integrated resource plan - tips · 2015. 7. 21. · generation expansion programme started in 2005...
TRANSCRIPT
![Page 1: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/1.jpg)
Repositioning Electricity Planning at the Core:
An Evaluation of the Effectiveness of South Africa’s
Integrated Resource Plan
Gaylor Montmasson-Clair and Georgina Ryan
Trade and Industrial Policy Strategies (TIPS)
TIPS Development Dialogue, Pretoria, South Africa
7 July 2015
![Page 2: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/2.jpg)
Outline
Introduction and key messages
Implications of planning
Presentation of the assessment framework
The 10-criterion assessment of the IRP
What does the assessment mean for SA’s
development?
Conclusion
2
![Page 3: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/3.jpg)
Introduction
Ensuring a reliable and
affordable supply of electricity
is at the core of development
National electricity planning,
as part of energy policy, has
emerged as the most
effective and efficient
framework to shape the
development of the ESI
3
![Page 4: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/4.jpg)
Key messages
Planning is critical for the sustainability of the ESI,
both in terms of security of supply and pricing
Planning for new build
Planning for maintenance
The current IRP bodes well on international standards
but substantial room for improvement remains, notably
on implementation
A clear long-term vision for the ESI is still missing: the
IRP should contribute to filling this gap
4
![Page 5: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/5.jpg)
Role of an IRP
Meeting the estimated demand in a specific period in the most
affordable and efficient manner,
also taking into account issues regarding equity,
environmental protection, reliability and other country-
specific goals
Providing a means for minimising the present and future costs
of meeting energy demand considering the impacts on utilities,
government, the environment and society.
5
![Page 6: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/6.jpg)
The IRP in South Africa
Prior to 2009, a traditional approach to planning with 3
separate plans developed respectively by Eskom,
NERSA and the then-DME
Driven by the utility planner’s projections of future demand
and expansion of its supply to meet anticipated demand
Often resulted in excess capacity and higher-than-necessary
energy costs
Spearheaded by the DoE since 2009
IRP1 > IRP 2010 > 2013 update > next fully-fledged iteration
(2016?)
Subset of the IEP, although the interaction between
the IRP and IEP remains a point of contention 6
![Page 7: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/7.jpg)
The IRP in South Africa
Policy choices:
cost-optimised
scenario
carbon emission
constraint
localisation objectives
roll-out of RE
technologies
7
![Page 8: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/8.jpg)
The IRP in South Africa
Occurring on the back of security of supply issues and
stringent electricity price increase
Generation expansion programme started in 2005
17.7 GW of generation capacity from 2005 to 2018/2019
ZAR 340 billion
The financing requirement have contributed to
pushing prices up and is expected to result in a
trebling of the average electricity price at ZAR 89.13
c/kWh from 2009/2010 to 2017/2018
8
![Page 9: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/9.jpg)
Impact on electricity supply
The role of planning is instrumental to ensuring the
adequate supply of electricity (timing, size, mix)
Planning impacts upon security of supply in 2 key
ways:
Timing and scale of expansion and maintenance
decisions
The expansion plan started in the 2000s replicates the
pattern witnessed in the 1970-1980s, when the lack of
adequate planning resulted in investments in excess
generation capacity. The delay in planning directly resulted
in insufficient generation capacity
9
![Page 10: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/10.jpg)
Impact on electricity supply
Delays in construction
The expansion plan is largely dependent on the
addition of 2 large coal-fired power stations (Medupi
and Kusile)
Significant delays for the
construction of both power
stations, aggravating the
gap in supply
10
![Page 11: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/11.jpg)
Impact on electricity pricing
Average real and nominal electricity prices in South Africa
between 1974 and 2011 (in ZAR cents per kWh) 11
![Page 12: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/12.jpg)
The assessment framework
Developed by the
World Resources
Institute and
Prayas, Energy
Group
Aimed at rendering
decision-making
processes more
transparent and
enabling greater
engagement
12
![Page 13: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/13.jpg)
Planning process
Substantial improvement since 2009 and the clarification of the
mandate of the DoE
Effective mobilisation of all necessary data and information (thorough
process and institutional arrangements)
Absence of labour and civil society from the decision-making process
Information asymmetry problems (in favour of the utility) remain and
should be addressed over time.
Extensive consultation process
Good degree of transparency (assumptions, data and methodologies
are all available for public scrutiny)
No clear process for ongoing updating of the IRP
No long-term vision for the ESI beyond generation capacity planning
13
![Page 14: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/14.jpg)
Parameter Nature Data owner
Demand forecast (energy and
maximum demand)
Demand input Eskom (System Operations and Planning division)
Gross domestic product Demand input National Treasury
Electricity intensity (short-term) Demand input the dti, NT, EDD, NPC
Electricity Intensity (long-term) Demand input the dti, NT, EDD, NPC
Price elasticity of demand Demand input National Treasury
Demand side management Demand input DoE
Energy efficiency Demand input DoE
Demand market participation /
demand response
Demand input Eskom
Energy conservation Demand input DoE, NERSA
Own generation Demand input DoE
Cost of unserved energy Supply input NERSA
Reserve margin Supply input DoE with input from NERSA and Eskom (System Operations and Planning division)
Discount rate Supply input National Treasury, DPE
Renewable energy Supply input DoE, Department of Environmental Affairs
Exchange rate Supply input National Treasury
Cogeneration Supply input DoE
Nuclear Supply input DoE
Imports Supply input Eskom
Generation life cycle cost Supply input DoE with input from Eskom (System Operations and Planning division), DST
Generating plant location Supply input DoE
Generation mix Supply input Eskom (System Operations and Planning division)
Funding and financing Supply input National Treasury
Climate change Externality Department of Environmental Affairs
Carbon tax Externality Department of Environmental Affairs, National Treasury
Water Externality Department of Environmental Affairs, DoE
Distribution infrastructure Externality Electricity distribution sector with direct influence from NERSA (via tariffs)
Base scenarios Output DoE
Generation cost cone Output DoE, NERSA
Rate of inflation Output National Treasury 14
![Page 15: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/15.jpg)
Composition of the IRP 2010 Task Team
Name Capacity/Area of expertise Affiliation (in 2010)
Nelisiwe Magubane DoE (Director-General and sponsor) DoE
Ompi Aphane DoE DoE
Thabang Audat DoE DoE
Ria Govender DoE DoE
Kannan Lakmeeharan Eskom (IRP) Eskom
Callie Fabricius Eskom (planning) Eskom
Mike Rossouw Regulatory and energy planning Xstrata
Ian Langridge IPP and energy planning Anglo American
Brian Day Demand models and climate change Exxaro
Piet van Staden Demand and IPP Sasol
Kevin Morgan REDs and demand management BHP Billiton
Paul Vermeulen Municipal City Power Johannesburg
Doug Kuni IPP and energy planning South African Independent
Power Producer Association
Roger Baxter (withdrew) Economist Chamber of Mines
Anton Eberhard Energy policy, planning, regulation,
investment
University of Cape Town
Shaun Nel Project manager Gobodo Incorporated
Source: TIPS, based on DoE, 2010f 15
![Page 16: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/16.jpg)
Plan objectives
Clear objectives, with the priority of security of supply is
established. Cost and climate change consideration follow.
Ensuring security of supply
Minimising the total cost to the economy
Reducing greenhouse gas emissions
Curtailing portfolio risk or uncertainty
Maximising localisation and job creation benefits
Reducing water usage
Enhancing regional
development (i.e. imports)
Multi-criteria
decision-making
process of the IRP
16
![Page 17: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/17.jpg)
Plan objectives (2)
Goals, and not only new generation building, should
be better aligned with each other and with the ST, MT,
LT sequencing of the IRP
Only inclusion: security of supply (“keeping the lights
on”) with the Medium Term Risk Mitigation Project
(2010 to 2016)
Direct linkages with other sectors and development
objectives are not directly considered
17
![Page 18: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/18.jpg)
Review of previous plans
Inability to capitalise policy learnings in the energy space,
repeating a similar faulty generation building pattern.
No particular reflection on domestic and international
experience
But Task Team of expert stakeholders with considerable
experience and expertise
Institutionalisation of the IRP: review of assumptions and
conditions of the IRP 2010 in the 2013 update
No analysis of the gaps between expected and actual
outcomes from earlier plans
18
![Page 19: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/19.jpg)
Demand forecast methodology
Clear and transparent demand forecast methodology
Good degree of transparency: public availability of data
Growth assumptions remain an important bone of contention
(aspirational 5.4% per annum).
Trade-offs associated with planning for both a low- and high-
growth path factored in 2013 update.
More regular updates of the demand forecast are needed,
along with new iteration of the IRP.
The level of future demand by larger industrial users remains
an area of disagreement, as is the reality of the aspirational
shift to a less energy-intensive economy in the future.
19
![Page 20: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/20.jpg)
Resource options assessment
All resource options for electricity generation are incorporated,
taking into account a range of technologies, their associated
costs and technical requirements.
Transparency: publically available data and working
assumptions for these options
20
![Page 21: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/21.jpg)
Resource options assessment (2)
Use of scenario-based methodologies to determine the most
optimal choices,
Best trade-off between least-investment cost, climate change mitigation,
diversity of supply, localisation and regional development. Economic
analyses are included for these options, however environmental and
social impact assessments are missing.
Contentious issues: overall mix of
technologies, the impact of the
remaining lifespans of current plants on
future generation decisions,
implications of maintenance
Need for accurate and up-to-date
information
21
![Page 22: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/22.jpg)
Policy instruments to achieve objectives
Implications of the prioritisation of the IRP over the
larger IEP
Project-based approach to planning instead of a
broad-based, integrated approach based on longer
term sustainability and vision.
Clear plan and implementation for specific projects
Lack of a clear articulation of the relationship between
the IRP and other higher-level policy and national
strategies
22
![Page 23: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/23.jpg)
Policy instruments to achieve objectives
Good degree of flexibility and adaptability around the policy
options relevant to the electricity
Implementation plan improved in the 2013 update:
Risk assessment
Sensitivity analyses on assumptions
Decisions trees
Principle of least regret decisions
23
![Page 24: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/24.jpg)
Regulatory and institutional frameworks
The institutional and regulatory framework governing the ESI
(and generation planning in particular) remains an important
issue to be addressed
Current governance system: competitive power relations, failed
balance of powers, confusion in the responsibility of various
institutions
The state holds the four distinct roles of shareholder, policymaker,
regulator and project developer, and decision-making processes appear
somewhat politicised and inconsistent over time.
24
![Page 25: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/25.jpg)
Regulatory and institutional frameworks
(2)
Generation: Positive sign of the introduction of IPPs,
although this remains essentially a programme-driven
initiative.
Transmission and distribution network issues: still
unresolved, with the ISMO Bill stalled in Parliament
Absence of implementation mechanisms: the rules and
regulation for the implementation of the IRP remain
unclear
The IRP is well positioned to bring more clarity and
certainty in terms of the regulation and institutional
framework
25
![Page 26: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/26.jpg)
Investment financing
Assessment of the scale of investment but no clear budget for
the financing of the plan (only a description of the potential
sources of financing).
Lack of public information on the financial planning of new
generation expansion programmes
Only made available in applications to NERSA in the MYPD
process at which stage the implementation is already
underway.
No assessment of the potential
for phasing out of fossil fuel
subsidies
26
![Page 27: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/27.jpg)
Social and environmental considerations
Limited to climate change considerations (and water use to
some extent)
GHG constraint insufficient to be compatible with SA’s
commitment
Implications of climate change mitigation (carbon tax)?
Lack of robust and clear SEIAs
Environmental aspects associated with electricity generation
(water use and water quality issues; water-energy nexus)
Lack of an adequate analysis of the social impacts (rural
communities and gender issues)
27
![Page 28: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/28.jpg)
Promotion of innovation and anticipation
of emerging challenges
Largely not addressed in the IRP
Only a research agenda which is easily dated and consequently
may be irrelevant for the planning process.
No plan for capacity building at both a technical (human capital)
and institutional level
No information on the potential for leapfrogging in the area of
R&D and innovation in energy technologies and energy
efficiency
Existing risk of adopting sub-optimal technologies and systems
in the electricity sector
28
![Page 29: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/29.jpg)
What does the assessment mean for
South Africa’s development?
Energy objectives
Security of supply
Quality of infrastructure (generation, transmission, distribution)
Economic objectives
GDP growth, investment,
macro-economic impacts
(inflation, exchange rate)
Industrial objectives
Impact on competitiveness, particularly on
the EIUG
Security of supply
Develop-mental
objectives
Universal access to electricity
Affordable electricity
(particularly for low-income households)
Social objectives
Job creation
Broad-Based Black Economic Empowerment
Financial objectives
Eskom’s financial stability
Municipalities
Private sector participation
Environ-mental
objectives
Energy-related environmental
impacts
Green economy
Sustainable development
Diverging objectives related to energy policy
Source: Das Nair, Montmasson-Clair & Ryan, 2014 29
![Page 30: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/30.jpg)
What does the assessment mean for
South Africa’s development? (2)
Energy objectives:
Good performance in theory (security of supply),
But problematic implementation (of the IRP and the MTRMP)
Economic objectives:
Overall impact on macro-economic conditions well considered (cost of
the generation pathways)
Revised growth projection in the update
High degree of flexibility so as to favour decisions of least regret
Industrial objectives:
Security of supply is the primary energy-related concern of industry and
one of the main constraints to growth
Consideration of the price effect
No direct consideration of the impact on competitiveness
30
![Page 31: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/31.jpg)
What does the assessment mean for
South Africa’s development? (3)
Financial objectives:
Not addressed in the IRP (only indirect goal of minimising the cost to the
economy.
Financing requirement not addressed (MYPD)
No specific provision to deal with unforeseen expenditure
No analysis of the impact on Eskom (and municipalities)
Development objectives:
Not paid enough attention (industrial, urban bias)
Link with the INEP and the goal of universal access to electricity?
Distribution issues not addressed
No consideration of the pricing impact on different customers
31
![Page 32: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/32.jpg)
What does the assessment mean for
South Africa’s development? (4)
Social objectives:
Localisation and job creation explicitly targeted but not discriminating
conditions for the assessment of scenarios.
Localisation and employment creation have been included (RE roll-out)
Other social issues (rural development and gender implications) not
considered
Environmental objectives:
Climate change: emission cap for the electricity sector; reduction of GHG
emissions as a key variable; reduction of the share of coal-based
electricity generation
But the 2013 update recognises that the IRP 2010 cap is insufficient to
reach SA’s international climate change mitigation commitment
Other environmental externalities, with the exception of water usage, are
not considered
32
![Page 33: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/33.jpg)
Conclusion
The IRP process has introduced substantial ameliorations in
terms of electricity planning in SA, compared to the
disorganised experience of the past century
IRP 2010 and 2013 update: a valuable first attempt as a fully-
fledged IRP.
Clear areas of improvement remain, in addition to issues
affecting the ESI as a whole
Going forward, further efforts should be provided to perfect the
design of the IRP, notably its regular and timely update.
Much more effort is required to ensure the effective and timely
implementation of the IRP
33
![Page 34: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing](https://reader034.vdocument.in/reader034/viewer/2022052021/6035a9083365885357779435/html5/thumbnails/34.jpg)
Thank you very much
for your attention!
Gaylor Montmasson-Clair ([email protected])
Georgina Ryan ([email protected])
Trade and Industrial Policy Strategies (TIPS)
www.tips.org.za
+27 12 433 93 40