Installation Guide10GX IDC X-Conn. Multiple Frames Installation
PX105226-EN Release B Page 1/10
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
A) General
Components
Standard components
1- BHHR194 - Two Post Self Supporting Rack2- AX104225 - Front-to-Back Trough Kit 42"3- BHVH006 - 6" Vertical Manager4- BHVH012 - 12" Vertical Manager
Optionnal components
5- AX104225-S Front-to-Back Trough Kit 38"6- AX104226 - Overhead Kit
Related Documents:- IS-8_BELDEN_V1:
Belden Cable Manager Installation Instructions- PX104781
10GX IDC Patch Panel- PX105081
10GX IDC Connecting Block TerminationProcedure
- PX10522410GX IDC X-Conn. Front-to-Back Cross-Conn.Cable Management Trough Kit
- PX10522510GX IDC X-Conn. Horizontal Cross-Conn.Cable Management Tray Kit
- TELIS00-2BELTwo Post Self-Supporting Equipment RackAssembly Instruction
2 or 5
1
1
3
4
6
Page 2/10
B) Floor Layout
10GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
C) Installation
Step 1:- Install first rack with a co-worker (referto PX105224 for 10GX IDC X-Conn. Front-to-Back Cross-conn. Cable Management TroughKit)
Page 3/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
Step 2:- Install end 6" vertical manager- Refer to IS-8_BELDEN_V1: BeldenCable Manager Installation Instructions
6" verticalmanager
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
Step 3:- Install center 12" vertical manager- Refer to IS-8_BELDEN_V1: BeldenCable Manager Installation Instructions
12" verticalmanager
Page 4/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
Step 4:- Install as many frames (Step-1) and 12"vertical manager (Step-3) with a co-worker- Refer to IS-8_BELDEN_V1: Belden CableManager Installation Instructions andPX105224 10GX IDC X-Conn. Front-to-Back Cross-Conn. Cable ManagementTrough Kit
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
6" verticalmanager
Step 5:- Install end 6" vertical manager- Refer to IS-8_BELDEN_V1: BeldenCable Manager Installation Instructions
Page 5/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
Step 6:- Install optional 10GX IDC X-Conn. HorizontalCross-Conn. Cable Management Tray Kit (AX104226)- Refer to PX105225 10GX IDC X-Conn. HorizontalCross-Conn. Cable Management Tray Kit InstallationInstructions
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
Page 6/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
Bundle 1
D) Cabel management
Step 1:- Dress each cable bundle (96 cable/bundel) and tie them at each trough
Bundle 7
Bundle 5
Bundle 6
Bundle 1
Bundle 7
Bundle 2
Bundle 3
Bundle 4
Bundle 5
Bundle 6
OVERHEAD KIT
Overhead kit is reserved to managecross-connect cables only.
CABLE LENGTH
Bundels shown at tie point.
Make sure to keep required slack toterminate connections
Page 7/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
E) Cross-ConnectManagement
BackVertical
manager
Option 1:Same rack, same half- Rout cross-connect cable from frontto back across trough
- Change level in hatched area ifrequired
CL CL
FrontCross-connect cable
Verticalmanager
Front
Back
Cross-connect cable
Change levelin this area
Page 8/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
BackVertical
manager
Option 2:Next rack, adjacent half- Rout cross-connect cable from frontto back across trough
- Change level in hatched area ifrequired
CL CL
FrontCross-connect cable
Verticalmanager
Front
Back
Cross-connect cable
Change levelin this area
Page 9/1010GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
This Installation Guide is available in the “Document Center” of the Belden Networking website - www.belden.com
BackVertical
manager
Option 3:Same rack, next half- Rout cross-connect cable from frontto back across trough
- Rout through overhead kit to reachnext half
- Change level in hatched area
CL CL
FrontCross-connect cable
Verticalmanager
Front
Back
Cross-connect cable
Cable ManagementTray Kit
Change levelin this area
Page 10/10
For additional information, call 1-800-belden1
Copyright 2008, Belden Inc.
10GX IDC X-Conn. Multiple Frames Installation PX105226-EN Release B
BackVertical
manager
Option 4:Any next rack, any next half- Rout cross-connect cable from front to backacross trough
- Rout through overhead kit to reach next half
- Change level in hatched area
CL CL
FrontCross-connect cable
Front
Back
Cable ManagementTray Kit
Cross-connect cable
Verticalmanager
Change levelin this area