Installation of the BP Atlantis Flowlines and Risers By HMC
IPLOCA 2008
Presented by: Simon Webb BP and Bas Zoon HMCDate: 7 October 2008
![Page 2: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/2.jpg)
2
HMC SOW highlights of the Atlantis Installation Projects
Semi Submersible Production Quarters (PQ) installed by HMC24 inch export oil line and a 16 inch export gas line, installed by HMCHMC flow line scope; transport and installation of work 5 PIP lines and one water injection line from drill centre to PQ offshore Gulf of Mexico
- Water Depth +2 km (7000 ft)- Length ~2 km Flowline and ~3 km Riser- 16 inch x 10.75 inch PIP
![Page 3: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/3.jpg)
3
The Atlantis Field
![Page 4: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/4.jpg)
4
The Atlantis Field
![Page 5: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/5.jpg)
5
Pipeline Design
Procurement
Fabrication
SCR pull-in equipment on the Atlantis Floater
System Integration Testing
Load out onto HMC provided Barges
Onshore Scope of Work
![Page 6: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/6.jpg)
6
The Atlantis Field
![Page 7: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/7.jpg)
7
Onshore Fabrication – Bayou, New Iberia
![Page 8: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/8.jpg)
8
Onshore Fabrication – Spool Piece Load out
![Page 9: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/9.jpg)
9
System Integration Testing
![Page 10: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/10.jpg)
10
SCR Pull-in Chain Jack on Atlantis PQ
![Page 11: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/11.jpg)
11
The Spread: Transportation Barge
![Page 12: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/12.jpg)
12
Keys to Success
• The Team!• Detailed Onshore Preparation • DCV Balder; The Proper
Equipment for the Work an Inherently flexible vessel
• Excellent Crew and interfaces with Client and SIMOPS
• Flexibility to manage schedule and procedures (using MOC processes)
• Contingency and Emergency response planning
• Safety Management
![Page 13: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/13.jpg)
13
Balder Deck During The Atlantis Project
![Page 14: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/14.jpg)
14
SIMOPS in Action
![Page 15: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/15.jpg)
15
Team Continuity and Achievement
![Page 16: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/16.jpg)
16
PLET PULL IN ANIMATION
![Page 17: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/17.jpg)
17
SLIDING PIP On Balder Deck and in Tower
![Page 18: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/18.jpg)
18
INNER PIPE PULL OUT
![Page 19: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/19.jpg)
19
Tower welding
![Page 20: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/20.jpg)
20
RISER TRANSFER - ANIMATION
Riser Transfer of 750 mT dry LoadTransfer with three systems, Crane A&R and Chain JackSpool piece installed on Balder No divers required
![Page 21: Installation of the BP Atlantis Flowlines and Risers By HMC BP... · HMC SOW highlights of the Atlantis Installation Projects Semi Submersible Production Quarters (PQ) installed by](https://reader030.vdocument.in/reader030/viewer/2022040323/5e64105432c342095f1f267d/html5/thumbnails/21.jpg)
21
Lessons Learned
Integrated team (BP and HMC) to work issues
Team continuity and team approach is essential to success –recognise the need for team career development over long projects
Three years of onshore engineering/planning ensured smooth offshore execution
Understand the technical complexity – resource accordingly
Plan for SIMOPS