integrated resource plan - tips · 2015. 7. 21. · generation expansion programme started in 2005...

34
Repositioning Electricity Planning at the Core: An Evaluation of the Effectiveness of South Africa’s Integrated Resource Plan Gaylor Montmasson-Clair and Georgina Ryan Trade and Industrial Policy Strategies (TIPS) TIPS Development Dialogue, Pretoria, South Africa 7 July 2015

Upload: others

Post on 07-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Repositioning Electricity Planning at the Core:

An Evaluation of the Effectiveness of South Africa’s

Integrated Resource Plan

Gaylor Montmasson-Clair and Georgina Ryan

Trade and Industrial Policy Strategies (TIPS)

TIPS Development Dialogue, Pretoria, South Africa

7 July 2015

Page 2: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Outline

Introduction and key messages

Implications of planning

Presentation of the assessment framework

The 10-criterion assessment of the IRP

What does the assessment mean for SA’s

development?

Conclusion

2

Page 3: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Introduction

Ensuring a reliable and

affordable supply of electricity

is at the core of development

National electricity planning,

as part of energy policy, has

emerged as the most

effective and efficient

framework to shape the

development of the ESI

3

Page 4: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Key messages

Planning is critical for the sustainability of the ESI,

both in terms of security of supply and pricing

Planning for new build

Planning for maintenance

The current IRP bodes well on international standards

but substantial room for improvement remains, notably

on implementation

A clear long-term vision for the ESI is still missing: the

IRP should contribute to filling this gap

4

Page 5: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Role of an IRP

Meeting the estimated demand in a specific period in the most

affordable and efficient manner,

also taking into account issues regarding equity,

environmental protection, reliability and other country-

specific goals

Providing a means for minimising the present and future costs

of meeting energy demand considering the impacts on utilities,

government, the environment and society.

5

Page 6: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

The IRP in South Africa

Prior to 2009, a traditional approach to planning with 3

separate plans developed respectively by Eskom,

NERSA and the then-DME

Driven by the utility planner’s projections of future demand

and expansion of its supply to meet anticipated demand

Often resulted in excess capacity and higher-than-necessary

energy costs

Spearheaded by the DoE since 2009

IRP1 > IRP 2010 > 2013 update > next fully-fledged iteration

(2016?)

Subset of the IEP, although the interaction between

the IRP and IEP remains a point of contention 6

Page 7: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

The IRP in South Africa

Policy choices:

cost-optimised

scenario

carbon emission

constraint

localisation objectives

roll-out of RE

technologies

7

Page 8: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

The IRP in South Africa

Occurring on the back of security of supply issues and

stringent electricity price increase

Generation expansion programme started in 2005

17.7 GW of generation capacity from 2005 to 2018/2019

ZAR 340 billion

The financing requirement have contributed to

pushing prices up and is expected to result in a

trebling of the average electricity price at ZAR 89.13

c/kWh from 2009/2010 to 2017/2018

8

Page 9: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Impact on electricity supply

The role of planning is instrumental to ensuring the

adequate supply of electricity (timing, size, mix)

Planning impacts upon security of supply in 2 key

ways:

Timing and scale of expansion and maintenance

decisions

The expansion plan started in the 2000s replicates the

pattern witnessed in the 1970-1980s, when the lack of

adequate planning resulted in investments in excess

generation capacity. The delay in planning directly resulted

in insufficient generation capacity

9

Page 10: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Impact on electricity supply

Delays in construction

The expansion plan is largely dependent on the

addition of 2 large coal-fired power stations (Medupi

and Kusile)

Significant delays for the

construction of both power

stations, aggravating the

gap in supply

10

Page 11: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Impact on electricity pricing

Average real and nominal electricity prices in South Africa

between 1974 and 2011 (in ZAR cents per kWh) 11

Page 12: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

The assessment framework

Developed by the

World Resources

Institute and

Prayas, Energy

Group

Aimed at rendering

decision-making

processes more

transparent and

enabling greater

engagement

12

Page 13: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Planning process

Substantial improvement since 2009 and the clarification of the

mandate of the DoE

Effective mobilisation of all necessary data and information (thorough

process and institutional arrangements)

Absence of labour and civil society from the decision-making process

Information asymmetry problems (in favour of the utility) remain and

should be addressed over time.

Extensive consultation process

Good degree of transparency (assumptions, data and methodologies

are all available for public scrutiny)

No clear process for ongoing updating of the IRP

No long-term vision for the ESI beyond generation capacity planning

13

Page 14: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Parameter Nature Data owner

Demand forecast (energy and

maximum demand)

Demand input Eskom (System Operations and Planning division)

Gross domestic product Demand input National Treasury

Electricity intensity (short-term) Demand input the dti, NT, EDD, NPC

Electricity Intensity (long-term) Demand input the dti, NT, EDD, NPC

Price elasticity of demand Demand input National Treasury

Demand side management Demand input DoE

Energy efficiency Demand input DoE

Demand market participation /

demand response

Demand input Eskom

Energy conservation Demand input DoE, NERSA

Own generation Demand input DoE

Cost of unserved energy Supply input NERSA

Reserve margin Supply input DoE with input from NERSA and Eskom (System Operations and Planning division)

Discount rate Supply input National Treasury, DPE

Renewable energy Supply input DoE, Department of Environmental Affairs

Exchange rate Supply input National Treasury

Cogeneration Supply input DoE

Nuclear Supply input DoE

Imports Supply input Eskom

Generation life cycle cost Supply input DoE with input from Eskom (System Operations and Planning division), DST

Generating plant location Supply input DoE

Generation mix Supply input Eskom (System Operations and Planning division)

Funding and financing Supply input National Treasury

Climate change Externality Department of Environmental Affairs

Carbon tax Externality Department of Environmental Affairs, National Treasury

Water Externality Department of Environmental Affairs, DoE

Distribution infrastructure Externality Electricity distribution sector with direct influence from NERSA (via tariffs)

Base scenarios Output DoE

Generation cost cone Output DoE, NERSA

Rate of inflation Output National Treasury 14

Page 15: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Composition of the IRP 2010 Task Team

Name Capacity/Area of expertise Affiliation (in 2010)

Nelisiwe Magubane DoE (Director-General and sponsor) DoE

Ompi Aphane DoE DoE

Thabang Audat DoE DoE

Ria Govender DoE DoE

Kannan Lakmeeharan Eskom (IRP) Eskom

Callie Fabricius Eskom (planning) Eskom

Mike Rossouw Regulatory and energy planning Xstrata

Ian Langridge IPP and energy planning Anglo American

Brian Day Demand models and climate change Exxaro

Piet van Staden Demand and IPP Sasol

Kevin Morgan REDs and demand management BHP Billiton

Paul Vermeulen Municipal City Power Johannesburg

Doug Kuni IPP and energy planning South African Independent

Power Producer Association

Roger Baxter (withdrew) Economist Chamber of Mines

Anton Eberhard Energy policy, planning, regulation,

investment

University of Cape Town

Shaun Nel Project manager Gobodo Incorporated

Source: TIPS, based on DoE, 2010f 15

Page 16: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Plan objectives

Clear objectives, with the priority of security of supply is

established. Cost and climate change consideration follow.

Ensuring security of supply

Minimising the total cost to the economy

Reducing greenhouse gas emissions

Curtailing portfolio risk or uncertainty

Maximising localisation and job creation benefits

Reducing water usage

Enhancing regional

development (i.e. imports)

Multi-criteria

decision-making

process of the IRP

16

Page 17: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Plan objectives (2)

Goals, and not only new generation building, should

be better aligned with each other and with the ST, MT,

LT sequencing of the IRP

Only inclusion: security of supply (“keeping the lights

on”) with the Medium Term Risk Mitigation Project

(2010 to 2016)

Direct linkages with other sectors and development

objectives are not directly considered

17

Page 18: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Review of previous plans

Inability to capitalise policy learnings in the energy space,

repeating a similar faulty generation building pattern.

No particular reflection on domestic and international

experience

But Task Team of expert stakeholders with considerable

experience and expertise

Institutionalisation of the IRP: review of assumptions and

conditions of the IRP 2010 in the 2013 update

No analysis of the gaps between expected and actual

outcomes from earlier plans

18

Page 19: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Demand forecast methodology

Clear and transparent demand forecast methodology

Good degree of transparency: public availability of data

Growth assumptions remain an important bone of contention

(aspirational 5.4% per annum).

Trade-offs associated with planning for both a low- and high-

growth path factored in 2013 update.

More regular updates of the demand forecast are needed,

along with new iteration of the IRP.

The level of future demand by larger industrial users remains

an area of disagreement, as is the reality of the aspirational

shift to a less energy-intensive economy in the future.

19

Page 20: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Resource options assessment

All resource options for electricity generation are incorporated,

taking into account a range of technologies, their associated

costs and technical requirements.

Transparency: publically available data and working

assumptions for these options

20

Page 21: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Resource options assessment (2)

Use of scenario-based methodologies to determine the most

optimal choices,

Best trade-off between least-investment cost, climate change mitigation,

diversity of supply, localisation and regional development. Economic

analyses are included for these options, however environmental and

social impact assessments are missing.

Contentious issues: overall mix of

technologies, the impact of the

remaining lifespans of current plants on

future generation decisions,

implications of maintenance

Need for accurate and up-to-date

information

21

Page 22: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Policy instruments to achieve objectives

Implications of the prioritisation of the IRP over the

larger IEP

Project-based approach to planning instead of a

broad-based, integrated approach based on longer

term sustainability and vision.

Clear plan and implementation for specific projects

Lack of a clear articulation of the relationship between

the IRP and other higher-level policy and national

strategies

22

Page 23: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Policy instruments to achieve objectives

Good degree of flexibility and adaptability around the policy

options relevant to the electricity

Implementation plan improved in the 2013 update:

Risk assessment

Sensitivity analyses on assumptions

Decisions trees

Principle of least regret decisions

23

Page 24: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Regulatory and institutional frameworks

The institutional and regulatory framework governing the ESI

(and generation planning in particular) remains an important

issue to be addressed

Current governance system: competitive power relations, failed

balance of powers, confusion in the responsibility of various

institutions

The state holds the four distinct roles of shareholder, policymaker,

regulator and project developer, and decision-making processes appear

somewhat politicised and inconsistent over time.

24

Page 25: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Regulatory and institutional frameworks

(2)

Generation: Positive sign of the introduction of IPPs,

although this remains essentially a programme-driven

initiative.

Transmission and distribution network issues: still

unresolved, with the ISMO Bill stalled in Parliament

Absence of implementation mechanisms: the rules and

regulation for the implementation of the IRP remain

unclear

The IRP is well positioned to bring more clarity and

certainty in terms of the regulation and institutional

framework

25

Page 26: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Investment financing

Assessment of the scale of investment but no clear budget for

the financing of the plan (only a description of the potential

sources of financing).

Lack of public information on the financial planning of new

generation expansion programmes

Only made available in applications to NERSA in the MYPD

process at which stage the implementation is already

underway.

No assessment of the potential

for phasing out of fossil fuel

subsidies

26

Page 27: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Social and environmental considerations

Limited to climate change considerations (and water use to

some extent)

GHG constraint insufficient to be compatible with SA’s

commitment

Implications of climate change mitigation (carbon tax)?

Lack of robust and clear SEIAs

Environmental aspects associated with electricity generation

(water use and water quality issues; water-energy nexus)

Lack of an adequate analysis of the social impacts (rural

communities and gender issues)

27

Page 28: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Promotion of innovation and anticipation

of emerging challenges

Largely not addressed in the IRP

Only a research agenda which is easily dated and consequently

may be irrelevant for the planning process.

No plan for capacity building at both a technical (human capital)

and institutional level

No information on the potential for leapfrogging in the area of

R&D and innovation in energy technologies and energy

efficiency

Existing risk of adopting sub-optimal technologies and systems

in the electricity sector

28

Page 29: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

What does the assessment mean for

South Africa’s development?

Energy objectives

Security of supply

Quality of infrastructure (generation, transmission, distribution)

Economic objectives

GDP growth, investment,

macro-economic impacts

(inflation, exchange rate)

Industrial objectives

Impact on competitiveness, particularly on

the EIUG

Security of supply

Develop-mental

objectives

Universal access to electricity

Affordable electricity

(particularly for low-income households)

Social objectives

Job creation

Broad-Based Black Economic Empowerment

Financial objectives

Eskom’s financial stability

Municipalities

Private sector participation

Environ-mental

objectives

Energy-related environmental

impacts

Green economy

Sustainable development

Diverging objectives related to energy policy

Source: Das Nair, Montmasson-Clair & Ryan, 2014 29

Page 30: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

What does the assessment mean for

South Africa’s development? (2)

Energy objectives:

Good performance in theory (security of supply),

But problematic implementation (of the IRP and the MTRMP)

Economic objectives:

Overall impact on macro-economic conditions well considered (cost of

the generation pathways)

Revised growth projection in the update

High degree of flexibility so as to favour decisions of least regret

Industrial objectives:

Security of supply is the primary energy-related concern of industry and

one of the main constraints to growth

Consideration of the price effect

No direct consideration of the impact on competitiveness

30

Page 31: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

What does the assessment mean for

South Africa’s development? (3)

Financial objectives:

Not addressed in the IRP (only indirect goal of minimising the cost to the

economy.

Financing requirement not addressed (MYPD)

No specific provision to deal with unforeseen expenditure

No analysis of the impact on Eskom (and municipalities)

Development objectives:

Not paid enough attention (industrial, urban bias)

Link with the INEP and the goal of universal access to electricity?

Distribution issues not addressed

No consideration of the pricing impact on different customers

31

Page 32: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

What does the assessment mean for

South Africa’s development? (4)

Social objectives:

Localisation and job creation explicitly targeted but not discriminating

conditions for the assessment of scenarios.

Localisation and employment creation have been included (RE roll-out)

Other social issues (rural development and gender implications) not

considered

Environmental objectives:

Climate change: emission cap for the electricity sector; reduction of GHG

emissions as a key variable; reduction of the share of coal-based

electricity generation

But the 2013 update recognises that the IRP 2010 cap is insufficient to

reach SA’s international climate change mitigation commitment

Other environmental externalities, with the exception of water usage, are

not considered

32

Page 33: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Conclusion

The IRP process has introduced substantial ameliorations in

terms of electricity planning in SA, compared to the

disorganised experience of the past century

IRP 2010 and 2013 update: a valuable first attempt as a fully-

fledged IRP.

Clear areas of improvement remain, in addition to issues

affecting the ESI as a whole

Going forward, further efforts should be provided to perfect the

design of the IRP, notably its regular and timely update.

Much more effort is required to ensure the effective and timely

implementation of the IRP

33

Page 34: Integrated Resource Plan - TIPS · 2015. 7. 21. · Generation expansion programme started in 2005 17.7 GW of generation capacity from 2005 to 2018/2019 ZAR 340 billion The financing

Thank you very much

for your attention!

Gaylor Montmasson-Clair ([email protected])

Georgina Ryan ([email protected])

Trade and Industrial Policy Strategies (TIPS)

www.tips.org.za

+27 12 433 93 40