installation operation, and maintenance manual · even air distribution to maximize cooling and...

73
1 MAGNAMAX GENERATOR INSTALLATION OPERATION, AND MAINTENANCE MANUAL

Upload: others

Post on 10-May-2020

11 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

1

MAGNAMAXGENERATOR

INSTALLATIONOPERATION, AND

MAINTENANCEMANUAL

Page 2: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

2

TABLE OF CONTENTS

TABLE OF CONTENTS ............................................................................................................... 2

SAFETY.......................................................................................................................................... 6

GENERAL INFORMATION ........................................................................................................ 7

MECHANICAL DESIGN ......................................................................................................................7General ............................................................................................................................................................... 7Conduit Box ....................................................................................................................................................... 7MagnaMAX UnirotorTM Construction ............................................................................................................ 7Adapters and Drive Discs.................................................................................................................................. 7

ELECTRICAL DESIGN........................................................................................................................8Temperature Rise .............................................................................................................................................. 8Standby Generator Ratings .............................................................................................................................. 8Premium Insulation System.............................................................................................................................. 8Power Factor...................................................................................................................................................... 8MagnaMAX Voltage Regulator ....................................................................................................................... 8

HOW TO READ A MODEL NUMBER...............................................................................................9

INSTALLATION.......................................................................................................................... 10

RECEIVING YOUR MAGNAMAX GENERATOR........................................................................10

UNPACKING AND HANDLING .......................................................................................................10

STORAGE.............................................................................................................................................10

PREPARATION FOR USE.................................................................................................................10

GENERATOR MOUNTING - SINGLE BEARING.........................................................................10

GENERATOR MOUNTING-TWO BEARING ................................................................................11

BELT DRIVE........................................................................................................................................11

ENVIRONMENTAL CONCERNS.....................................................................................................11

ELECTRICAL CONNECTIONS ................................................................................................ 12

GENERATOR LEAD CONNECTIONS............................................................................................12

12 LEAD HIGH WYE CONNECTION..............................................................................................13

12 LEAD LOW WYE CONNECTION...............................................................................................13

12 LEAD HIGH DELTA CONNECTION .........................................................................................14

12 LEAD LOW DELTA CONNECTION ..........................................................................................14

10 LEAD HIGH WYE CONNECTION..............................................................................................15

10 LEAD LOW WYE CONNECTION...............................................................................................15

6 LEAD WYE CONNECTION ...........................................................................................................16

6 LEAD DELTA CONNECTION .......................................................................................................16

3 LEAD DELTA CONNECTION .......................................................................................................17

4 LEAD WYE CONNECTION ...........................................................................................................17

Page 3: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

3

DOUBLE DELTA -- SINGLE PHASE CONNECTION ..................................................................18

LOW ZIG ZAG -- SINGLE PHASE CONNECTION ......................................................................18

HIGH ZIG ZAG -- SINGLE PHASE CONNECTION .....................................................................18

PARALLELING OPERATIONS................................................................................................. 19

PRIME MOVER...................................................................................................................................19

VOLTAGE REGULATOR..................................................................................................................19

SWITCHGEAR.....................................................................................................................................19

PARALLELING BASICS....................................................................................................................19

REACTIVE LOAD CONTROL..........................................................................................................20

PARALLELING CIRCUITRY ...........................................................................................................20

THYRISTOR OR SCR LOADING .............................................................................................. 21

OPERATION................................................................................................................................ 21

PRE-START INSPECTION................................................................................................................21

STARTING-UP THE GENERATOR.................................................................................................22

FIELD FLASHING ..............................................................................................................................22

VOLTAGE ADJUSTMENTS..............................................................................................................22

OTHER ADJUSTMENTS ...................................................................................................................23

MAINTENANCE ......................................................................................................................... 23

GENERAL INFORMATION..............................................................................................................23

AIR INTAKE AND EXHAUST...........................................................................................................23

ELECTRICAL CONNECTIONS, WINDINGS ................................................................................24

LUBRICATION....................................................................................................................................24

DRYING ELECTRICAL INSULATION...........................................................................................26Space Heaters................................................................................................................................................... 26Oven.................................................................................................................................................................. 26Forced Air ........................................................................................................................................................ 26“Short Circuit” Method .................................................................................................................................. 26

CLEANING METHODS......................................................................................................................27Solvents............................................................................................................................................................. 27Cloth and Compressed Air ............................................................................................................................. 27Brushing and Vacuum Cleaning .................................................................................................................... 27Shell Blasting.................................................................................................................................................... 27Steam Cleaning ................................................................................................................................................ 27

DISASSEMBLY ........................................................................................................................... 28

REMOVAL FROM PRIME MOVER................................................................................................28

CONDUIT BOX REMOVAL ..............................................................................................................29

EXCITER STATOR (FIELD) REMOVAL .......................................................................................30

EXCITER ARMATURE (ROTOR) REMOVAL..............................................................................30

Page 4: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

4

PMG STATOR REMOVAL................................................................................................................31

MAIN ROTOR REMOVAL................................................................................................................33

FRONT END BRACKET REMOVAL...............................................................................................35

EXCITER INSPECTION ............................................................................................................ 35

EXCITER STATOR.............................................................................................................................35

EXCITER (ROTOR) ARMATURE....................................................................................................36

PMG INSPECTION..................................................................................................................... 37

PMG STATOR......................................................................................................................................37

PMG ROTOR .......................................................................................................................................37

MAIN ROTOR INSPECTION .................................................................................................... 37

BEARING..............................................................................................................................................37

FAN ........................................................................................................................................................38

MAIN ROTOR CORE AND WINDINGS..........................................................................................40

DRIVE DISCS (SINGLE BEARING GENERATORS ONLY) .......................................................40

FRONT (EXCITER) END BRACKET INSPECTION .............................................................. 40

DRIVE END BRACKET OR SAE ADAPTER INSPECTION.................................................. 41

MAIN STATOR INSPECTION................................................................................................... 42

FRONT END BRACKET INSTALLATION .............................................................................. 42

MAIN ROTOR INSTALLATION ............................................................................................... 42

PMG INSTALLATION................................................................................................................ 45

EXCITER INSTALLATION ....................................................................................................... 46

CONDUIT BOX INSTALLATION ............................................................................................. 47

ASSEMBLY TO PRIME MOVER .............................................................................................. 48

TROUBLESHOOTING ............................................................................................................... 50

INTRODUCTION.................................................................................................................................50

SYMPTOM: ..........................................................................................................................................51NO VOLTAGE OR RESIDUAL VOLTAGE............................................................................................... 51LOW VOLTAGE - .......................................................................................................................................... 52NO LOAD ........................................................................................................................................................ 52LOW VOLTAGE WHEN LOAD IS APPLIED ........................................................................................... 53HIGH VOLTAGE ........................................................................................................................................... 53VOLTAGE IS FLUCTUATING .................................................................................................................... 54OPERATES SATISFACTORILY WHEN COLD, BUT SHUTS DOWN WHEN WARM ..................... 54BUILDS VOLTAGE FROM STARTUP,THEN GOES TO LOW (RESIDUAL) VOLTAGE ................ 54EQUIPMENT RUNS NORMALLY ON UTILITY POWER, BUT WILL NOT RUN ON GENERATOR SET ................................................................................................................................................................... 54

GENERATOR TESTING ............................................................................................................ 55

VISUAL INSPECTION........................................................................................................................55

Page 5: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

5

CONSTANT EXCITATION (12V BATTERY) TEST.......................................................55

MEASURING VOLTAGES.................................................................................................................56

TYPICAL VOLTAGE MEASUREMENTS ......................................................................................57Generator Output Voltage ................................................................................................................................. 57Regulator Output (Exciter Stator Input) ............................................................................................................ 57Regulator Sensing.............................................................................................................................................. 57Regulator Input Volts (PMG Output Volts) ..................................................................................................... 57

CURRENT (AMP) MEASUREMENTS.............................................................................................57

MEASURING RESISTANCE .............................................................................................................58Main Stator ...................................................................................................................................................... 58Exciter Rotor.................................................................................................................................................... 58

TESTING DIODES (RECTIFIERS) ..................................................................................................58

INSULATION RESISTANCE - MAIN STATOR.............................................................................59

GENERATOR TESTING ....................................................................................................................59

INSULATION RESISTANCE - MAIN ROTOR...............................................................................59

INSULATION RESISTANCE - EXCITER STATOR......................................................................60

INSULATION RESISTANCE - EXCITER ROTOR........................................................................60

MAIN ROTOR FIELD AC IMPEDANCE TEST .............................................................................60

MAGNAMAX EXPLODED VIEW ....................................................................................................61

STANDARD TOOLS.................................................................................................................... 64

SPECIAL TOOLS ................................................................................................................................65

MISCELLANEOUS .............................................................................................................................66

PREPARATION FOR SHIPMENT OR EXTENDED STORAGE........................................... 66

SHIPPING INSTRUCTIONS..............................................................................................................66

STORAGE INSTRUCTIONS..............................................................................................................66

TABLE 12-1: MAGNA MAX - FASTENER AND TORQUE SPECIFICATIONS ................. 68

TABLE 12-2: CAPSCREW TORQUE VALUES........................................................................ 69

TABLE 12-3:EXCITATION DATA -60 HZ - 1800 RPM .......................................................... 70

TABLE 12-3:EXCITATION DATA -50 HZ - 1500 RPM .......................................................... 71

TABLE 12-5: RESISTANCE VALUES - MAIN WINDINGS................................................... 72

TABLE 12-6: RESISTANCE VALUES - EXCITER WINDINGS............................................ 73

Page 6: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

6

SAFETY

PLEASE REMEMBER SAFETY FIRST. If you are not sure of the instructions or procedures,seek qualified help before continuing.

This service manual emphasizes the safety precautions necessary during the installation, opera-tion, and maintenance of your generator.

Each section has caution and warning messages. These messages are for your safety and thesafety of the equipment involved. If any of the cautions or warnings is not readily understood,seek clarification from qualified personnel before proceeding.

Before any service work is done, disconnect all power sources and, where appropriate, lock outall controls, to prevent an unexpected start-up of the generator set. Proper grounding incompliance with local and national electrical codes must be provided. These safety precautionsare necessary to prevent potential serious personal injury, or even death.

The hazards associated with lifting or moving the generator are pointed out in the installation andservice sections; incorrect lifting or moving can result in personal injury or property damage.

Whenever the generator is running, always assume and proceed as if voltage is present. Residualvoltage is present at the generator leads and at the regulator panel connections, even with theregulator fuse removed. Caution must be observed, or serious personal injury or death can result.

Whenever solvents, cleaners, or flammable liquids are present, adequate ventilation must beavailable to avoid fire, explosion, and health hazards. Always avoid breathing vapors and usesuitable personal protective equipment to prevent personal injuries. (Such as eyes, face, and handprotection.)

This manual is not intended to be a substitute for properly trained personnel. Only qualifiedtrained people should attempt repairs. The cautions and warnings point out known conditionsthat are potentially dangerous. Each installation will create its own set of circumstances. Nomanual can cover every possible situation.

When in doubt, ask. Don’t be embarrassed to ask, “dumb questions”. Remember that dumbquestions are much easier to handle than dumb mistakes.

Page 7: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

7

GENERAL INFORMATION

MECHANICAL DESIGN

General

All single and two bearing units aremanufactured with cast iron end bracketsand adapters, and fabricated steel frames.Flexible drive discs and SAE adapters aremachined to SAE standards. Pre-lubricated,regreasable, shielded ball bearings are usedon MagnaMAX generators. Standard unitsare fully guarded. Drip proof shields areavailable as an option.

Conduit BoxThe large end mounted conduit box is con-structed of formed sheet steel that will allowthe addition of top mounted controlpackages. Refer to Marathon Electric for topmounted controls of more than 240 lbs.There is ample room inside the conduit boxfor a circuit breaker (through 800A Frame)and other options. The conduit box coverproperly directs outside ventilating airthrough the generator.

MagnaMAX UnirotorTM Construction

An aluminum die cast rotor core affordshigh mechanical integrity and low vibrationat operating speeds. Amortisseur windingand coil supports are die cast as an integralpart of the rotor. Laminations are 4-pole,one piece laminations which are shrunk fitand keyed to the shaft. No dovetails, crossbolts or other pole to shaft connectingdevices are used. The cast unidirectionalaluminum alloy ventilation fan provideseven air distribution to maximize coolingand generator efficiency.

Adapters and Drive Discs

All single bearing units are available withseveral adapters and drive discarrangements. These can be shipped to orderor can be changed in the field with standardshop tools. When changing flexible drivediscs, spacers are used between the discs andthe cast iron hub to maintain SAE standarddimensions.

Page 8: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

8

ELECTRICAL DESIGNAll standard products have 2/3 pitch mainwindings to eliminate the third harmonic.This serves to lower operating temperatures,give lower harmonic content and betterwaveform, and extend the overall life of thegenerator.

Temperature RiseAll ratings and frame sizes are based onNEMA and CSA Class F and Class Htemperature rises on both the rotor and statorwindings. Ratings for British, German,French, IEC and all popular marine agenciesare available.

Standby Generator RatingsSynchronous generators used on emergencybackup power can have temperature rises upto 25°C above those for continuousoperation. (NEMA MG1 -22.40 and MG 1-22.84).

Premium Insulation System

All MagnaMAX generators are built withClass H or better insulation materials. Allstandard generators are suitable forcontinuous duty at Class F temperature riseand will give equivalent or better windinglife expectancy to generators supplied withClass A or B insulation systems operatedwithin their temperature limits. Thevarnishes and epoxies used are synthetic,non-hygroscopic. Multiple dip and bake

cycles of the main winding, plus a final coatof epoxy, make the standard windingmoisture and fungus resistant. TheMagnaMAX rotor is wet wound withthermo-setting epoxy applied between eachlayer, plus a final coating of epoxy formoisture and abrasion resistance.

MagnaMAX generators can be ordered withan epoxy vacuum pressure impregnatedinsulation system as an option. (MagnaMAXgenerators with form wound coils includeVPI as standard.)

Power FactorAll standard generators are designed foroperation at rated kVA at 0.8 lagging powerfactor but can be operated at rated kVA overthe 0.8 to 1 .0 power factor range.

MagnaMAX Voltage Regulator

The standard voltage regulator is a fullyencapsulated, static types with a solid statebuild up circuit. Standard features include 3-phase RMS sensing, paralleling, adjustableunder frequency protection, and overexcitation protection. The regulator meetsEMI suppression to Mil Std-461B, part 9.An optional feature is adjustable armaturecurrent limiting. See the regulator manualfor more information.

Page 9: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

9

HOW TO READ A MODEL NUMBERIt is extremely important to properly identify the machine when requesting parts or service.Always have the generator model number and serial number when requesting information fromthe factory. We cannot help you without this information.An Example For MagnaMAX Generators 431RSL 2000 AA - 000

Character Category Description1st three characters Frame Number4th character Winding type R—Random Wound

F—Form Wound5th character Bearing arrangement S—1 Bearing

D—2 Bearings6th character Voltage range L—Up to 480 volts

M—1000-6600 voltsS—600 volts

7th Character Product style 4-Magna8th Character Type9th & 10th Character Wk2 Code11th Character Modification A-Z assigned sequentially12th Character Mounting Arrangement A-Y see chart figurer 2-113th, 14th & 15th characters Modification numbers For internal use only

Arrangement Adapter SAE Size Drive Disc SAE SizeA 3 11-1/2B 2 11-1/2C 4 8D 3 10E 1 11-1/2F 1 14G 4 7-1/2H 1 DelcoJ 1/2 14K 2 10L 1/2 DelcoM 0 14N 2 Small Delco0 None NoneP 0 18S 0 DelcoU 00 18V 4 6-1/2W 00 21Y 4 10

Figure 2-1

Page 10: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

10

INSTALLATION

RECEIVING YOUR MAGNAMAXGENERATOR

Upon receipt of the generator, it isrecommended that it be carefully examinedfor possible damage incurred in shipment.The generator was given to the FreightCompany in good condition, and they areresponsible for the product from our dock toyours. Any damage should be noted on thefreight bill before accepting the shipment.Claims for damages must be promptly filedwith the Freight Company.

UNPACKING AND HANDLING

Read all instruction cards carefully. Whenlifting, attach an overhead crane to thelifting lugs on the generator frame. Applylifting forces in a vertical direction.

WARNINGTHE LIFTING LUGS ON THE

GENERATOR ARE DESIGNED TOSUPPORT THE GENERATOR ONLY.

DO NOT LIFT COMPLETEGENERATOR SET BY MEANS OF

LIFTING DEVICES ON THEGENERATOR. PERSONAL INJURY

OR QUIPMENT DAMAGE MAYOCCUR.

STORAGE

In the event that the generator is not to beinstalled on the prime mover immediately, itis recommended that it be stored in a clean,dry area that is not subject to rapid changes

in temperature and humidity. See"STORAGE INSTRUCTIONS" for moreinformation.

PREPARATION FOR USE

Although the generator is carefullyinspected and tested in operation before itleaves the factory, it is recommended theunit be thoroughly inspected. The insulationon the wire should be inspected and all boltsshould be checked for tightness.

Remove all shipping tapes, bags, blocks, andskids, which are used to prevent vibrationand rotor movement during shipment. Dry,low-pressure compressed air ofapproximately 30 PSI (206 KPA) can beused to blow out the interior of thegenerator. In the case of two bearingmachines, it is possible to turn the rotor byhand to make sure that it rotates smoothlywithout binding.

If the machine has been in storage for a yearor longer it is recommended that it belubricated according to the lubricationinstructions and chart supplied in themaintenance section.If the machine has been exposed to damp,humid conditions the insulation resistanceshould be checked. Refer to the instructionssupplied in this manual.

GENERATOR MOUNTING - SINGLEBEARINGSingle bearing generators are provided withan SAE flywheel adapter and flexible drivediscs. Very close tolerances are maintainedin the manufacture of the generator so thatthe alignment procedure is extremelysimple. A coupling hub of nodular iron isshrunk on the shaft and special steel drive

Page 11: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

11

discs are bolted to the hub. Holes areprovided in the periphery of the couplingdisc, which correspond to tapped holes inthe flywheel. The outside diameter of thediscs fits in a rabbet in the flywheel so thatconcentricity is assured in all cases.

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFITNG ORFOR ROTATING THE GENERATOR

ROTOR. DISREGARDING THESEINSTRUCTIONS MAY CAUSE

PERSONAL INJURY OR EQUIPMENTDAMAGE

CAUTION: GRADE 8 CAPSCREWSOR GRADE 8 PLACE-BOLTS ANDHARDENED WASHERS ARE REC-OMMENDED TO MOUNT THE DRIVEDISCS TO THE FLYWHEEL.DO NOTUSE HELICAL OR OTHER LOCKINGDEVICES UNLESS APPROVED.

The SAE adapter and the flywheel housingare designed to match each other with nofurther alignment necessary. Shims may benecessary under the feet of the generator toinsure a solid mounting. See THE SERVICESECTION for more information.

GENERATOR MOUNTING-TWOBEARINGTwo bearing generators are provided with ashaft extension and key way. For direct-coupled sets the assembler furnishes a flexiblecoupling which is installed between the driverand the generator shaft.

IMPORTANT: Aligning the two machinesas accurately as possible will reducevibration, increase-bearing life, and insures

minimum coupling wear. It may benecessary to shim the generator feet forproper support and alignment. Consult thecoupling manufacturer’s instructions foralignment specifications and procedures.

BELT DRIVEPlease refer to Marathon Electric forapplications involving belt driveninstallations.

ENVIRONMENTAL CONCERNSDirt, moisture, heat, and vibration areenemies of electrical equipment. Theambient temperature should not exceed thevalue shown on the generator nameplate.Generators for outdoor application should beprotected from the elements by housingswith proper openings for ventilation. Thisprotection should be designed to prevent thedirect contact of wind driven rain, snow, ordust with the generator. In moist or humidareas, such as the Tropics and marine serv-ice, additional protection is recommended.Although the standard windings arehumidity and moisture resistant, specialinsulation and accessories such as spaceheaters can increase generator life. Inextremely dirty and dusty environments ameans of providing filtered cooling air to thegenerator is recommended. Please refer toMarathon Electric for filter kits that areavailable.

Page 12: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

12

ELECTRICAL CONNECTIONS

The generator conduit box constructionallows conduit to enter the top, bottom, oreither side of the box. A hole-saw or anysuitable tool can be used to provide for theconduit entrance. Protect the interior of thegenerator from shavings when drilling orsawing. An approved connector must beused in conjunction with the conduit.

To minimize the transmission of vibration, itis essential that flexible conduit be used forall electrical cable entrance to the generator.

Refer to the connection diagram suppliedwith the generator and / or the properdiagrams shown in this section. Install allintercomponent and external wiring inaccordance with the regulations of thenational and local electrical codes. Clean allcontact surfaces to assure good electricalbonding with the generator lugs or bus bars.Use heavy-duty terminal lugs or goodquality clamps for making all connections.Insulate all connections in accordance withnational and local regulations.

Be sure the generator frame is grounded toall the other components of the system witha ground wire in accordance with nationaland local regulations.

GENERATOR LEAD CONNECTIONS

The electrical connections in the conduit boxshould be made in accordance with theappropriate “connection diagram.” Use thediagram appropriate for the number of leadsand voltage range required. Refer to thedrawings supplied with the generator and todrawings in this section.

The final voltage setting is establishedwithin the selected range by an adjustmentof the voltage regulator.

CAUTION: SOME GENERATORSHAVE MULTIPLE, IDENTICALLYMARKED, CABLES FOR EACH LEAD.CONNECT ALL IDENTICALLYMARKED CABLES TOGETHERWHEN MAKING CONNECTIONS.

Page 13: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

13

12 LEAD HIGH WYE CONNECTION

T6

T3

L3

T12

T9

T5

T2

T11

T8

T1

T4

L1

L2

T10

T7L - L

L - N

V O L T A G E

L - L L - N

6 0H Z

4 8 04 6 04 4 04 1 63 8 0

2 7 72 6 62 5 42 4 02 1 9

5 0H Z

4 1 64 0 03 8 0

2 4 02 3 12 1 9

12 LEAD LOW WYE CONNECTION

L2

T7

T10

T1

T4

L1

L3

T5

T2

T11

T8

T6

T3

T12

T9

L - L

L - N

V O L T A G E

L - L L - N

6 0H Z

2 4 02 3 02 2 02 0 81 9 0

1 3 91 3 31 2 71 2 01 1 0

5 0H Z

2 0 82 0 01 9 0

1 2 01 1 51 1 0

Page 14: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

14

12 LEAD HIGH DELTA CONNECTION

L1

L2L3

T1

T4

T7

T10

T2T5T8T11

T12

T9

T6

T3

L - L

L - N

`

V O L T A G E

L - L L - N

6 0H Z

2 4 02 7 7

1 2 01 3 9

5 0H Z

2 0 02 2 02 4 0

1 0 01 1 02 2 0

12 LEAD LOW DELTA CONNECTION

L1

L2L3

T1

T4

T7

T10

T2T5

T8T11

T3

T6

T12

T9

L - L

L - L

V O L T A G E

L - L L - N

6 0H Z

1 2 01 3 9

N A

5 0H Z

1 0 01 2 0

N A

Page 15: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

15

10 LEAD HIGH WYE CONNECTION

T6

T3

L3

T9

T5

T2

T8

T1

T4

L1

L2

T0

T7L - L

L - N

V O L T A G E

L - L L - N

6 0H Z

4 8 04 6 04 4 04 1 63 8 0

2 7 72 6 62 5 42 4 02 1 9

5 0H Z

4 1 64 0 03 8 0

2 4 02 3 12 1 9

10 LEAD LOW WYE CONNECTION

L2

T7

T0

T1

T4

L1

L3

T5

T2

T8

T6

T3

T9

L - L

L - N

V O L T A G E

L - L L - N

6 0H Z

2 4 02 3 02 2 02 0 81 9 0

1 3 91 3 31 2 71 2 01 1 0

5 0H Z

2 0 82 0 01 9 0

1 2 01 1 51 1 0

Page 16: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

16

6 LEAD WYE CONNECTION

T 3

L3 T2

T1

L1

L2

T7L - L

L - N

TT

T

46

5

V O LTA G EL -L L -N

6 0 H Z

1 3 8 0 06 6 0 04 1 6 03 3 0 02 4 02 3 02 2 02 0 31 9 0

7 9 6 73 8 1 12 4 0 01 9 0 51 3 9

1 3 6 31 2 71 2 01 1 0

5 0 H Z 1 1 0 0 06 6 0 03 3 0 02 0 82 0 01 9 0

6 3 5 13 8 1 11 9 0 51 2 01 1 51 1 0

6 LEAD DELTA CONNECTION

L1

L2L3

T1

T4

T2T5

T6

T3

L - L

V O L T A G EL - L L - N

6 0H Z

7 9 6 72 4 0 0

N A

5 0H Z

6 3 5 11 9 0 5

N A

Page 17: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

17

3 LEAD DELTA CONNECTION

L1

L2L3

T1

T2T3

L - L

VOLTAGEL-L L-N

60 HZ 79672402

NANA

50 HZ 63511905

NANA

4 LEAD WYE CONNECTION

T 3

L3 T2

T1

L1

L2

L - L

L - N

T0

VOLTAGEL-L L-N

60 HZ

138006600416033002400600480380

79673811240019051386346277219

50 HZ1100066003300416400380

635138111905240231219

Page 18: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

18

DOUBLE DELTA -- SINGLE PHASE CONNECTION

T3

L1L2 T1 T4 T7 T10

T6

T5

T2 T12

T9

T11

T8

L - N L - N

L - L

V O L T A G EL - L L - N

6 0H Z

2 4 02 2 02 0 0

1 2 01 1 01 0 0

5 0H Z

2 2 02 0 0

1 1 01 0 0

LOW ZIG ZAG -- SINGLE PHASE CONNECTION

L2

T3

T6

L1T7

T10

T1T4

T2

T5

T8

T11

T12

T9

L - N L - N

L - L

V O L T A G EL - L L - N

6 0H Z

2 4 02 2 02 0 0

1 2 01 1 01 0 0

5 0H Z

2 2 02 0 0

1 1 01 0 0

HIGH ZIG ZAG -- SINGLE PHASE CONNECTION

L1L2

T1

T4

T7

T10 T2T5T8T11

T12

T9

T6

T3

L - N L - N

L - L

V O L T A G EH Z L - L L - N6 0 4 8 0

4 4 02 4 02 2 0

5 0 4 4 04 0 0

2 2 02 0 0

Page 19: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

19

PARALLELING OPERATIONS

MagnaMAX generators come standard withamortisseur windings die cast as an integralpart of the rotor. This exclusive, UnirotorTM,construction makes all MagnaMAXgenerators suitable for paralleling operationswhen the proper control equipment is added.Paralleling with other generator sets and / orwith the utility power grid offers a number ofadvantages. Multiple unit installationsincrease power capacity; they can be added orremoved from the line depending on the loadrequirements; they can be better maintainedand repaired (since single source breakdownwould mean total loss of power), and theyoften provide more reliable, efficient, andeconomical operation.

Successful parallel operation means that thegenerators deliver power to the externalsystem without delivering power to eachother, or accepting power from the load bus orpower grid. Additional equipment is necessaryto insure safe and successful operation.

PRIME MOVER

The prime mover provides the speed andtorque which will be necessary to keep themachines in synchronized operation. Agovernor controls the prime mover's speed.The governor will directly control the watt orkW output and frequency of the unit. Thegovernor must have special parallelingprovisions to permit parallel operation withthe other machines.

VOLTAGE REGULATOR

The voltage regulator controls the generatoroutput voltage and the reactive power suppliedby the generator. When two or more ac

generators operate in parallel, the voltage regulatormust have paralleling provisions (either internallyor external to the regulator) to control the reactiveor VAR load while it is in parallel operation. Aseparate paralleling current transformer is requiredto sense the reactive current and signal the voltageregulator. This additional paralleling circuitry isabsolutely necessary to control the reactive currentflowing between the generator sets.

SWITCHGEAR

There are additional relays and breaker controlsthat are necessary to insure safe, trouble freeoperation of paralleled units. Reverse power relaysmonitor the direction of power flow to insure thatthe generator is delivering power, not accepting it.These power relays control breakers, which are ameans of connecting and disconnecting the gen-erator from the load. The total system can includeover-voltage, over-current protection, under fre-quency protection, power factor correction provi-sion and a variety of associated control equipmentfrom manual switchgear to microprocessors. Theamount of control gear and level of sophisticationwill be determined by the needs and requirementsof the particular application.

PARALLELING BASICS

The following points are basic criteria which mustbe met before two units can be paralleled. THIS ISNOT MEANT TO BE SPECIFICINSTRUCTIONS FOR PARALLELINGOPERATION.

1. Additional paralleling circuitryA. Voltage regulator-paralleling provisionsB. Paralleling current transformer(s)C. Paralleling provisions on governor controlsD. Switchgear

2. The voltage and frequency must be the same forall sets with voltages in phase.

Page 20: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

20

3. The voltage regulation characteristics of theindividual generators should be similar.

4. The generators must have the same phaserotation.

5.The driving engines should have the samespeed regulation characteristics and thegovernors should be adjusted to give the samespeed regulation.

Before operating generator sets in parallel,each set should be checked by starting,operating, and adjusting the sets as individualunits before attempting paralleling.

REACTIVE LOAD CONTROLWhen two identical generators are operatingtogether in parallel and an unbalance occurs infield excitation, circulating currents begin toflow between the generators. This current willappear as a lagging power factor or inductiveload to the highly excited generator, and as aleading power factor or capacitive load to thegenerator with the lower field current. This isknown as the reactive circulating current andthere are two methods of controlling it inparallel operation:

1. Reactive droop compensation. (Formerlyknown as parallel droop compensation.)The bus voltage droops, or decreases, as thereactive lagging power factor load isincreased.

2. Reactive differential compensation.(Formerly known as cross currentcompensation.) The reactive differentialcompensation circuit allows parallelgenerators to share reactive loads with nodecrease or droop in generator voltage.

The circuit must meet the following criteria:

A. All paralleling current transformers for all thegenerators being paralleled must be included inthe secondary interconnection loop.

B. When different size generators are paralleledall paralleling current transformers must have thesame proportional ratios that give approximatelythe same secondary current.

C. Voltage regulator paralleling circuitry must bethe same.

D. Current transformer secondary and thegenerator lines must be isolated electrically.

E. It is also desirable to have an auxiliary contacton the main generator breaker to short the parallelCT secondary when that breaker is open (notconnected to the load bus).

Because of the above criteria, reactive differentialcompensation cannot be used when parallelingwith the utility power grid. There is no limit,however, in the number of generators that can beincluded in this type of circuit.

PARALLELING CIRCUITRY

Because of the number of variables involved inparalleling generator sets, every installation willhave its own circuitry and methods or procedureof bringing paralleled units on line. There arenumerous ways of connecting paralleled units andan almost unlimited variety of applications andassociated equipment.

When parallel operation is desired, it is importantthat the control manufacturer, the generator manu-facturer, and the systems engineer work togetherto insure the proper selection of all components.Please refer to Marathon Electric for applicationassistance.

Page 21: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

21

THYRISTOR OR SCR LOADING

Solid state electronic control devices whichutilize thyristors or SCR firing circuits (suchas variable frequency induction motorcontrols, precision motor speed controls, no-break powered battery chargers, etc.) canintroduce high frequency harmonics whichadversely affect or destroy the normalwaveform of the generator. This createsadditional heat in the generator stator androtor, and can cause overheating. Thesedevices can and do present problems to non-utility power generating equipment or anylimited power bus system. The problems thatcan occur are not limited to the generatoritself, but can effect the solid state controldevice, the equipment it controls, otherassociated loads, monitoring devices or anumber of combinations over the entiresystem.

MagnaMAX generators can supply power tothyristor or SCR loads when properly applied.The standard voltage regulator is PMGpowered and senses 3 phase RMS voltages formaximum stability against severely distortedwaveforms. SCR type applications such ascranes, shovels, etc., require specialconsideration of the generator insulationsystem due to greater dielectric stress andsevere environmental conditions. It is impor-tant that the control manufacturer, thegenerator manufacturer, and the systemsengineer work together to insure the properselection of all components. Please refer toMarathon Electric for application assistance.

OPERATION

PRE-START INSPECTIONBefore operating the generator for the firsttime, the following checks are recommended.

1. A visual inspection should be made to checkfor any loose parts, connections, or foreignmaterials

2. Check for clearance in the generator and exciterair gap. Be sure the generator set turns over freely.Bar the generator over by hand at least 2revolutions to be sure there is no interference.

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFITNG ORFOR ROTATING THE GENERATOR

ROTOR. DISREGARDING THESEINSTRUCTIONS MAY CAUSE

PERSONAL INJURY OR EQUIPMENTDAMAGE

3. Check all wiring against the proper connectiondiagrams and make sure all connections areproperly insulated. Support and tie leads to keepthem from being damaged by rotating parts or bychafing on sharp corners.

4. Be sure the equipment is properly grounded.

5. Inspect for any remaining packing materials andremove any loose debris, building materials, rags,etc. that could be drawn into the generator.

6. Check fasteners for tightness.

7. Check to be sure no tools or other hardwarehave been left inside or near the machine.

8. Install and check to be sure all covers andguards are in place and secure.

WARNINGRESIDUAL VOLTAGE IS PRESENT AT THE

GENERATOR LEADS AND AT THEREULATOR PANEL CONNECTIONS EVENWITH THE REGULATOR FUSE REMOVED.

CAUTION MUST BE OBSERVED ORSERIOUS PERSONAL INJURY OR DEATH

CAN RESULT.

Page 22: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

22

STARTING-UP THE GENERATOR

The following procedure should be followedfor starting-up the generator for the first time:

1.The generator output must be disconnectedfrom the load. Be certain that the main circuitbreaker is open.

2. Disable the voltage regulator by removingthe fuse.

WARNINGDO NOT OVERSPEED THEGENERATOR. EXCESSIVE

CENTRIFUGAL FORCES COULDDAMAGE THE ROTATING FIELDS. BE

PREPARED FOR AN EMERGENCYSHUTDOWN.

3. Follow the manufacturer's instructions andstart the prime mover. Check the speed andadjust to the RPM shown on the generatornameplate.

4. Replace the regulator fuse and adjust thevoltage to the required. Check all line to lineand line to neutral voltages to be sure they arecorrect and balanced. If the voltages are notcorrect shut down immediately and recheck allconnections.

5. Close the main circuit breaker and apply theload.

6. Monitor the generator output current toverify it is at or below nameplate amps.

7. Adjust engine speed at full load to 1800rpm for 60 hertz, 1500 rpm for 50 hertz.(Refer to prime mover/governor instructionmanuals.)

8. Before stopping the engine, remove the loadby tripping the main circuit breaker.

FIELD FLASHINGThe standard MagnaMAX generator is suppliedwith a PMG (permanent magnet generator). It willnever require field flashing. In rare cases where aspecial generator may be furnished without aPMG, refer to the factory for more detailedinformation. Include the complete generator modeland serial number.

VOLTAGE ADJUSTMENTSThe voltage regulator controls the generator outputvoltage. There is a cover to access the controlpanel on the side of the generator conduit box

Figure 4-1

Figure 4-2 Regulator Access

Refer to the regulator manual for detailedinformation. In cases where special or remotemounted regulators are used, refer to instructionssupplied by the generator set assembler and to thevoltage regulator manual.

Page 23: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

23

OTHER ADJUSTMENTS

Depending upon application, adjustments toother protective and control gear may berequired. Refer to instructions provided by theby the supplier of the generator set.

The standard MagnaMAX voltage regulatoralso has many protective and control circuits.It is imperative that the set up instructions forany regulator supplied be followed.

MAINTENANCE

GENERAL INFORMATION

Dirt, heat, moisture, and vibration arecommon enemies of a generator. Keeping thegenerator clean and dry, maintaining properalignment of the generator and its primemover, and preventing overloads will result inefficient operation and long life.

Generators that are outdoors should beprotected from the elements by suitablehouses or enclosures.

Dirt and dust will conduct electricity betweenpoints of different electrical potential.Moisture will aggravate the problem further.Insulation system failure can result ifcorrective action is not taken. Measuringinsulation resistance can test the condition ofthe insulation system. (See Generator Testing.).

Insulation resistance should be checked whenputting the generator into service after it hasbeen in storage and anytime contamination bymoisture and dirt is suspected. Normally,moisture buildup is not a problem while thegenerator is running, since heat producedinternally will tend to keep it dry but cancollect in the generator when it is shut down.The problem will be worse in humid environ-

ments or in areas where extreme temperaturechanges cause condensation (dew) to form insidethe generator. Space heaters, air filters, andpremium insulation systems, such as our VPIprocess, should be considered in difficultenvironments.

Accumulations of dust and dirt not only contributeto insulation breakdown, but they can also increasetemperature by restricting the dissipation of heat.Materials such as talc, lint, rock dust, or cementdust may obstruct the ventilation.

The most harmful types of foreign materials includecarbon black, metallic dust and similar substancesthat not only impede ventilation, but also form aconductive film over the insulation, increasing thepossibility of insulation failure.

Machines operating in dirty places should bedisassembled and cleaned periodically.

AIR INTAKE AND EXHAUST

Check the area around the air intake and exhaustopenings to be sure they are unobstructed.

.Figure 5-1

Page 24: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

24

ELECTRICAL CONNECTIONS,WINDINGS

Inspect for loose or contaminated connectionsCheck wires for cracked or frayed insulation.Tighten connections and replace defective oroil soaked insulation.

If inspection shows that varnish coatings onthe windings have deteriorated, they should becoated with insulating varnish. Please refer toMarathon Electric for insulation systemrequirements.

LUBRICATION

All generators are lubricated before leavingthe factory and are ready for operation. As ageneral rule, bearings should be re-lubricatedannually or at the indicated intervals in table5-3, whichever occur first.

Unusually severe operating conditions, suchas high ambient or dusty environments,require more frequent lubrication (every sixmonths or one half the table intervals,whichever occurs first).

Use Chevron SRI or equivalent anti-frictiontype high quality, grease with a lubricationtemperature’ range of -22° to +350° F (-30°to +175° C)

To add or renew grease, proceed as follows:

1. Stop unit.

2. Wipe the grease plugs and surrounding parts toinsure they are clean.

3. Remove both the fill and drain plugs.See figure 5-2

4. Insert 1/8” N.P.T. grease fitting in fill pipe.

5. Free the drain holes of any hard grease, using apiece of wire it necessary.

6. Using a low-pressure grease gun, add greaseaccording to the amounts in table 5-3.

7. Start unit with drain plug removed - fill pipemay be open or closed. Allow unit to run 15minutes to allow excess grease to drain.

8. Stop unit, wipe off any drained grease, andreplace filler and drain plugs.

Figure 5-2

Page 25: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

25

The amount of grease added is very important! Only enough grease should be added to replacethe grease used by the bearing.

CAUTION: TOO MUCH GREASE CAN BE AS HARMFUL AS INSUFFICIENTGREASE. USE THE PROPER AMOUNT.

Type FrameSize

BearingSize Amount of Grease

Intervals ---Max. hours orannually

Ounces Cubic Inches Teaspoons 60 Hz 50 HzSingle 431,432, 433 314 1.2 2.1 7.0 6500 8400Bearing 571,572,Units 573, 574 316 1.5 2.6 8.3 5600 7200

741, 742,743,744

322 2.4 4.2 14.0 3000 4500

431,432 318 1.7 3.0 9.9 4600 6200Double 571, 572,Bearing 573, 574 318 1.7 3.0 9.9 4600 6200Units

741, 742,743, 744

322 2.4 4.2 14.0 3000 4500

TABLE 5-3

During an overhaul, the grease reservoir should b thoroughly cleaned and new grease added. Thereservoir should be 1/3 to 1/2 filled with new grease

Page 26: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

26

DRYING ELECTRICAL INSULATION

Electrical components must be dried beforeplacing in operation if tests indicate that theinsulation resistance is below a safe value.(See Generator testing for test procedure.)

Machines that have been idle for sometimein unheated and damp locations, may haveabsorbed moisture. Sudden changes intemperature can cause condensation or thegenerator may have become wet byaccident. Windings should be dried outthoroughly before being put into service.The following are recommended dryingmethods.

Space HeatersElectric space heaters can be installed insideof the generator. When energized (from apower source other than the generator) theywill heat and dry the inside of the generator.If an alternate source of electricity is notavailable, enclose the generator with acovering and insert heating units to raise thetemperature 15-18 degrees F (8-10 degreesC) above the temperature outside of theenclosure. Leave a hole at the top of theenclosure to permit the escape of moisture.

OvenPlace the machine in an oven and bake it at atemperature not to exceed 194 F (90°C). Thevoltage regulator and any electroniccomponent accessories must be removedfrom the generator when using this method.

Forced AirA portable forced air heater can be used bydirecting heat into the air intake (conduitbox) and running the generator with no loadand without excitation (this can beaccomplished by removing the regulatorfuse). Heat at point of entry should notexceed 150° F (66° C).

“Short Circuit” MethodUsing this method can dry out the generatorquickly and thoroughly.

WARNING:BE SURE THAT ALL OF THE

FOLLOWING STEPS AREPERFORMED AND ALL PRECAU-

TIONS TAKEN AS PERSONALINJURY OR SERIOUS DAMAGE TOTHE GENERATOR COULD RESULT.

1. Disconnect exciter leads Fl and F2 fromthe regulator.

2. Connect a battery or other dc power sourceapproximately 20-35 volts to the exciter leadFl and F2. An adjustable voltage sourcedesirable, however, a rheostat (ratedapproximately 2 amps) in series with the dcpower source will work.

3. Short circuit the generator output leadwires to each other (L1 to L2 to L3). If usingjumpers, be sure they are large enough tocarry full load amps.

4. Start the generator and measure thecurrent through the output leads with a clip-on ammeter.

5. Adjust the voltage source to produceapproximately 80% of the rated acnameplate current but in no case exceednameplate amps. If a adjustable source is notavailable and current is excessive, use alower dc source voltage or larger resistor inseries with the source.

Running time will be determined by theamount of moisture present in the machine.Insulation resistance checks should be takenevery one to four hours until a fairlyconstant value obtained. (See section -Generator testing for instructions onmeasuring insulation resistance.)

Page 27: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

27

6. After the generator is dry and theinsulation resistance is brought up tospecification remove the short circuit fromthe line lead disconnect the dc source andreconnect the F and F2 leads at theregulator. Be sure all connections are tightand correct before attempting to run thegenerator.

CLEANING METHODSWhen electrical components get dirty, theinsulation must be cleaned. There are anumber of acceptable methods for cleaningthe generator, each of which will necessitatedisassembly of the unit. The kind of dirt, andwhen the unit must be returned to servicewill determine the method of cleaning.Drying after cleaning is necessary.

Whenever the generator is disassembled, thewindings should be given a thoroughinspection and the insulation cleaned, ifnecessary. The inspection should include theconnection of the windings, insulation, andvarnish coverage. Check the winding tiesand coil supports. Look for any signs of coilmovement or looseness and repair asrequired.

An electric motor repair shop in your areacan normally assist with the proper cleaningof the generator windings. They may also beexperienced in special problems (such asseacoast, marine, oilrig, mining, etc.) thatmay be peculiar to a certain area.

SolventsA solvent is usually required to removeaccumulated soil containing oil or grease.Only petroleum distillates should be used forcleaning electrical components. Petroleumsolvents of the safety type with a flash pointgreater than 100° F (38° C) arerecommended.

CAUTION: A SOLVENT THAT DOES NOTATTACK EPOXY OR POLYESTERBASED MATERIALS SHOULD BE USED.

Apply the solvent with a soft brush or rag.Be careful not to damage the magnet wire orinsulation on the windings.Dry components thoroughly with moisture-free, low pressure compressed air.

Cloth and Compressed AirCleaning with a dry cloth may besatisfactory when components are small, thesurfaces are accessible and only dry dirt isremoved. Blowing dirt out with compressedair is usually effective particularly when thedirt has collected in places that cannot bereached with a cloth. Use clean dry air at 30PSI (206 KPA).

Brushing and Vacuum CleaningDry dust and dirt may be removed bybrushing with bristle brushes followed byvacuum cleaning. Do not use wire brushes.Vacuum cleaning is an effective anddesirable method of removing dry and loosedirt.

Shell BlastingAir blasting with ground nut shells may besatisfactory for removal of hard dirt depositsfrom insulation. Use mild abrasives such as12-20 mesh ground walnut shells.

Steam CleaningIf the generator is completely disassembled,including bearings and electroniccomponents, steam cleaning of the majorparts and windings is very effective.However, the machine must be thoroughlydried in an oven to remove all moisturebefore the generator can be put back intoservice.

Page 28: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

28

DISASSEMBLY

REMOVAL FROM PRIME MOVER

BE SURE ALL POWER IS OFFBEFORE SERVICING. FAILURE TOFOLLOW ALL SAFETYINSTRUCTIONS CAN RESULT INSERIOUS INJURY OR DEATH.

NOTE:Before disconnecting any electricalwiring, be sure it is marked and can beidentified for reinstallation. Re-label asrequired.

1. Remove conduit box covers(Figure 6-1 and 6-2)

Figure 6-1

Figure 6-2

2. Disconnect all external wiring from thegenerator leads inside the conduit box.

3. Remove all conduits or ducting from theconduit box.

4. Attach a suitable hoist to the generatorlifting

5. For single bearing generators, remove thebolts mounting the screen assembly to theSAE adapter and remove the screen.(Figure 6-3.)

.Figure 6-3

(NOTE: Do not remove the drip cover fromthe screen assembly if so equipped )Removethe cap screws attaching the drive discs tothe flywheel and remove the cap screwsattaching the SAE adapter to the flywheelhousing. For two-bearing generators, disconnect thecoupling or sheave and belts between thegenerator and prime mover. (Follow thecoupling manufacturer’s instructions fordirect connection.)

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFTING ORROTATING THE GENERATOR

Page 29: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

29

CONDUIT BOX REMOVAL

1. Note the location and markings (re-markas required) and remove connections fromvoltage regulator (Figure 6-4), capacitor(Figure 6-5), and any other conduit boxmounted controls.

Figure 6-4

Figure 6-5

2. On generators equipped with bus bars,mark all connections and disassemble mainstator (power) leads from the generator sideof the bus bars.

3. Remove bolts holding conduit box inplace. (Figure 6-6.)

Figure 6-6

4. Remove conduit box. (Figure 6-7).

Figure 6-7

Page 30: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

30

EXCITER STATOR (FIELD) REMOVAL

1. Disconnect Fl and F2 leads from thecorresponding Fl and F2 terminals on theregulator.

2. Remove all cable ties so the Fl and F2leads can be removed with the exciter stator.Remove the four cap screws and Bellevillewashers holding the exciter stator in place.(Figure 6-8.)

Figure 6-8

Remove the exciter stator. Using a liftingstrap or fixture. (Figure 6-9.)

Figure 6-9

EXCITER ARMATURE (ROTOR)REMOVAL

1. Note markings and disconnect the mainrotor leads coming out of the lead hole ofthe aluminum standoff plate from therectifier aluminum angle. (Figure 6-10.)

Figure 6-10

2. Remove the cap screw and Bellevillewasher that holds the exciter (rotor)armature to t generator shaft. (Figure 6-11.)

Figure 6-11

3.Use a six inch, 3/4-16NF, cap screw for apuller (See section 9.) The hole that themounting bolt goes through is threaded.Screw the pull bolt into the hole and it willpush against the end of the shaft. (Figure 6-12.)

Page 31: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

31

Figure 6-12

Carefully feed the main rotor leads throughthe hole as the exciter armature is removed.(Figure 6-13.)

Figure 6-13

CAUTION:DO NOT TIGHTEN THE PULLER

BOLT BEYOND THE END OF THETHREADS. IF A BOLT WITH

SUFFICIENT THREAD LENGTHCANNOT BE FOUND, USE A PIECEOF THREADED ROD WITH A NUT

WELDED ON THE END.

PMG STATOR REMOVAL

1. Remove exciter armature. (Followinstructions found earlier in this section.)

2. Remove the PMG output leads from thecapacitor (Figure 6-14) and loosen all cableties so the leads can be removed with thePMG stator.

Figure 6-14

3. Note the position of the PMG stator leadsthat exit at the left inboard side or mark thestator so it can be reinstalled in the sameposition.

4. Remove the four mounting cap screws.(See Figure 6-15.)

Figure 6-15

Page 32: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

32

5. Carefully remove the PMG stator from itsmounting pads and slide over the PMGrotor. The magnets used in the PMG arevery strong and will resist removal of thePMG stator. (Figure 6-16.)

Figure 6-16

PMG ROTOR REMOVAL

1. Remove the exciter armature and PMGstator. (Follow instructions found earlier inthis section.)

2. Remove the snap ring that holds the PMGrotor in place on the shaft. (Figure 6-17 and6-18.)

Figure 6-17

Figure 6-183. Slide the PMG rotor off of the shaft.(Figure 6-19.)

Figure 6-19

4. Remove the loading spring. (if the loadingspring is not on the shaft, check to see if it isstuck on the back of the PMG rotor.).

5. On 430 frame generators a second snapring is used inboard of the PMG rotor.(Larger generators have a step on the shaft.)

Page 33: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

33

This snap ring must be removed before thegenerator main rotor can be removed.(Figure 6-20.)

Figure 6-20

MAIN ROTOR REMOVAL

1. Remove the exciter armature and PMG.

2. For single bearing generators, remove thefour cap screws holding the bearing caps tothe front-end bracket. (Figure 6-21.)Remove the outer cap. (Figure 6-22.)

For two-bearing generators, remove thedrive coupling or sheave and key from theshaft extension. Remove the four cap screwsholding the bearing lock to the drive endbracket. (Figure 6-23.) Remove the four capscrews holding the bearing caps to the front-end bracket. (Figure 6-21.) Remove theouter cap. (Figure 6-22.)

Figure 6-21

Figure 6-22

Figure 6-23

Page 34: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

34

3. If the screen assembly is still mounted,remove bolts securing the screen assemblyto the drive end bracket or the SAE adapterand remove the screen assembly. (Figure 6-24.) (NOTE: Do not remove the drip coverfrom the screen assembly if so equipped.)

Figure 6-24

4. For single bearing generators, remove thecap screws and hardened washers holdingthe drive discs to the drive hub. (Figure 6-25.) Remove all drive discs (and spacers ifany).

Figure 6-25

5. For single bearing generators, remove thecap screws holding the SAE adapter to thegenerator and remove the adapter. (Figure 6-26 and 6-27.)

Figure 6-26

Figure 6-27

CAUTION: ON LARGE GENERATORS, AHOIST AND LIFTING STRAP SHOULD

BE USED TO ASSIST IN DRIVE ENDBRACKET OR SAE ADAPTOR REMOVAL

For two bearing generators remove the capscrews holding the drive end bracket to thegenerator and remove the bracket (Figures 6-26 and figure 6-28)

Figure 6-28

Page 35: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

35

6. Using a rotor lifting fixture and a suitablehoist, carefully remove the rotor assemblyfrom the main stator and frame assemblythrough the drive end. (Figure 6-29.)

CAUTION:SPECIAL CARE SHOULD BE TAKEN

WHEN REMOVING THE MAIN ROTOR,WINDING DAMAGE COULD RESULT IFTHE ROTOR IS ALLOWED TO HIT THE

MAIN STATOR.

Figure 6-29

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFTING OR

ROTATING THE GENERATORROTOR. DISREGARDING THESE

INSTRUCTIONS MAY CAUSE PER-SONAL INJURY OR EQUIPMENT

DAMAGE.

FRONT END BRACKET REMOVAL1. Remove front bracket mounting

screws. (Figure 6-30.)

2. Remove the front-end bracket from themain stator assembly. (Figure 6-31.)

CAUTION: ON LARGE GENERATORS,A HOIST AND LIFTING STRAP SHOULDBE USED TO ASSIST IN THE FRONT ENDBRACKET REMOVAL

Figure 6-30

Figure 6-31

EXCITER INSPECTION

EXCITER STATOR

1. Clean dust and dirt from the exciter statorwinding. (Figure 6-32.) (See section 5.)

Figure 6-32

Page 36: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

36

2. Check the exciter stator for a loose,frayed, or burnt winding. Measure windingresistance and insulation resistance. (Seesection 8.)

Repair or replace as necessary. If field repairof the winding is necessary, contactMarathon Electric for special windingprocedures and materials.

3. Look for score marks in the bore of theexciter core caused by rubbing. (This couldindicate bearing or assembly problems andshould be investigated.)

EXCITER (ROTOR) ARMATURE

1. Clean dust and dirt from and rectifierassembly. (Figure 6-33) (See Section 5)

Figure 6-33

2. Check the exciter armature for burrs onthe mating surfaces.

3. Check the rectifiers and surge protectorfor proper operation. Replace defectiveparts.

CAUTION: THREE FORWARD ANDTHREE REVERSE POLARITY DIODES AREUSED. BE SURE THE CORRECT PART ISINSTALLED IN THE CORRECT LOCATION.THE SURGE SUPRESSOR IS POLARIZED.OBSERVE POLARITY MARKINGS WHENCHANGING THE SURGE SUPRESSOR

Figure 6-34

Torque mounting nuts to 80 in-lb. Torquelead terminal nuts to 25 in-lb. Never torqueagainst the diode terminal - use a 7/16-in.wrench to support the terminal.

Figure 6-35

4. Check the exciter armature and rectifierassembly for loose, frayed, or burnt windingor loose connections. Measure windingresistance and insulation resistance. DONOT megger diodes or surge suppressor.Repair or replace as necessary. If field repairof the winding is necessary, contactMarathon Electric for special windingprocedures and materials.

Page 37: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

37

5. Look for score marks on the outsidediameter of the armature core caused byrubbing. (This could indicate bearing orassembly problems and should beinvestigated.)

PMG INSPECTION

PMG STATOR1. Clean dust and dirt from the PMG statorwinding.

Figure 6-36

2. Check PMG stator for a loose, frayed, orburnt winding. Measure winding resistanceand insulation resistance. (See section 8.)Repair or replace as necessary. ContactMarathon Electric for special windingprocedures and materials.

3. Look for score marks in the bore causedby rubbing.

PMG ROTOR

WARNINGTHE PMG ROTOR USES VERY STRONG

MAGNETS. KEEP AWAY FROM IRONAND STEEL PARTS THAT COULD BE

DRAWN TO THE MAGNETS AS WELL ASOTHER COMPONENTS THAT CAN BE

DAMAGED BY MAGNETIC FIELDS.

Figure 6-37

1. Clean dust and dirt from the PMG rotor.

2.Check to be sure all magnets are tightlybonded to the PMG rotor.

3.Check the bore and keyway of the PMGrotor for burrs or corrosion.

4.Look for score marks on the outsidediameter caused by rubbing. (This couldindicate bearing or assembly problems andshould be investigated.)

5. Inspect snap rings and loading spring,replace as required.

MAIN ROTOR INSPECTION

BEARING

1. Check the bearing for damage or wear.Clean old grease from the bearing cap, andfill bearing cap grease cavity 1/3 to 1/2 fullof r Chevron SRI (or equivalent).

CAUTION: If the bearing needs to beremoved any reason, always install a newbearing.

2. If the bearing is to be replaced, removewith suitable puller. (Figure 6-38.)

Page 38: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

38

Figure 6-38

3.Be sure the inner bearing cap is on theshaft before installing the new bearing.

4. Heat the new bearing in an oven to amaximum temperature of 212°F (100°C).Apply a thin coat of clean lubricating oil tothe press-fit area of rotor shaft. Install thebearing over the end of the shaft until itseats against the shaft shoulder as shown inFigure 6-39. The bearing should slide on theshaft and seated without excessive force. Ifthe bearing binds on the shaft before beingfully seated a piece of tubing, slightly largerthan the press area, can be used to drive thebearing into place. Using light taps with asoft mallet, apply pressure to the inner raceonly.

CAUTION:UNDER NO CIRCUMSTANCES SHOULD

PRESSURE BE APPLI ED TO THE OUTERRACE OF THE BEARING, AS

PERMANENT BEARING DAMAGECOULD RESULT.

Figure 6-39

Allow the bearing to cool for onehour before attempting to assemble thegenerator.

FAN

1. Check the fan for cracks or broken blades.Replace the fan if defective.

2. Mark the hub and fan for alignment, thisis necessary to be sure the balance weightswill be in the same position when the fan isreinstalled.

3. For single bearing generators. Remove thefan mounting cap screws (Figure 6-40) andslide the fan off the shaft. (Figure 6-41.)For two-bearing generators, remove thedrive end bearing and bearing cap. (Seebearing removal instructions.) Remove thefan mounting cap screws and slide fan offthe shaft. (Figure 6-40 and 6-41.)

Page 39: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

39

Figure 6-40

Figure 6-41

4. To reinstall, slide the fan on the shaftmaking sure the fan-mounting surface istoward the drive hub. Align reference marks(this is important for assembly balance) andmount the fan to the drive hub with the capscrews and Belleville washers. (Figure 6-42.) Torque the cap screws to 60 ft-lb. (81N-m).

Figure 6-42

5. NOTE: Balance weights on the fan are forbalance of the complete rotor assembly. Therotor assembly should be rebalance if a newfan has been installed.

6. On two-bearing generators, install bearingcap and new bearing according to thebearing assembly instructions. (Item A.)

Drive Hub (Single Bearing Generators)

1. Check the drive hub for cracks or strippeddrive disc mounting holes. Replace the hubif defective.

2. If the hub is to be replaced, remove thefan (See Item B) and install a suitable pullerto the hub. Remove the two set screws in thehub over the key. Using a torch, rapidly heatthe hub at the outer diameter whiletightening the puller. (This must be donerapidly before the heat can expand theshaft.) Remove the hub. (Figure 6-43)

Figure 6-43

3. To insure proper fan location, mark thenew hub in the same place as the old hubrelative to the keyway. Install key in shaft.Heat the new hub in an oven to 500°-600°F(260°-316°C). Use suitable heat resistantgloves, slide the hub over the key in theshaft until it seats against the shaftshoulder. (Figure 6-44.)

Page 40: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

40

Figure 6-44

4. Allow the hub to cool for one hour. Afterthe hub has cooled, tighten the set screws inthe hub to 50 ft-lbs. (68 N.M.) torque. Matchthe alignment marks on the fan and hub andmount the fan. (See item B.)

5. Rebalancing the rotor assembly is notnecessary if only the hub is replaced and thefan is mounted in the same location relativeto the hub and shaft.

MAIN ROTOR CORE AND WINDINGS

1. Clean all parts. Remove dust and dirtfrom the rotor winding air passages withlow-pressure, moisture-free air.

Figure 6-45

2. Check the rotor for loose, frayed, orburned windings. Measure winding

resistance an insulation resistance. Test forshorted turns using an A-C impedance test Adefective rotor winding must be rewoundThe rotor assembly must be rebalanced afterany rework or repair has been completed.

DRIVE DISCS (SINGLE BEARINGGENERATORS ONLY)

1. Inspect the drive discs for distorted orbent edges. (Figure 6-46) Inspect for wornmounting holes. Replace all defective discsas necessary.

Figure 6-46

2. Inspect the drive disc mounting capscrews for damaged threads. Replace capscrews if damaged.

FRONT (EXCITER) ENDBRACKET INSPECTION

1. Remove the filler and drain grease pipesand the grease plugs from outer bearing cap.(Figure 6-47.)

Figure 6-47

Page 41: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

41

2. Clean the end bracket, outer bearing cap,grease pipes, and cap screws to remove alldust, dirt, and grease.

3. Inspect the cap screws for stripped threadsand replace if defective.

4. Inspect the end bracket for strippedthreads, cracks, and burred or rough matingsurfaces. Inspect the bearing bore for burrsor wear. If the bracket shows excessivebearing bore wear, it should be repaired orreplaced. (Figure 6-48.)

Figure 6-48 5. Inspect the mounting pads for the PMGstator and exciter stator. Be sure they aresmooth, clean, and free of any burrs or rust.That could interfere with proper alignment.(Figure 6-47 and 6-48.)

6. Re-assemble the grease pipes and fittingsto the bearing cap.

DRIVE END BRACKET OR SAEADAPTER INSPECTION

1. For two-bearing generators, remove thegrease plugs from the bracket.

2. Clean the bracket or adapter, cap screwsand screen assembly to remove all dust, dirt,and grease.

3. Inspect the cap screws for stripped threadsand replace if defective.

4. Inspect the bracket or adapter for strippedthreads, cracks, and burred or rough matingsurfaces. (Figure 6-49 and 6-50.)

Figure 6-49

Figure 6-50

5. For two-bearing generators, inspect thebearing bore for burrs or wear. If the driveend bracket shows excessive bearing borewear, it should be repaired or replaced.

Page 42: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

42

MAIN STATOR INSPECTION

1. Clean dust and dirt from the stator frameand winding. (Figure 6-51.) (See section 5.)

Figure 6-51

2. Inspect the frame for stripped threads,cracks, burred mating surfaces, or otherdamage.

3. Inspect the stator for a loose, frayed, orburnt winding. Measure winding resistanceand insulation resistance. (See section 8.)Repair or replace as necessary.

FRONT END BRACKETINSTALLATION

1.Install two guide pins (threaded rod can beused) into the generator side of the endbracket mounting holes. Align the guidepins with the holes in the generator frameand slide the bracket onto the frame. (Figure6-52.) Install bracket mounting cap screws.(Figure 6-53.)

Figure 6-52

CAUTION: ON LARGE GENERATORS, AHOIST AND LIFTING STRAP SHOULD

BE USED TO ASSIST IN THE FRONT ENDBRACKET INSTALLATION.

Figure 6-53

2. Remove the two guide pins and insert theremaining cap screws and torque tospecifications given in section 12.

MAIN ROTOR INSTALLATION

1. Grease bearing cavity and bearing withChevron SRI (or equivalent) grease.

2. Using a rotor lifting fixture and a suitablehoist, carefully install the rotor assemblyinto the main stator assembly through thedrive end. (Figure 6-54.) Carefully feed therotor leads through the front-end bracketshaft hole as the rotor is installed.

Page 43: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

43

Figure 6-54

CAUTION:SPECIAL CARE SHOULD BE TAKEN

WHEN INSTALLINGTHE ROTORASSEMBLY. WINDING DAMAGECOULD RESULT IF THE ROTORIS ALLOWED TO HIT THE MAIN

STATOR.

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFTING OR

ROTATING THE GENERATORROTOR. DISREGARDING THESE

INSTRUCTIONS MAY CAUSE PER-SONAL INJURY OR EQUIPMENT

DAMAGE.

3. For single bearing generators, slide theSAE adapter over the fan and secure to themain stator and frame assembly with capscrews torqued per section 12. (Figure 6-55and 6-56.) It may be necessary to raise therotor assembly slightly to allow themounting of the SAE adapter.

Figure 6-55

Figure 6-56

Figure 6-57 For two-bearing generators, insert twoguide pins in the rear bearing lock holes.(Figure 6-57.) Fill the grease cavity of thedrive end bracket 1/3 to 1/2 full of ChevronSRI (or equivalent) grease. Assemble allgrease plugs in the bracket. Mount thebracket on the bearing and guide the bearinglock pins through the bracket holes. (Figure6-58.)

Page 44: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

44

Figure 6-58

Align the drive end bracket and mount withthe cap screws. (Figure 6-59.) Insert two capscrews with lock washers into the bearinglock and tighten. Remove the guide pins andreplace with the remaining two cap screwswith lock washers. Torque bearing capscrews to 25 lb.-ft (34 NM). Torque bracketmounting cap screws per specificationsgiven in section 12.

Figure 6-59

CAUTION:ON LARGE GENERATORS, A HOISTAND LIFTING STRAP SHOULD BE

USED TOASSIST IN THE DRIVE ENDBRACKET OR THE SAE ADAPTER

ASSEMBLY.

4. For single bearing generators, insert aguide stud into the drive hub. Position all

spacers (if any), then all drive discs, one at atime until all discs are installed. (Figure 6-61.)

Figure 6-61

Make sure that all disc mounting holes atthe inner and outer diameter are properlyaligned. Secure the discs with the gradeeight 5/8-18 cap screws and hardenedwashers. Torque to 192 ft-lb. (260 N-m).Torque the bolts in sequence according toFigure 6-62.

Figure 6-625. Install the outer bearing cap on the exciterend. (Figure 6-63.) Align holes in inner andouter bearing cap and install cap screws.Torque to 25 lb.-ft (34 N-M) (Figure 6-64.)

Page 45: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

45

Figure 6-63

Figure 6-64

PMG INSTALLATION1. Install inboard snap ring, where supplied,and loading spring on shaft. (Figure 6-65.)

Figure 6-65

2. Slide PMG rotor onto shaft. (Figure 6-66.)

Figure 6-66

3. Install snap ring. (Figure 6-67.) Use apiece of pipe slightly larger than the shaft(2-3/4 inches) to push the rotor back againstthe loading spring until the snap ring seats inthe slot. (Figure 6-68.)

Figure 6-67

Figure 6-68

4. Install the PMG stator on its mountingpads, with the leads in the left (9:00 o’clock)inboard position, and secure with the four

Page 46: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

46

mounting cap screws and Belleville washers.(Figure 6-69 and 6-72.)Torque to 4 ft-lb. (5 N-M).

Figure 6-69

5. Route and secure PMG moving parts.

EXCITER INSTALLATION

1. Attach a wire to the main rotor leads andfeed the wire through the armature bore andthe lead hole in the aluminum standoff plate.On larger exciters, it will be helpful toinstall a guide pin in the end of the shaft tosupport the armature while fishing the rotorleads through. (Figure 6-70.)

Figure 6-70

Align the key in the armature bore to thekeyway in the shaft. Slide the armature onthe shaft while feeding the main rotor leads

through the lead hole in the aluminumstandoff plate. (Figure 6-71.)

Figure 6-71

Insert the cap screw and Belleville washer(Figure 6-72.) through the mounting hole inthe aluminum standoff plate and secure tothe shaft (Figure 6-73). Tighten the capscrew until the armature seats on the shaft.Torque to 84 lb.-ft (114 N-M).

Figure 6-72

Figure 6-732. Observe the polarity markings andconnect the main rotor leads to the rectifier

Page 47: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

47

assembly. (Figure 6-74.) Torque the nuts to4 ft-lb. (5.4 N-M).

Figure 6-74

3. Position the exciter field leads at the left(9:o’clock) inboard position. Using asuitable lifting device, mount the exciterstator on the front e bracket mounting padsand align the mounting holes. (Figure 6-75.)Mount the cap screws with Bellevillewashers. (Figure 6-72.) Torque t cap screwsto 60 ft-lb. (81 N-M). Route and secure theexciter stator leads away from any movingparts.

Figure 6-75

CONDUIT BOX INSTALLATION1. Install the conduit box over the mainstator leads (be sure the leads are in theupper compartment and secure with boltsand lock washers. (Fig 6-76 and 6-77.)

Figure 6-76

Figure 6-77

2. On generators with bus bar assemblies,reassemble main stator leads and insulatingblocks to bus bars. (Figure 6-78.)

Figure 6-78

Page 48: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

48

3. Reconnect exciter leads, PMG leads andother accessories according to theconnection prints and markings installedbefore disassembly.

ASSEMBLY TO PRIME MOVER1. Attach a suitable hoist to the generatorlifting lugs, and move the generator until thegenerator foot mounting holes are alignedwith the base and slightly above.

2. For single bearing generators, if thescreen assembly is mounted on the adapter,remove the mounting bolts and remove thescreen. (Figure 6-79.)

Figure 6-79

(NOTE: Do not remove the drip cover fromthe screen assembly if so equipped.)Insert two guide pins in the flywheel andtwo in the flywheel housing. Adjust thegenerator position until the drive discs arepiloted in the flywheel. Remove the guidepins and secure the discs with Grade 8 placebolts and hardened washers or Grade 8 capscrews and heavy series lockwashers.

Torque per specifications given in section12.

Position the generator so that the SAEadapter mates with the flywheel housing.

WARNINGDO NOT APPLY ANY FORCE TO THEGENERATOR FAN FOR LIFTING OR

ROTATING THE GENERATORROTOR. DISREGARDING THESE

INSTRUCTIONS MAY CAUSE PER-SONAL INJUY OR EQUIPMENT

DAMAGE.

CAUTION:DO NOT FORCE THE ALIGNMENT

OFTHE UNITS. SHIFT THEGENERATOR FROM SIDE TO SIDE

OR RAISE OR LOWER WITH ALIFTING DEVICE AS NECESSARY.

It may be necessary to use shims under themounting feet of either the generator or theprime mover to obtain proper alignment.Use the same shims as removed under dis-assembly or proceed as follows: Using theextreme bottom four cap screws, mount theSAE adapter to the flywheel housing.

With a .0015 to .002 inch feeler gauge at theextreme top of the adapter to flywheelhousing fit, raise the generator or lower theprime mover until the gauge is snug. Relievejust enough to release the feeler gauge andtorque the remaining SAE adapter capscrews to the flywheel housing.

Mount the screen assembly and tighten themounting bolts.

For two-bearing generators, align the coup-ling halves or sheaves between the generatorand the prime mover by adding shims underthe feet.

3. Shim under the generator feet for propersupport, ensuring that the generatormounting surfaces are level.

Page 49: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

49

4. Install the mounting bolts that secure thegenerator to the base.

5. For two bearing generators, assemble thecoupling halves or sheave belts between thegenerator and the prime mover. (Follow thecoupling manufacturer’s instructions forassembly and alignment.)

6. Connect all conduits and ducting to theconduit box.

7. Connect all external wiring to thegenerator inside the conduit box.

8. Check the exciter air gap (the gapbetween exciter armature and stator) byinserting a .010 inch feeler gauge in the gapand rotating around the armature diameter toensure the minimum air gap is available.(See Figure 80.) If the feeler gauge cannotbe rotated full revolution, then check for a“cocked" exciter stator or loose statormounting screws.

Figure 6-80

NOTE: On single bearing units, the exciterair gap cannot be checked properly until thegenerator is mounted to the prime mover.

9. Install the conduit box covers.

Page 50: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

50

TROUBLESHOOTING

INTRODUCTION

This section is intended to suggest asystematic approach to locating andcorrecting generator or regulatormalfunctions. The sections are arrangedaccording to the symptoms of the problem.The steps in each section have beenarranged in an attempt to do the easy checksfirst then to prevent further damage whentroubleshooting a disabled machine.

The first and perhaps most important step oftroubleshooting should be to gather as muchinformation as possible from personnel whomay have been present during the failure.Information on how long the generator hadbeen running, what loads were on the line,weather conditions, what protective equip-ment operated, etc., can help isolate theproblem.

Always make a thorough visual inspectionto check for any obvious problems beforeattempting to run the generator.

WARNINGHIGH VOLTAGES CAN BE PRESENT

AT THE GENERATOR ANDREGULATOR TERMINALS. HIGHRESIDUAL VOLTAGES CAN BE

PRESENT EVEN WITH THEREGULATORDISCONNECTED OR

ITS FUSES REMOVED. SOMEEQUIPMENT (SUCH AS

SPACEHEATERS) MAY BEENERGIZED WHEN THE

GENERATOR IS OFF. TOOLS,EQUIPMENT, CLOTHING, AND

YOUR BODY MUST BE KEPT CLEAROF ROTATING PARTS AND

ELECTRICAL CONNECTIONS.

SPECIAL CAUTION MUST BE TAKENDURING TROUBLESHOOTING SINCEPROTECTIVE COVERS AND SAFETYDEVICES MAY BE DISABLED TOGAIN ACCESS AND MAKE TESTS.

BE CAREFUL. SERIOUS PERSONALINJURY OR DEATH CAN RESULTFROM THESE HAZARDS. CONSULTQUALIFIED PERSONNEL WITH ANYQUESTIONS.

Page 51: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

51

SYMPTOM:

NO VOLTAGE ORRESIDUAL VOLTAGE

Regulator Fuse BlownCheck fuse with ohmmeter.

Voltmeter Off

Defective Voltmeter

Incorrect Connections

DefectiveConnections/Wiring

No Regulator Input

Defective Diodes, SurgeSuppressor

Voltage RegulatorProtective ShutdownCircuits are Operating

Voltage RegulatorInoperative

Replace bad fuse.

Check to be sure meter phaseselector switch is not in the offposition.

Verify proper operation of panelmeter with another meter that isknown to be accurate.

Verify generator connections.

Inspect all wiring for grounds, opencircuits & short circuits.

Measure voltage at regulator input(PMG output)

Test generator with constantexcitation (12 volt battery test) referor Generator Windings

Correct problem and adjustregulator. Refer to regulatormanual.

Adjust or replace regulator. Refer toregulator manual.

Page 52: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

52

LOW VOLTAGE -

NO LOAD

Under speed Operation

Defective Voltmeter

Residual Voltage

Incorrect GeneratorConnections

Defective Connections /Wiring

Regulator Adjustments

Defective Diodes, SurgeSuppressor, GeneratorWindings

Voltage Regulator notOperating

Check speed using tachometersand/or frequency meters.

Verify operation of panel meterwith another meter that is known tobe accurate.

Disconnect Fl and F2 leads at thevoltage regulator. If voltage goesdown continue on to next step, ifvoltage does not change refer totroubleshooting for symptoms of“No Voltage - No ResidualVoltage”.

Verify generator connections referto drawings supplied V generatorset and section 3.

Inspect all wiring for grounds, opencircuits, short circuits, and looseand dirty connections.

Adjust regulator. Refer to regulatormanual. Check exciter field volts.

Test generator with constantexcitation (12 volt battery test)

Adjust or replace regulator. Refer toregulator manual. Properly

Page 53: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

53

LOW VOLTAGE WHENLOAD IS APPLIED

Overload

Defective Ammeter

Droop Circuit

Continue troubleshootingfor symptoms “GeneratorProduces Low Voltage -No Load”.

Measure amps and verify that theload does not exceed nameplaterating of the generator

Verify operation of ammeter byusing a separate meter known to beaccurate

If the generator set is equipped forparalleling, some voltage droop isnormal as load increases. Refer tothe regulator instruction manual

Continue troubleshooting forsymptoms “Generator ProducesLow Voltage - No Load”.

HIGH VOLTAGEDefective Voltmeter

Incorrect Operating Speed

Incorrect Connections

Defective Connections /Wiring

Regulator Adjustments

Diode Polarity Incorrect

Voltage Regulator notOperating

Verify operation of panel meterwith another meter that is known tobe accurate

Verify speed with tachometer orfrequency meter.

Verify generator connectionsRefer to drawings supplied withgenerator set

Inspect all wiring for grounds, opencircuits, and short circuits.

Adjust regulator. Refer to regulatormanual

Check diodes, verify proper diodesare installed and polarity is correct.

Adjust or replace regulator. Refer toregulator instruction manual.

Page 54: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

54

VOLTAGE ISFLUCTUATING

Incorrect Speed

Unstable Speed

Voltage Regulator Stability

Defective / LooseConnections

Defective Diodes, SurgeSuppressor or GeneratorWindings

Remote Voltage Adjust

Defective Regulator

Verify speed with tachometer orfrequency meter.

Verify governor stability.

Adjust regulator stability.Refer to regulator manual.

Inspect all wiring for loose or dirtyconnections.

Test generator with constantexcitation (12-volt battery test).

Check operation. Refer to regulatormanual.

Replace regulator. Refer toregulator manual.

OPERATESSATISFACTORILYWHEN COLD, BUTSHUTS DOWN WHENWARM

Regulator Shutdown onOver Temperature

Correct cooling problems. Refer toregulator manual.

BUILDS VOLTAGEFROM STARTUP,THENGOES TO LOW(RESIDUAL) VOLTAGE

Regulator ProtectiveCircuit is Operating

Check indicators on regulator.Correct problems and adjust asrequired. Refer to regulator manual.

EQUIPMENT RUNSNORMALLY ON UTILITYPOWER, BUT WILL NOTRUN ON GENERATORSET

Voltage Waveform isDistorted

Analyze load. Excessive SCR(Thyristor) loading will causedistortion. Some equipment may besensitive to distorted waveforms.Refer to Marathon Electric.

Page 55: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

55

GENERATOR TESTING

VISUAL INSPECTION

Whenever testing and troubleshooting agenerator set, it is always a good practice tomake a thorough visual inspection. Removecovers and look for any obvious problems.Burnt windings, broken connectors, leads,mounting brackets, etc., can usually beidentified. Look for any loose or frayedinsulation, loose or dirty connections,broken wires. Be sure all wiring is clear ofrotating parts.

Verify that the generator is connected for thevoltage required this is especially importanton new installations.

Check for any foreign objects, loose nuts,bolts, and electrical connectors. Clear paper,leaves, building materials, etc., that could besucked into the generator. (Generators areair-cooled. Air enters the lower portion ofthe conduit box.) Check the air gap forclearance or obstructions (main generatorand exciter).

If possible, rotate the generator rotor byhand to be sure it turns freely.

If serious problems can be identified beforeattempting to operate the machine,additional damage can be avoided.

CONSTANT EXCITATION(12V BATTERY) TEST

THEORY: The generator output voltage isdependent on generator speed, generatordesign, load, and exciter input current. If thegenerator speed and exciter input are known,the output voltage at no load can bemeasured and compared to the design value.

Problems can be isolated to either the gen-erator or regulator system by using this test.

TEST PROCEDURE:

1. Shut the generator set down.

2. Connect a voltmeter to the generatoroutput.

3. Disconnect the Fl and F2 leads at theregulator.

4. Connect a 12-volt battery capable ofsupplying 1 amp to the Fl and F2 leads. Fl isplus (+), F2 is minus (—).

CAUTION: Beware of arcing whenconnecting leads. Stay clear of battery vents.Escaping hydrogen gas can explode. Ifhazardous conditions exist - use a suitableswitch to connect or disconnect the battery.

5. With no load on the generator, (mainbreakers open) run generator at rated speed.

6. Measure the generator output voltage.

7. Shut generator down.

8. Disconnect battery (see Caution - Step 3).

9. Compare voltage reading with valueshown in section 12.

Conclusion: If voltage readings are normal,the main generator and exciter are operatingproperly. Troubleshooting should continuewith the regulator. If readings are not normalthe problem is in the generator. Continuetesting diodes, surge suppressor, windings.

Page 56: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

56

MEASURING VOLTAGES

When testing the generator and regulator,the most frequent (and usually easiest)measurement will be a voltage. Thegenerator will need to be running at ratedspeed and may have some of the protectiveguards and covers removed. BE CAREFUL.Keep yourself and your test leads out of theway. It is best to shut the unit down whenconnecting meters. When using alligatorclips or push on terminals, be sure the leadsre supported so vibration does not shakethem loose when running the generator set.

See figure 8-1 for measurement points andexpected meter range settings.When in doubt, start with a higher range andwork down.Consult meter instruction manual to verifyits operation and limitations.

Figure 8-1

Page 57: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

57

TYPICAL VOLTAGE MEASUREMENTS

Voltage Measurement Test Point Meter/Range SelectionRequirement

Generator Output VoltageOutput “T” leads or bus bars,also main circuit breaker“line” side.

System voltage - volts AC Seegenerator nameplate andconnection diagram.

Regulator Output (ExciterStator Input)

Fl and F2 terminals at theregulator.

200 volts D.C. range. Fl isplus (+), F2 if minus (—

Regulator SensingEl, E2, E3 terminals at theVoltage the regulator.

Usually the same as thesystem voltage (generatoroutput volts). However, insome cases, sensing takenfrom winding center taps orinstrument potentialtransformers. Maximum 600volts ACExample: Center tap of 480-volt system would give 240volts El, E2, or E3.Example:A 4160-volt system must use atransformer to step voltagedown below 600 volts.See the connection diagramsupplied with generator set.

Regulator Input Volts(PMG Output Volts)

“PMG” leads at the regulatoror capacitor.

200-240 VAC 300 Hz@ 1800 rpm180-220 VAC 250 Hz@ 1500 rpm

CURRENT (AMP) MEASUREMENTSCurrent measurement (AC) can be easilytaken with a clamp on type meter.NOTE: Most clamp type ammeters will notmeasure D.C.

When measuring generator output current,be sure the clamp is around all cables for

each phase. If the physical size of theconductors or the capacity of the meters willnot permit all cables to be measured at once,Each one can be measured individually. Addthe individual readings together to get thetotal. Compare readings to the generatornameplate (nameplate ratings are alwaysgiven per phase).

Page 58: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

58

Amperage should never exceed thenameplate rating when running the intendedload. (Amperage may go above nameplatemomentarily when starting large motors.)When measuring exciter field amps (Fl andF2 leads) a D.C. meter is required. Themaximum field current under full regulatorforcing is 6.5 amps D.C.

MEASURING RESISTANCE

The generator windings can be measuredand compared to the values shown in theservice specifications.

Main Stator

The main stator winding resistance is verylow. A meter capable of readings in themilliohm range would be required.However, a standard V.O.M. can be used tocheck for continuity, shorts, or grounds.

Example: With leads disconnected, ameasurement from T1 to T4 should be verylow (continuity most V.O.M’s). Measuredfrom T1 orT4 to any other lead should beinfinite. Measure from the ‘T’ lead thegenerator frame to check for grounds(reading should be infinite).

Normal full load reading is approximately 3amps.

The exciter stator resistance is measured bydisconnecting the Fl and F2 leads at theregulator. Measure the resistance betweenthe leads (this value is 22-24 ohms onstandard generators). Measure from theleads to the frame to check for grounds.

Note markings and disconnect the mainrotor leads (Fl leads and F2 leads) from therectifier assembly. Measure the resistance ofthe main rotor winding. Compare reading tovalue shown in service specification section12. Measure from the leads to the exciter-mounting bolt to check for grounds.

Exciter Rotor

Disconnect the exciter rotor leads at thediodes (leave leads disconnected ifproceeding to check diodes). Measureresistance between phases. Compare valueto service specification section 12. Measurefrom the leads to the exciter-mounting boltto check for grounds.

TESTING DIODES (RECTIFIERS)

Diodes perform the function of an “electricalcheck valve”. They conduct in one directiononly and are used to “rectify” ac current intodc current. To test, measure the resistancefirst in one direction and then reverse theleads and test in the other direction. Thereading should be high in the reversedirection and low in the forward direction. Ashorted diode will read low in bothdirections. An open diode will read high inboth directions.

NOTES:1. Two different polarities of diodes areused. The only difference is in the way thedevice is mechanically placed in the case.When changing diode, be sure the correctpolarity is used.Refer to section 6 figure 6-34.

2. Some meters do not have enough voltageoutput from their internal batteries to turnthe diode on (about 0.6 volts is required),and the voltage can change with different

Page 59: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

59

range settings. Consult the instructionmanual for your meter.3. Polarities supplied by the meters internalbattery may or may not correspond to the(+) (—) markings on the meter.

INSULATION RESISTANCE -GENERAL

Insulation resistance is a measurement of theintegrity of the insulating materials thatseparate the electrical windings from thegenerators steel core. This resistance candegrade over time or due to contaminants(dust, dirt, oil, grease, and especiallymoisture). Most winding failures are due toa breakdown in the insulation system. Inmany cases, low insulation resistance iscaused by moisture collected when thegenerator is shut down. The problem can becorrected simply by drying out the windings.Section 5.

Normally the resistance of the insulationsystem is on the order of millions of ohms. Itis measured with a device called a “megger”which is a megohm meter (Meg is formillion) and a power supply. The powersupply voltage varies, but the most commonis 500 volts. A megger voltage over 500 isnot recommended except for measuringmedium voltage (2400/4160) stators only.

CAUTION: First disconnect any electroniccomponents, regulators, diodes, surgeprotectors, protective relays, etc., will bedestroyed if subjected to the high meggervoltages.

To measure insulation resistance, connectthe red or positive megger lead to the leadsfor the winding to be tested, connect theback or negative megger lead to thegenerator frame. Be sure the leads of thepart being tested are not touching any metalparts of the generator. (If the neutral is

grounded, it must be disconnected.) Takemegger reading (refer to the manual for themegger).

INSULATION RESISTANCE - MAINSTATORCAUTION: Be sure the regulator, and anyother electronic components, metering,protective relays, etc., are disconnectedbefore meggering. High megger voltageswill destroy these parts. All stator leads mustbe isolated from ground and connectedtogether (on most systems with groundedneutrals - the neutral can be isolated fromground and used as a test point). Connect thepositive megger lead to the main statorleads. Connect the negative megger lead tothe generator grounding stud. Take themegohm reading (refer to instructions forthe megger).

GENERATOR TESTINGThe minimum acceptable value can becalculated using the following formula.Minimum Insulation Resistance = Gen.Voltage + 1 (Megohms) / 1000Example:For a 480 volt generator480 + 1 = 1.48 MegohmsIf the reading is below the recommendedvalue, the winding must be dried out orrepaired.

INSULATION RESISTANCE - MAINROTOR

Disconnect the main rotor leads from thediode bridge on the exciter rotor. Connectthe leads together with the positive meggerlead. Connect the negative megger lead to agood ground on the rotor assembly such asthe exciter mounting bolt. Take the megohm

Page 60: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

60

reading (refer to instructions for themegger).The minimum acceptable value is 1.5megohms.

If the reading is low, the winding must bedried out or repaired.

INSULATION RESISTANCE -EXCITER STATOR

Disconnect the exciter leads Fl and F2 fromthe regulator. Never subject the regulator toa megger. Connect Fl and F2 together withthe positive megger lead. Connect thenegative megger lead to the ground stud.Take the megohm reading (refer toinstructions for the megger).

The minimum value is 1.5 megohms.

If the reading is low, the winding must bedried out or repaired.

INSULATION RESISTANCE -EXCITER ROTOR

Disconnect the exciter rotor windings (6leads from the diodes). Connect all leadstogether with the positive megger lead.Connect he negative megger lead to a goodground on the rotor assembly such as themounting bolt. Take the megohm reading(refer to the instructions for the megger).

The minimum acceptable value is 1.5megohms.

If the reading is low, the winding must bedried out or repaired.

MAIN ROTOR FIELD AC IMPEDANCETEST

THEORY: The main rotor resistance can bemeasured with a very accurate meter that isable to measure low (1 ohm) resistance but itis difficult to determine if there are turn toturn shorts in the field pole windings. Oneshorted turn would only change a resistancereading on the order of one half of onepercent.

The ac impedance test measures theimpedance (inductance and resistance) ofthe field pole coils. Shorted turns in the fieldpole windings change the coil inductance toa much greater degree than the resistance.

PROCEDURE:

Step 1: The rotor must be supported on anon-magnetic surface such as a woodenskid. Do not use a steel table that wouldcreate a magnetic “short circuit” between thepoles.

Step 2: Apply 120 volts ac to disconnectedmain rotor leads Fl and F2.

Step 3: Measure and record voltages pole.Between points “A” and “C”, “C” and “D”,“D” and “E” across each “B”, “B” and(Figure 8-1).

Step 4: The voltage readings should balancewithin one volt.

RESULTS: If the ac voltages are notbalanced (30v ± lv ac with 120v ac input)across each pole, the winding has shortedturns and should be rewound.

Refer to Marathon Electric for furtherinformation.

Page 61: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

61

MAGNAMAX EXPLODED VIEW

Page 62: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

62

TABLE 9-1 PARTS LISTNOTE: The parts in this list are subject to change, model number and serial number mustaccompany any parts order or inquiry.

430 Frame Series 570 Frame Series 740 Frame SeriesItem Part DescriptionPart Number Qty. Part Number Qty. Part Number Qty.

1 Screen Assembly ScreenScreen Mounting Bolt ScreenMounting Nut

B-525565-1A-9646-200A-7551-18

122

B-525565-2 A-9646-200 A-7551-18

122

B-525565-3A-9646-200A-7551-18

122

2 Drip Cover assembly B-525566-1 1 B-525566-2 2 B-525566-3 1

3 Adapter#3Adapter#2Adapter#1 Adapter#1/2 Adapter#0Adapter#00 Adapter (#18 Disc)#00 Adapter (#21 Disc)

B-525512AB-525512BB-525513AB-525514BB-525514A

11111

B-525618AB-525616AB-525603AB-525617AB-526228A

11111

B-525720AB-525721AB-52572 1A

111

4 Disc Mounting FastenersCap screw for #11-1/2Cap screw for #14Cap screw for #18Cap screw for #21Cap screw for DelcoHardened Washer

A-9674-200A-9674-150A-9674-150

A-9674-150A-9667-1

666

66

A-9674-150A-9674-150

A-9674-150A-9667-1

99

99

A-9674-200A-9674-150A-9674-200A-9667-1

18181818

5 Drive Discs #11-1/2 Disc #14 Disc #18 Disc #21 Disc Delco Disc (17.75” 0.0.)

A-525506A-525508B-525975 —A-525507

554—5

—A-525508A-525579

A-525507

—55

5

— —A-525579A-525580A-525507

——101010

6 Spacers For #11-1/2 Disc For #14 Disc For#18 Disc For #21 Disc For Delco Disc

A-525567A-525567 — — —

145———

—A-525503 — —A-525503

—6——1

— —A-525503 —A-525503

——10—12

7 Fan Mounting Fasteners Cap screw Cap screw (2 Brg. Only) Belleville Washer

A-9626-150A-9626-150A-9682-1

444

A-9626-150A-9626-200A-9682-1

888

A-9626-1 50A-9626-200A-9682-1

888

8 Fan B-525510A 1 B-525604A 1 B-525719A 19 Hub

Drive Hub [Sgl Brg. Only) Fan Hub (2 Brg. Only)

B-525509AA-525568A

11

B-525606AB-525694A

11

B-525726AB-525750A

11

10 Drive Hub Set Screws — A-9675-50 2 A-9675-50 2

Page 63: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

63

TABLE 9-1 PARTS LISTNOTE: The parts in this list are subject to change, model number and serial number mustaccompany any parts order or inquiry.

430 Frame Series 570 Frame Series 740 Frame SeriesItem Part DescriptionPart Number Qty. Part Number Qty. Part Number Qty.

11 Drive Hub Key A-25658-30 1 A-25658-30 1 A-25658-46 112 Main Rotor Assembly with

WindingsREFER TO FACTORY

13 Front Bearing Cap B-525519A 1 B-525613A 1 B-525743A 114 Front Ball Bearing A-7812R-70 1 A-7812R-80 1 A-7812R-1 10 115 Main Body Assembly REFER TO FACTORY16 Adapter Mounting Fasteners

Cap screwLock WasherFlat Washer

-A-9680-125A-7653-3A-7656-8

121216

A-9680-125A-7653-3A-7656-8

161616

A-9626-1 50A-7653-4A-9667-1

161616

17 Bracket Mounting Fasteners Cap screw Lock Washer Flat Washer

-A-9680-1 25A-7653-3A-7656-8

888

-A-9680-1 25A-7653-3A-7656-8

-888

-A-9626-150A-7653-4A-9667-1

-888

18 Front Bracket B-525518A 1 B-525605A 1 B-525739A 119 PMG Bearing Cap B-525520A 1 B-525612A 1 B-525742A 120 Bearing Cap Fasteners

Cap screw Lock Washer

-A-9680-350A-7653-3

-44

-A-9680-400A-7653-3

-44

-A-9680-450A-7653-3

-44

21 Conduit Box D-525673 1 D-525680 1 D-525771 122 Conduit Box Mtg. Fasteners

Cap screwLock Washer

A-9680-75A-7675-2

88

A-9680-75A-7675-2

88

A-9626-75A-7675-4

88

23 Snap Ring - Inner A-7610-275 1 — —24 Loading Spring A-7661-45 1 A-7661-45 1 A-7661-45 125 PMG Rotor A-525529 1 A-525529 1 A-525529 126 Snap Ring-Outer A-7610-275 1 A-7610-275 1 A-7610-275 127 PMG Stator A-525548-1 1 A-525548-1 1 A-525548-1 128 PMG Stator Mtg. Fasteners

Cap screwBelleville Washer

A-9812-200 A-9682-2

44

A-9812-200A-9682-2

44

A-9812-200A-9682-2

44

29 Exciter Stator A-400N-200A I A-400N-300A I See Table 9-2 130 Exciter Stator Fasteners

Cap Screw Belleville Washer

-A-9626-300A-9682-1

-44

-A-9626-400A-9682-1

-44

-See Table 9-2A-9682-1

-44

31 Exciter Rotor Assy. (IncI. 42) 430 Frame - All 570 Frame - Low Voltage 570 Frame - Med. Voltage

-B-525524-2 — —

-I——

- —B-525524-3B-525524-10

-—11

See Table 9-2

32 Exciter Rotor FastenerCap screwBelleville Washer

-A-9670A-200A-9682-1

-11

-A-9670A-200A-9682-1

-11

-A-9670A-200A-9682-1

-11

Page 64: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

64

TABLE 9-1 PARTS LISTNOTE: The parts in this list are subject to change, model number and serial number mustaccompany any parts order or inquiry.

430 Frame Series 570 Frame Series 740 Frame SeriesItem Part DescriptionPart Number Qty. Part Number Qty. Part Number Qty.

33 Grounding Stud Assembly Stud Washer Nut

-A-26937-300A-9787-1A-9786-1

-121

-A-26937-300A-9787-1A-9786-1

-122

-A-525574-400A-9787-3A-9786-3

-I22

34 Bus Bar Assembly REFER TO FACTORY35 Voltage Regulator

PM100APM200A(optional)

C-512481C-512482

11

C-512481C-512482

11

C-512481C-512482

11

36 Capacitor A-525582-1 1 A-525582-1 1 A-525582-1 137 Side Panels Blank

Machined for AVRB-525679AB-525679B

1I

B-525686AB-525686B

11

B-525707AB-525707B

11

38 Fuse A-525698-1 1 A-525698-1 1 A-525698-1 139 Fuse Holder Cap A-525893 1 A-525893 1 A-525893 140 Solid Cover B-525676 1 B-525687 1 B-525706 141 Louvered Cover C-525562 1 C-525647 1 C-525670 142 Exciter Rectifier Assy.

(Includes 43,44,45)B-525528A 1 B-525528A 1 B-525528B 1

43 Diode Standard Polarity B-525570-1 3 B-525570-1 3 B-525570-2 344 Diode Reverse Polarity B-525571-1 3 B-525571-1 3 B525571-2 345 Surge Suppressor B-526482-1 1 B-526482-1 1 B-526482-2 146 Cover Mtg. Screws A-9646-75 33 A-9646-75 33 A-9646-75 33

TABLE 9-2 : EXCITER ASSEMBLIESFrame Type Insulation Exciter Stator Exciter Stator

Mtg. Cap screwsExciter Rotor

572 RSL Standard A-400N-2504 A-9626-350 B-526483-24573.574 RSL Standard A-400N-300A A-9626-400 B-526483-3572 RSL VPI A-400N-250AA A-9626-350 B-526483-25573.574 RSL VPI A-400N-300AA A-9626-400 B-526483-9573,574 FSM VPI A-400N-300AA A-9626-400 B-526483-10741, 742 RSL Standard A-400N-500A A-9626-600 B-526483-5741, 742, 743 RSL VPI A-400N-500A A-9626-600 B-526483-11741, 742 FSM VPI A-400N-500A A-9626-600 B-526483-11743 FSM VPI A-400N-600A A-9626-700 B-526483-12744 RSL VPI A-400N-600A A-9626-700 B-526483-12744 FSL VPI A-400N-650A A-9626-750 B-526483-13

STANDARD TOOLSThe MagnaMAX generator is assembledwith American standard SAE hardware.

Page 65: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

65

All fasteners should be properly torqued.(See section 12). Torque wrenches rangingfrom 25 in-lb. through 200 ft-lb. should beavailable.

Electrical test equipment should include avoltmeter or multimeter (VOM), clamp onammeter, accurate frequency meter ortachometer, and a megohmmeter. Seesection Generator Testing for more informa-tion.

SPECIAL TOOLSIn addition to the standard tools mentionedabove, the following special tools wouldfacilitate removal and installation of largeand/or special parts. These tools can beobtained from the Marathon Electric partsdepartment.

Exciter stator lifting fixture (Figure 10-1).

Figure 10-1

In cases where the exciter stator is to beserviced without removing the generator

conduit box this fixture can be used withoverhead rigging to remove and reinstall theexciter stator.

Exciter rotor puller bolt (Figure 10-2). Theexciter rotor has a built in pulling system.With the use of this bolt, the rotor can beeasily removed from the shaft withoutdamage to the winding.

Figure 10-2

The PMG rotor is installed to the generatorshaft with a snap ring.

The nominal shaft diameter is 2-3/4 inchesand the ring must be spread approximately3/4 inches for removal. To install the snapring, use a piece of pipe with a 2-3/4 inchI.D. (Figure 10-4). Push the PMG rotor andsnap ring onto the shaft until the ring snapsinto the groove.

Figure 10-4

Rotor lifting fixture (Figure 10-5). The maingenerator rotor is heavy (approximately 1/2the weight of the generator) and difficult tohandle. The proper fixture should be usedwhenever removing or installing the main

Page 66: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

66

rotor into the main stator. Without propercare and equipment, the windings can beeasily damaged.

Figure 10-5

MISCELLANEOUSA selection of wiring devices such aselectric connectors, tape, cable ties,crimping and stripping tools, etc., shouldalso be a part of the generator service toolkit. The standard regulator uses flat 1/4 inchfemale insulated terminals for AWG #14wire.

PREPARATION FOR SHIPMENTOR EXTENDED STORAGE

SHIPPING INSTRUCTIONS

Shipping and handling will be much easier ifthe generator is fastened to a suitableshipping skid that will allow handling by aforklift. The skid should extend beyond thegenerator in all directions. If the originalskid is available it should be used. MarathonElectric will supply shipping skid drawingsupon request.Overseas shipping may require specialexport crating. Check with your freightcarrier.

When installed, single bearing generatorrotors are supported on the drive end by thedrive discs bolted to the engine flywheel.When the engine is removed, the rotor mustbe supported by an appropriate fixture toprevent main rotor, main stator or exciterdamage (Figure 11-1). Before shipping anysingle bearing generator, the main rotormust be supported by the adapter using anappropriate fixture.

Figure 11-1

STORAGE INSTRUCTIONS

If the generator is placed in storage, thefollowing precautions should be taken toprotect it:

A. Equipment must be kept clean.

1. Store indoors.

2. Keep covered to eliminate airborne dustand dirt.

3. Cover openings for ventilation, conduitconnections, etc. to prevent entry of rodents,snakes, birds, and insects, etc.

B. Equipment must be kept dry.

1. Store in a dry area indoor.

Page 67: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

67

2. Temperature swings should be minimal toprevent condensation.

3. If stored in an unheated or damp building,space heaters will be required to preventinternal condensation.

4. Treat unpainted flanges, shafts, drivediscs, and fittings with a rust inhibitor.

5. Check insulation resistance of allwindings before starting the generator. Ifreadings are low, the windings must bedried.

C. Keep bearings lubricated.

1. Every six months rotate shaftseveral turns to distribute grease in bearings.

2. If unit has been stored more thanone year, add grease before start-up.

D. Review and follow instructions inSections 3 and 4 before putting the gen-setinto service.

CAUTIONDO NOT ATTEMPT TO TRANSPORT

ANYGENERATOR WITHOUTPROPER ROTOR

SUPPORT, EXTENSIVEEQUIPMENTDAMAGE CAN OCCUR.

Page 68: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

68

TABLE 12-1: MAGNA MAX - FASTENER AND TORQUE SPECIFICATIONSPart

DescriptionFastener Spec. 430-570 Frames 740 Frames

Size Dia.-Thread

Torque Ft-Lb. Size Dia.-Thread

TorqueFt-Lb.

Front Bracket Grade 5 cap screws withflat and lock washers

3/8 - 16 25 1/2 - 13 60

Bearing Caps Grade 5 cap screws withlock washers

3/8 - 16 25 3/8 - 16 25

Drive Disc Grade 8 cap screws withhardened washers

5/8 - 18 192 5/8 - 18 192

Adapter(or rearbracket)

Grade 5 cap screws withflat and lock washers

3/8 - 16 25 1/2-13 60

Conduit Box Grade 5 cap screw withstar type lock washer

3/8 - 16 25 1/2-13 60

PMG Stator Grade 5 cap screws withBelleville washers

1/2-13 4 1/2-13 4

Exciter Stator Grade 5 cap screws withBelleville washers

1/2-13 60 1/2-13 60

ExciterArmature

(rotor)

Grade 8 cap screw withBelleville washer

1/2-13 84 1/2-13 84

Cooling Fan Grade 5 cap screws withBelleville washers

1/2-13 60 1/2-13 60

Main RotorCoil Supports

Grade 8 cap screws withBelleville washers

5/16-18 19 3/8 - 16 35

RectifierAssemblyMounting

Grade 5 cap screws 1/4-20 4 1/4-20 4

Drive Hub SetScrew

Socket head set screw 1/4in. hex key

1/2-13 50 1/2-13 50

NOTES: For table 12-1All fasteners are SAE (American) standard.All torque values are for plated hardware that is standard on the MagnaMAX.If hardware is replaced with non-plated, refer to Table 12-2.Always use quality hardware of the grade specified.Main Rotor Coil Supports 570 and 740 frame only. Not used on 430 frames.

Page 69: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

69

TABLE 12-2: CAPSCREW TORQUE VALUESNOTES: Cap screws threaded into aluminum may require reductions in torque of 3O% or more.

Cap screw Diameter and Ultimate Tensile Strength (PSI)To 1/2 - 69,000 PSITo 3/4 - 64,000 PSITo l - 55,000 PSI

To 3/4 - 120,000 PSITo 1 - 115,000 PSI

150,000 PSI

SAEGrade

1 OR 2 5 8

Size(Inches) -(Thread)

Torque Ft-LB (N-M) Torque Ft-Lb. (N-M) Torque Ft-LB (N-M)

Dry Oiled Plated Dry Oiled Plated Dry Oiled Plated

1/4-20 5(7) 4.5 (6) 4(5) 8 (11) 7 (9) 6 (8) 12 (16) 11 (15) 10 (14 )1/4-28 6(8) 5.4 (7) 4.8 (6) 10 (14) 9 (12) 8 (11) 14 (19) 13 (18) 11 (15)5/16-18 11 (15) 10 (14) 9 (12) 17 (23) 15 (20) 14 (19) 24 (33) 22 (30) 19 (26)5/16-24 13 (18) 12 (16) 10 (14) 19 (26) 17 (23) 15 (20) 27 (37) 24 (33) 22 (30)3/8-16 18 (24) 16 (22) 14 (19) 31 (42) 28 (38) 25 (34) 44 (60) 40 (54) 35 (47)3/8- 24 20 (27) 18 (24) 16 (22) 35 (47) 32 (43) 28 (38) 49 (66) 44 (60) 39 (53)7/16 - 14 28 (38) 25 (34) 22 (30) 49 (66) 44 (60) 39 (53) 70 (95) 63 (85) 56 (76)7/16-20 30 (41) 27 (37) 24 (33) 55 (75) 50 (68) 44 (60) 78 (106) 70 (95) 62 (84)1/2-13 39 (53) 35 (47) 31 (42) 75 (102) 68 (92) 60 (81) 105 (142) 95 (129) 84 (114)1/2-20 41 (56) 37 (50) 33 (45) 85 (115) 77 (104) 68 (92) 120 (163) 108 (146) 96 (130)9/16-12 51 (69) 46 (62) 41 (56) 110 (149) 99(134) 88(119) 155 (210) 140 (190) 124 (168)9/16-18 55 (75) 50 (68) 44 (60) 120 (163) 108 (146) 96 (130) 170 (230) 153 (207) 136 (184)5/8-11 83 (113) 75 (102) 66 (89) 150 (203) 135 (183) 120 (163) 210 (285) 189 (256) 168 (228)5/8-18 95 (129) 86 (117) 76 (103) 170 (230) 153 (207) 136 (184) 240 (325) 216 (293) 192 (260)3/4-10 105 (142) 95 (130) 84 (114) 270 (366) 243 (329) 216 (293) 375 (508) 338 (458) 300 (407)3/4-16 115 (156) 104 (141) 92 (125) 295 (400) 266 (361) 236 (320) 420 (569) 378 (513) 336 (456)7/8-9 160 (217) 144 (195) 128 (174) 395 (535) 356 (483) 316 (428) 605 (820) 545 (739) 484 (656)1-14 175 (237) 158 (214) 140 (190) 435 (590) 392 (531) 348 (472) 675 (915) 608 (824) 540 (732)1 -8 235 (319) 212 (287) 188 (255) 590 (800) 531 (720) 472 (640) 910 (1234) 819 (1110) 728 (987)1- 14 250 (339) 225 (305) 200 (271) 660 (895) 594 (805) 528 (716) 990 (1342) 891 (1208) 792 (1074)

Page 70: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

70

TABLE 12-3:EXCITATION DATA -60 HZ - 1800 RPMModel NumberLow Volts

Exciter FieldResistance-Ohms@25°C

Exciter Field Volts Fland F2 at regulatorNo Load 240/480Volts

No Load Output Voltage WithFixed ExcitationHigh Wye Connection®

12V DC 24V DC431RSL2004431RSL2006431RSL2008432RSL2010

22.522.522.522.5

10.49.510.410.8

500520500495

595610595590

432RSL2012432RSL2014432RSL2016432RSL2018

22.522.522.522.5

13.511.315.314.1

460490440450

550575530545

433RSL2023433RSL2027

22.522.5

16.913.7

425445

520545

571RSL2020571RSL2024571RSL2028

23.023.023.0

8.19.910.6

540500500

640600590

572RSL2032572RSL2037572RSL2040572RSL2045

23.023.023.023.0

10.812.010.612.7

490480500470

580560580560

573RSL2048573RSL2052573RSL2056

23.023.023.0

12.413.314.0

470465450

560550540

741RSL2060741RSL2064741RSL2068741RSL2072

22.522.522.522.5

10.812.212.811.9

500480465480

600570575580

742RSL2076 22.7 13.0 460 570744RSL2284744RSL2288

22.022.0

15.016.0

430410

570540

No Load Output Voltage With FixedNo Load Output Voltage With FixedNo Load Output Voltage With FixedNo Load Output Voltage With FixedExcitation Wye ConnectionExcitation Wye ConnectionExcitation Wye ConnectionExcitation Wye Connection

Model NumberModel NumberModel NumberModel NumberMedium VoltsMedium VoltsMedium VoltsMedium Volts

Exciter FieldExciter FieldExciter FieldExciter FieldResistance-OhmsResistance-OhmsResistance-OhmsResistance-Ohms

@25°C@25°C@25°C@25°C

Exciter Field Volts FlExciter Field Volts FlExciter Field Volts FlExciter Field Volts Fland F2 at Regulatorand F2 at Regulatorand F2 at Regulatorand F2 at RegulatorNo Load 4160 VoltsNo Load 4160 VoltsNo Load 4160 VoltsNo Load 4160 Volts 12V DC12V DC12V DC12V DC 24V DC24V DC24V DC24V DC

573FSM2328573FSM2336

23.023.0

16.317.2

36003500

47004600

574FSM2340574FSM2348574FSM2352

23.023.023.0

14.918.717.5

370034003500

480045004600

741FSM2360741FSM2364741FSM2368

22.722.722.7

12.912.913.2

400040003900

510051005100

742FSM2372742FSM2376742FSM2380

22.722.722.7

15.916.616.8

360036003500

470047004600

743FSM2384743FSM2388

22.022.0

17.616.9

33003500

46004600

For rated load exciter field volts - see generator nameplate.For low wye connection: divide value shown in table by 2.For high delta connection: divide value shown in table by 1 .732.For delta connection: divide value shown in table by 1 .732.

Page 71: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

71

TABLE 12-3:EXCITATION DATA -50 HZ - 1500 RPMModel Number

Low VoltsExciter FieldResistance-Ohms@25°C

Exciter Field Volts Fland F2 at regulatorNo Load 240/480Volts

No Load Output Voltage WithFixed ExcitationHigh Wye Connection

12V DC 24V DC431RSL2004431RSL2006431RSL2008432RSL2010

22.522.522.522.5

12.210.412.412.6

415430410410

495510490490

432RSL2012432RSL2014432RSL2016432RSL2018

22.522.522.522.5

15.813.118.516.9

380400360370

455480440450

433RSL2023433RSL2027

22.522.5

20.716.7

335360

430445

571RSL2020571RSL2024571RSL2028

23.023.023.0

9.211.512.0

440420410

530500490

572RSL2032572RSL2037572RSL2040572RSL2045

23.023.023.023.0

12.413.812.715.0

400390400380

480470480460

573RSL2048573RSL2052573RSL2056

23.023.023.0

14.315.417.0

390380370

470455450

741RSL2060741RSL2064741RSL2068741RSL2072

22.522.522.522.5

12.413.714.614.0

405390380390

500480470480

742RSL2076 22.7 14.9 380 470744RSL2284744RSL2288

22.022.0

17.218.9

350340

470440

No Load Output Voltage With FixedNo Load Output Voltage With FixedNo Load Output Voltage With FixedNo Load Output Voltage With FixedExcitation Wye ConnectionExcitation Wye ConnectionExcitation Wye ConnectionExcitation Wye Connection

Model NumberModel NumberModel NumberModel NumberMedium VoltsMedium VoltsMedium VoltsMedium Volts

Exciter FieldExciter FieldExciter FieldExciter FieldResistance-OhmsResistance-OhmsResistance-OhmsResistance-Ohms

@25°C@25°C@25°C@25°C

Exciter Field Volts FlExciter Field Volts FlExciter Field Volts FlExciter Field Volts Fland F2 at Regulatorand F2 at Regulatorand F2 at Regulatorand F2 at RegulatorNo Load 3300 VoltsNo Load 3300 VoltsNo Load 3300 VoltsNo Load 3300 Volts 12V DC12V DC12V DC12V DC 24V DC24V DC24V DC24V DC

573FSM2328573FSM2336

23.023.0

15.015.4

30002900

39003800

574FSM2340574FSM2348574FSM2352

23.023.023.0

12.815.416.1

320029002800

400038003800

741FSM2360741FSM2364741FSM2368

22.722.722.7

12.011.812.5

330033003300

430043004200

742FSM2372742FSM2376742FSM2380

22.722.722.7

15.215.016.1

290029002700

380038003800

743FSM2384743FSM2388

22.022.0

15.415.4

29002900

39003800

For rated load exciter field volts - see generator nameplate.For low wye connection: divide value shown in table by 2.For high delta connection: divide value shown in table by 1 .732.For delta connection: divide value shown in table by 1 .732.

Page 72: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

72

TABLE 12-5: RESISTANCE VALUES - MAIN WINDINGSNOMINAL COLD (25°C) RESISTANCE IN OHMS

Base ModelLow Voltage

WindingH-SG-

MainStator

MainRotor

431RSL2004431RSL2006431RSL2008432RSL2010

430011430012430013430014

.1160

.0898

.0685

.0534

.139

.149

.160

.170432RSL2012432RSL2014432RSL2016432RSL2018

430018430015430017430016

.0389

.0353

.0245

.0228

.186

.189

.225

.226433RSL2023433RSL2027

430042430039

.0144

.0137.286.297

571RSL2020571RSL2024571RSL2028

570020570021570022

.0316

.0253

.0214

.306

.322

.328572RSL2032572RSL2037572RSL2040572RSL2045

570023570024570025270026

.0159

.0144

.0109

.0092

.363

.374

.402

.419573RSL2048573RSL2052573RSL2056

570027570028570029

.0082

.0068

.0054

.457

.490

.542741RSL2060741RSL2064741RSL2068741RSL2072

740021740022740023740024

.0061

.0046

.0042

.0037

.609

.647

.679

.718742RSL2076 740025 .0032 .750744RSL2284744RSL2288

740026740027

.0026

.0018.8921.044

Base ModelMedium Voltage

WindingH-SG-

MainStator

MainRotor

573FSM2328573FSM2336

570201570202

1.249.837

.383

.424574FSM2340574FSM2348574FSM2352

570203570204570205

.694

.526

.410

.458

.498

.553741FSM2360741FSM2364741FSM2368

740201740202740203

.462

.380

.297

.609

.662

.694742FSM2372742FSM2376742FSM2380

740204740205740206

.223

.185

.151

.768

.825

.888743FSM2384743FSM2388

740207740208

.127

.101.9541.053

Main stator values shown are line to line on the high wye connection. For low wye connectiondivide value shown in table by 4.

Page 73: INSTALLATION OPERATION, AND MAINTENANCE MANUAL · even air distribution to maximize cooling and generator efficiency. Adapters and Drive Discs All single bearing units are available

73

TABLE 12-6: RESISTANCE VALUES - EXCITER WINDINGSNOMINAL COLD (25°C) RESISTANCE IN OHMS

Low Voltage Exciter Stator(Field)

Exciter Rotor(Armature)

PMGStator

430 Frames 22.5 0.023 2.0570 Frames 23.0 0.045 2.0741 Frames 22.5 0.043 2.0742 Frames 22.7 0.048 2.0744 Frames 22.0 0.066 2.0

MediumVoltage

Exciter Stator(Field)

Exciter Rotor(Armature)

PMGStator

570 Frames 23.0 0.070 2.0741 Frames 22.7 0.048 2.0742 Frames 22.7 0.048 2.0743 Frames 22.0 0.065 2.0