed according to the DAP specifications explained

    on chapter 5. 

  • 8/18/2019 Installation Guide-2015 Edition

    42/79

    41

    DNS Installation Guide-2015 Edition

    2.7 Surge Arresters Installation

    2.7.1  Surge Arresters Near ODU

      IF surge arrester should be installed at the point of IF cable connects to the ODU.

     The GND cable of the surge arrester should be connected to the structure using C clampmethod.

      If the surge protector cannot be directly connected to the IF interface on the ODU due to the

    structural restriction or the antenna parts, need to attach a matching angle N-type adapter.

    Picture 2.7.1: surge arrester with straight arrester

    Picture 2.7.2: surge arrester with angle N-type adaptor

    Outdoor cable ties

  • 8/18/2019 Installation Guide-2015 Edition

    43/79

    42

    DNS Installation Guide-2015 Edition

      Near the ODU, surge arresters should be properly weatherproofed as per below guidelines.

      For the sealing first apply insulation tape, bonding tape, again insulation tape.

    Finally silicon can be used for added security.

     

    After sealing, total arrester may look like below figure.

    Picture 2.7.3: Surge arrester installation at ODU

    2.7.2 

    Surge arresters Near MW rack

      Surge arrester should be installed between IDU/INU & bulk head, within 1 meter distance from

    bulk head.

     

    A mounting plate or ECB can be used for mounting indoor IF surge arresters as shown on below

    picture. It depends on the arrester type. This mounting plate should be connected to nearest

    ECB using the shortest path possible using 16mm2 or higher earth cables.

    Picture 2.7.4: Surge arrester installation inside the cabin

  • 8/18/2019 Installation Guide-2015 Edition

    44/79

    43

    DNS Installation Guide-2015 Edition

    2.8 

    INU/IDU Installation

      MW IDUs should be installed on top of all other equipment on the 19” rack in indoor cabin sites.

    It should be installed just under the rectifier in outdoor cabinets

    Picture 2.8.1: MW INU just below the rectifier in an outdoor cabinet

      Minimum distance between two units on MW rack is 1U (>1.5”) for ensuring proper ventilation.

    Picture 2.8.2: MW IDU on top of other equipment at indoor sites

  • 8/18/2019 Installation Guide-2015 Edition

    45/79

    44

    DNS Installation Guide-2015 Edition

      IDU grounding should be done using 10mm2-16mm

    2 earth cables.

    Picture 2.8.3: MW IDU on top of other equipment at indoor site 

      All IDUs installed in Indoor sites should be grounded to ECB of the same 19” rack. ECB must be

    connected to bulk head ECB using 25mm2

     or higher earth cables.

    Picture 2.8.4: MW IDU grounding cables connected to 19” rack ECB 

      If it is outdoor site, all IDUs grounding points should be connected to nearest earth plate.

    Picture 2.8.5: Earth plate beside the 19” rack in an outdoor cabinet 

  • 8/18/2019 Installation Guide-2015 Edition

    46/79

    45

    DNS Installation Guide-2015 Edition

    2.9 

    INU Power Connections

      2.5mm2-6mm

    2  of standard colors (Blue for negative & black or red for positive) flexible DC

    power cables must be used if the INU/IDU power cables are not provided with manufacturer

    installation kit.

    Picture 2.9.1: INU power cables 

      Polarity and the power connection order (1&2 or primary/secondary) should be labeled at both

    ends of all the power cables according to the DAP Labeling standards given on chapter 7 of this

    document.

      Power to MW equipment should be drawn from nearest MW fuse panel/PDU. Should be

    connected to 6-10A breaker on critical side of the rectifier if separate fuse panel/PDU is not

    provided.

    2.10 

    MW Tributary Cable/DDF Installations

      Tributary cables should be extended to the common DDF. If there is no common DDF, crone tags

    should be placed at the bottom of the same MW rack. Need to take guidelines from regional PM

    in an exceptional situation.

      All the tributary cables should be labeled at the both ends as per the DAP labeling guide

    provided on chapter 7 of this document.

      Crone tag blocks should be labeled as shown on below picture.

    Picture 2.10.1: properly labeled tributary block for 16 E1 link

  • 8/18/2019 Installation Guide-2015 Edition

    47/79

    46

    DNS Installation Guide-2015 Edition

      All the E1s of one link should be clustered if there is no special scenario. DAP regional PMs

    guidance must be followed if there is space issue on DDF/MW rack space.

      One tag block space should be kept between two links tributary clusters.

    Picture 2.10.2: tributary clusters of different links should be separated for easy identification

      Only 3 crone tag frames should be installed parallel on 19” MW rack. 

    Picture 2.10.3: only 3 tag blocks parallel on one side of 19” rack  

      Extra length of tributary cable can be rolled to sag of 1 ft in diameter and kept at behind the

    MW rack as shown below. Maximum loops for one cable should not exceed 5 if not specially

    instructed to keep more. Only one loop for outdoor cabinets.

    Picture 2.10.4: extra length of tributary cable on the back of MW rack

  • 8/18/2019 Installation Guide-2015 Edition

    48/79

    47

    DNS Installation Guide-2015 Edition

      All unused E1s should be looped after checking them with the E1 analyzer.

    Picture 2.10.5: All the unused E1 should be looped

      Crone tag frames should be grounded to the MW rack ECB using 6-10mm2 earth cables.

      Fiber/Eth Cables 

      Eth cable & Fiber cable should be labeled as per DAP standards on chapter 7 of this

    document.

      Fiber patch cords between 2 racks must be installed through flexible conduits.

      All cabling should be very neatly done on MW racks.

     

    All the cables should be routed on MW rack in a way that they could not disturb installing new

    equipment on free space of the rack or O&M (replacing/removing) existing units.

    2.11  Things to do Before Power up TX Equipment

      Check and take all safety measures for yourself and then equipment.

      Complete all installation work and check with given Work Order/s (WO) or Project Proposal

    Document/s.

      Clean the site (Indoor + Out Door) & collect all garbage.

      Check bracket arrangement (Verticality, Pole diameter, Bracket Type).

      Check Antenna/ODU installation with given guild lines.

      Check OD lightning arresters are connected correctly & sealed properly.

     

    Check IF cable installations meet the DAP guide lines.  Check OD grounding points are well connected.

      Check water proofing (According to given instruction).

      Check Bulkhead is used efficiently & properly sealed after installation.

      Check indoor lightning arresters are properly installed & grounded.

      Check all indoor grounding points are tightened.

      Check IF Cable connectivity using a multi meter as described on IF cable installation guide.

      Check DC cable connectivity (correct polarity +/- connection to both rectifier, DCDU & INU/TX

    equipment sides & any physical damages to the cables).

      Check Earth cable connectivity & the cable sizes comply with DAP standards.

      Check DC Breaker capacity is matched with MW link manufacturer instructions.

     Check DC power connected side in the rectifier. All the TX Equipment should be connected tocritical side.

      Measure DC/AC voltage levels & note down.

      Check all modules are installed in to correct slots as per the WO.

      Check whether all accessories available in the IDU. (Fan Cards, Dummy cards etc.)

      Check tightness of all installed nuts/bolts of power and TX equipment.

      Check correct labeling for all installed equipment’s as per the DAP standards.

      Switch on the link.

  • 8/18/2019 Installation Guide-2015 Edition

    49/79

    48

    DNS Installation Guide-2015 Edition

    RECTIFIER INSTALLATION

    3.1 

    Indoor Cabin Rectifier Installation

    3.1.1 

    Placing and Mounting the Rectifier(ID)

      Area should be cleaned before placing the rectifier at the given location on the work order.

      It should not be placed under air conditioner but should ensure suitable ventilation for removing

    the heat generated.  For easy operation, rectifier system should be able to access from at least 2 sides. All three sites

    except back side is the best. It should be placed with minimum clearance to the wall/walls

    specified by the manufacturer.

    Picture 3.1.1: sufficient clearance for operation around the rectifier 

      Rectifier should be leveled & properly mounted using anchor bolts provided with installation kit.

      Each installation team/Operation team must take responsibility to neat up all the cables after

    any installation or removal.

    Picture 3.1.2: need to keep the neatness after any installation 

  • 8/18/2019 Installation Guide-2015 Edition

    50/79

    49

    DNS Installation Guide-2015 Edition

    3.1.2 

    1P & 3P Power Connections (DB/SPD) (ID)

      6mm2  four core cables should be used for power connection between rectifier and the main

    distribution panel.

      32A/4p MCBs should be installed for the rectifier input at the distribution panel expecting future

    augmentation.

     If the site is supplied with single phase power, line ports of rectifier breaker at the distributionpanel should be looped using short-circuit copper bars to utilize all four cores of the load cable

    & hence power the all module slots of the rectifier as it is connected to 3phase power supply.

      Power cables should be routed separately from the signaling cables, at least 30 mm away from

    each other, to avoid the interference & lightning damages due to induced currents. Same

    procedure should be followed inside cable casings & cable ducts as it is on the cable gantry.

    Picture 3.1.3: Earth cables/power cables & signaling cables should be separated inside the cable casings  

     

    Must avoid any joints on power cables.

  • 8/18/2019 Installation Guide-2015 Edition

    51/79

    50

    DNS Installation Guide-2015 Edition

      A second level protector should be installed closer to main distribution board on rectifier supply.

    The protector earth should be separately connected to the common ground near bulk head.

    Picture 3.1.4: Level 2 protector for rectifier load installed near main DB  

    3.1.3 

    Number of Rectifier Modules(ID)

      Maximum load of the site should be catered by the total capacity of the modules.

      Total capacity of all modules >= 110% X (Load + (10% X BB total capacity)

      If there is a 3P supply, modules should be installed in to the slots in a way they balance the site

    load (Not the rectifier load) among all three phases.

    Picture 3.1.5: Total capacity of modules (90A) marginally enough only to chargethis battery bank of 800Ah.

    It is not enough even for boost charge,

  • 8/18/2019 Installation Guide-2015 Edition

    52/79

    51

    DNS Installation Guide-2015 Edition

    3.1.4 

    Battery Strings Connections(ID)

      Battery breaker/Fuse should be equal or greater than 125A.

      Cable sizes must be used according to the BB capacity. Please refer below table for battery bank

    cables less than 5 meter in length. Please take regional PM consent for other scenarios.

    Battery capacity for one rectifier

    connection

    Minimum cable size

    200 Ah 25mm2

    400 Ah 35mm2 

    600 Ah 50mm2 

    Above 800 Ah Need take regional PM consentTable 3.1.1: Minimum cable sizes as per the BB capacity

      The connections should be tightened to torque values specified by the battery bank

    manufacturer using torque wrench.

    3.1.5 

    Rectifier Grounding(ID)

      Rectifier chassis should be connected to the common ground using 16mm2  or higher earth

    cable. This must be done as the first thing after mounting the rectifier.

    Picture 3.1.6: Rectifier grounding cable connected to rectifier chassis

     

    Routing the grounding cable should be done as per the DAP standard described on chapter 6.2 of this document.

    3.1.6 

    Indoor Casings for Cable installations(ID)

      PVC cable casings must be used for each and every cables laid along the cabin wall.

      Signaling cables should be separated as much as possible from Earth cables/power cables.

      All the cables should be bound to the base of the casing using indoor tie wraps.

      Cables in the PVC casings should not cross each other.

  • 8/18/2019 Installation Guide-2015 Edition

    53/79

    52

    DNS Installation Guide-2015 Edition

    3.1.7 

    Alarms Cable Installation(ID)

      Prepare 2 alarm cables using standard cat 5 cables. (Cables with RJ45 connectors crimped using

    standard Ethernet color code at the BTS end for Huawei BTS).

      Alarm cables should be arranged neatly and bounded properly to the rack.

      Alarm cables should not be routed near any power or earth cable. Use the area described on

    chapter 6.2 of this document.  Configure/connect rectifier alarms as per below table.

    Alarm O/P Alarm

    ALM 1 Rectifier Fault

    ALM 2 Mains fail

    ALM 3 Fuse Fail

    ALM 4 Battery Deep discharge

    ALM 5 Battery High TempTable 3.1.2: Rectifier alarms sequence

    3.1.8 

    BSS/TX/Other DC Load Connecting to the rectifier(ID)

      Strictly follow manufacturer specifications of the equipment to select correct breaker capacity.

      Use below guidelines to connect loads to critical & non critical sides correctly.

      Critical side

      MW links

      Fiber nodes

      Switches/Routers

      Any broadband BS (LTE TDD/Wimax/Wipll/Cambium)

      Non Critical side

      2G nodes

     

    3G Nodes  LTE FDD

      CDMA

      Always MW links should be placed in critical side & BTSs should be on Non-critical side.

    Picture 3.1.7: Critical & Non Critical loads are separated in every rectifier

  • 8/18/2019 Installation Guide-2015 Edition

    54/79

    53

    DNS Installation Guide-2015 Edition

      Any rectifier breaker swapping/replacing modification with higher/lower capacities must be

    prier approved by the regional PM.

      Labeling should be done for all the cables as per the DAP standards described on chapter 7 of

    this document. 

    3.1.9 

    General Settings(ID)

      LVD end voltage for the critical side should be set to 43.2V.

      LVD end voltage for the non-critical load must be set according to the total load and the battery

    capacity of the site. Please take regional PM consent before adjusting.

      Use Recommended Settings by the battery bank manufacturer for float/boost voltages &

    temperature compensation settings. You may refer below table for commonly used battery

    banks in DAP network.

    Table 3.1.3: battery bank related rectifier settings

    3.1.10 

    Things to do Before Power up Rectifier(ID)

      Rectifier grounding cable should be tightly connected at both ends.

      The ground cable, AC power cables, and internal signaling cables should be correctly connected

    and screws should be tightened to maximum possible torque relevant to screw/bolt size.

      Earth cables & power cables should be laid along the paths specified on the  chapter 6 of this

    document.

      Check the temperature sensors are placed correctly. One should be inside the rectifier & one

    should be on battery banks (between batteries).  Check positive bus bar connectivity to the PGND.

      Check that rectifier modules are correctly installed to the module slots. Half connected modules

    may end up burnt.

      Check all the interconnections of the battery bank are tighten to the correct torque.

      Check every battery strings voltage before turning on the battery breaker or plugging the

    battery fuse.

      Again check that input and output power cables and ground cables are correctly tightened to

    bus bars/breakers without being short circuited.

  • 8/18/2019 Installation Guide-2015 Edition

    55/79

    54

    DNS Installation Guide-2015 Edition

      Check all the cables for physical damages & examine if they are neatly bound to the cable

    tray/supported all along the cable routing path. 

    3.2 Outdoor Cabin Rectifier Installation

    3.2.1 

    Placing and Mounting the Rectifier(OD)

      Rectifier must be mounted on the top position of the outdoor cabinet rack (Picture 2.5.2).

      Need to keep proper clearance (at least one U) for the ventilation and routing the cables. Please

    adhere to the OD cabinet vendor specification if they have described on ventilation spaces.

    Picture 3.2.1 typical arrangement of outdoor equipment cabinet

    3.2.2 

    1P & 3P Power Connections to the Rectifier (DB/SPD) (OD)

      6mm2 four core cables should be used for power connection between rectifier and the outdoor

    distribution panel.

      Shield of the cable should be grounded at the distribution panel end if the underground

    armored cable used for this requirement.

      32A/4p MCBs should be installed for the rectifier input at the distribution panel expecting future

    augmentation.

      If the site is supplied with single phase power, line ports of rectifier breaker at the distribution

    panel should be looped using short-circuits copper bars to utilize all four cores of the cable &hence power the all module slots of the rectifier.

      Power cables should be routed separately from the signaling cables, at least 30 mm away from

    each other, to avoid the interference & lightning damages due to induced currents

  • 8/18/2019 Installation Guide-2015 Edition

    56/79

    55

    DNS Installation Guide-2015 Edition

      Rectifier supply must be protected using level 2 surge protector at the outdoor distribution

    panel.

    Picture 3:2:2 Level 2 SPD installed for OD cabinet

      Must avoid any joints on power cables.

    3.2.3 

    Number of power modules(OD)

     

    Maximum load of the site should be catered by the total capacity of the modules.

    Total capacity of all modules >= 110% X (Load + (10% X BB total capacity)

      If there is a 3P supply, modules should be installed in to the slots in a way they balance the

    rectifier load among all three phases.

    3.2.4 

    Battery Strings Connections(OD)

      Battery breaker/Fuse should be equal or greater than 125A.

      Cable sizes must be used according to the BB capacity. Please refer below table for battery bank

    cables less than 5 meter in length.

    Battery capacity for one rectifierconnection

    Minimum cable size

    200 Ah 25mm2

    400 Ah 35mm2 

    600 Ah 50mm2 

    Above 800 Ah Need take regional PM consentTable 3.2.1: Cable sizes as per the BB capacity  

  • 8/18/2019 Installation Guide-2015 Edition

    57/79

    56

    DNS Installation Guide-2015 Edition

      The battery terminals should be tightened to torque values specified by the battery bank

    manufacturer.

      Must use exactly matching tools with correct torque setting for tightening battery terminals.

    Damages to any battery terminal will lead to malfunctioning of entire battery bank.

    3.2.5  Rectifier Grounding(OD)

      When installing a PGND cable, ensure that the terminals on the PGND cable are oriented

    correctly and that the screws are tightened, as shown in Fig. 04, No washers between grounding

    point and lug.

    Picture 3.2.1 correct and incorrect terminal mounting

      Use 35mm2 or higher sizes for Ground cables and Need to Ground external Grounding bus bar.

    3.2.6 

    Alarm Cable Installation(OD)

      Prepare 2 alarm cables using standard cat 5 cables. (Cables with RJ45 connectors crimped using

    standard Ethernet color code at the BTS end for Huawei BTS).

      Cables should be arranged neatly and bounded properly to the rack.

      Alarm cables should be separated from power/Earth cables as much as possible.

      Configure/connect rectifier alarm outputs as below.

    Alarm O/P Alarm

    ALM 1 Rectifier Fault

    ALM 2 Mains fail

    ALM 3 Fuse Fail

    ALM 4 Battery Deep discharge

    ALM 5 Battery High TempTable 3.2.2: External alarm sequence

    3.2.7 

    BSS/TX/Other DC Power Supply(OD)

     

    Strictly follow manufacturer specifications of the equipment to select correct breaker capacity.

      Use below guidelines to connect loads to critical & non critical sides correctly.

      Critical side

      MW links

      Fiber nodes

      Switches/Routers

      Any broadband BS (LTE TDD/Wimax/Wipll/Cambium)

  • 8/18/2019 Installation Guide-2015 Edition

    58/79

    57

    DNS Installation Guide-2015 Edition

      Non Critical side

      2G nodes

      3G Nodes

      LTE FDD

      CDMA

      Always MW links should be placed in critical side & BTS should be on Non-critical side.

      Any breaker swapping/replacing with higher/lower capacities must be prier approved by the

    regional PM.

      Labeling should be done for all the cables as per the DAP standards described on chapter 7 of

    this document.

    3.2.8 

    General Settings(OD)

      LVD end voltage for the critical side should be set to 43.2.

      LVD end voltage for the non-critical load must be set according to the total load and the battery

    capacity of the site. Please take regional PM consent before adjusting.

      Use Recommended Settings by the battery bank manufacturer for float/boost voltages &

    temperature compensation settings. You may refer below table for commonly used battery

    banks in DAP network.

    Table 3.2.3: battery bank related rectifier settings

    3.2.9 

    Things to do Before Power up Rectifier(OD)

      Rectifier grounding cable should be tightly connected at both ends.

      The ground cable, AC power cables, and internal signaling cables should be tightly connected

    and all the screws to be tightened to maximum possible torque relevant to the bolt size.

      Earth cables & power cables should be laid along the paths specified on the chapter 6 of this

    document.

  • 8/18/2019 Installation Guide-2015 Edition

    59/79

    58

    DNS Installation Guide-2015 Edition

      Check positive bus bar connectivity to the PGND.

      Check that rectifier modules are correctly installed to the module slots. Half connected modules

    may end up burnt.

      Check all the interconnections of the battery bank are tighten to the correct torque.

      Check the battery bank voltage before turning on the battery breaker or plugging the battery

    fuse.

     

    Again check that input and output power cables and ground cables are correctly connected

    without being short circuited.

      Check all the cables for external damages & examine if they are neatly bound to the cable

    tray/support, all along the cable routing path. 

  • 8/18/2019 Installation Guide-2015 Edition

    60/79

    59

    DNS Installation Guide-2015 Edition

    BATTERY BANK INSTALLATION

    4.1 

    Indoor Cabin battery bank Installation

    4.1.1 

    Battery Rack Mounting & Placing(ID)

      Clean the area before begin installation.

    Picture 4.1.1: area not cleaned before beginning the installation

      Avoid any air conditioners on top of the battery bank when selecting the place.

      Keep the battery bank as close as possible to the rectifier to avoid voltage drop & heat

    dissipation in BB cables.

    Picture 4.1.2: BB & rectifier placed closely

  • 8/18/2019 Installation Guide-2015 Edition

    61/79

    60

    DNS Installation Guide-2015 Edition

    4.1.2 

    Battery placing and inter connections(ID)

      Place the batteries as per the instruction manual of the battery manufacturer.

      Keep at least 10mm gap between batteries to cater proper ventilation if not specified on the

    installation manual.

      Tightening the battery terminals should follow the manufacturer specifications (Torque setting

    in Nm) & must use torque wrench.

    4.1.3 

    Casings for Battery Strings/cables(ID)

      Battery bank cables should be routed through PVC casings on wall area.

    Table 4.1.3: Battery cables should be laid via PVC casings

      Earth cables & DC power cables must be separated as much as possible inside the casing.

      Cables should be bound to the casing base using indoor cable ties.

    4.1.4 

    Battery Strings connections(ID)  Must use standard colors for battery bank cables. Blue for – polarity & Black for + polarity.

      Must apply grease provided with installation kit on the terminals after fixing to avoid any

    corrosion.

    Picture 4.1.4: grease applied for corrosion protection

      Must be labeled as per the DAP standards described chapter 7 on this document

      Power cables should be laid separately from the earth cables as much as possible.

      If the interconnection cables are not provided with installation kit, interconnection cables must

    be made under the guide lines described on chapter 1.13 of this document.

  • 8/18/2019 Installation Guide-2015 Edition

    62/79

    61

    DNS Installation Guide-2015 Edition

    4.1.5 

    Rack Grounding(ID)

      All the battery racks should be connected to common ground using 16mm2 or higher grounding

    cables.

    4.1.6  Things to do before connecting to rectifier(ID)

     

    Check again, all the battery terminals are tightened to the torque values specified by the batterybank manufacturer.

      Temperature sensors should be in place.

      Any physical damages to interconnection cables or battery bank cables.

      Check the physical status of each battery, if they are free of damages/cracks, and experience no

    leakage.

      Check the battery string voltages, string by string. Should be around 48V.

    4.2 Outdoor Cabin battery bank Installation

    4.2.1 

    Battery placing and inter connections(OD)

     Install Battery banks at the bottom of the outdoor cabin and away from heat sources as much aspossible.

      Keep proper clearance between batteries according to the BB manufacturers Specification.

    Picture 4.2.1: keep the manufacturer specified clearance between batteries for ventilation

      Tighten the connections according to the specified torque values by the manufacturer.

  • 8/18/2019 Installation Guide-2015 Edition

    63/79

    62

    DNS Installation Guide-2015 Edition

    4.2.2 

    Battery Cable Laying from OD battery cabinet to equipment cabin. (OD)

      Cables between two cabinets should be routed through PVC casings/Gi flexibles & the casings

    must be sealed as much as possible. GI flexible must be connected to common ground at one

    end.

      Cables should be labeled as per DAP labeling guide on this document.

     Joints on any DC power cable are not accepted.  Finishing of the battery bank cable terminals should comply with the guide lines on chapter 1.13 

    of this document.

    4.2.3  Battery Strings connections(OD)

      Must use standard colors for battery bank cables. Blue for – polarity & Black for + polarity.

    Picture 4.2.2: standard colors for correct polarity, Red for Positive

      Must be labeled as per the DAP standards described chapter 7 on this document

      Power cables should be laid separately from the earth cables as much as possible.

      If the interconnection cables are not provided with installation kit, interconnection cables must

    be made under the guide lines described on chapter 1.13 of this document

    4.2.4 

    Things to do before connecting to the rectifier(OD)

      Check again, all the battery terminals are tightened to the torque values specified by the battery

    bank manufacturer.

      Temperature sensors should be in place.

      Any physical damages to interconnection cables or battery bank cables.

     Check the physical status of each battery, if they are free of damages/cracks, and experience noleakage.

      Check the battery string voltages, string by string. Should be around 48V.

  • 8/18/2019 Installation Guide-2015 Edition

    64/79

    63

    DNS Installation Guide-2015 Edition

    WATERPROOFING/WEATHERPROOFING

    5.1 

    Why Waterproofing/Weatherproofing.

      Moisture build up within the RF/IF connectors can wreak havoc on a system’s performance. 

      The coaxial cable’s dielectric is typically made of open-cell foam, which can act like a sponge,

    absorbing and retaining moisture.

     

    Moisture encourages corrosion around the connector, potentially leading to a scenario whereRF signals inadvertently mix and generate passive intermodulation (PIM) distortion.

      PIM can interfere with neighboring frequencies, prompting a host of legal and regulatory

    headaches for the operator. Also it will generate high VSWR values and damage transmitter

    equipment at some point.

    Picture 5.1.1: RF cable damaged by moisture. 

    5.2 Common procedure for outdoor RF/IF connector water proofing.

      Step 1- Vinyl insulation tapes should apply as the first layer. It should be wrapped from top to

    Bottom to avoid draining water inward if the mastic/Rubber tape layer is damaged at any

    position and water leaked in to the seal.

     Step 2- Then 2 layers of mastic/Scotch, typically made of butyl rubber should be applied. Thislayer should form a seal against water intrusion, completely covering the connector/joint.

      Step 3- then 2 layers of Vinyl tape should be applied to secure the mastic in place and protect it

    from UV rays. This wrapping also should begin from the top and end on bottom side of the

    connection. The end product should look like a smooth, round bump on the cable.

      Finally a tie wrap tighten at both ends of the sealing can ensure stability of vinyl tape edge.

    Picture 5.2.1: Waterproofing steps for Sandwich Mastic layer method.

  • 8/18/2019 Installation Guide-2015 Edition

    65/79

    64

    DNS Installation Guide-2015 Edition

      Properly wrapping connections with tape and mastic (left of below pic) requires skill. If done

    poorly (center and right, mastic layer was skipped) water can seep in, potentially resulting in

    service outages.

    Picture 5.2.2: Correct and incorrectly done water proofing

    Picture 5.2.3: RF jumper termination points waterproofed

    5.3 

    Cellular Antenna/RRU unused ports waterproofing

      First unused ports of the Cellular antennas/RRUs should be covered with the dust proof cap

    initially provided with the antenna or RRU.

      Then it should be sealed as per above 5.2 guidelines.

    5.4 

    TX Waveguides waterproofing  Need to seal the waveguide ends with PVC tape & 3M rubber tape as per the same guide lines

    on 5.2. 

      Silicon must be used in addition in waveguide scenario. Because, applying vinyl tape may not

    cover whole interface between waveguide & Radio or Waveguide & antenna as it is not a

    regular shape like RF/IF connector. So the screw tightening area of the face plate can be covered

    using silicon.

  • 8/18/2019 Installation Guide-2015 Edition

    66/79

    65

    DNS Installation Guide-2015 Edition

    Picture 5.4.1: waveguides sealed at connecting points

      Unused ports of MW couplers should be sealed using cover plates or the method accepted by

    the manufacturer.

    Picture 5.4.2: cover plate used for covering unused coupler port

  • 8/18/2019 Installation Guide-2015 Edition

    67/79

    66

    DNS Installation Guide-2015 Edition

    5.5 

    RF/IF Connectors waterproofing