interconnection of grid systems for maui and oahu counties · 2019-11-08 · acknowledgement: this...
TRANSCRIPT
![Page 1: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/1.jpg)
Interconnection of Grid Systems for
Maui and Oahu Counties: Different Mixes of Renewable Generation
and Several Possible Future Scenarios
Prepared for the
U.S. Department of Energy
Office of Electricity Delivery and Energy Reliability
Under Cooperative Agreement No. DE-EE0003507
Hawai‘i Energy Sustainability Program
Task 2: Energy Modeling and Scenario Analysis
Prepared by
GE Energy Consulting
Submitted by
Hawai‘i Natural Energy Institute
School of Ocean and Earth Science and Technology
University of Hawai‘i
February 2014
![Page 2: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/2.jpg)
Acknowledgement: This material is based upon work supported by the United States
Department of Energy under Cooperative Agreement Number DE-EE0003507.
Disclaimer: This report was prepared as an account of work sponsored by an agency of the
United States Government. Neither the United States Government nor any agency thereof, nor
any of their employees, makes any warranty, express or implied, or assumes any legal liability
or responsibility for the accuracy, completeness, or usefulness of any information, apparatus,
product, or process disclosed, or represents that its use would not infringe privately owned
rights. Reference here in to any specific commercial product, process, or service by tradename,
trademark, manufacturer, or otherwise does not necessarily constitute or imply its
endorsement, recommendation, or favoring by the United States Government or any agency
thereof. The views and opinions of authors expressed herein do not necessarily state or reflect
those of the United States Government or any agency thereof.
![Page 3: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/3.jpg)
Final Report:
Stage 2 Oahu-Maui
Interconnection Study
Prepared for:
Hawaiian Electric Company
Hawaii Natural Energy Institute
Prepared by:
GE Energy Consulting
May 21, 2013
![Page 4: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/4.jpg)
Hawaii Stage 2 Interconnection Study Legal Notices
GE Energy Consulting ii Final Report 5/21/2013
Legal Notices
This report was prepared by General Electric International, Inc. as an account of work
sponsored by Hawaiian Electric Company and Hawaii Natural Energy Institute. Neither
Hawaiian Electric Company, Hawaii Natural Energy Institute, General Electric International,
Inc., nor any person acting on their behalf:
1. Makes any warranty or representation, expressed or implied, with respect to the use of any information contained in this report, or that the use of any information, apparatus, method, or process disclosed in the report may not infringe privately owned rights.
2. Assumes any liabilities with respect to the use of or for damage resulting from the use of any information, apparatus, method, or process disclosed in this report.
![Page 5: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/5.jpg)
Hawaii Stage 2 Interconnection Study Foreword
GE Energy Consulting iii Final Report 5/21/2013
Foreword
This report was prepared by General Electric International, Inc. (GEII), acting through its
Energy Consulting group (EC) based in Schenectady, NY, and submitted to Hawaiian Electric
Company and Hawaii Natural Energy Institute. Technical and commercial questions and any
correspondence concerning this document should be referred to:
Richard Piwko or Derek Stenclik
GE, Energy Consulting
General Electric International, Inc.
Building 53
One River Road
Schenectady, New York 12345
Phone: 518-385-7610 or 518-385-4998
![Page 6: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/6.jpg)
Hawaii Stage 2 Interconnection Study Project Teams
GE Energy Consulting iv Final Report 5/21/2013
Project Teams
General Electric
Richard Piwko Gary Jordan Derek Stenclik Shakeer Meeran Yan Pan Wei Ren Ryan Konopinski
Hawaiian Electric Company
Dean Arakawa Ron Bushner Marc DeNarie Marc Matsuura Dora Nakafuji Dean Oshiro Ross Sakuda Robert Uyeunten Robert Young
Hawaii Natural Energy Institute
Leon Roose Richard Rocheleau
![Page 7: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/7.jpg)
Hawaii Stage 2 Interconnection Study Table of Contents
GE Energy Consulting v Final Report 5/21/2013
Table of Contents 1 Introduction 1
1.1 Study Objectives and Approach 1
1.2 Study Scope & Limitations 2
2 Inputs & Assumptions 4
2.1 Macroeconomic Assumptions 4
2.1.1 Load 4
2.1.2 Fuel 6
2.1.3 Emissions Prices 6
2.2 Transmission 7
2.3 Existing Generation Mix 8
2.4 Thermal Plant Configurations 9
2.5 Operating Practices 13
2.5.1 Fixed Operating Schedules 13
2.5.2 Planned Outages and Maintenance Schedules 13
2.5.3 Quick-Start Capability 14
2.5.4 Independent Power Producers 15
2.5.5 Combined Cycle Plant Modeling 15
2.6 Wind & Solar Plants 16
2.6.1 Wind & Solar Profiles 16
2.6.2 Forecasting 17
2.6.3 Curtailment 18
2.7 Reserves 19
2.7.1 Up Reserve Requirements 19
2.7.2 Down Reserve Requirements 20
3 Scenario Overview 22
3.1 Renewable Capacity Additions 22
3.2 Available Renewable Energy 24
3.3 DC & AC Interconnection 25
3.4 Reserve Strategy 26
4 Results 30
4.1 Interconnecting Maui, Molokai and Lanai 30
4.2 Base Case and Scenario 1 34
4.2.1 Total System Energy Production 34
4.2.2 Thermal Unit Operation 36
4.2.3 Emissions 39
4.2.4 Curtailment of Renewable Generation 39
4.2.5 Interisland Line Flows 41
4.2.6 Weekly Generation Profiles 43
4.3 Production Cost Analysis 47
4.4 Delivered Renewable Generation 50
4.5 Renewable Curtailment 54
![Page 8: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/8.jpg)
Hawaii Stage 2 Interconnection Study Table of Contents
GE Energy Consulting vi Final Report 5/21/2013
4.6 DC & AC Line Flows 57
4.7 Value of Renewable Energy Resources 63
4.8 Emissions 65
4.9 Thermal Cycling 67
4.10 Down-Regulation and Up-Range 69
4.11 Key Observations 73
5 Changes to Operational Practices 74
5.1 Production Cost Impacts 75
5.2 Curtailment and Renewable Generation 78
5.3 DC Cables Constrained 83
5.4 Value of Renewable Energy Resources 87
5.5 Other Impacts 90
5.6 Key Observations 93
6 Sensitivity Analysis 94
6.1 Load Growth Sensitivities 94
6.2 Fuel Price Sensitivities 96
7 Energy Storage Options 99
7.1 Energy Storage as a Reserve Asset 99
7.2 Energy Storage as an Energy Shifting Asset 104
7.3 Comparison of Energy Storage Results 106
8 Cost-Benefit Analysis 109
8.1 Capital Cost Data 109
8.2 Capital Costs for Study Scenarios 111
8.3 Annual Benefits with Existing Operating Practices 112
8.4 Annual Capital Recovery Required 113
8.5 Cost of Renewable Electricity (COE) 117
8.6 Cost-Benefit Analysis with Modified Operating Practices 118
8.7 Total Cost Including PPA Costs 122
9 Observations & Conclusions 125
10 Future Research 126
11 References 128
11.1 Previous Studies 128
11.2 Capital Cost Assumptions 128
12 Appendix 129
12.1 GE MAPS Description 129
12.2 Maintenance and Outage Schedule 130
12.3 Detailed Capital Cost Assumptions 132
![Page 9: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/9.jpg)
Hawaii Stage 2 Interconnection Study List of Figures
GE Energy Consulting vii Final Report 5/21/2013
List of Figures Figure 2-1: Total System Load and Peak Demand by Month ........................................................................................ 5
Figure 2-2: Average Weekly Load Pattern .............................................................................................................................. 5
Figure 2-3: Base Case Installed Capacity by Island, by Fuel .......................................................................................... 8
Figure 2-4: Weekly Snapshot of Wind & Solar Forecast and Real-Time Profiles .............................................. 17
Figure 2-5: Wind & Solar Forecast Error Duration Curves between Scenario 1 and 7 .................................. 17
Figure 3-1: Renewable Capacity (MW) ................................................................................................................................... 23
Figure 3-2: Scenario Tree ............................................................................................................................................................ 23
Figure 3-3: Available Renewable Energy (GWh) ............................................................................................................... 25
Figure 3-4: System Interconnections with Two HVDC Cables .................................................................................. 25
Figure 3-5: Oahu Base Case Variable Operating Reserve versus Wind and Solar Generation ................ 26
Figure 3-6: Maui County Operating Reserve versus Wind and Solar Generation ........................................... 26
Figure 3-7: Combined System Operating Reserve versus Wind and Solar Generation ............................... 27
Figure 3-8: Combined System Operating Reserve Duration Curves by Scenario ........................................... 28
Figure 3-9: Maximum Operating Reserves by Scenario .............................................................................................. 29
Figure 4-1: Spinning Reserve Requirements for Maui Alone and Maui County Interconnected.............. 32
Figure 4-2: Quick-Start Capability for Maui Alone and Maui Combined with Lanai and Molokai ........... 32
Figure 4-3: Energy Production by Power Plant for Scenario 1 ................................................................................. 36
Figure 4-4: Capacity Factors of Generating Plants for Base Case and Scenario 1 ........................................ 37
Figure 4-5: Average Annual Hours of Operation and Starts for Thermal Generation, by Type ................ 38
Figure 4-6: Annual Emissions for Base Case and Scenario 1 .................................................................................... 39
Figure 4-7: Average Hourly Available and Delivered Wind Power by Time of Day, Scenario 1 ................ 40
Figure 4-8: Duration Curve of Wind and Solar Curtailment, Base Case and Scenario 1 ............................. 41
Figure 4-9: Interisland Line Flow Duration Curves for Scenario 1 .......................................................................... 42
Figure 4-10: Interisland Line Flows for Highest Load Week ...................................................................................... 43
Figure 4-11: Scenario 1 Generation Profiles for Week with Maximum Renewable Energy Penetration
(% of Load) ............................................................................................................................................................................... 44
Figure 4-12: Scenario 1 Generation Profiles for Week with Maximum Renewable Generation (MW) ... 45
Figure 4-13: Scenario 1 Generation Profiles for Week with Worst Wind & Solar Forecast Error ............. 45
Figure 4-14: Scenario 1 Generation Profiles for Week with Peak Demand, Showing Changes from
Base Case ................................................................................................................................................................................. 46
![Page 10: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/10.jpg)
Hawaii Stage 2 Interconnection Study List of Figures
GE Energy Consulting viii Final Report 5/21/2013
Figure 4-15: Production Costs for All Scenarios, by Generation Type ................................................................... 49
Figure 4-16: Generation by Type for All Scenarios ......................................................................................................... 50
Figure 4-17: Wind, Solar, and Firm Renewable Energy for All Scenarios ............................................................ 51
Figure 4-18: Annual Renewable Energy Penetration for All Scenarios ................................................................. 52
Figure 4-19: Duration Curves of Hourly Wind and Solar Penetration Levels as % of Load for All
Scenarios .................................................................................................................................................................................. 53
Figure 4-20: Duration Curves of Wind and Solar Penetration Levels for Different Time Periods,
Scenarios 1 and 8 ................................................................................................................................................................. 54
Figure 4-21: Wind and Solar Curtailment Duration Curves for All Scenarios .................................................... 55
Figure 4-22: Wind, Solar and Firm Renewable Energy Delivered and Curtailed, as % of Load ................ 56
Figure 4-23: Available Wind, Solar and Firm Renewable Energy versus Curtailment ................................... 56
Figure 4-24: Curtailment of the Maui 100 MW Wind Plant for Scenarios 8, 9 and 10. ................................. 57
Figure 4-25: Duration Curves for Maui County to Oahu DC Cable Flows ............................................................ 59
Figure 4-26: Energy Transfer on Maui County to Oahu DC Cables, with and without Power Flow
Constraints ............................................................................................................................................................................... 60
Figure 4-27: Flow Duration Curves for AC Cables Interconnecting Maui, Lanai and Molokai................... 61
Figure 4-28: Total Emissions from Dispatchable Thermal Generation ................................................................. 65
Figure 4-29: Reductions in Emissions from Thermal Generation Relative to Base Case ............................. 66
Figure 4-30: Duration Curve of AES Output for All Scenarios .................................................................................... 68
Figure 4-31: Hourly Generation Profiles and System Down-Regulation Range for One Week, Scenario
1 .................................................................................................................................................................................................... 69
Figure 4-32: Duration Curve of Down-Regulation Range for Scenarios 1 and 10 .......................................... 70
Figure 4-33: Hourly Generation Profiles and System Up-Range for One Week, Scenario 1 ...................... 71
Figure 4-34: Up-Range Duration Curves for Scenarios 1 and 10 (Min & Max Renewables) ....................... 72
Figure 4-35: Reserve Requirements and System Up-Range for Scenarios 1 and 10 .................................... 72
Figure 4-36: Hourly Up-Range and DC Cable Flow for Week with Highest DC Cable in Scenario 10 ... 73
Figure 5-1: Sequential Changes to Operational Practices ........................................................................................... 74
Figure 5-2: Production Cost Savings by Sensitivity for Scenario 1 .......................................................................... 76
Figure 5-3: Impact of Operating Changes on Production cost for Scenarios 1-10 ......................................... 76
Figure 5-4: Production Cost Savings from all Changes ................................................................................................. 78
Figure 5-5: Reduced Curtailment due to Operational Changes for Scenario 1 ................................................. 79
Figure 5-6: Curtailment of Renewable Energy by Sensitivity for Scenarios 1-10 ............................................. 80
![Page 11: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/11.jpg)
Hawaii Stage 2 Interconnection Study List of Figures
GE Energy Consulting ix Final Report 5/21/2013
Figure 5-7: Potential Total Reduction in Curtailment ..................................................................................................... 81
Figure 5-8: Impact on Renewable Penetration of Modified Operational Changes. ......................................... 82
Figure 5-9: Change in Curtailment with Modified Operating Practices by Scenario ...................................... 82
Figure 5-10: DC Cable Flow Duration Curves for Scenario 10 by Operating Sensitivity ................................ 83
Figure 5-11: Maximum DC Cable Flows (MW) by Operating Sensitivity ................................................................ 84
Figure 5-12: Energy Flows (GWh) on DC Cables by Sensitivity ................................................................................... 85
Figure 5-13: DC Cable Flow (MW) Duration Curves for Scenario 1-10 with Operating Changes .............. 86
Figure 5-14: DC Cable Energy Flows (GWh) by Scenario with Operating Changes in Place ....................... 87
Figure 5-15: Comparison of Values of Renewable Resources with Different Operating Assumptions . 89
Figure 5-16: Kahe and AES Plant Operating Impacts for Scenario 10 ................................................................... 90
Figure 5-17: Oahu Baseload Unit Operating Impacts for Scenario 10 .................................................................. 91
Figure 5-18: Maui Baseload Unit Operating Impacts for Scenario 10 ................................................................... 91
Figure 5-19: Oahu Up-Range Duration Curve with Operating Changes .............................................................. 92
Figure 5-20: Oahu Down-Regulation Duration Curves by Sensitivity .................................................................... 92
Figure 6-1: Load Growth Sensitivity Hourly Duration Curves ..................................................................................... 94
Figure 6-2: Change in Production Cost in Load Sensitivities ...................................................................................... 95
Figure 6-3: Wind & Solar Curtailment by Load Growth Sensitivity .......................................................................... 95
Figure 6-4: Fuel Cost as a Component of Overall Production Cost ......................................................................... 97
Figure 6-5: Elasticity of Fuel Prices and Production Cost ............................................................................................. 97
Figure 6-6: Change in Production Cost in Fuel Sensitivities ........................................................................................ 98
Figure 7-1: Operating and Contingency Reserve Duration Curves with Energy Storage .......................... 100
Figure 7-2: Annual Production Cost Savings with Energy Storage as a Reserve Asset .............................. 101
Figure 7-3: Oahu Baseload Unit Operating Impacts with Reduced Reserve Requirement ...................... 103
Figure 7-4: Value of Energy Storage as an Energy Shifting Device ...................................................................... 104
Figure 7-5: Utilization of Energy Storage Device to Shift Energy ........................................................................... 105
Figure 7-6: Utilization of Energy Storage by Time of Day.......................................................................................... 105
Figure 7-7: Impact of 200MW, 6hr Storage Device on Renewable Curtailment and Coal Generation106
Figure 7-8: Comparison of Savings for a 2-hour Storage Device ......................................................................... 107
Figure 7-9: Comparison of Storage Options .................................................................................................................... 108
Figure 7-10: Comparison of Storage Options for a Range of Sizes ...................................................................... 108
Figure 8-1: Capital Cost Assumptions by Technology ................................................................................................ 110
![Page 12: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/12.jpg)
Hawaii Stage 2 Interconnection Study List of Figures
GE Energy Consulting x Final Report 5/21/2013
Figure 8-2: Cost-Benefit Analysis (M$/Year) by Scenario Using Different Capital Cost Assumptions and
Assuming a 14% FCR ....................................................................................................................................................... 114
Figure 8-3: Cost-Benefit Analysis (M$/Year) by Scenario Using Different FCR Assumptions and
Assuming Average Capital Costs ............................................................................................................................... 115
Figure 8-4: Cost Benefit Analysis ($/MWh) Based on Delivered Renewable Energy .................................... 118
Figure 8-5: Cost-Benefit Analysis (M$/Year) with Modified Operating Practices ........................................... 119
Figure 8-6: Cost-Benefit Analysis ($/MWh) Based on Delivered Renewable Energy with Modified
Operating Practices .......................................................................................................................................................... 120
Figure 8-7: Total Operating Cost by Scenario (M$) ....................................................................................................... 123
Figure 8-8: Comparison of Total Cost (M$) with Existing and Modified Operating Practices ................... 124
Figure 10-1: Determining the Incremental Value of Interconnection vs. Modified Operating Practices
.................................................................................................................................................................................................... 126
![Page 13: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/13.jpg)
Hawaii Stage 2 Interconnection Study List of Tables
GE Energy Consulting xi Final Report 5/21/2013
List of Tables Table 2-1: Summary of Load by Island .................................................................................................................................... 4
Table 2-2: Fuel Prices (2015$/MMBtu) ...................................................................................................................................... 6
Table 2-3: Load Flow Assignment by Scenario .................................................................................................................... 7
Table 2-4: Base Case Installed Capacity by Island, by Fuel (MW) ................................................................................ 9
Table 2-5: Oahu Thermal Unit Characteristics .................................................................................................................. 11
Table 2-6: Maui County Thermal Unit Characteristics ................................................................................................... 12
Table 2-7: Planned Maintenance Schedule ........................................................................................................................ 14
Table 2-8: Base Case Wind & Solar Plants ........................................................................................................................... 16
Table 2-9: Wind and Solar Curtailment Order ................................................................................................................... 18
Table 2-10: Down Reserves by Unit ........................................................................................................................................ 20
Table 3-1: Renewable Capacity (MW) .................................................................................................................................... 22
Table 3-2: Available Renewable Energy (GWh) ................................................................................................................ 24
Table 3-3: Maximum Operating Reserves by Scenario. ............................................................................................... 28
Table 4-1: Annual Production Costs and Energy for Maui County System......................................................... 31
Table 4-2: Wind and Solar Energy Delivered and Curtailed for Maui County System ................................... 31
Table 4-3: Annual Production Costs and Energy for Base Cases and Scenario 1 ........................................... 35
Table 4-4: Generation Utilization for Base Case and Scenario 1 ............................................................................. 37
Table 4-5: Annual Renewable Energy Available and Delivered for Base Case and Scenario 1 ............... 40
Table 4-6: Annual Production Costs and Energy for All Scenarios ......................................................................... 48
Table 4-7: Annual Generation in GWh by Type and by Island for All Scenarios ............................................... 49
Table 4-8: Wind, Solar and Firm Renewable Energy Delivered and Curtailed for All Scenarios............... 52
Table 4-9: Maximum and Average Hourly Penetration Levels for Wind and Solar Resources ................. 53
Table 4-10: Wind and Solar Energy Curtailment for All Scenarios ......................................................................... 55
Table 4-11: Maui County to Oahu DC Cable Flows for All Scenarios ..................................................................... 60
Table 4-12: Flows (MW) for AC Cables Interconnecting Maui, Lanai and Molokai by Percentile ............... 62
Table 4-13: Value of Additional Renewable Resources with Existing Thermal Plant Operating
Practices ................................................................................................................................................................................... 63
Table 4-14: Average Annual Starts and Hours of Operation by Unit Type ......................................................... 67
Table 5-1: Reduced Minimum Power Limits on Oahu Units ........................................................................................ 75
Table 5-2: Production Cost Impact (M$) of Operating Changes................................................................................ 77
![Page 14: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/14.jpg)
Hawaii Stage 2 Interconnection Study List of Tables
GE Energy Consulting xii Final Report 5/21/2013
Table 5-3: Incremental Savings (M$) from Operating Changes for Scenario 1-10 .......................................... 77
Table 5-4: Curtailment (GWh) of Renewable Energy by Sensitivity for Scenarios 1-10 ................................. 80
Table 5-5: Reduction in Curtailment by Sensitivity .......................................................................................................... 81
Table 5-6: Energy Flows (GWh) on DC Cables by Sensitivity ....................................................................................... 85
Table 5-7: DC Cable Flow Summary with Operating Changes .................................................................................. 86
Table 5-8: Value of Additional Renewable Resources with Modified Operating Practices .......................... 88
Table 5-9: Comparison of the Value of Renewable Resources Based on Operating Assumptions ......... 88
Table 7-1: Annual Production Cost Savings with Energy Storage as a Reserve Asset ............................... 101
Table 7-2: Delivered Wind and Solar Energy with Energy Storage as a Reserve Asset ............................. 102
Table 7-3: Energy Generation by Island with Energy Storage as a Reserve Asset ....................................... 102
Table 8-1: Capital Cost Data for Wind, Solar and Geothermal from External Sources ($/KW) ............... 109
Table 8-2: Total Estimated Capital Cost by Scenario (M$)......................................................................................... 111
Table 8-3: Annual Capital Recovery Required ($/Year) by Scenario using a 14% FCR................................ 112
Table 8-4: Existing PPA Prices by Plant ............................................................................................................................... 112
Table 8-5: Annual Benefits by Scenario with Existing Operating Practices ...................................................... 113
Table 8-6: Break Even Cost of the AC Cable Network Assuming a 14% FCR ................................................... 116
Table 8-7: Annual Benefits by Scenario with Modified Operating Practices .................................................... 119
Table 8-8: Break Even Cost of the AC Cable Network Assuming a 14% FCR and Modified Operating
Practices ................................................................................................................................................................................ 121
Table 12-1: Maui County Weekly Maintenance and Outage Schedule .............................................................. 130
Table 12-2: Oahu Weekly Maintenance and Outage Schedule ............................................................................. 131
Table 12-3: Capital Cost Calculator using Minimum Cost Assumptions ............................................................ 132
Table 12-4: Capital Cost Calculator using Average Cost Assumptions .............................................................. 132
Table 12-5: Capital Cost Calculator using Maximum Cost Assumptions........................................................... 133
Table 12-6: Capital Cost Assumptions for the DC Cable Interconnections ...................................................... 133
![Page 15: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/15.jpg)
Hawaii Stage 2 Interconnection Study List of Acronyms
GE Energy Consulting xiii Final Report 5/21/2013
List of Acronyms $M Million Dollars AGC Automatic Gain Control BESS Battery Energy Storage System BTU British Thermal Unit CO2 Carbon Dioxide DC Direct Current GE General Electric International, Inc. GE MAPSTM GE Multi Area Production Simulation GE PSLFTM GE Positive Sequence Load Flow GW Gigawatt GWh Gigawatt Hours HC&S Hawaiian Commercial & Sugar HECO Hawaiian Electric Company HNEI Hawaii Natural Energy Institute HPOWER Honolulu Program of Waste Energy Recovery HVDC High-Voltage Direct Current IPP Independent Power Producer KW Kilowatt NOX Nitrogen Oxides MECO Maui Electric Company MMBTU Million British Thermal Units MW Megawatt MWh Megawatt Hours PPA Power Purchase Agreement PV Photovoltaic RE Renewable Energy RT Real Time Dispatch SCUC/EC Security Constrained Unit Commitment / Economic Dispatch SO2 Sulfur Dioxide VOC Variable Operation Cost
![Page 16: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/16.jpg)
Hawaii Stage 2 Interconnection Study Introduction
GE Energy Consulting 1 Final Report 5/21/2013
1 Introduction
1.1 Study Objectives and Approach
This study addresses the following objectives
1. To quantify the value of interconnecting three islands in Maui County (Maui, Lanai, Molokai) and operating them as one combined system.
2. To quantify the value of interconnecting the Oahu and Maui County grids and operating them as one combined system, considering several possible future scenarios with different mixes of renewable generation.
The analysis was performed using production simulation models of the Oahu and Maui power
system originally developed for the Oahu Wind and Transmission Integration Study (OWITS) and the
Hawaii Solar Integration Study (HSIS). Two base cases were developed for this study:
Oahu Base Case: Includes 100 MW wind generation and 100 MW solar PV resources on Oahu as
well as 200 MW wind generation on Lanai connected to Oahu by a dedicated 200 MW DC cable.
Maui County Base Case: Includes 15 MW distributed solar PV and three wind plants with
combined rating of 72 MW on Maui.
Note that between the commencement of this study and the time of publishing, the distributed PV
system on Maui had grown to over 25 MW, with an additional 1 MW on Lanai and 1 MW on Molokai.
Although this will cause absolute values in the report to deviate from reality, the overall findings
concerning comparison of scenarios are unchanged given the 12 MW increase in solar capacity.
Using the GE-MAPS production cost simulation tool, production costs (variable costs) were calculated
for the Oahu and Maui County systems operating separately (i.e., not interconnected). Production
costs were also calculated for the Oahu and Maui County systems operating as one interconnected
system. The study examined 10 scenarios for interconnected operation, with each scenario having a
different combination of wind, solar, and firm renewable energy resources. Four of the scenarios
included one 200 MW DC cable interconnecting Oahu and Maui County; six scenarios included two
200 MW DC cables.
The study also included cost-benefit analysis to assess the relative values of the renewable energy
resources in the scenarios. Benefits were calculated as reductions to system production costs
(primarily fuel and variable operating costs for thermal plants). Costs were calculated in two ways:
1. From estimates of the capital costs for new renewable energy resources and DC cable equipment, and
2. From a combination of actual and estimated PPA costs for renewable energy.
Although this study includes capital cost estimates for renewable capacity additions and DC cable
infrastructure, it does not include estimates for AC cable infrastructure between the Maui County
islands or the necessary capital costs for thermal generating unit or system upgrades required to
achieve the changes to operating practices discussed in Chapter 5.
![Page 17: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/17.jpg)
Hawaii Stage 2 Interconnection Study Introduction
GE Energy Consulting 2 Final Report 5/21/2013
1.2 Study Scope & Limitations
All modeling and forecasting research is limited by a variety of factors and is often constrained by
the accuracy of study inputs. It is neither possible nor necessary to have perfect economic
representation of the Oahu and Maui County power systems. On the other hand, it is necessary to
understand modeling assumptions and their impact on the study results. In cases where inputs or
assumptions are uncertain and may have a significant impact on results, this study attempted to
conduct sensitivity analyses to properly bound and “bookend” the problem. Throughout the study
period, HECO, HNEI and GE Energy Consulting worked together to formulate study scenarios and
sensitivities that reflect reasonable and rational future scenarios available for an interconnected
Hawaii System. However there are several important research items that are not contained in the
scope of this study and will not be addressed at this time. These include, but are not limited to, the
following items:
1. Not an Integrated Resource Plan (IRP): The objective of this study was to quantify various impacts of interconnecting the Oahu, Maui, Lanai, and Molokai power systems, with a focus on renewable energy penetration. This study is not intended to be an overall integrated resource plan for the islands and does not fully outline necessary plans, financial costs and implications associated with each scenario outlined. Instead, this study attempts to provide a high-level “bookend” analysis to identify potential mitigation strategies and options to be more fully investigated in future study work. The primary goal of this study was to establish how an interconnected system will work within the existing and future infrastructure, and it provides insights into the relative benefits of various mitigating options, including changes in the generation portfolio and operations that could improve system performance and economics.
2. Production Cost as the Critical Economic Metric: Throughout this report, the focus is on “variable operating cost”, also known as “production cost”. Production cost is NOT the total cost incurred to serve load, but rather it is the component of cost that varies with operation, and which can be affected by operating decisions. It includes the cost of fuel, the costs of starting and stopping plants, and the costs of operation and maintenance that vary with energy produced (variable O&M). Other costs are fixed and do not count towards production cost. The cost of capital for all plant and equipment is fixed. The cost of operation and maintenance independent of energy production (i.e. the cost that a plant incurs just to stay able to produce power) is fixed. While these costs may play a role in whether to invest in new plant or keep a plant in service, they play no role in operational decision making. Production cost also does NOT include the PPA price that HECO/MECO must pay to procure wind, solar and firm renewable energy. These energy sources are considered price takers with zero fuel cost and will always be accepted by the grid if possible, regardless of PPA prices. In addition, production cost does NOT include any capital costs associated with plant upgrades necessary to change operational practices.
3. Changes to existing operating routines: This study includes sensitivity analysis involving changes to the existing baseload unit operating schedules currently practiced in HECO’s grid operations. Changes to operating schedules will not be possible without plant and/or transmission modifications. This study does not describe, in detail, the necessary modifications required or the potential costs associated with those modifications. In addition, changes to unit minimums may not be technically feasible or economically justifiable.
![Page 18: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/18.jpg)
Hawaii Stage 2 Interconnection Study Introduction
GE Energy Consulting 3 Final Report 5/21/2013
4. HVDC Transmission Design: This study considers only the power transfer capability of HVDC
transmission lines. Further analysis will be required to assess HVDC short-circuit requirements, control design, and control stability for scenarios that are considered economically and operationally viable.
![Page 19: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/19.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 4 Final Report 5/21/2013
2 Inputs & Assumptions The Stage 2 Oahu-Maui Interconnection Study builds upon previous production simulation modeling
conducted for the Hawaii Solar Integration Study (HSIS) and the Oahu Wind Integration and
Transmission Study (OWITS). The MAPSTM production simulation models were utilized as the starting
point for the Stage 2 analysis. As a result, the underlying system parameters and unit characteristics
have been validated and benchmarked in great detail over many years and provide an accurate and
reliable simulation of the islands’ electric power grids.
The independent Maui County and Oahu models were merged together to form the interconnected
database. This section describes the many inputs and assumptions used throughout the production
simulation modeling, including system load, fuel prices, transmission, reserve strategy, wind and
solar profiles and unit characteristics.
2.1 Macroeconomic Assumptions
2.1.1 Load
The production simulation modeling performed in this study utilizes a weather normalized hourly
load shape for each area in the study system; Oahu, Maui, Molokai, and Lanai. Table 2-1 shows the
overall system load characteristics for each island. Oahu has the largest electricity load, with a peak
demand nearly six times larger than Maui and 86 percent of total system load. The Maui grid
constitutes much of the remaining load, with less than 1 percent of total system load from the Lanai
and Molokai systems. Table 2-1 shows summary load statistics by island used throughout the study.
Table 2-1: Summary of Load by Island
Oahu Maui Molokai Lanai Total
System
Net Energy for Load (GWh) 8,084 1,264 31 26 9,406
Peak Demand (MW) 1,263 210 5.9 5.0 1,473
Minimum Load (MW) 577 69 0.5 1.7 675
Average Load (MW) 923 144 3.5 3.0 1,074
Load Factor 73% 69% 60% 59% 73%
Percent of Total System Load 86% 13% 0.3% 0.3% 100%
Using hourly load shapes allows for detailed modeling of seasonal, weekly, and daily variation. The
temporal nature of load patterns is an important driver of system operation, especially when
combined with wind and solar profiles. Figure 2-1 shows the total system load, measured in energy,
and the total system peak demand for each month of the year.
![Page 20: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/20.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 5 Final Report 5/21/2013
Figure 2-1: Total System Load and Peak Demand by Month
Weekly and daily patterns are also important for system operation. Figure 2-2 shows the average
weekly load pattern and highlights the on-peak and off-peak nature of the weekdays and weekends.
Loads tend to be lower on Saturdays and Sundays when commercial and industrial users reduce
consumptions. In addition, the figure highlights the daily load profile as well. In general there is a
large morning load ramp occurring in the early morning hours (5:00 to 9:00 am), peak load occurring
just after 6:00 pm, and minimum loads occurring during the overnight periods. The cycling of load
profiles will be looked at in greater detail throughout the report, highlighting times of low system load
and potential curtailment.
Figure 2-2: Average Weekly Load Pattern
![Page 21: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/21.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 6 Final Report 5/21/2013
2.1.2 Fuel
Fuel price is one of the most important variables in production cost modeling and fuel consumption
typically accounts for the vast majority of total production cost. Table 2-2 lists the fuel price
assumptions used throughout the study. Fuel assignments to individual generating units can be
found in Section 2.4. The assumed prices represent HECO’s best estimate of fuel prices in 2015,
however fuel prices are particularly volatile and difficult to predict. As a result, several sensitivities
were run using various levels of fuel prices to demonstrate how potential changes to assumed fuel
prices impact system operation, total production cost and overall economic benefits. For more
information on fuel sensitivities, see Section 6.2.
Table 2-2: Fuel Prices (2015$/MMBtu)
The majority of the Oahu and Maui County thermal units use some derivative of fuel oil (distillate,
residual, diesel, etc.). AES is the only coal plant on the system and has a significantly lower fuel price
of $1.87 per MMBtu. This price makes the AES coal plant the most economic unit on the system.
2.1.3 Emissions Prices
Although the MAPSTM model has the ability to include emission prices in the production cost
optimization, this study does not include any emission policy, either through prices or emission caps.
However, this study recognizes the important policy implications of emission reductions and
quantifies the total system emissions of NOX, SOX and CO2 for each scenario. This will help grid
operators and policy makers quantify ancillary benefits associated with different operating regimes.
AES CoalBiodiesel
(CT1, DG)
Honolulu
LSFO
Kahe
LSFO
Kalaeloa
LSFO
Lanai
LSFO
Maui
HSFO
Maui
LSFO
Molokai
LSFO
Waiau
Diesel
Waiau
LSFO
1.87 42.57 17.35 16.82 17.38 27.08 14.81 23.09 24.65 21.88 16.82
![Page 22: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/22.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 7 Final Report 5/21/2013
2.2 Transmission
The production simulation modeling used throughout this study uses a full transmission, security
constrained economic dispatch model, however transmission outage contingencies were outside the
scope of this study. As a result, the MAPSTM model optimizes the system dispatch while taking into
account hourly limits on existing transmission infrastructure. To do this, the model utilizes a PSLFTM
solved load flow for the transmission topology. The load flows originated from other studies
conducted by GE Energy Consulting on the islands of Oahu, Maui, Lanai, and Molokai, and include all
transmission lines, generator busses, load busses, and significant transmission interfaces. The load
flows used throughout this study originated from two separate load flows from Maui County
(including AC connections between Lanai, Molokai and Maui) and Oahu. The separate load flows were
then connected via 1 or 2 DC cables depending on the scenario. As a result, a total of four PSLFTM
load flows were used throughout this study. The load flow assignment for each scenario is provided
in Table 2-3.
Table 2-3: Load Flow Assignment by Scenario
Maui County
Load Flow Oahu Load
Flow
Interconnect Load Flow
(1 DC Cable)
Interconnect Load Flow
(2 DC Cables)
Maui Only* X Maui County Base X Oahu Base X Scenario 1 X Scenario 1B X Scenario 1C X Scenario 3 X Scenario 2 X Scenario 4A X Scenario 4B X Scenario 4C X Scenario 4D X Scenario 4E X
*Note: The Maui only simulation without the AC connection of Lanai and Molokai was run using the Maui County Load Flow, with no generation or load assigned to the Lanai and Molokai areas.
For the purposes of this study, the DC cable was implemented unconstrained in the direction towards
Oahu. This allows the analysis to calculate the maximum rating necessary for the DC cables in each
of the study scenarios, rather than constraining flow on the lines to 200 MW. However, flow on the
DC cables is constrained to 30 MW in the opposite direction (from Oahu to Maui County). This
constraint is included to ensure that the single largest contingency on Maui County does not become
larger than 30 MW.
![Page 23: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/23.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 8 Final Report 5/21/2013
2.3 Existing Generation Mix
The baseline scenario used in this study includes the existing and expected future online generating
capacity for both Oahu and Maui County. Overall, the system is comprised of 2,536 MW of installed
capacity; 2,178 MW of which are on Oahu and 358 MW are on Maui County. The Maui County
capacity value includes the 11 MW of capacity on Lanai and 15 MW of capacity on Molokai.
Traditionally, the two systems have relied on thermal generators to provide the majority of all
electricity generation. In particular, generation is predominantly from burning oil fuels (diesel,
distillate oil, residual oil, etc.) due to resource constraints and reliance on imports. The only thermal
units that do not fit into this category are the AES coal plant on Oahu and a few biomass, biodiesel
and waste units throughout the system (Honua Power waste, HPower waste, Honolulu Airport
biodiesel, CIP CT-1 biodiesel, HC&S Sugar biomass plant).
Recent developments and new projects have greatly increased the amount of renewable generating
capacity on both Oahu and Maui. The Base Case in this study includes 100 MW of wind and 100 MW
solar on Oahu and an additional 72 MW of wind and 15 MW of solar on Maui. In addition, the Oahu
Base Case includes 200 MW of wind capacity on Lanai. Note that the 200 MW Lanai wind plant is
included in the Oahu Base case because the existing plan is for the plant to be electrically isolated
from the rest of the Lanai grid, with a direct DC link to Oahu. Also note that the 15 MW of distributed
solar on Maui represents the amount of solar anticipated when this study began. However, solar
installations on Maui have exceeded expectations and are already at 30 MW when this report was
published, with additional fast growth expected.
Figure 2-3 and Table 2-4 provide the capacity resource mix by fuel, in MW ratings and percentages,
for the existing and expected installed capacity included in the study’s Base Cases. “Oil” includes all
fuels derived from oil products (diesel, distillate oil, residual oil, etc.) and “Other” includes all biomass,
biodiesel and waste units.
Figure 2-3: Base Case Installed Capacity by Island, by Fuel
![Page 24: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/24.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 9 Final Report 5/21/2013
Table 2-4: Base Case Installed Capacity by Island, by Fuel (MW)
2.4 Thermal Plant Configurations
In order to accurately model the detailed system operation of the Oahu and Maui County grids, each
individual thermal generating unit is modeled according to its unique characteristics. Working closely
with HECO and MECO, GE developed individual unit specifications used throughout the study. This
section first defines the many different variables required by the model, and concludes with a table
outlining the characteristics for each unit. For detailed description of operating practices, refer to
Section 2.5. Table 2-5 and Table 2-6 summarize the following unit characteristics:
Unit Name: An eight-character MAPS unit name is assigned to each generating unit included in
the model. This is used throughout the analysis to identify individual units.
Plant Name: In instances where there are multiple generating units at a single plant, this field is
used to aggregate data and tabulate results.
Area: This field represents which system the generating unit is assigned to. In most cases, this is
the physical location and island of the unit. However in the case of the Lanai wind plant, the area
assignment is Oahu because it is electrically integrated with the Oahu grid in the base case. This
field is used for aggregating and summarized data only; it does not impact economic dispatch
because each unit is sited to an individual bus in the load flow.
Fuel: Each unit is assigned to a specific fuel type. Although multiple fuels assignments are
possible, this study only evaluated a single, primary fuel for each unit. The fuel assignment is
used to calculate emissions and total fuel cost. For more details on prices associated with each
fuel, please refer to Section 2.1.2.
Type: Each unit is also assigned to a unit type; Baseload, Cycling, or Peaking. Again, this field does
not impact utilization of the plant throughout the simulations, and is only used to aggregate and
summarize data throughout the report. The assignments were provided by HECO and are based
on historical and expected utilization.
Quick-Start: Quick-start units refer to units that can be started and ramped to full-load 10-
minutes. This feature is technology specific and is most often attributed to combustion turbines
or reciprocating diesel units. There are two stages in the MAPS production simulation model;
commitment and dispatch. The commitment sequence schedules the thermal units and
determines which ones must be available to provide at least their minimum power. The dispatch
sequence then determines how much power each unit will produce for a given hour. Quick-start
Oahu Maui Molokai LanaiTotal
System
Oil 1,393 233 15 11 1,652
Coal 185 0 0 0 185
Other 200 13 0 0 213
Wind 300 71 0 0 371
Solar 100 15 0 0 115
Total Island 2,178 332 15 11 2,536
![Page 25: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/25.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 10 Final Report 5/21/2013
units are ones that are always committed at 0 MW, and are available to reach full load within the
hour. These are the only units that have the ability to turn on during the dispatch sequence and
are vital to system operation to solve renewable forecast error.
Capacity: Each unit has a maximum capacity rating (MW). This represents the maximum amount
of power a given unit can produce.
Minimum Rating: Minimum rating refers to the minimum stable power output for each unit. The
number of MW between the minimum rating and maximum capacity represents the unit’s
operating range. In addition, once a unit is committed and online, it must operate at least at the
minimum powerpoint. For some units, the values listed in following table include MWs carried for
down-reserve regulation (see Section 2.7.2).
FLHR: Full-Load Heat Rate represents the total fuel consumption (btu) to produce a KWh of
energy while a unit is at its maximum power. Often this represents the most efficient point on the
unit’s average heat rate curve. Although not represented in this section, each unit also has a heat
rate curve allowing for varying levels of fuel consumption at each level of power output.
Start-Up Energy: Start-up energy, in mbtu, is the amount of fuel consumption required to start-
up a unit. If multiplied by the fuel cost, the resulting value represents the total start-cost for the
unit. This cost is applied every time the unit comes online.
Variable O&M: Variable operations and maintenance is also captured during the production cost
optimization. These values are dependent on the unit’s utilization and represent ancillary costs
associated with running a unit that are not fixed. This includes, but is not limited to, things such
as maintenance on turbine parts, water consumption, lubricating oils, etc. Two values are given
to each unit; one in dollars per MWh of energy produced, and the other in dollars per factor-fired
hour.
Min Down Time & Min Run Time: In order to constrain the operational flexibility of a unit, each
generator is given a minimum down time and minimum run time in hours.
Emissions Rates: Each unit is assigned an emission rate curve. The value included in the
following table is the emission rate for a unit operating at full capacity. Emission rates are
included for SOX, NOX and CO2. Although the emissions from each unit are tracked throughout
the study, there is no cost associated with the emissions, so this variable does not impact
utilization or production cost.
Forced Outage Rate: In order to account for unexpected and random generator outages, each
unit is given a forced outage rate dictating the amount of time that the unit is unavailable to
produce energy. For this study, the forced outage rates are a five year average of historical
outages. This outage rate is in addition to any planned or scheduled maintenance or fixed
operating schedules (outlined in Section 2.5.2).
![Page 26: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/26.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 11 Final Report 5/21/2013
Table 2-5: Oahu Thermal Unit Characteristics
*Note: Units modeled with a minimum rating of 0 MW do not actually have a minimum load of 0 MW. Instead, the units are modeled in this way to act as quick-start
generators, which are “online” at 0 MW and ready to be dispatched to full-load during the dispatch process. For more information, see Section 2.5.3.
**Note: The H Power and Honua Waste unit are modeled on a fixed generation schedule. For more information, see Section 2.5.4.
Unit Name Plant Name Area Fuel TypeQuick
Start
Capacity
(MW)
Minimum
Rating
(MW)
FLHR
(btu/kwh)
Start Up
Energy
(mbtu)
Variable
O&M
($/MWh)
Variable
Cost
($/hr)
Min Down
Time (hrs)
Min Run
Time (hrs)
Forced
Outage
Rate
SOX Rate
(lbs/MWh)
NOX Rate
(lbs/MWh)
CO2 Rate
(lbs/MWh)
Percent Spin
Contribution
HONH8 Honolulu Oahu Honolulu LSFO Cycling N 53.4 22.3 11,264 190.30 0.32 0.00 5 3 15.1% 4.73 5.21 2,074 100%
HONH9 Honolulu Oahu Honolulu LSFO Cycling N 54.4 22.3 11,399 190.30 0.32 0.00 5 3 15.1% 4.51 5.20 1,957 100%
WAIW3 Waiau Oahu Waiau LSFO Cycling N 46.6 22.3 11,903 337.44 0.32 0.00 5 3 15.0% 4.34 5.29 1,575 100%
WAIW4 Waiau Oahu Waiau LSFO Cycling N 46.6 22.3 11,832 337.44 0.32 0.00 5 3 12.0% 4.35 5.05 2,135 100%
WAIW5 Waiau Oahu Waiau LSFO Cycling N 54.5 22.5 11,526 276.67 0.32 0.00 5 3 4.7% 4.69 4.88 1,902 100%
WAIW6 Waiau Oahu Waiau LSFO Cycling N 53.5 22.5 11,617 276.67 0.32 0.00 5 3 4.7% 4.70 4.82 2,074 100%
WAIW7 Waiau Oahu Waiau LSFO Baseload N 82.9 32.0 10,600 5,044.06 0.32 0.00 1 0 5.2% 3.10 4.02 1,740 100%
WAIW8 Waiau Oahu Waiau LSFO Baseload N 86.1 32.0 10,205 5,044.06 0.32 0.00 1 0 5.2% 2.83 4.02 1,724 100%
WAIW9 Waiau Oahu Waiau Diesel Peaking Y 52.9 0.0 13,115 36.04 0.00 99.19 1 0 10.9% 22.51 1.50 2,730 0%
WAIW10 Waiau Oahu Waiau Diesel Peaking Y 49.9 0.0 12,499 32.60 0.00 99.19 1 0 10.9% 21.98 1.44 2,949 0%
KAHK1 Kahe Oahu Kahe LSFO Baseload N 82.1 41.5 10,100 5,044.06 0.32 0.00 1 0 3.6% 4.61 4.21 1,716 100%
KAHK2 Kahe Oahu Kahe LSFO Baseload N 82.1 41.7 9,914 5,044.06 0.32 0.00 1 0 3.6% 3.88 4.23 1,712 100%
KAHK3 Kahe Oahu Kahe LSFO Baseload N 86.1 41.3 9,702 5,044.06 0.32 0.00 1 0 5.2% 2.92 4.20 1,636 100%
KAHK4 Kahe Oahu Kahe LSFO Baseload N 85.3 41.3 9,927 5,044.06 0.32 0.00 1 0 5.2% 2.97 4.19 1,582 100%
KAHK5 Kahe Oahu Kahe LSFO Baseload N 134.3 59.7 9,691 4,586.43 0.32 0.00 1 0 3.2% 4.35 4.15 1,729 100%
KAHK6 Kahe Oahu Kahe LSFO Baseload N 134.4 59.0 10,059 9,274.24 0.32 0.00 1 0 2.1% 1.79 4.17 1,464 100%
KALKAL1 Kalaeloa CC Oahu Kalaeloa LSFO Baseload N 90.0 69.5 8,585 0.00 0.00 0.00 5 0 1.5% 2.84 2.53 996 100%
KALKAL2 Kalaeloa CC Oahu Kalaeloa LSFO Baseload N 90.0 69.5 8,585 0.00 0.00 0.00 5 0 1.5% 2.84 2.53 996 100%
KALKAL3 Kalaeloa GT Oahu Kalaeloa LSFO Baseload N 28.0 0.1 8,651 0.00 0.00 0.00 1 0 1.5% 4.05 3.62 1,422 0%
AES AES Coal Oahu AES Coal Baseload N 185.0 72.0 17,313 0.00 0.00 0.00 1 0 1.5% 1.84 1.24 3,482 100%
HPOWER H Power Oahu Waste Baseload N 73.0 46.0 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 0%
CIPCT1 CIP CT Biodiesel Oahu Biodiesel Peaking Y 113.0 0.0 11,688 126.00 40.76 0.00 1 0 15.0% 1.51 3.63 1,417 0%
AIRDSG8 Airport DSG Oahu Biodiesel Peaking Y 8.0 0.0 10,205 126.00 37.46 0.00 1 0 0.0% 1.51 3.63 1,417 0%
HONUA Honua Waste Unit Oahu Waste Baseload N 6.0 6.0 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 0%
![Page 27: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/27.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 12 Final Report 5/21/2013
Table 2-6: Maui County Thermal Unit Characteristics
*Note: Units modeled with a minimum rating of 0 MW do not actually have a minimum load of 0 MW. Instead, the units are modeled in this way to act as quick-start
generators, which are “online” at 0 MW and ready to be dispatched to full-load during the dispatch process. For more information, see Section 2.5.3.
Unit Name Plant Name Area Fuel TypeQuick
Start
Capacity
(MW)
Minimum
Rating
(MW)
FLHR
(btu/kwh)
Start Up
Energy
(mbtu)
Variable
O&M
($/MWh)
Variable
Cost
($/hr)
Min Down
Time (hrs)
Min Run
Time (hrs)
Forced
Outage
Rate
SOX Rate
(lbs/MWh)
NOX Rate
(lbs/MWh)
CO2 Rate
(lbs/MWh)
Percent Spin
Contribution
X1 Maalaea X Maui Maui LSFO Peaking Y 2.5 0.0 10,288 0.80 0.51 28.49 1 1 8.5% 1.87 34.22 1,729 0%
X2 Maalaea X Maui Maui LSFO Peaking Y 2.5 0.0 10,288 0.80 0.51 28.49 1 1 8.5% 1.90 34.37 1,740 0%
M1 Maalaea Maui Maui LSFO Peaking Y 2.5 0.0 10,288 0.80 0.51 28.49 1 1 8.5% 1.89 20.87 1,754 0%
M2 Maalaea Maui Maui LSFO Peaking Y 2.5 0.0 10,288 0.80 0.51 28.49 1 1 8.5% 1.97 22.83 1,772 0%
M3 Maalaea Maui Maui LSFO Peaking Y 2.5 0.0 10,288 0.80 0.51 28.49 1 1 8.5% 1.87 34.25 1,732 0%
M4 Maalaea Maui Maui LSFO Cycling N 5.5 0.0 10,149 5.05 1.57 21.59 1 1 1.8% 1.93 34.74 1,758 0%
M5 Maalaea Maui Maui LSFO Peaking Y 5.5 1.9 10,149 5.05 1.57 21.59 1 1 1.8% 1.91 46.66 1,769 66%
M6 Maalaea Maui Maui LSFO Cycling N 5.5 0.0 10,149 5.05 1.57 21.59 1 1 1.8% 1.97 35.61 1,803 0%
M7 Maalaea Maui Maui LSFO Peaking N 5.5 1.9 10,149 5.05 1.57 21.59 1 1 1.8% 1.89 64.01 1,816 66%
M8 Maalaea Maui Maui LSFO Cycling N 5.5 1.9 9,848 12.71 0.84 36.57 1 1 0.7% 1.91 34.33 1,737 0%
M9 Maalaea Maui Maui LSFO Cycling N 5.5 1.9 9,848 12.71 6.29 26.69 1 1 0.7% 1.87 34.33 1,737 0%
M10 Maalaea Maui Maui LSFO Cycling N 12.3 5.9 9,323 43.49 0.51 85.27 2 1 0.5% 1.82 29.64 1,676 36%
M11 Maalaea Maui Maui LSFO Cycling N 12.3 5.9 9,323 43.49 0.51 85.27 2 1 0.5% 1.77 35.08 1,627 36%
M12 Maalaea Maui Maui LSFO Cycling N 12.3 5.9 9,323 41.61 0.51 85.27 2 1 0.5% 1.73 19.35 1,606 36%
M13 Maalaea Maui Maui LSFO Cycling N 12.3 5.9 9,323 41.61 0.51 85.27 2 1 0.5% 1.73 19.35 1,616 36%
M141516 Maalaea CC Maui Maui LSFO Baseload N 53.0 35.0 8,494 233.00 0.35 116.46 13 1 0.3% 1.24 0.91 1,222 20%
M1718 Maalaea CC Maui Maui LSFO Baseload N 27.1 18.5 9,210 233.00 0.69 213.76 11 1 0.7% 1.12 0.77 1,098 20%
M171819 Maalaea CC Maui Maui LSFO Baseload N 52.8 41.6 7,432 233.00 0.35 106.88 11 1 0.7% 1.14 0.83 1,119 20%
K1 Kahului Maui Maui HSFO Baseload N 4.7 2.3 15,445 36.29 1.41 0.14 7 1 0.0% 31.35 6.27 2,822 0%
K2 Kahului Maui Maui HSFO Baseload N 4.8 2.3 15,551 36.29 1.43 0.14 7 1 0.0% 30.23 6.19 2,787 0%
K3 Kahului Maui Maui HSFO Baseload N 11.0 7.0 13,249 279.34 1.25 0.14 12 1 0.0% 1.00 1.00 2,201 0%
K4 Kahului Maui Maui HSFO Baseload N 11.9 7.0 13,786 279.34 1.35 0.14 12 1 0.0% 26.80 4.91 2,428 0%
HC&S Hawaii Commercial and Sugar Maui Biomass Baseload N 13.0 9.0 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 0%
GEN_LAN1 Lanai Generation 1 Lanai Lanai LSFO Peaking Y 1.0 0.0 13,469 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN2 Lanai Generation 2 Lanai Lanai LSFO Peaking Y 1.0 0.0 13,155 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN3 Lanai Generation 3 Lanai Lanai LSFO Peaking Y 1.0 0.0 10,351 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN4 Lanai Generation 4 Lanai Lanai LSFO Peaking Y 1.0 0.0 11,897 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN5 Lanai Generation 5 Lanai Lanai LSFO Peaking Y 1.0 0.0 12,744 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN6 Lanai Generation 6 Lanai Lanai LSFO Peaking Y 1.0 0.0 12,342 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN7 Lanai Generation 7 Lanai Lanai LSFO Peaking Y 2.2 0.0 9,914 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LAN8 Lanai Generation 8 Lanai Lanai LSFO Peaking Y 2.2 0.0 9,957 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_LANM Lanai Monele Bay CHP Lanai Lanai LSFO Peaking Y 0.8 0.0 9,877 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL1 Molokai Generation P1 Molokai Molokai LSFO Peaking Y 1.3 0.0 11,579 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL2 Molokai Generation P2 Molokai Molokai LSFO Peaking Y 1.3 0.0 11,403 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL3 Molokai Generation P3 Molokai Molokai LSFO Peaking Y 1.0 0.0 11,544 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL4 Molokai Generation P4 Molokai Molokai LSFO Peaking Y 1.0 0.0 11,591 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL5 Molokai Generation P5 Molokai Molokai LSFO Peaking Y 1.0 0.0 12,136 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL6 Molokai Generation P6 Molokai Molokai LSFO Peaking Y 1.0 0.0 11,192 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL7 Molokai Generation P7 Molokai Molokai LSFO Peaking Y 2.2 0.0 9,688 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL8 Molokai Generation P8 Molokai Molokai LSFO Peaking Y 2.2 0.0 9,456 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOL9 Molokai Generation P9 Molokai Molokai LSFO Peaking Y 2.2 0.0 9,809 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
GEN_MOLS Molokai Generation Solar CT Molokai Molokai LSFO Peaking Y 2.2 0.0 17,890 0.80 4.00 0.00 1 0 3.0% 1.51 3.63 1,417 0%
![Page 28: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/28.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 13 Final Report 5/21/2013 Final Report 4/30/2013
2.5 Operating Practices
2.5.1 Fixed Operating Schedules
Oahu and Maui systems have several baseload power plants. In this report these units are also
referred to, interchangeably, as must-run and fixed operating schedule units. The baseload units are
generally the largest and most efficient units to operate and are economically dispatched to meet
system load. These plants were not designed to be cycled on and off on a daily basis, and have
therefore been historically operated 24 hours per day. In the model simulations, the units are always
running at least at their minimum output plus the required down reserve and are unable to be turned
off except for planned or unplanned outages. This is required to ensure appropriate down-reserves,
voltage support and frequency, which cannot be modeled directly using the production simulation
software.
On Oahu, the baseload units include AES, Kalaeloa CC, and Kahe 1-6. In addition, Waiau 7 and 8 are
required to support the Oahu transmission system voltage between the generation area in the
southwest and the load are in the southeast. In addition, several units followed fixed daily or weekly
schedules of availability;
Kalaeloa CC: The Unit 1 GT (KALKAL1) is taken down every week from 9pm on Friday to 9am on Saturday for wash and maintenance and Unit 2 GT (KALKAL2) is taken down from 9pm on Saturday to 9am on Sunday.
The Airport Biodiesel unit (AIRDSG8) is taken down and is unavailable all day Saturday and Sunday each week.
Honolulu 8 & 9 are unavailable each night during off-peak hours from 11pm to 8am.
On Maui the fixed operating schedules include M141516 or M1718 or M1819, K3 and K4. In addition,
K1 and K2 were assumed to be must-run during the hours of 2pm and 11pm daily and alternate
operation daily. Additional operating constraints for the Maalaea plant were also captured. M4 – M9
were assumed to be unavailable nightly from 11pm to 7am. These fixed operating schedules are only
an approximation of the actual operating schedules used by grid operators, which typically vary day-
by-day depending on real-time system loads and other needs.
In future operating scenarios with high levels of renewable penetration, conventional baseload units
may need to be cycled more than historical operations. As a result, investing in system or unit
modifications to remove the operating constraints highlighted above may lead to reduced renewable
curtailment, and lower operating costs. However, the capital costs associated with the required
modifications need to be weighed against the benefits from reduced production costs. In order to
simulate modified operating schemes, sensitivity analyses were conducted by modifying the fixed
operating schedules. For more information on these sensitivities, see Chapter 5.
2.5.2 Planned Outages and Maintenance Schedules
In addition to the random and forced outages highlighted in Section 2.4 and the weekly availability
schedules highlighted in Section 2.5.1, the production simulation modeling includes extended
outages for planned unit maintenance and overhaul. Typically these extended outages take multiple
weeks to complete and are important assumptions when modeling grid operations. The planned
maintenance schedules can be found in the Table 2-7. In addition, Table 12-1 and Table 12-2 in the
![Page 29: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/29.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 14 Final Report 5/21/2013 Final Report 4/30/2013
appendix provide a complete weekly outage schedule for the system, including all planned, forced,
and random outages.
Table 2-7: Planned Maintenance Schedule
2.5.3 Quick-Start Capability
In the production simulation modeling, a unit must be committed in the commitment process in
order to be online and available to serve load during the real-time (RT) dispatch process. Once
committed the units must be dispatched at least at their minimum load level. An exception to this
rule is made for quick-start capable plants. In the production simulation modeling, these units (also
referred to as peakers) are ones that can be started and brought to full load in at least 10 minutes.
The peaking units are available during the RT dispatch by committing them each hour and assuming
a minimum load of zero for these units, even if not actually committed during the scheduling process.
This modeling allows the peaking units to alleviate problems associated with forecast error from
renewables. For example, if 200 MW of wind energy is expected to show up during an hour, the
commitment process will take that forecast into account. However, if only 100 MW of wind shows up
during the RT dispatch process, then the system is short by 100 MW. The peaking units are the only
ones available to make up that discrepancy in real-time. As a result, the peaking units are likely to
operate a very few number of hours, but are crucial to accurately modeling high renewable
scenarios. For a list of units that are quick-start capable, see Table 2-5 and Table 2-6.
UnitNumber of
WeeksDates Unit
Number of
WeeksDates
CIPCT1 0.7 April 26th to May 1st M1 2.6 January 1st to January 19th
HONH8 7.6 May 3rd to June 26th M2 2.6 February 1st to February 19th
HONH9 1.6 March 29th to April 10th M3 7.9 February 1st to March 26th
KAHK1 1.7 February 15th to February 27th M10 7.6 September 1st to October 24
KAHK2 1.7 January 18th to January 30th M11 7.4 July 1st to August 23rd
KAHK3 14.4 August 16th to November 27th M141516 3.7 April 1st to April 27th
KAHK4 3.6 July 12th to August 7th M171819 3.6 May 1st to May 26th
KAHK5 17.4 March 8th to July 10th M1718 1.6 May 1st to May 12th
KAHK6 1.4 January 4th to January 14th K1 3.6 November 1st November 26th
KALKAL1 1.9 February 1st to February 14th K2 3.6 January 1st to January 26th
KALKAL2 4.1 February 8th to March 7th K3 3.6 June 1st to June 26th
KALKAL3 5.1 February 1st to March 7th K4 3.6 March 1st to March 26th
WAIW10 6.6 March 8th to April 24th
WAIW3 1.7 March 15th to March 27th
WAIW4 1.7 May 3rd to May 15th
WAIW5 2.4 August 2nd to August 19th
WAIW6 2.4 September 6th to September 23rd
WAIW7 1.7 January 18th to January 30th
WAIW8 5.7 November 1st to December 10th
WAIW9 0.6 October 26th to October 30th
Oahu Unit Planned Maintenance Maui Unit Planned Maintenance
![Page 30: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/30.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 15 Final Report 5/21/2013 Final Report 4/30/2013
2.5.4 Independent Power Producers
On the Oahu and Maui County systems a variety of Independent Power Producers (IPPs) provide
energy to the grid based on existing operating agreements, independent of economic dispatch.
These units also do not add to total production costs.
HC&S: Between the hours of 7am to 9pm Monday through Saturday, HC&S provides a constant 13 MW of energy. During the hours of 9pm and 7am, and all day Sunday, HC&S provides 9 MW of energy.
HPower: Modeled to follow a fixed dispatch schedule of 73 MW every hour.
Honua Waste: modeled to follow a fixed dispatch schedule of 6 MW every hour.
In addition, the AES and Kalaeloa plants are IPPs, but their cost structure is included in the economic
dispatch. Therefore, the AES and Kalaeloa plant’s utilization is determined based on the model’s
production cost optimization.
2.5.5 Combined Cycle Plant Modeling
The two combined cycle plants on the system, Kalaeloa CC on Oahu and Maalaea CC on Maui, are
modeled with unique configurations in order to simulate actual operation. Kalaeloa was modeled as
three separate units; Unit 1 (CT + ½ ST) rated for 67-90 MW, Unit 2 (CT + ½ ST) rated for 67-90 MW,
and Unit 3 rated for 28 MW and only available when Units 1 and 2 are operating at max capacity. In
addition, Kalaeloa operates in single train mode (67-90 MW) for at least five hours before starting
dual train mode (134-180 MW). The heat rate curves for Units 1 and 2 were based on the dual-train
configuration efficiency. This was necessary to accurately capture the heat rate of the plant when
the two units are both in operation (i.e. dual-train combined cycle configuration). As a result, when
the individual units are operated independently, actual heat rate is expected to be higher (less
efficient operation) than the model results may suggest.
On Maui, the Maalaea CC units are also modeled with a unique configuration. The combined cycle
plant was broken into three sets of units; M141516, M1718 and M171819. M141516 is modeled as a
single 53 MW unit, available all of the time. The rest of the combined cycle plant is modeled as two
separate groups of units. M171819 is modeled as a 52.8 MW unit that is available only during on-
peak hours. During off-peak hours the unit is composed only of M1718, with an available capacity of
27.1 MW. This allows the model to accurately simulate the cycling utilization of the CC plant.
![Page 31: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/31.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 16 Final Report 5/21/2013 Final Report 4/30/2013
2.6 Wind & Solar Plants
Included in the Oahu base case is 100 MW of wind, 100 MW of solar, plus the 200 MW of wind
located on Lanai. On Maui there is 72 MW of wind and 15 MW of solar. Table 2-8 shows the installed
wind and solar capacity in the Base Case. See Chapter 3 for a discussion about renewable additions
in future scenarios. The second column shows the plants total installed capacity, the third column
shows the available capacity factor, while the fourth column shows the annual available energy.
Available energy represents the maximum potential energy the plant can produce in a single year,
assuming no curtailment. The annual energy was developed using hourly wind and solar profiles
discussed in the following section. Centralized solar represents solar units that can be controlled by
the grid operators whereas distributed solar cannot be dispatched or curtailed.
Table 2-8: Base Case Wind & Solar Plants
2.6.1 Wind & Solar Profiles
Unlike thermal plants, wind and solar plants are modeled as load modifiers. This means that each
wind and solar plant is given an “8760” hourly profile based on resource availability. The wind and
solar profiles were provided by AWS Truepower and used in previous modeling work for Hawaii
including the Hawaii Solar Integration Study (HSIS) and the Oahu Wind Integration and Transmission
Study (OWITS). AWST provided 10-minute and 2-second datasets for modeled wind and solar plants
based on observed weather patterns in 2007 and 2008. Both the 10-minute and 2-second datasets
were used for developing the operating reserve requirements necessary to cover expected wind and
solar variability (see the following section for more information on the reserve analysis). After the
reserve analysis was completed, data was then aggregated into hourly data for use in the production
simulation model. Each wind and solar plant was given a unique operating profile, which was held
constant throughout the study period.
Capacity
(MW)
Available
Capacity
Factor
Available
Energy
(GWh)
Capacity
(MW)
Available
Capacity
Factor
Available
Energy
(GWh)
Kawailoa Wind 70 42% 255 KWP I Wind 30 49% 129
Kahuku Wind 30 39% 103 KWP II Wind 21 49% 90
Lanai Wind Addition 200 52% 902 Auwahi Wind 21 48% 88
Oahu Centralized Solar 60 22% 117 Maui Distributed Solar 15 19% 25
Oahu Distributed Solar 40 18% 63
Total Wind 300 48% 1260 Total Wind 72 49% 307
Total Solar 100 21% 180 Total Solar 15 19% 25
Oahu Wind & Solar Maui County Wind & Solar
![Page 32: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/32.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 17 Final Report 5/21/2013 Final Report 4/30/2013
2.6.2 Forecasting
Each wind and solar plant is also given a 4-hour forecast profile for each hour of the year
representing the expected wind and solar resource availability in MW. The forecast is used during the
commitment process to schedule the thermal fleet. A 4-hour forecast was used for wind and solar
plants because the commitment of cycling units requires about a 4-hour advance notice.
Figure 2-4 shows the aggregated hourly forecast and real-time energy profiles of each wind and
solar plant for a week with high wind penetration. These represent the input shapes only, not actual
dispatched energy, which may vary due to curtailment.
Figure 2-4: Weekly Snapshot of Wind & Solar Forecast and Real-Time Profiles
During the dispatch process separate real-time wind and solar profiles are used. Due to the
variability in wind and solar forecast error, the thermal units are committed against a net load profile
that is determined by the system load profile and the forecasted wind and solar resource profiles.
Figure 2-5 shows an annual duration curve of forecast error in Scenario 1 and Scenario 7. Positive
forecast errors represent hours where the actual, real-time, wind and solar available energy is
greater than the forecasted energy. Negative forecast errors represent hours where the actual, real-
time, wind and solar available energy is less than the forecast energy.
Figure 2-5: Wind & Solar Forecast Error Duration Curves between Scenario 1 and 7
![Page 33: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/33.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 18 Final Report 5/21/2013 Final Report 4/30/2013
Positive forecast error is less problematic from a grid stability perspective because a worst-case
scenario only causes additional curtailment due to over-commitment. The result of this is captured
as lost economic value, but the grid remains stable. The negative forecast error is potentially more
problematic because it could represent time periods of under-commitment. In this scenario, thermal
units must make up the shortfall in wind and solar generation. As a result, there must be enough up-
range on the operating units, or additional quick-start capacity for the grid to operate.
2.6.3 Curtailment
As zero variable cost resources, wind and solar energy is always utilized if possible. However, there
are times when accepting all of the available wind and solar energy is not possible due to constraints
on the system. These constraints could include fixed operating schedules, operating reserve
requirements, down-regulation requirements, transmission limits, and excess commitment due to
forecast error. When all available wind and solar energy for a given hour cannot be accepted by the
grid, the system will curtail (spill) excess wind and solar energy. From a total curtailment standpoint, it
does not matter which individual wind or solar plant is curtailed first, but for the purposes of this
study a predefined curtailment order is used in order to assess the impact of curtailment on each
project.
Table 2-1 shows the curtailment order for all scenarios analyzed. When curtailment is required, units
with a lower curtailment order will be curtailed first. If curtailment is required from more than one
plant, the model will select the next wind or solar plant with available energy. The curtailment order
listed in Table 2-9 is based on current contractual terms or assumptions made for future resources.
Note that the Lanai and Molokai wind units have the same curtailment order, which will result in
equal curtailment across the wind plants. In addition, distributed, roof-top solar and the firm
renewable energy cannot be curtailed. Curtailment is discussed in detail throughout this report;
please see following chapters for a more detailed discussion.
Table 2-9: Wind and Solar Curtailment Order
Note: Small hydro and FIT projects were not modeled in this study.
Unit ScenarioCurtailment
Order
Maui 100 MW Wind Addition Scen 8 - 10 1
Molokai 200 MW Wind Addition Scen 5 - 10 2
Lanai 200 MW Wind Addition Scen 1 - 10 2
Oahu Centralized Solar Scen 1 - 10 3
KWP II Wind Scen 1 - 10 4
Kawailoa Wind Scen 1 - 10 5
Auwahi Wind Scen 1 - 10 6
KWP I Wind Scen 1 - 10 7
Kahuku Wind Scen 1 - 10 8
Oahu Distributed Solar Scen 1 - 10 N/A
Maui Distributed Solar Scen 1 - 10 N/A
Maui Firm Renewable Addition Scen 2,3,6,7,9,10 N/A
![Page 34: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/34.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 19 Final Report 5/21/2013 Final Report 4/30/2013
2.7 Reserves
2.7.1 Up Reserve Requirements
The production simulation modeling takes into account operating reserve constraints to simulate the
precautions a grid operator takes to prepare for unexpected events such as a generator trip or
variation in wind and solar resource availability. Current practice requires that all operating reserves
on the Hawaii system be covered by traditional thermal sources. The production cost simulations
ensure that for any given hour the required operating reserves are being carried by the system’s
thermal fleet based on the wind and solar forecast. The total reserve scheme is defined by several
different components:
1. Contingency Reserve: MWs to cover for the largest system contingency 2. Operating Reserve: MWs to cover for the variability of wind and solar power, including both
spinning and non-spinning reserves, a. Spinning Reserve: Available headroom (MWs) from committed thermal units, which
are considered available immediately when needed and automatically controlled by governor and AGC.
b. Non-spinning Reserve: Available MWs capacity from quick-start units; the availability is dependent on the reaction time of operator to physically start the units and is limited by start-up time and ramp rate of the units.
Based on the above definitions, two important equations can be formulated:
(2-1)
(2-2)
The contingency reserves outlined above are fairly straightforward and practiced across the industry.
For the Oahu system, the single largest contingency is the loss of AES generator at 185 MW. In
scenarios with the DC cable, the largest contingency may change to the flow on the DC cable.
However, since the flows on the DC cables are less than 200 MW during most hours of the year, the
185 MW contingency was deemed an appropriate approximation to continue throughout this study.
On the Maui County system the single largest contingency is currently NOT covered with contingency
reserves due to the additional costs required to do so. Instead, the Maui County system uses a load-
shedding scheme to cover large contingencies.
Operating reserves represent a much more complicated form of reserves and one that is less
consistently applied across the industry. As seen in Equation 2-2, operating reserves are required to
be larger than the expected renewable variation. This variation is a function of power output and is
dependent on the time interval of consideration. This study developed operating reserve
requirements based on the drops in wind and solar output over multiple time windows up to one
hour. The operating reserves assumed in this study are designed to capture 99.9% of the sub-hourly
drops in wind and solar output.
The reserve strategy is dependent on the hourly wind and solar variability. As a result, each scenario
has a specific reserve requirement based on the scenario’s installed renewable capacity. For more
discussion on the reserve strategy for each scenario, see Section 3.4.
![Page 35: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/35.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 20 Final Report 5/21/2013 Final Report 4/30/2013
2.7.2 Down Reserve Requirements
Adequate down reserves are required to provide the necessary operating range on thermal units in
the event that they must decrease their output in response to a loss of load contingency event. These
reserves are classified as contingency reserves for load rejection on the system. HECO performed an
analysis of Oahu feeder loading and previous load rejection events and determined that up to 140
MW could be lost during a single daytime event and 90 MW could be lost as night. Currently, all
down-reserves are carried by traditional thermal generators. On Oahu, the operating practice
modeled in this study requires that in hours when the thermal units may be backed down (especially
during off-peak periods), the system operators will always ensure that the total dispatched output is
at least 90 MW greater than their minimum power level. For Maui County, the total down reserves
carried is 7 MW during all hours.
In order to capture the down regulation requirements of the HECO and MECO systems, generating
unit dispatch minimums were increased above the minimum power limit. On Oahu, the 90 MW down
reserve requirement is distributed equally across nine units (AES, Kahe #1-6, Waiau 7&8, and
Kalaeloa). For example, the Kahe 1 unit on Oahu is able to turn down to 32.5 MW, however the
minimum dispatch power the generator can produce in the simulations 41.5 MW, thus ensuring that
when the unit is online, it is providing at least 9 MW of down reserves. For Maui County the down
reserves are carried at the Maalaea combined cycle plant. The total amount of down reserves carried
by unit is listed in Table 2-10 for Oahu and Maui County.
Table 2-10: Down Reserves by Unit
In current grid operations on Oahu, the amount of down-reserves is typically not problematic
because thermal units rarely sit at, or close to, their minimum power level. However, in a future
scenario with high wind or solar penetration, carrying adequate down-reserves is more important
because thermal generators will be backed down in an effort to accept more renewable generation.
The impact of operating the thermal generating fleet at their minimum levels during most hours of
the year was not assessed in this study. This could result in more O&M expense as well as changes in
operating practice such as ramping baseload units to their maximum levels occasionally to avoid
clogging of exhaust systems. It is likely that in a high renewable scenario, the down reserve
requirement may be a binding constraint during many hours of the year. Investing in system or unit
modifications to remove this constraint could result in potentially lower costs associated with system
Unit Name
Technical
Minimum
Power
Down
Regulation
Min Capacity
with Down
Regulation
Unit Name
Technical
Minimum
Power
Down
Regulation
Min Capacity
with Down
Regulation
AES 63.0 9.0 72.0 M14, M15, M16 34.0 1.0 35.0
Kahe 1 32.5 9.0 41.5 M17, M18 16.5 2.0 18.5
Kahe 2 32.7 9.0 41.7 M17, M18, M19 37.8 4.0 41.8
Kahe 3 32.3 9.0 41.3
Kahe 4 32.3 9.0 41.3
Kahe 5 50.7 9.0 59.7
Kahe 6 50.0 9.0 59.0
Waiau 7 23.0 9.0 32.0
Waiau 8 23.0 9.0 32.0
Kalaeloa 1 65.0 4.5 69.5
Kalaeloa 2 65.0 4.5 69.5
Oahu Down Reserves (Total = 90 MW) Maui County Down Reserves
![Page 36: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/36.jpg)
Hawaii Stage 2 Interconnection Study Inputs & Assumptions
GE Energy Consulting 21 Final Report 5/21/2013 Final Report 4/30/2013
operation, however the cost of the system or unit modifications must be weighed against the
benefits associated with reduced operating cost. To account for this, sensitivity analyses were
conducted in order to demonstrate the economic benefits associated with lower minimum turndown
levels. For more information on relaxing the down reserve requirements, refer to Chapter 5.
![Page 37: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/37.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 22 Final Report 5/21/2013 Final Report 4/30/2013
3 Scenario Overview The objective of this study is to quantify and compare the operational performance and costs of the
combined Oahu and Maui County system under a variety of possible future expansion scenarios.
Renewable energy alternatives include Wind, Solar and Firm Renewables (i.e. Geothermal) in various
combinations. As initial results were analyzed new combinations were considered. The final list of
scenarios was then reorganized and is presented here in a more logical, orderly fashion.
3.1 Renewable Capacity Additions
Scenario 1 closes the interconnection between the two Base Cases (Oahu and Maui County) to
determine the impact of the combined operation of the two systems. All other scenarios build onto
this initial interconnected system. The base operating assumptions are held through the initial
analysis presented in Chapter 4. Chapter 5 then examines the impact of changes to some of the
operational practices.
Table 3-1 shows the list of renewable capacity additions for the ten scenarios developed. Scenarios
1 through 4 have a single HVDC connection between Oahu and Lanai, nominally 200 MW, along with
the 200 MW wind plant on Lanai. Scenarios 2 and 3 add 50 and 100 MW respectively of firm
renewable energy in Maui to the initial Scenario 1. Scenario 4 adds 260 MW of solar capacity on
Oahu to Scenario 1.
Table 3-1: Renewable Capacity (MW)
Scenarios 5 through 10 have two HVDC connections between Oahu and Maui County along with 200
MW of wind generation on both Lanai and Molokai. Scenario 8 adds an additional 100 MW of wind
generation on Maui. The remaining scenarios add the 50 MW and 100 MW firm renewable to
Scenarios 5 and 8 respectively. Figure 3-1 and Figure 3-2 show the capacity additions graphically.
Lanai Molokai
ScenarioOahu-
Lanai
Oahu-
Molokai
Wind
(MW)
Solar
(MW)
Firm RE
(MW)
Wind
(MW)
Solar
(MW)
Firm RE
(MW)
Wind
(MW)
Wind
(MW)
Wind
(MW)
Solar
(MW)
Firm RE
(MW)
Scenario 1 200 100 100 79 72 15 13 200 372 115 92
Scenario 2 200 100 100 79 72 15 63 200 372 115 142
Scenario 3 200 100 100 79 72 15 113 200 372 115 192
Scenario 4 200 100 360 79 72 15 13 200 372 375 92
Scenario 5 200 200 100 100 79 72 15 13 200 200 572 115 92
Scenario 6 200 200 100 100 79 72 15 63 200 200 572 115 142
Scenario 7 200 200 100 100 79 72 15 113 200 200 572 115 192
Scenario 8 200 200 100 100 79 172 15 13 200 200 672 115 92
Scenario 9 200 200 100 100 79 172 15 63 200 200 672 115 142
Scenario 10 200 200 100 100 79 172 15 113 200 200 672 115 192
HVDC Maui Renewables Total SystemOahu Renewables
![Page 38: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/38.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 23 Final Report 5/21/2013 Final Report 4/30/2013
Figure 3-1: Renewable Capacity (MW)
Figure 3-2: Scenario Tree
![Page 39: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/39.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 24 Final Report 5/21/2013 Final Report 4/30/2013
3.2 Available Renewable Energy
The previous section considered the capacity of the renewable resource additions. Table 3-2 and
Figure 3-3 show the corresponding renewable energy that is available under each scenario. The
total energy available from wind, solar and firm renewables ranges from 19% to 41% of the total
system load for the ten scenarios. It is important to note that this is the available energy and not
necessarily the delivered energy. System operating constraints generally cause some curtailment to
occur. The results presented in Chapters 4 and 5 will quantify the curtailment in each scenario and
how that can be effected by changes in operating practices.
Another aspect that can be seen is that the capacity factors are not the same for the different types
of renewable generation. Even though Scenario 4 has more renewable capacity than Scenario 3 it
has less renewable energy. This is because Scenario 3 had 100 MW of firm renewable energy with
an assumed 100% capacity factor while Scenario 4 had 260 MW of solar capacity with roughly a
20% capacity factor. The wind capacity factors ranged from 43% to 51% depending on the location.
Table 3-2: Available Renewable Energy (GWh)
Lanai Molokai
ScenarioWind
(GWh)
Solar
(GWh)
Firm RE
(GWh)
Wind
(GWh)
Solar
(GWh)
Firm RE
(GWh)
Wind
(GWh)
Wind
(GWh)
Wind
(GWh)
Solar
(GWh)
Firm RE
(GWh)
Total
(GWh)
Total
(%)
Scenario 1 358 180 647 307 25 96 902 1,568 205 743 2,516 27%
Scenario 2 358 180 647 307 25 534 902 1,568 205 1,181 2,953 31%
Scenario 3 358 180 647 307 25 970 902 1,568 205 1,617 3,390 36%
Scenario 4 358 636 647 307 25 96 902 1,568 661 743 2,971 32%
Scenario 5 358 180 647 307 25 96 902 754 2,322 205 743 3,270 35%
Scenario 6 358 180 647 307 25 534 902 754 2,322 205 1,181 3,707 39%
Scenario 7 358 180 647 307 25 970 902 754 2,322 205 1,617 4,144 44%
Scenario 8 358 180 647 734 25 96 902 754 2,749 205 743 3,696 39%
Scenario 9 358 180 647 734 25 534 902 754 2,749 205 1,181 4,134 44%
Scenario 10 358 180 647 734 25 970 902 754 2,749 205 1,617 4,571 49%
Maui Renewables Total SystemOahu Renewables
![Page 40: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/40.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 25 Final Report 5/21/2013 Final Report 4/30/2013
Figure 3-3: Available Renewable Energy (GWh)
3.3 DC & AC Interconnection
Figure 3-4 shows the HVDC and AC interconnections between the islands for Scenarios 5 through 10.
The first four scenarios are similar but do not include the HVDC connection between Molokai and
Oahu. All of the scenarios include the AC interconnections between Molokai, Lanai and Maui which
were added as part of the Maui County Base Case.
Figure 3-4: System Interconnections with Two HVDC Cables
Although the HVDC cables were assumed to be nominally 200 MW, no limits were assumed in the
modeling. Similarly, the AC cables connecting the islands in Maui County were assumed to have
similar impedance characteristics but no power transfer limits were enforced.
Oahu-Maui Interconnection MapScenarios with 2 HVDC Cables
Maui
Molokai
Oahu
Maui
County
Lahaina
69 kV
Lanai
Iwilei
138 kV
![Page 41: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/41.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 26 Final Report 5/21/2013 Final Report 4/30/2013
3.4 Reserve Strategy
As described in Chapter 2 the total operating reserves are a function of the contingency reserves and
the variability of the wind and solar generation. Figure 3-5 shows the variable operating reserve
component for the Oahu Base Case as a function of total wind and solar generation. These curves
were developed for both day and night since the variability is different in those two time frames. Also
shown on these curves is the operating reserve for the Oahu Only case which does not include the
200 MW of wind generation on Lanai. Figure 3-6 shows a similar curve for the Maui County Base
Case. The upper curve represents the original operating reserve requirements and the lower curve is
the final requirements after taking credit for the Maui, Lanai and Molokai quick start generation and
the KWP2 Battery Energy Storage System (BESS).
Note: This chart includes operating reserves only. In addition 185 MW of contingency reserve is carried during all hours.
Figure 3-5: Oahu Base Case Variable Operating Reserve versus Wind and Solar Generation
Note: Note: This chart includes operating reserves only. In addition 185 MW of contingency reserve is carried during all hours.
Figure 3-6: Maui County Operating Reserve versus Wind and Solar Generation
![Page 42: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/42.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 27 Final Report 5/21/2013 Final Report 4/30/2013
Interconnecting the Oahu and Maui County systems has two primary impacts on operating reserves:
1. The reserves are combined into one pool, so the total reserve requirement is smaller than the sum of the individual reserve requirements for Oahu and Maui.
2. The system operator can take advantage of the increased diversity and availability of the combined system resources.
The resulting combined system operating reserves as a function of the wind and solar generation
(excluding contingency reserves) is shown in Figure 3-7. Note that many of the scenarios have the
same operating reserve characteristics since the Firm Renewables are considered dispatchable and
do not contribute to the variability. These curves are then combined with the corresponding
chronological wind and solar generation to develop the chronological operating reserve
requirements for each scenario. Figure 3-8 shows annual duration curves of the hourly operating
reserve requirements for the ten scenarios examined.
Note: This chart includes operating reserves only. In addition 185 MW of contingency reserve is carried during all hours.
Figure 3-7: Combined System Operating Reserve versus Wind and Solar Generation
![Page 43: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/43.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 28 Final Report 5/21/2013 Final Report 4/30/2013
Note: This chart includes operating reserves only. In addition 185 MW of contingency reserve is carried during all hours.
Figure 3-8: Combined System Operating Reserve Duration Curves by Scenario
Table 3-3 shows the maximum operating reserves for each scenario. The data is shown graphically
in Figure 3-9.
Table 3-3: Maximum Operating Reserves by Scenario.
ScenarioContingency
(MW)
Operating
(MW)
Contingency
(MW)
Operating
(MW)
Contingency
(MW)
Operating
(MW)Total (MW)
Scenario 1 185 98 0 6 185 104 289
Scenario 2 185 98 0 6 185 104 289
Scenario 3 185 98 0 6 185 104 289
Scenario 4 185 146 0 6 185 152 337
Scenario 5 185 174 0 6 185 180 365
Scenario 6 185 174 0 6 185 180 365
Scenario 7 185 174 0 6 185 180 365
Scenario 8 185 208 0 6 185 214 399
Scenario 9 185 208 0 6 185 214 399
Scenario 10 185 208 0 6 185 214 399
Oahu Maui County Total System
![Page 44: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/44.jpg)
Hawaii Stage 2 Interconnection Study Scenario Overview
GE Energy Consulting 29 Final Report 5/21/2013 Final Report 4/30/2013
Figure 3-9: Maximum Operating Reserves by Scenario
![Page 45: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/45.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 30 Final Report 5/21/2013 Final Report 4/30/2013
4 Results This chapter presents results of technical analysis for all 10 study scenarios, assuming the existing
operating practices for Oahu and Maui baseload units as described in Chapters 2 and 3. In
particular:
Maui baseload units are assumed to follow the existing operating schedules (also referred to as Maui Must-Run Rules in the MAPS production cost simulations)
Oahu baseload units are assumed to have their existing minimum power limits, Pmin. Reduced Pmin limits on selected Oahu units were also considered, and those results are presented in Chapter 5
Oahu baseload units are assumed to follow existing operating schedules (also referred to as Oahu Must-Run Rules in the MAPS production cost simulations)
Most of the analysis in this chapter is derived from production cost simulations using GE-MAPS. In
this analysis, production costs include system operating costs for thermal power plants (fuel, start-up
costs, variable O&M). Production costs do not include the PPA costs for wind, solar, or firm renewable
energy. Chapter 8 presents the results of cost-benefit analysis, where capital costs for wind, solar
and firm renewable resources are included.
This chapter is organized as follows:
Section 4.1 examines the operational and economic impacts of interconnecting Maui, Molokai and
Lanai. Section 0 describes the analytical results for the Base Case and Scenario 1 in detail,
comparing isolated versus interconnected operation of the Oahu and Maui County systems. The
analytical methods are also described. The subsequent sections show analytical results for all 10
study scenarios together so they can be compared to each other as well as to the Base Case.
4.1 Interconnecting Maui, Molokai and Lanai
The Maui power system is served by a diverse mix of generating resources, including combined cycle
(baseload), diesel, biomass, oil-fired steam, wind, and solar. Lanai and Molokai are each served by a
fleet of diesel generators. Table 4-1 shows production cost simulation results for Lanai, Molokai and
Maui operating as separate power grids and operation together as one interconnected power grid.
The total annual production cost for Lanai, Molokai and Maui is $7.1M +$7.4M +$185M = $199.5M. If
the islands are interconnected and operated as one integrated system, the annual production cost is
$188M, which is $11.5M lower than for separate operation. Some of this reduction in production cost
is due to an 18 GWh decrease in curtailment. However, the additional accepted wind and solar
generation must be paid for by the utility according to existing PPA structures on Maui. As a result,
the additional wind and solar generation costs $3.5 million (see Chapter 8 for more discussion on PPA
prices). Therefore, the total annual savings when interconnecting the Maui County system is $8
million per year. Assuming a fixed charge rate (FCR) of 14%, the break-even cost of the AC cable
infrastructure would be $57 million.
Table 4-2 shows delivered wind and solar energy for both separate and interconnected operation.
Delivered wind and solar energy increases from 84% to 89% with interconnected operation.
![Page 46: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/46.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 31 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-1: Annual Production Costs and Energy for Maui County System
Table 4-2: Wind and Solar Energy Delivered and Curtailed for Maui County System
Maui
OnlyLanai Only
Molokai
Only
Sum of
Maui, Lanai,
Molokai
Maui
County
Base
210 5 6 221 219
233 11 15 259 259
15 15 15
72 72 72
13 13 13
18 18 8
332 332 332
1,271 26 31 1,328 1,324
278 278 296
97 97 97
896 26 31 953 931
Thermal 896 896 929
Wind & Solar 278 278 296
Firm Renew 97 97 97
26.0 26.0 0.0
30.9 30.9 1.5
185 185 188
7.1 7.1 0.01
7.4 7.4 0.37
185 7 7 200 188
11.5
48.9 48.9 52.4
3.5
8.0
Available Wind & Solar Energy (GWh)
Peak Load (MW)
Thermal Capacity (MW)
Solar Capacity (MW)
Wind Capacity (MW)
Firm Renewable Capacity (MW)
Max Reserve Requirement (MW)
Total Generation (GWh)
Wind & Solar Generation (GWh)
Firm Renewable Generation (GWh)
Thermal Generation (GWh)
Maui
Lanai
Molokai
Generation
by Island
(GWh)
Maui
Lanai
Molokai
Production
Cost by Island
(M$)
Total Annual Production Cost (M$)
Annual Production Cost Savings (M$)
Annual PPA Cost (M$)
Annual Change in PPA Cost (M$)
Total Annual Savings (M$)
Maui
Only
Maui
CountyDelta
Maui
Only
Maui
CountyDelta
KWP I Wind 30 129 127 128 1 99% 100% 1%
KWP II Wind 21 90 50 62 12 56% 69% 13%
Auwahi Wind 21 88 75 81 6 86% 92% 6%
Maui Distributed Solar 15 25 25 25 0 100% 100% 0%
Total Wind & Solar 87 332 277 296 19 84% 89% 5%
Capacity
(MW)
Available
Energy
(GWh)
Delivered Energy (GWh) Delivered Energy (%)
![Page 47: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/47.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 32 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-1: Spinning Reserve Requirements for Maui Alone and Maui County Interconnected
Figure 4-2: Quick-Start Capability for Maui Alone and Maui Combined with Lanai and Molokai
![Page 48: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/48.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 33 Final Report 5/21/2013 Final Report 4/30/2013
Reserve requirements change when the systems are interconnected, and this also contributes to the
reduction in operating costs. Reserves are provided by a combination of spinning reserves (from
committed/running units) and non-spinning reserves (from quick-start units). Figure 4-1 shows that
spinning reserves for the interconnected system are considerably lower than for the Maui system
alone. This is because Maui has a limited quick-start capacity and the quick-start units require more
than 10 minutes to start and deliver power. The diesel units on Lanai and Molokai are capable of
starting faster than the units on Maui (see Figure 4-2). In an isolated system, Maui requires 20
minutes to turn on a quick-start unit. This includes 10 minutes allocated to operator decision-making
and an addition 10 minutes for the unit to be brought up to speed. On Lanai and Molokai, the diesel
units start faster and can begin producing some power shortly after the operator’s decision period.
The Lanai diesel units become the interconnected system’s first resource during events that require
flexible, quick-start generation, followed by the Molokai diesels. As a result, when the Lanai and
Molokai diesel units are added to the Maui generation fleet for interconnected operation, the need for
spinning reserves declines because more of the total reserve requirement can be satisfied by non-
spinning reserves from quick-start units.
![Page 49: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/49.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 34 Final Report 5/21/2013 Final Report 4/30/2013
4.2 Base Case and Scenario 1
4.2.1 Total System Energy Production
Table 4-3 shows production cost (fuel cost + VOM + start cost) simulation results for the Base Cases
and Scenario 1. The second column shows production costs for the Maui County Base Case (Maui
and Lanai and Molokai operating together as one system, but not connected to Oahu). The third
column shows production costs for the Oahu Base Case (Oahu system with 200 MW of wind capacity
on Lanai, but not interconnected with the Maui County system). The fourth column shows the sum of
the production costs for the Maui County and Oahu Base Case systems. The last column shows
production costs for Scenario 1, where the Maui County and Oahu systems are interconnected and
operating as one combined system. Comparing the two right-hand columns yields the following
observations for interconnected operation versus separate operation:
Thermal generation on Oahu increases by 166 GWh while thermal generation in Maui County decreases by 173 GWh. The AES, Kalaeloa and Kahe units on Oahu are more economical than the baseload units on Maui.
Wind and solar generation on Oahu decreases by 13 GWh while wind and solar generation in Maui County increases by 30 GWh. (Note that the 200 MW wind plant on Lanai is part of the Oahu system and in Scenario 1 that wind plant is first in the curtailment order.)
Molokai and Lanai generation increases. Some of the Lanai and Molokai diesel units have lower operation costs than the cycling and peaking units on Maui.
The annual production cost for operating the Maui County and Oahu systems separately is $1,043M. The production cost for Scenario 1 (interconnected operation) is $1,035, a difference of $8M per year.
![Page 50: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/50.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 35 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-3: Annual Production Costs and Energy for Base Cases and Scenario 1
Note: Production costs do not include PPA costs for wind, solar, or firm renewable energy.
Maui
County
Base
Oahu
Base
Sum of
Maui
County &
Oahu
Scenario
1
219 1,263 1,482 1,473
259 1,699 1,958 1,958
15 100 115 115
72 300 372 372
13 79 92 92
8 308 316 289
332 1,441 1,773 1,773
1,324 8,019 9,343 9,358
296 1,315 1,611 1,628
97 647 744 744
931 6,056 6,987 6,986
Thermal 6,056 6,056 6,222
Wind & Solar 1,315 1,315 1,302
Firm Renew 647 647 647
Thermal 929 929 756
Wind & Solar 296 296 326
Firm Renew 97 97 97
0.0 0.0 2.3
1.5 1.5 5.9
855 855 878
188 188 155
0.01 0.01 0.7
0.37 0.37 1.2
188 855 1,043 1,035
8.1
Available Wind & Solar Energy (GWh)
Peak Load (MW)
Thermal Capacity (MW)
Solar Capacity (MW)
Wind Capacity (MW)
Firm Renewable Capacity (MW)
Max Reserve Requirement (MW)
Total Generation (GWh)
Wind & Solar Generation (GWh)
Firm Renewable Generation (GWh)
Thermal Generation (GWh)
Generation
by Island
(GWh)Maui
Lanai
Molokai
Oahu
Production
Cost by Island
(M$)
Oahu
Maui
Lanai
Molokai
Total Annual Production Cost (M$)
Annual Production Cost Savings (M$)
![Page 51: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/51.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 36 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-3: Energy Production by Power Plant for Scenario 1
Figure 4-3 shows energy by power plant for Scenario 1. This provides a total overview of how the
energy resources on each island are contributing to the operation of the entire interconnected
system.
4.2.2 Thermal Unit Operation
Figure 4-4 shows how the capacity factors of the thermal plants change from the Base Case (isolated
operation) to Scenario 1 (interconnected operation). Table 4-4 summarizes the annual energy output
for the various types of generation resources. On Oahu, energy from baseload and cycling units
increases while energy from peaking units decreases. In Maui County, energy from baseload and
cycling units decreases while energy from peaking units increases. Energy from Lanai and Molokai
Total Generation: 8,171 GWhOahu
Total Generation: 1,178 GWhMaui County
![Page 52: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/52.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 37 Final Report 5/21/2013 Final Report 4/30/2013
thermal units also increases, as they are more economically attractive for peaking in comparison to
other units on Maui and Oahu.
Figure 4-4: Capacity Factors of Generating Plants for Base Case and Scenario 1
Table 4-4: Generation Utilization for Base Case and Scenario 1
Baseload
Cycling
Peaking
GWh CF GWh CF GWh CF
Oahu Baseload 6,394 59% 6,543 60% 149 1.4%
Oahu Cycling 266 10% 304 11% 38 1.4%
Oahu Peaking 44 2% 22 1% -22 -1.1%
Oahu Wind & Solar 1,315 38% 1,302 37% -14 -0.4%
Oahu Total 8,019 42% 8,170 43% 152 0.8%
Maui Baseload 821 57% 730 50% -91 -6.3%
Maui Cycling 104 17% 18 3% -86 -13.8%
Maui Peaking 2 1% 7 4% 5 2.6%
Maui Wind & Solar 392 35% 423 37% 31 2.7%
Maui Total 1,319 39% 1,178 35% -141 -4.1%
Lanai Thermal 0 0% 2 2% 2 2.4%
Molokai Thermal 1 1% 6 4% 4 3.3%
Maui County Total 1,321 36% 1,186 33% -134 -3.7%
Base Case Scenario 1 Delta
![Page 53: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/53.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 38 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-5: Average Annual Hours of Operation and Starts for Thermal Generation, by Type
Figure 4-5 shows the average annual hours of operation and starts for thermal generators for the
Base Case (isolated) and Scenario 1 (interconnected). Operating hours and starts for baseload units
are unchanged, since most of these units are operated on fixed schedules. Operating hours and
starts for Maui cycling and Oahu peaking units decline in Scenario 1, while hours and starts for Oahu
cycling and Maui County peaking units increase.
Base Case Scenario 1 Base Case Scenario 1 Base Case Scenario 1
Oahu Baseload 6,558 6,558 9 9 765 765
Oahu Cycling 1,974 2,243 207 234 10 10
Oahu Peaking 411 179 165 64 2 3
Maui Baseload 4,518 4,518 130 130 35 35
Maui Cycling 2,412 533 281 123 9 4
Maui Peaking 82 434 37 157 2 3
Lanai Peaking 2 184 2 64 1 3
Molokai Peaking 87 328 60 121 1 3
Average Hours Average Starts Average Starts
![Page 54: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/54.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 39 Final Report 5/21/2013 Final Report 4/30/2013
4.2.3 Emissions
Figure 4-6: Annual Emissions for Base Case and Scenario 1
Figure 4-6 summarizes total NOx, SOx and CO2 emissions for the Base Case and Scenario 1. NOx
declines, SOx increases slightly (likely due to an increase in energy production from the AES coal
plant), and CO2 remains the same.
4.2.4 Curtailment of Renewable Generation
Table 4-5 summarizes the annual available, delivered and curtailed renewable energy for the Base
Case (isolated) and Scenario 1 (interconnected). Curtailment of wind resources on Maui is 30 GWh
lower in Scenario 1. With the interconnection to Oahu, more of that energy is transferred to Oahu.
Curtailment of the Lanai 200 MW wind plant increases by 13 GWh in Scenario 1. This is because of
the assumption that in the interconnected system, the Lanai wind plant would be curtailed before
the existing wind plants on Maui. Overall, curtailment of wind and solar generation is 17 GWh lower
in Scenario 1 than in the Base case. This accounts for most of the reduction in production costs for
Scenario 1 (see Table 4-3), as this this renewable energy displaces thermal generation.
Figure 4-7 shows the average hourly available and delivered wind power by time of day for Scenario
1. Nearly all of the curtailment occurs during the nighttime hours, between 10 pm and 6 am. Figure
4-8 is a duration curve of wind and solar curtailment for the Base Case and Scenario 1. There is not
much difference in the total curtailment. This is primarily due to the assumptions that:
Oahu and Maui baseload units are operated on fixed schedules, per existing practices
Oahu baseload units have existing minimum power limits.
These baseload units cannot be turned off at night. Wind generation forces baseload units on both
Oahu and Maui to operate at minimum power limits at night. Excess wind generation must be
curtailed. The interconnection between the islands does not help reduce curtailment if all units on
both islands are operating at minimum power and cannot be decommitted.
Base Case Scenario 1
NOX Emissions (Tons) 12,469 11,208
SOX Emissions (Tons) 12,142 12,316
CO2 Emissions (K Tons) 6,989 6,997
![Page 55: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/55.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 40 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-5: Annual Renewable Energy Available and Delivered for Base Case and Scenario 1
Figure 4-7: Average Hourly Available and Delivered Wind Power by Time of Day, Scenario 1
Base
Case
Scenario
1Delta
Base
Case
Scenario
1Delta
Maui County 87 332 296 326 30 36 6 -30
KWP I Wind 30 129 126 129 2 2 0 -2
KWP II Wind 21 90 64 86 22 27 4 -22
Auwahi Wind 21 88 81 87 6 7 1 -6
Maui Distributed Solar 15 25 25 25 0 0 0 0
Oahu 400 1,441 1,315 1,302 -14 125 139 14
Kahuku Wind 30 103 102 103 0 1 1 0
Kawailoa Wind 70 255 248 247 -1 7 8 1
Lanai Wind Addition 200 902 785 772 -13 118 131 13
Oahu Centralized Solar 60 117 117 117 0 0 0 0
Oahu Distributed Solar 40 63 63 63 0 0 0 0
Total Wind & Solar 487 1,773 1,611 1,628 17 161 145 -17
Delivered Energy (GWh) Curtailment (GWh)Available
Energy
(GWh)
Capacity
(MW)
![Page 56: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/56.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 41 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-8: Duration Curve of Wind and Solar Curtailment, Base Case and Scenario 1
4.2.5 Interisland Line Flows
Figure 4-9 show annual duration curves of interisland line flows for Scenario 1. The top plot shows
the flow on the DC cable from Lanai to Oahu. The shaded red area represents the power output of
the Lanai wind plant. If the two systems are isolated (Base Case), all of this wind power flows on the
DC cable to Oahu. With the two systems interconnected (Scenario 1), the flow is somewhat lower,
because thermal generation on Maui is partially displaced by more economical thermal generation
on Oahu. The flow from Oahu to Lanai was intentionally limited to 30 MW in this analysis, so that loss
of the DC cable would not create a contingency larger than the loss of a single generating unit on
Maui.
The bottom plot in Figure 4-9 shows flows on the three ac cables interconnecting Maui, Lanai and
Molokai. These traces give an indication of the expected loading on the cables. Note that if one of
the cables experiences an outage, the flows on the other two cables would increase. However,
contingency analysis to quantify contingency flow levels was not in the scope of this study.
Figure 4-10 is a chronological plot of interisland line flows for the week with maximum system load.
The red trace is the power flow from Lanai to Oahu. The shaded area represents the output of the
Lanai wind plant. The profile of the line flow from Lanai to Oahu is similar to the output of the Lanai
200 MW wind plant, but somewhat lower in magnitude. For a period on August 12, the wind plant
output is zero and the DC cable flow changes direction (from Oahu to Lanai). The green trace
represents the flow from Lanai to Maui which changes direction several times but is from Lanai to
Maui for most hours of the week.
![Page 57: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/57.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 42 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-9: Interisland Line Flow Duration Curves for Scenario 1
Total Flow
(GWh)
Max Flow
(MW)
Min Flow
(MW)
Avg Flow
(MW)
DC: Lanai to Oahu 665 203 -30 76
AC: Lanai to Maui 139 66 -32 11
AC: Molokai to Maui 64 31 -17 4
AC: Lanai to Molokai 77 36 -17 7
![Page 58: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/58.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 43 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-10: Interisland Line Flows for Highest Load Week
4.2.6 Weekly Generation Profiles
The figures in this section illustrate how different types of generation resources work together to
serve load, hour-by-hour, for several selected weeks. Figure 4-11 shows generation profiles for the
week with the highest hourly % penetration of wind and solar generation (on Sunday morning,
delivered wind and solar energy is 40% of total load energy). The lower blue areas represent
baseload generation, the violet bands above represent cycling units, light blue represents peaking
units, green represents wind, and orange (at the top) represents solar. The solid and dotted green
lines near the bottom of the plot represent available and forecasted wind and solar power. The light
blue trace at the bottom represents curtailment, which occurs at night when baseload units are
operating at minimum power and there is more wind energy available than can be absorbed by the
load.
Figure 4-12 shows a similar plot for the week with the highest wind and solar generation, in MW. On
Monday through Thursday, the wind and solar generation is always above 200 MW, and as high as
400 MW for several hours. At noon on Tuesday, total wind and solar generation reaches 433 MW.
Figure 4-13 shows a similar plot for the week with the highest wind and solar forecast error. At mid-
day on Monday, the forecast predicted that wind and solar power would decline. But wind and solar
generation declined faster than the forecast predicted (a forecast error of 219 MW at 3 pm). Peaking
units were committed to make up for the shortfall. The forecast error on Saturday night through
Sunday was over 100 MW. Again, peaking generation was used to help fill the shortfall.
![Page 59: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/59.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 44 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-14 shows generation profiles for the week with the highest system load (demand) for
Scenario 1. The bottom of this figure shows the differences in generation output as compared to the
Base Case (isolated operation). The traces show that:
Wind generation in Maui increases and wind generation in the Oahu system decreases (Lanai 200 MW wind plant, due to curtailment order)
Baseload generation on Oahu increases
Use of peakers in Oahu decreases
Solar generation does not change (note that distribution-connected solar cannot be curtailed)
This section has summarized Scenario 1 and compared it to the Base Case (isolated operation). The
following sections of this chapter show analytical results for all 10 scenarios and compare those
scenarios to each other.
Figure 4-11: Scenario 1 Generation Profiles for Week with Maximum Renewable Energy
Penetration (% of Load)
![Page 60: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/60.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 45 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-12: Scenario 1 Generation Profiles for Week with Maximum Renewable Generation (MW)
Figure 4-13: Scenario 1 Generation Profiles for Week with Worst Wind & Solar Forecast Error
![Page 61: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/61.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 46 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-14: Scenario 1 Generation Profiles for Week with Peak Demand, Showing Changes from
Base Case
![Page 62: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/62.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 47 Final Report 5/21/2013 Final Report 4/30/2013
4.3 Production Cost Analysis
Table 4-6 shows the annual production costs (fuel cost + VOM + start cost) for the Base Case and all
10 study scenarios. The top section of the table (blue) shows the total system peak load as well as
the MW capacity of installed generation resources for each scenario. The scenarios are arranged so
that renewable generation capacity increases from Scenario 1 to 10. Scenarios 1-4 have one 200
MW DC cable interconnecting Oahu with Maui County; Scenarios 5-10 have two 200 MW cables.
The next section of the table (light blue) shows how much energy from wind, solar, firm renewable
and thermal generation was delivered in each scenario. The middle section of the table (blue)
summarizes energy broken down by island. The section below that (light blue) summarizes
production costs for the thermal generation resources on each island.
The bottom two rows of the table show total annual production cost for each scenario, as well as the
production cost savings relative to the Base Case.
The Base Case and Scenario 1 have the same generation resources. In the Base Case, Oahu and
Maui County are isolated and therefore have separate reserve requirements (higher total reserves,
see 6th row). In Scenario 1, the Oahu and Maui County systems are interconnected and operated as
one system with one common pool of reserves (lower total reserves than the Base case). The total
annual production cost for Scenario 1 is $8M lower than the Base Case. These savings are due to:
Interconnected grid operation which enables dispatch of generation resources on all islands to serve total system load in the most economical manner.
Reduced total system reserve requirements, and
Reduced curtailment of wind and solar resources, primarily on Maui.
Baseload units on Oahu are more economical to operate than the baseload and cycling units on
Maui, so the interconnected scenarios dispatch Oahu resources more and Maui resources less. Table
4-7 shows generation by type and by island for all the scenarios. The differences between separate
and interconnected operation can be seen by comparing data in the columns for the Base Case and
Scenario 1.
Production costs for all scenarios are plotted in Figure 4-15. The height of each bar represents the
total production costs, and the colored segments show the breakdown by generation type. In the
scenarios with higher renewable energy penetration, the renewable generation primarily displaces
Oahu thermal generation. Also, the scenarios with increased levels of firm renewable generation on
Maui (Scenarios 3, 7, 10) show lower utilization of cycling units. Maui baseload generation is nearly
constant across the scenarios, primarily because of the fixed operating schedules of those units.
Figure 4-16 shows delivered energy by type of resource for all the scenarios. The orange, green and
gray segments at the top of each bar represent the annual energy delivered from solar, wind and
firm renewable resources. Total energy from these resources ranges from 2,372 GWh in Scenario 1
to 3,624 GWh in Scenario 10. Significant amounts of renewable energy are also curtailed, especially
in the higher penetration scenarios. The next two sections discuss delivered and curtailed renewable
energy.
![Page 63: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/63.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 48 Final Report 5/21/2013
Table 4-6: Annual Production Costs and Energy for All Scenarios
![Page 64: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/64.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 49 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-7: Annual Generation in GWh by Type and by Island for All Scenarios
Figure 4-15: Production Costs for All Scenarios, by Generation Type
One 200 MW DC Cable Two 200 MW DC Cables
Scenario
ScenarioDC
MW
Wind
MW
Solar
MW
Firm RE
MW
1 200 200 0 0
2 50
3 100
4 260 0
5 400 400 0 0
6 50
7 100
8 500 0
9 50
10 100
![Page 65: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/65.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 50 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-16: Generation by Type for All Scenarios
4.4 Delivered Renewable Generation
This section describes how much new renewable energy is available in each scenario, how much is
used to serve load, and how much must be curtailed. Note that these scenarios assume existing
baseload thermal unit operating practices.
Figure 4-17 illustrates the total wind, solar and firm renewable energy available and delivered for all
scenarios. The green portion of each bar is delivered wind energy, the orange portion is delivered
solar energy, the dark blue portion is delivered firm renewable energy, and the light blue portion on
top is curtailed energy. The total height of each bar represents the total available wind, solar and
firm renewable energy.
In this analysis, wind energy is curtailed before firm renewables. Scenario 2 adds a 50 MW firm
renewable energy resource to Scenario 1. As a result, delivered wind energy declines and
curtailment increases. Scenario 3 adds another 50 MW firm renewable resource (100 MW total).
Delivered wind energy declines further and curtailment increases. Similar trends are evident in
Scenarios 5-6-7 and Scenarios 8-9-10.
![Page 66: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/66.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 51 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-17: Wind, Solar, and Firm Renewable Energy for All Scenarios
Table 4-8 summarizes wind, solar, and firm renewable energy delivered and curtailed for all
scenarios. The right-hand column shows delivered wind, solar and firm renewable energy as a
percent of load.
Figure 4-18 is illustrates total renewable energy penetration for all scenarios. The green portion of
each bar represents wind, solar and firm renewable resources. This includes all existing wind, solar
and firm renewable plants (HC&S biomass, H-Power, Honua) as well as new renewable additions. In
Scenario 1, 25% of load energy is served by renewable energy resources. In Scenario 10, 39% of load
energy is served by renewables.
![Page 67: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/67.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 52 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-8: Wind, Solar and Firm Renewable Energy Delivered and Curtailed for All Scenarios
Figure 4-18: Annual Renewable Energy Penetration for All Scenarios
Scenario
Renewable
Capacity
(MW)
Available
Energy
(GWh)
Delivered
Energy
(GWh)
Curtailment
(GWh)
Percent
Delivered
Percent
Curtailed
Percent of
Load
Base 578 2,516 2,354 162 94% 6% 25%
1 578 2,516 2,371 145 94% 6% 25%
2 629 2,953 2,730 223 92% 8% 29%
3 679 3,387 3,066 321 91% 9% 33%
4 839 2,971 2,804 167 94% 6% 30%
5 778 3,270 2,896 373 89% 11% 31%
6 828 3,707 3,198 509 86% 14% 34%
7 878 4,141 3,471 671 84% 16% 37%
8 878 3,697 3,118 579 84% 16% 33%
9 928 4,133 3,383 751 82% 18% 36%
10 978 4,568 3,623 945 79% 21% 39%
![Page 68: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/68.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 53 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-19 is an hourly duration curve showing wind and solar energy penetration for all scenarios.
Table 4-9 summarizes for useful statistics from the duration curves, including maximum hourly
percent penetration and average annual energy penetration. In Scenario 1, the average annual
energy penetration for wind and solar resources is 17%. However, for one hour the penetration
reaches 40%. The average annual penetration of wind and solar energy for Scenario 8 is 24% and
the maximum hourly penetration is 54%.
Figure 4-19: Duration Curves of Hourly Wind and Solar Penetration Levels as % of Load for All
Scenarios
Table 4-9: Maximum and Average Hourly Penetration Levels for Wind and Solar Resources
Max Hourly
Penetration (%)
Average Annual
Penetration (%)Hours > 40%
Base Case 39% 17% 0
Scenario 1 40% 17% 0
Scenario 2 38% 16% 0
Scenario 3 38% 15% 0
Scenario 4 50% 21% 467
Scenario 5 50% 22% 642
Scenario 6 48% 20% 392
Scenario 7 46% 18% 193
Scenario 8 54% 24% 1,336
Scenario 9 51% 21% 891
Scenario 10 48% 19% 515
![Page 69: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/69.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 54 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-20 provides some insights into how wind and solar energy penetration varies as a function
of the time period considered. In Scenario 1, the total annual energy from wind and solar resources
is 17% of the annual load energy. The dotted horizontal line represents annual average penetration.
The purple line shows wind and solar energy penetration calculated on a monthly basis, which varies
from 12% to 21%. The green trace shows weekly penetration, which ranges from 5% to 28%. Daily
penetration (blue) ranges from 2% to 32% and hourly penetration (red) ranges from zero to 40%. A
similar plot is shown for Scenario 8, which has the highest penetrations of wind and solar energy.
Figure 4-20: Duration Curves of Wind and Solar Penetration Levels for Different Time Periods,
Scenarios 1 and 8
4.5 Renewable Curtailment
This section presents wind and solar curtailment information for the study scenarios in several
different forms:
Figure 4-21 shows duration curves of hourly wind and solar curtailment.
Table 4-10 summarizes a few statistics for curtailment, including total wind and solar energy available, total curtailed energy, maximum hourly curtailment in MW, and number of hours of curtailment in a year.
Figure 4-22 illustrates total wind, solar and firm renewable energy delivered and total curtailment as % of load.
Figure 4-23 is a scatter plot showing curtailment as a function of wind, solar and firm renewable energy available in each scenario.
Figure 4-24 illustrates curtailment of the 100 MW wind plant on Maui that is included in Scenarios 8, 9 and 10.
Scenario 1: 17% Annual Penetration Scenario 8: 25% Annual Penetration
![Page 70: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/70.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 55 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-21: Wind and Solar Curtailment Duration Curves for All Scenarios
Table 4-10: Wind and Solar Energy Curtailment for All Scenarios
Total
Available
(GWh)
Total
Curtailment
(GWh)
Max
Curtailment
(MW)
Hours of
Curtailment
Scenario 1 1,773 145 313 1,386
Scenario 2 2,210 223 348 1,889
Scenario 3 2,647 321 351 2,452
Scenario 4 2,228 167 313 1,703
Scenario 5 2,527 373 496 2,511
Scenario 6 2,964 509 527 3,118
Scenario 7 3,401 671 527 3,775
Scenario 8 2,953 579 588 3,263
Scenario 9 3,391 751 617 3,841
Scenario 10 3,827 945 617 4,438
![Page 71: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/71.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 56 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-22: Wind, Solar and Firm Renewable Energy Delivered and Curtailed, as % of Load
Figure 4-23: Available Wind, Solar and Firm Renewable Energy versus Curtailment
![Page 72: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/72.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 57 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-24: Curtailment of the Maui 100 MW Wind Plant for Scenarios 8, 9 and 10.
Scenarios 8, 9 and 10 include an additional 100 MW wind plant on Maui (as compared to Scenario 5).
This plant is assumed to be the last addition to the system and therefore first in the curtailment
order. Figure 4-24 shows how much of the available energy from that plant is delivered and
curtailed. In Scenario 8, where this 100 MW wind plant is the only addition relative to Scenario 5, only
211 GWh of the plant’s 425 GWh of available energy can be delivered (about 50% curtailment). In
Scenario 10, where there is also a 100 MW firm renewable energy resource on Maui, about 67% of
the wind plant’s available energy must be curtailed. This high level of curtailment is mostly driven by
the fact that with this plant, total wind generation on the interconnected system is 672 MW (100 MW
existing on Oahu, 72 MW existing on Maui, and 200 MW new on Lanai, 200 MW new on Molokai, and
100 MW new on Maui). Wind patterns are similar and correlation is high. There are many periods
where there is just too much wind energy available. Chapter 5 examines modified practices to reduce
curtailment.
4.6 DC & AC Line Flows
The production simulations assumed that the DC cable flows were not constrained to their nominal
ratings. As a result, the analysis shows the flow levels that would maximize economic operation of
the interconnected power system (i.e., dispatch lowest cost generation, minimize renewable energy
curtailment).
Figure 4-25 shows duration curves of DC cable flows from Maui County to Oahu. Table 4-11
summarizes some statistics related to the cable flows.
The Base Case and Scenarios 1-4 have one 200 MW DC cable.
In the Base Case the maximum flow is 192 MW and the average flow is 89 MW (roughly a 45% capacity factor). 780 GWh of energy from the Lanai wind plant is transferred to Oahu on the DC cable.
ScenarioDC
MW
Wind
MW
Solar
MW
Firm RE
MW
1 200 200 0 0
2 50
3 100
4 260 0
5 400 400 0 0
6 50
7 100
8 500 0
9 50
10 100
![Page 73: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/73.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 58 Final Report 5/21/2013 Final Report 4/30/2013
In Scenario 1, Oahu and Maui County systems are interconnected. The peak flow (205 MW) on the DC cable is higher than the Base Case but the average flow (76 MW) is lower. The cable capacity factor is 38%. 665 GWh of energy is transferred from Maui County to Oahu.
In Scenario 2, a 50 MW firm renewable energy resource is added on Maui. With this resource, the DC cable flow increases by about 40 MW for many hours of the year. Total energy flow is 892 GWh (51% capacity factor) versus 665 GWh for Scenario 1 (see Table 4-11). There are 820 hours when flow exceeds 200 MW, representing 11 GWh of energy or 1.3% of the total cable flow.
In Scenario 3, a 100 MW firm renewable energy resource is added on Maui (relative to Scenario 1). With this resource, the DC cable flow increases by about 80 MW for many hours of the year. Total energy flow is 1194 GWh (68% capacity factor) versus 665 GWh for Scenario 1. There are 2301 hours when flow exceeds 200 MW, representing 76 GWh of energy or 6.4% of the total cable flow.
In Scenario 4, 260 MW of solar generation is added on Oahu. Given that this resource is on Oahu, cable flow from Maui County to Oahu is nearly the same as Scenario 1.
Scenarios 5-10 have two 200 MW DC cables interconnecting Maui County and Oahu.
In Scenario 5, there is a 200 MW wind plant on Lanai and another 200 MW wind plant on Molokai. The DC cables transfer most of the energy from those plants to Oahu. Total energy flow is 1147 GWh (33% capacity factor) and power flows are below 400 MW for all hours.
In Scenario 6, a 50 MW firm renewable energy resource is added on Maui (relative to Scenario 5). Total energy flow on the DC cables is 1352 GWh (39% capacity factor). There are 4 hours when flow exceeds 400 MW, but the energy in the excess flow is insignificant (less than 0.5 GWh).
In Scenario 7, a 100 MW firm renewable energy resource is added on Maui (relative to Scenario 5). Total energy flow on the DC cables is 1603 GWh (46% capacity factor). There are 117 hours when flow exceeds 400 MW, but the energy in the excess flow is only 1 GWh (0.06% of total cable flow).
In Scenario 8, a 100 MW wind plant is added on Maui (relative to Scenario 5). Total energy flow on the DC cables is 1329 GWh (38% capacity factor). There are 48 hours when flow exceeds 400 MW, but the energy in the excess flow is insignificant (less than 0.5 GWh).
In Scenario 9, a 100 MW wind plant and a 50 MW firm renewable energy resource are added on Maui (relative to Scenario 5). Total energy flow on the DC cables is 1511 GWh (43% capacity factor). There are 301 hours when flow exceeds 400 MW, but the energy in the excess flow is only 6 GWh (0.4% of total cable flow).
In Scenario 10, a 100 MW wind plant and a 100 MW firm renewable energy resource are added on Maui (relative to Scenario 5). Total energy flow on the DC cables is 1732 GWh (49% capacity factor). There are 589 hours when flow exceeds 400 MW, but the energy in the excess flow is only 18 GWh (1% of total cable flow).
Figure 4-26 compares energy transfer on the DC cables to Oahu for all study scenarios. The blue
portion of each bar represents energy transfer within the 200 MW rating of each DC cable. The red
portion of the bars indicates energy that could not be transferred if the DC cables are constrained to
200 MW each. The only significant congestion is in Scenario 3, where 6.4% of the possible flow falls
above the assumed cable ratings.
![Page 74: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/74.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 59 Final Report 5/21/2013 Final Report 4/30/2013
In general, the output of additional renewable energy resources considered in these scenarios is not
restricted by the nominal 200 MW transfer capacity of the DC cables. However, a large amount of
renewable energy is curtailed due to assumed fixed operating schedules and existing minimum
power limits for baseload generation. Chapter 5 discusses the impacts of changing these
assumptions.
Figure 4-27 shows flows on the three ac cables interconnecting Maui, Lanai and Molokai. These
traces give an indication of the expected loading on the cables. Note that if one of the cables
experiences an outage, the flows on the other two cables would increase. Contingency analysis was
not in the scope of this study. This data is represented in tabular form in Table 4-12.
Figure 4-25: Duration Curves for Maui County to Oahu DC Cable Flows
One 200 MW
DC Cable
Two 200 MW DC Cables
![Page 75: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/75.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 60 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-11: Maui County to Oahu DC Cable Flows for All Scenarios
Figure 4-26: Energy Transfer on Maui County to Oahu DC Cables, with and without Power Flow
Constraints
![Page 76: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/76.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 61 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-27: Flow Duration Curves for AC Cables Interconnecting Maui, Lanai and Molokai
Lanai to Maui
Molokai to Maui
Lanai to Molokai
![Page 77: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/77.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 62 Final Report 5/21/2013 Final Report 4/30/2013
Table 4-12: Flows (MW) for AC Cables Interconnecting Maui, Lanai and Molokai by Percentile
20% 40% 60% 80% 100%
Base Case -2.2 -3.0 -3.0 -3.7 -4.9
Scenario 1 23.8 16.9 7.6 -4.3 -32.0
Scenario 2 -3.3 -13.8 -23.5 -35.3 -69.5
Scenario 3 -33.9 -45.2 -54.5 -65.6 -96.4
Scenario 4 24.3 17.4 8.2 -3.9 -41.0
Scenario 5 19.9 12.1 5.3 -3.9 -38.4
Scenario 6 -3.4 -11.7 -18.6 -27.9 -63.4
Scenario 7 -26.3 -35.0 -41.7 -50.8 -87.7
Scenario 8 11.9 2.5 -7.2 -19.7 -65.7
Scenario 9 -10.8 -19.6 -28.9 -40.2 -87.3
Scenario 10 -32.8 -41.4 -49.8 -61.3 -112.2
20% 40% 60% 80% 100%
Base Case -2.6 -3.0 -3.1 -4.2 -5.2
Scenario 1 10.4 6.9 2.5 -3.3 -17.2
Scenario 2 -3.3 -8.5 -13.2 -19.0 -34.8
Scenario 3 -18.7 -24.2 -28.8 -34.2 -48.6
Scenario 4 10.7 7.2 2.7 -3.3 -21.3
Scenario 5 18.0 9.3 1.1 -8.5 -41.4
Scenario 6 -5.3 -14.4 -21.9 -31.4 -67.6
Scenario 7 -27.6 -37.2 -44.3 -53.4 -88.2
Scenario 8 11.5 -0.2 -11.6 -25.7 -75.9
Scenario 9 -11.1 -21.3 -32.1 -45.7 -89.1
Scenario 10 -32.8 -42.3 -52.0 -66.2 -111.0
20% 40% 60% 80% 100%
Base Case 0.4 0.2 0.1 -0.1 -2.5
Scenario 1 13.5 9.8 5.2 -1.0 -17.4
Scenario 2 0.1 -5.3 -10.1 -16.3 -34.6
Scenario 3 -15.1 -20.9 -25.6 -31.2 -47.4
Scenario 4 13.9 10.0 5.5 -0.6 -22.0
Scenario 5 12.9 4.3 0.1 -4.4 -46.9
Scenario 6 11.9 3.3 0.1 -4.3 -47.8
Scenario 7 11.2 1.8 0.1 -4.2 -46.6
Scenario 8 12.9 4.3 0.1 -4.4 -46.9
Scenario 9 11.9 3.3 0.1 -4.3 -47.8
Scenario 10 11.2 1.8 0.1 -4.2 -46.6
Lanai to Maui
Molokai to Maui
Lanai to Molokai
![Page 78: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/78.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 63 Final Report 5/21/2013 Final Report 4/30/2013
4.7 Value of Renewable Energy Resources
In this section, production cost results are used to calculate the value, in $/kW, for the renewable
resources that are added to Scenarios 1, 5 and 8.
Scenario 2 is built upon Scenario 1 with the addition of a 50 MW firm renewable resource on Maui.
As shown in Table 4-13, the total production cost is $1,035M/yr for Scenario 1 and $982M/yr for
Scenario 2. The reduction in thermal plant production costs is $53M/yr. In other words, the addition
of a 50 MW firm resource with zero fuel cost reduced total system production costs by $53M/yr. By
dividing the change in production cost by the rating of the firm renewable resource, the value of the
resource is calculated to be $1,051/kW/yr. If the fixed charge rate (cost of capital) is assumed to be
14%, then the value of the firm renewable resource in Scenario 2 is $7,505/kW.
The top four rows in Table 4-13 show the values of adding zero variable cost firm renewable
resources or solar PV resources to Scenario 1. Adding a 50 MW zero variable cost firm renewable
resource on Maui is worth $7,505/kw, a 100 MW firm renewable resource is worth $6,899/kW, and a
260 MW Solar PV resource on Oahu is worth $1,730/kW.
Note that production costs are reduced by delivered renewable energy, not curtailed energy.
Therefore, the values presented here are based only on renewable energy that is delivered. A
resource that causes more curtailment would have a lower value than and resource that causes less
curtailment.
Table 4-13: Value of Additional Renewable Resources with Existing Thermal Plant Operating
Practices
The middle four rows in Table 4-13 show the values of adding firm renewable resources or wind
resources to Scenario 5. Adding a 50 MW firm renewable resource on Maui is worth $6,037/kw, a
100 MW firm renewable resource is worth $5,493/kW, and a 100 MW wind resource on Maui is worth
$1,616/kW.
ScenarioAdditional
Renewable Resource
Total
Production
Cost (M$)
Change in
Production
Cost (M$)
Rating of
Additional
Resource
(MW)
Resource
Value
($/kw/yr)
Value
Assuming
14% FCR
($/kw)
1 -- $1,035 -- -- -- --
2 50 MW Firm RE $982 $53 50 $1,051 $7,505
3 100 MW Firm RE $938 $97 100 $966 $6,899
4 260 MW Solar PV $972 $63 260 $242 $1,730
5 -- $970 -- -- -- --
6 50 MW Firm RE $928 $42 50 $845 $6,037
7 100 MW Firm RE $893 $77 100 $769 $5,493
8 100 MW Wind $948 $23 100 $226 $1,616
8 -- $948 -- -- -- --
9 50 MW Firm RE $910 $37 50 $743 $5,308
10 100 MW Firm RE $880 $67 100 $674 $4,816
![Page 79: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/79.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 64 Final Report 5/21/2013 Final Report 4/30/2013
The bottom three rows in Table 4-13 (highlighted in blue) show the values of adding firm renewable
resources to Scenario 8. Adding a 50 MW firm renewable resource on Maui is worth $5,308/kw and a
100 MW firm renewable resource is worth $4,816/kW.
Note that the value of a given resource declines as the renewable energy penetration level increases.
In Scenario 2, a 50 MW firm renewable resource on Maui is worth $7,505/kW. In Scenario 5, which
has 200 MW more wind resources than Scenario 1, a 50 MW firm renewable resource is worth
$6,037/kW. The diminishing returns are because the 50 MW firm renewable resource causes more
wind energy curtailment in Scenario 6 than in Scenario 2.
The production simulations that provide the basis for this analysis assumed existing operating
practices for Oahu and Maui thermal plants (fixed operating schedules, existing minimum power
limits). In Chapter 5, the resource values presented here are recalculated assuming modified
operating practices. The modified operating practices reduce curtailment and increase the values of
the renewable resources.
![Page 80: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/80.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 65 Final Report 5/21/2013 Final Report 4/30/2013
4.8 Emissions
Figure 4-28 shows total CO2, SOx and NOx emissions for the study scenarios. Figure 4-29 illustrates
the reductions in total emissions relative to the Base Case, assuming zero emissions from the new
firm renewable plants.
The tabulated data in Figure 4-29 shows that SOx and CO2 emissions in Scenario 1 are higher than in
the Base Case (negative values for reduction). This is because the AES coal plant produces more
energy in Scenario 1. Given that AES is the most economical unit on the system, it displaces some
energy from the Maui baseload units when the islands are interconnected.
Note: Assumes zero emissions from biomass and new firm generation additions
Figure 4-28: Total Emissions from Dispatchable Thermal Generation
ScenarioDC
MW
Wind
MW
Solar
MW
Firm RE
MW
1 200 200 0 0
2 50
3 100
4 260 0
5 400 400 0 0
6 50
7 100
8 500 0
9 50
10 100
![Page 81: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/81.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 66 Final Report 5/21/2013 Final Report 4/30/2013
Note: Assumes zero emissions from biomass and new firm generation additions
Figure 4-29: Reductions in Emissions from Thermal Generation Relative to Base Case
CO2
(KTons)
SOX
(Tons)
NOX
(Tons)
Scenario 1 -8 -173 1,261
Scenario 2 338 444 2,081
Scenario 3 661 987 2,697
Scenario 4 401 619 2,063
Scenario 5 623 834 2,341
Scenario 6 922 1,310 2,935
Scenario 7 1,188 1,713 3,402
Scenario 8 845 1,119 2,615
Scenario 9 1,110 1,532 3,152
Scenario 10 1,344 1,881 3,574
![Page 82: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/82.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 67 Final Report 5/21/2013 Final Report 4/30/2013
4.9 Thermal Cycling
Table 4-14 summarizes the annual hours of operation and starts for thermal baseload, cycling and
peaking units. This data is on a per unit basis. For example, the number of starts for a particular unit
type is determined by dividing the total number of starts for all units of that type by the number of
individual generating units of that type.
The hours of operation and number of starts for baseload units are the same for all scenarios. This is
because of the assumption that existing baseload unit operating practices would remain the same
for all scenarios (i.e., baseload units are operated on fixed schedules and are never decommitted).
Duty on cycling units decreases in nearly all interconnected scenarios as compared to the Base Case.
The exceptions are:
Scenario 1, where Oahu cycling unit hours and starts are slightly higher, and
Scenario 4, where Oahu cycling starts are higher.
Duty on Oahu peaking units decreases substantially in all interconnected scenarios. Instead, peaking
services are provided by increased utilization of peaking units on Maui, Lanai and Molokai.
Table 4-14: Average Annual Starts and Hours of Operation by Unit Type
Note: Baseload unit operation is dependent on fixed operating schedules. For example, starts are dictated by fixed daily
schedules and CC plants cycled individual turbines regularly. For more information, see Section 2.5.
![Page 83: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/83.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 68 Final Report 5/21/2013 Final Report 4/30/2013
Of particular importance for thermal cycling is the AES coal plant because it represents the lowest
variable cost of any thermal resource on the system. Because of this, AES will be the last unit backed
down to its minimum power during periods of high renewable penetration. This makes AES an
interesting plant to look at to observe cycling trends across the scenarios.
Figure 4-30 shows the annual duration curves for the AES coal plant for each scenario. From this
figure it can be observed that the number of partload hours increases dramatically as renewable
penetration increases. In the base case, AES runs about 33% of the time at minimum load (72 MW). In
Scenario 10 this ratio increases to around 55%.
Figure 4-30: Duration Curve of AES Output for All Scenarios
![Page 84: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/84.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 69 Final Report 5/21/2013 Final Report 4/30/2013
4.10 Down-Regulation and Up-Range
Figure 4-31 shows hourly generation profiles and system down-regulation range for the Scenario 1
week with the most renewable energy. During nighttime hours when load is low and wind
generation is high, some of the available wind generation is curtailed because the thermal units
cannot be decommitted and they cannot be dispatched below the level required to maintain
required down-regulation reserves (90 MW at night). This simulation result assumes that thermal
units are operated on fixed schedules, per existing operating practices.
Figure 4-31: Hourly Generation Profiles and System Down-Regulation Range for One Week,
Scenario 1
Thermal fleet operating at minimum power,
which forces curtailment of wind and solar generationDown-Regulation
![Page 85: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/85.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 70 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-32: Duration Curve of Down-Regulation Range for Scenarios 1 and 10
Figure 4-32 is an annual duration curve showing hourly down-regulation range for Scenario 1 (least
renewable energy resources) and Scenario 10 (most renewable energy resources). In Scenario 1, the
thermal fleet is operating at its minimum down-regulation limit for about 8% of the time. In Scenario
10, the thermal fleet is at its minimum down-regulation limit for more than 50% of the time. Two
options for reducing hours at minimum power and thereby reducing curtailment are:
Relax the existing practice of fixed operating schedules for all baseload units
Reduce the minimum power limits on some of the baseload units
Both of these options are examined in Chapter 5 to determine the benefits these options can provide
to the system. However, the costs for these options and extent to which these options can be
implemented are not currently known and not considered in this study.
90 MW = Min Required Down-Reg at Night
![Page 86: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/86.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 71 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-33: Hourly Generation Profiles and System Up-Range for One Week, Scenario 1
Figure 4-33 shows hourly generation profiles and system up-range for the Scenario 1 week with the
most renewable energy. Up-range is at its highest level (about 500 MW) during periods when the
thermal fleet is at its minimum power limit, which is also when wind generation is curtailed.
Figure 4-34 is an annual duration curve showing hourly up-range for Scenarios 1 and 10 (least and
most renewable energy resources). The plot illustrates that as renewable energy resources increase,
the thermal fleet is dispatched to lower power levels, thereby increasing up-range significantly for
nearly all hours of the year. Figure 4-35 shows these same two traces together with the hourly total
spinning reserve requirements for Scenarios 1 and 10. The system commitment and dispatch are
dictated by reserve requirement about 16% of the time in Scenario 1 and 21% of the time in Scenario
10. The rest of the time, the system has a significant up-range surplus, primarily due to the existing
practice of operating baseload units on fixed schedules.
![Page 87: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/87.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 72 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-34: Up-Range Duration Curves for Scenarios 1 and 10 (Min & Max Renewables)
Figure 4-35: Reserve Requirements and System Up-Range for Scenarios 1 and 10
Un
it c
om
mit
me
nt
dic
tate
d b
y r
es
erv
es
Unit commitment dictated by
fixed operating schedules
Un
it c
om
mit
me
nt
dic
tate
d b
y r
es
erv
es
Unit commitment dictated by
fixed operating schedules
![Page 88: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/88.jpg)
Hawaii Stage 2 Interconnection Study Results
GE Energy Consulting 73 Final Report 5/21/2013 Final Report 4/30/2013
Figure 4-36: Hourly Up-Range and DC Cable Flow for Week with Highest DC Cable in Scenario 10
Figure 4-36 shows the hourly up-range (blue shaded area) for the week with the highest flow on the
two DC cables from Maui County to Oahu. The black dotted trace shows the total flow on both DC
cables. The red regions indicate a few time periods when DC cable flow exceeds the up-range of the
thermal generation on Oahu. This plot shows that with existing operating practices, the Oahu
thermal fleet has adequate up-range to fully cover the double-contingency loss of both DC cables
most of the time. The lower dotted trace shows the flow on one DC cable. The up-range is more
than adequate to cover the loss of one DC cable in all hours.
4.11 Key Observations
This chapter presented scenario analysis assuming existing operating practices and minimum power
limits for baseload generation. The results show that:
Interconnecting Maui County and Oahu reduces thermal plant production cost relative to the base case, lowers overall reserve requirements and adds flexibility in the combined generation fleet.
Much more renewable energy can be delivered to serve load, however there is curtailment of renewable energy in each case, which increases with increasing levels of renewable energy added to the system.
DC cables with 200 MW nominal ratings are able to transfer the all the additional renewable energy from Maui County to Oahu most of the time.
Curtailment occurs mostly at night when baseload units are running at minimum power and cannot
be decommitted given existing operating practices. Results suggest that curtailment could be
significantly reduced if baseload unit operating schedules are relaxed and minimum power limits are
reduced. Chapter 5 examines the impact of mitigation measures on curtailment.
Week of July 6-12: High DC Line Flow
MW
![Page 89: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/89.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 74 Final Report 5/21/2013 Final Report 4/30/2013
5 Changes to Operational Practices One of the key results from Chapter 4 was that curtailment of renewable energy would occur in all
scenarios studies, and at higher penetrations the curtailment could be as much as 25% of available
wind and solar energy. Any modifications that could be made to the operating practices that would
reduce curtailment would reduce the production cost of energy by delivering more of the renewable
energy without having to install any additional capacity. To investigate this, three levels of sensitivity
cases were run on each of the scenarios, each building upon the results of the prior analysis. These
sensitivities are shown pictorially in Figure 5-1 and explained in more detail below.
Figure 5-1: Sequential Changes to Operational Practices
Step “A” was to remove the fixed operating schedules on the Maui baseload generation. These are
units which have historically been operated on fixed daily schedules but which may not be needed to
operate at all times with the addition of new renewable generation. The Maui units that were
affected are the Maalaea Combined Cycle units (M141516 and M171819) and the Kahului generators
(K1-K4). Allowing these units to shut down during periods of low load and/or high renewables could
help reduce total renewable curtailment and improve the operating efficiency of the remaining
thermal generation.
Step “B” was to reduce the minimum power limits on some of the Oahu units. The minimum limits on
some units were assumed to be reduced by 50% from their initial values. For example, the Kahe 1
unit, with a full load capacity of 82.1 MW, had its operating minimum reduced from 32.5 MW to 16.25
MW. In both cases the unit was required to hold 9.0 MW of Down Regulation so that the minimums
used in the modeling were 41.5 MW and 25.25 MW respectively. In this example the reduced
minimum on the Kahe 1 unit could allow the renewable curtailment to be reduced by 16.25 MW in an
hour. Table 5-1 shows the modifications for all of the units that were affected.
The final sensitivity, Step “C”, was to remove the fixed operating schedules on the Oahu generation.
The units affected were Waiau 7&8 and Kahe 1-4.
This section investigates possible future modifications to grid operations. However, the Oahu and
Maui County systems cannot currently operate according to the assumptions outlined above and the
modified units cannot currently run as assumed in this chapter. In addition, the feasibility and costs
required for these modifications is unknown and not considered in the cost-benefit analysis found in
Chapter 8.
![Page 90: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/90.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 75 Final Report 5/21/2013 Final Report 4/30/2013
It is important to note that the modifications are incremental to one another and that the order of
the modifications matter relative to the overall benefits accrued to each step. For example, if the
Oahu fixed operating schedules were removed prior to the Maui fixed operating schedules, the
incremental value associated with that change in isolation would be different. However, regardless of
the order, the final “modified operating practices” of all three steps would be unchanged.
Table 5-1: Reduced Minimum Power Limits on Oahu Units
5.1 Production Cost Impacts
The production cost (fuel cost + VOM + start cost) impacts for Scenario 1 are shown in the waterfall
chart in Figure 5-2. Eliminating the fixed operating schedules for Maui baseload units reduced the
production costs by $17.4M. Reducing the Oahu minimum power limits saved an additional $23.1M
and eliminating the Oahu must-run requirements further reduced costs by $10.4M. Overall the three
changes reduced the annual system production costs by $51 million, or approximately 5%. This is
also six times the value seen from interconnecting the two independent systems when going from
the two Base Cases to Scenario 1.
Unit Name
Technical
Minimum
Power
Decreased
Minimums
Down
Regulation
Min Capacity
with Down
Regulation
Kahe 1 32.5 16.3 9.0 25.3
Kahe 2 32.7 16.4 9.0 25.4
Kahe 3 32.3 16.2 9.0 25.2
Kahe 4 32.3 16.2 9.0 25.2
Kahe 5 50.7 25.4 9.0 34.4
Waiau 7 23.0 11.5 9.0 20.5
Waiau 8 23.0 11.5 9.0 20.5
AES 63.0 N/A 9.0 72.0
Kalaeloa 1 65.0 N/A 4.5 69.5
Kalaeloa 2 65.0 N/A 4.5 69.5
Oahu Down Reserves (Total = 90 MW)
![Page 91: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/91.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 76 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-2: Production Cost Savings by Sensitivity for Scenario 1
Figure 5-3 and Table 5-2 show graphically and in tabular form the production cost impacts of each
of the sensitivities for Scenarios 1 through 10.
Figure 5-3: Impact of Operating Changes on Production cost for Scenarios 1-10
![Page 92: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/92.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 77 Final Report 5/21/2013 Final Report 4/30/2013
Table 5-2: Production Cost Impact (M$) of Operating Changes
Table 5-3 shows the incremental changes in production costs for each of the sensitivities for the ten
scenarios. As the renewable zero cost generation increases, the value of these operational changes
triples from roughly $50 million in Scenario 1 to nearly $150 million in Scenario 10. This is a
significant impact on the total system production costs and curtailment. Figure 5-4 shows the total
savings impact of all three operating changes as a portion of the original production cost or each
scenario.
Table 5-3: Incremental Savings (M$) from Operating Changes for Scenario 1-10
Existing Operating
Practices
Step A: Remove Maui
Fixed Operating
Schedules
Step B: Reduced Oahu
Minimums
Step C: Remove Oahu
Fixed Operating
Schedules
Scenario 1 1,035 1,017 994 984
Scenario 2 982 957 927 912
Scenario 3 938 906 868 847
Scenario 4 972 952 921 910
Scenario 5 970 943 903 885
Scenario 6 928 894 845 822
Scenario 7 893 853 796 765
Scenario 8 948 916 865 844
Scenario 9 910 861 808 785
Scenario 10 880 821 761 733
Step A: Remove Maui
Fixed Operating
Schedules
Step B: Reduced Oahu
Minimums
Step C: Remove Oahu
Fixed Operating
Schedules
Total Production
Cost Savings
Scenario 1 17.4 23.1 10.4 51.0
Scenario 2 25.5 29.8 15.2 70.4
Scenario 3 32.7 37.9 21.1 91.7
Scenario 4 20.3 30.4 11.2 61.9
Scenario 5 26.7 40.3 17.7 84.7
Scenario 6 34.2 48.4 23.4 106.0
Scenario 7 40.1 57.3 30.3 127.7
Scenario 8 31.9 50.6 21.3 103.9
Scenario 9 49.1 53.1 22.3 124.5
Scenario 10 58.7 60.3 27.9 146.9
![Page 93: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/93.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 78 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-4: Production Cost Savings from all Changes
5.2 Curtailment and Renewable Generation
Although some of the production cost savings shown in the previous section were due to the
remaining thermal fleet operating more efficiently, the bulk of the savings were simply due to the
reduced curtailment of zero cost renewable energy displacing high cost thermal generation. This
section examines the impact on curtailment directly. Figure 5-5 shows a waterfall of the total
renewable curtailment for Scenario 1 under existing operating practices and each of the three
assumed changes. The existing practices resulted in 145 GWh of curtailment. Removing the Maui
fixed operating schedules reduced curtailment by 36 GWh. Reducing the minimum ratings on the
Oahu units reduced curtailment by an additional 78 GWh, and elimination of the Oahu fixed
operating schedules provided a savings of 25 GWh. Overall the curtailment dropped from 145 GWh
to only 6 GWh, a reduction of over 95%. Also note that adding the assumed modifications in a
different order would produce different incremental results, although the final “modified operating
practices” would be unchanged.
![Page 94: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/94.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 79 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-5: Reduced Curtailment due to Operational Changes for Scenario 1
Figure 5-6 and Table 5-4 show the total curtailment for each of the three operating sensitivities for all
ten scenarios. As the renewable penetration increases so does the impact of these operating
changes. Figure 5-7 and Table 5-5 show the corresponding reductions in curtailment.
![Page 95: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/95.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 80 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-6: Curtailment of Renewable Energy by Sensitivity for Scenarios 1-10
Table 5-4: Curtailment (GWh) of Renewable Energy by Sensitivity for Scenarios 1-10
Existing Operating
Practices
Step A: Remove Maui
Fixed Operating
Schedules
Step B: Reduced Oahu
Minimums
Step C: Remove Oahu
Fixed Operating
Schedules
Scenario 1 145 108 31 6
Scenario 2 223 170 59 13
Scenario 3 321 254 105 31
Scenario 4 167 122 33 6
Scenario 5 373 301 143 71
Scenario 6 509 413 208 109
Scenario 7 671 554 299 168
Scenario 8 579 481 257 156
Scenario 9 751 565 322 218
Scenario 10 945 723 431 303
![Page 96: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/96.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 81 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-7: Potential Total Reduction in Curtailment
Table 5-5: Reduction in Curtailment by Sensitivity
Figure 5-8 revisits the renewable penetration by scenario. The dark blue portion of each bar
represents the amount of renewable energy delivered to the system under existing operating
practices. The medium blue segment shows the additional percent of load that can be served by the
renewable generating units when the operating practices are relaxed. Finally, the light blue piece
shows the remaining curtailed energy in each scenario. In all cases the curtailment has been
significantly reduced and in some instances all but eliminated. Figure 5-9 compares curtailment
across scenarios with existing and modified operating practices.
Step A: Remove Maui
Fixed Operating
Schedules
Step B: Reduced Oahu
Minimums
Step C: Remove Oahu
Fixed Operating
Schedules
Total Reduction
Scenario 1 36.2 77.7 25.1 139.0
Scenario 2 52.8 111.4 45.6 209.8
Scenario 3 67.1 149.0 73.5 289.6
Scenario 4 44.3 89.6 26.8 160.7
Scenario 5 72.5 158.2 72.0 302.7
Scenario 6 96.6 204.2 98.9 399.7
Scenario 7 116.8 254.6 130.8 502.3
Scenario 8 98.3 223.5 101.5 423.3
Scenario 9 185.2 243.7 104.0 532.8
Scenario 10 221.8 291.7 128.2 641.7
![Page 97: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/97.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 82 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-8: Impact on Renewable Penetration of Modified Operational Changes.
Figure 5-9: Change in Curtailment with Modified Operating Practices by Scenario
Existing Operating Practices Modified Operating Practices
![Page 98: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/98.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 83 Final Report 5/21/2013 Final Report 4/30/2013
5.3 DC Cables Constrained
Figure 5-10 shows duration curves of the flow on the DC cables for Scenario 10 under existing
operating practices as well as the three operating sensitivities. The initial sensitivity, removing the
Maui fixed operating schedules, reduces the flow on the lines because more of the renewable energy
can now displace higher cost energy in Maui County. The other two sensitivities, which affect the
operation of the thermal units on Oahu, then increase the flows on the lines due largely to reduced
curtailment. The maximum flow on the line, however, never exceeds the value found under the
existing practices.
Figure 5-10: DC Cable Flow Duration Curves for Scenario 10 by Operating Sensitivity
![Page 99: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/99.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 84 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-11 shows the maximum flow on the DC cables for current operating practices and the three
operating sensitivities for all ten scenarios. The maximum flow for all of the sensitivity cases is
always less than the original flow for each of the scenarios.
Figure 5-11: Maximum DC Cable Flows (MW) by Operating Sensitivity
![Page 100: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/100.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 85 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-12 and Table 5-6 show the resulting energy flows for each scenario and operating
sensitivity. In some of the cases the energy flow has increased above that seen in the corresponding
base scenario.
Figure 5-12: Energy Flows (GWh) on DC Cables by Sensitivity
Table 5-6: Energy Flows (GWh) on DC Cables by Sensitivity
![Page 101: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/101.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 86 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-13 shows the flow duration curves on the DC cables for all ten scenarios. Remember, the
first four scenarios have a single DC cable with a nominal rating of 200 MW. The remaining scenarios
have two cables with a combined nominal rating of 400 MW, although these ratings were not
imposed in the analysis.
Figure 5-13: DC Cable Flow (MW) Duration Curves for Scenario 1-10 with Operating Changes
Table 5-7 includes various operating statistics for the DC cables for each of the scenarios with all of
the suggested operating changes in place. Included in the statistics is the number of hours with
flows exceeding the nominal ratings and the total energy flows that would have occurred above
those ratings. Figure 5-14 shows the total energy flows below and above the nominal ratings.
Table 5-7: DC Cable Flow Summary with Operating Changes
Total Flow
(GWh)
Max Flow
(MW)
Min Flow
(MW)
Avg Flow
(MW)
Hours of
Flow from
Lanai to
Oahu
Hours
>200 MW
Total
Energy
>200 MW
Scenario 1 625 190 -30 71 70% 0 0
Scenario 2 837 228 -30 96 83% 218 2
Scenario 3 1,143 263 -30 131 97% 1,978 41
Scenario 4 618 188 -30 71 68% 0 0
Scenario 5 1,229 334 -60 140 80% 0 0
Scenario 6 1,455 381 -60 166 89% 0 0
Scenario 7 1,747 417 -51 199 99% 51 0
Scenario 8 1,511 412 -60 172 82% 16 0
Scenario 9 1,727 457 -60 197 91% 366 6
Scenario 10 1,994 487 -47 228 99% 1,009 30
![Page 102: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/102.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 87 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-14: DC Cable Energy Flows (GWh) by Scenario with Operating Changes in Place
5.4 Value of Renewable Energy Resources
Section 4.7 examined the value (in $/KW), based on reductions in annual production cost, of the
various renewable energy resources assuming existing operating practices. This value was
determined by looking at the change in production costs between the various scenarios. As the
previous sections have shown, relaxing some of the operating constraints will make the total
production costs drop. This section will re-examine the value of the resources based on the new
operating costs. Table 5-8 shows the updated values of the renewable resources using the
production costs from Table 5-2 based on the modified operating practices. Table 5-9 compares
these results to those shown previously in Table 4-13. This comparison is shown graphically in Figure
5-15. In all cases the resources are more valuable with the relaxed operating constraints. The
impact of diminishing returns is still evident in that in all cases the 100 MW of firm renewable did not
cause as much of a reduction in total production costs, in average $/KW, as the initial 50 MW. Also,
the impact of the firm renewable generation decreases as it is added into base systems with
increasing levels of wind resources.
![Page 103: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/103.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 88 Final Report 5/21/2013 Final Report 4/30/2013
Table 5-8: Value of Additional Renewable Resources with Modified Operating Practices
Table 5-9: Comparison of the Value of Renewable Resources Based on Operating Assumptions
ScenarioAdditional
Renewable Resource
Total
Production
Cost (M$)
Change in
Production
Cost (M$)
Rating of
Additional
Resource
(MW)
Resource
Value
($/kw/yr)
Value
Assuming
14% FCR
($/kw)
1 -- $984 -- -- -- --
2 50 MW Firm RE $912 $72 50 $1,440 $10,284
3 100 MW Firm RE $847 $137 100 $1,373 $9,807
4 260 MW Solar PV $910 $74 260 $284 $2,030
5 -- $885 -- -- -- --
6 50 MW Firm RE $822 $63 50 $1,266 $9,046
7 100 MW Firm RE $765 $120 100 $1,201 $8,576
8 100 MW Wind $844 $41 100 $412 $2,944
8 -- $844 -- -- -- --
9 50 MW Firm RE $785 $59 50 $1,173 $8,377
10 100 MW Firm RE $733 $111 100 $1,110 $7,928
Existing
Operating
Pracitices
Modified
Operating
Practices
1 -- -- --
2 50 MW Firm RE $7,505 $10,284
3 100 MW Firm RE $6,899 $9,807
4 260 MW Solar PV $1,730 $2,030
5 -- -- --
6 50 MW Firm RE $6,037 $9,046
7 100 MW Firm RE $5,493 $8,576
8 100 MW Wind $1,616 $2,944
8 -- -- --
9 50 MW Firm RE $5,308 $8,377
10 100 MW Firm RE $4,816 $7,928
Value Assuming 14% FCR
ScenarioAdditional
Renewable Resource
![Page 104: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/104.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 89 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-15: Comparison of Values of Renewable Resources with Different Operating
Assumptions
![Page 105: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/105.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 90 Final Report 5/21/2013 Final Report 4/30/2013
5.5 Other Impacts
Other operating impacts were examined as well. Figure 5-16 examines the effect on unit operations
for Scenario 10. The curve on the left shows the total output from Kahe 1-5 for the changes in
operating practices. The lowering of the minimum power limit and the elimination of fixed operating
schedules allow this plant to cycle down significantly from its initial operation. Contrastingly, the
curve on the right shows how the AES coal plant can increase its utilization when other operating
practices are relaxed.
Figure 5-16: Kahe and AES Plant Operating Impacts for Scenario 10
Figure 5-17 shows the combined duration curves of the Oahu baseload unit dispatch for each hour
of the year under the existing operating practices and the modified operating practices discussed
previously in this chapter. In addition, it shows the number of Oahu baseload units online under the
two sets of assumptions. Scenario 10 was selected for this comparison because it represents the
highest penetration of renewable energy and therefore the largest potential reduction in baseload
unit utilization. Under the modified operating practices there is a concern that too many units will be
turned off and the system may have less thermal resources available during times of stress
(contingency events or high renewable variability). However, these charts highlight that the value
from reduced production costs can be captured with only a small change in the minimum number of
baseload units online. Figure 5-18 shows the similar chart for Maui baseload units.
![Page 106: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/106.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 91 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-17: Oahu Baseload Unit Operating Impacts for Scenario 10
Figure 5-18: Maui Baseload Unit Operating Impacts for Scenario 10
Figure 5-19 and Figure 5-20 examine the up-range and down regulation duration curves for Oahu for
Scenario 10. The excess up-range is tightened up significantly in the first figure. The second shows
that the down regulation is generally larger, although removing the fixed operating schedules
allowed the down regulation to drop slightly below the requirement about 25% of the time because
units were decommitted. Due to the way that the MAPS model allocated the down regulation to
individual units, their portion was lost when the unit was decommitted. In practice the down
regulation that those units were carrying would be picked up by other units but that should not
significantly affect the overall results shown here.
![Page 107: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/107.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 92 Final Report 5/21/2013 Final Report 4/30/2013
Figure 5-19: Oahu Up-Range Duration Curve with Operating Changes
Figure 5-20: Oahu Down-Regulation Duration Curves by Sensitivity
![Page 108: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/108.jpg)
Hawaii Stage 2 Interconnection Study Changes to Operational Practices
GE Energy Consulting 93 Final Report 5/21/2013 Final Report 4/30/2013
5.6 Key Observations
This chapter presented the scenario analysis assuming modified operating practices and reduced
minimum power limits for baseload generation. The results show that:
Significant reductions in production costs can be achieved compared to existing practices. The benefits of reduced production costs increase with increasing renewable penetration. However, the thermal units cannot currently run as assumed in this analysis and the feasibility and costs required to do so is currently unknown. These costs, in addition to the cost of the additional renewable energy provided, would need to be taken into account to determine the value of these modifications.
The benefits from reduced production cost occur largely due to the reduction in renewable curtailment and subsequent reduced utilization of the dispatchable thermal units. In some cases the curtailment is all but eliminated.
The maximum flows on the DC cables are lower than those seen under existing practices. The
energy flows above the nominal ratings (200 MW per cable) have also been reduced.
![Page 109: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/109.jpg)
Hawaii Stage 2 Interconnection Study Sensitivity Analysis
GE Energy Consulting 94 Final Report 5/21/2013 Final Report 4/30/2013
6 Sensitivity Analysis Chapter 2 covered the standard set of assumptions that were used throughout the analysis. In order
to isolate the impact of increased renewables on the interconnected system, load and fuel prices
were held constant throughout each scenario. This section provides load and fuel sensitivities to
understand how the results would be impacted, given a change to the load and fuel price
assumptions.
6.1 Load Growth Sensitivities
Sensitivity analysis was conducted by increasing and decreasing the hourly load patterns by a
constant 5%. No changes were made to the overall annual load shape; rather each hour was
changed by a constant percentage. Figure 6-1 shows the annual hourly duration curves for the base
case and the sensitivities used in this study. The load sensitivities were conducted on two scenarios,
Scenario 1 and Scenario 7, because those scenarios have the largest difference wind and solar
generation. The results discussed in this section look at the change in production cost (fuel cost +
VOM + start cost) and annual wind and solar curtailment.
Figure 6-1: Load Growth Sensitivity Hourly Duration Curves
Figure 6-2 shows the change in production cost between the different load scenarios. The x-axis is
the amount of annual load on the system. On the left plot, the y-axis is total annual production cost
(M$) and the right plot shows the change in production cost relative to the base case.
Figure 6-3 shows the change in wind and solar curtailment under different load sensitivities for
Scenario 1 and Scenario 7. The x-axis represents the amount of load on the system, and the y-axes
represent the amount of curtailment. The left axis represents curtailment in GWh and the right axis
as a percent of total available wind and solar energy.
![Page 110: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/110.jpg)
Hawaii Stage 2 Interconnection Study Sensitivity Analysis
GE Energy Consulting 95 Final Report 5/21/2013 Final Report 4/30/2013
Figure 6-2: Change in Production Cost in Load Sensitivities
Figure 6-3: Wind & Solar Curtailment by Load Growth Sensitivity
![Page 111: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/111.jpg)
Hawaii Stage 2 Interconnection Study Sensitivity Analysis
GE Energy Consulting 96 Final Report 5/21/2013 Final Report 4/30/2013
From these two plots it can be determined that;
The total production costs increase in the sensitivities with increased load, and decrease in the sensitivities with decreased load. This is not surprising because increased demand for electricity must be served, at least in part, by increased thermal generation. For example, in Scenario 1 a 5% increase in load will ultimately lead to a $72 million increase in production cost (7%).
Although the trends in Scenario 1 and Scenario 7 are similar, the rate of change (slope) of production cost change is smaller for Scenario 7. For example, overall production cost only increases by $42 million (4.8%) for the same change in load. This is because in a high renewables scenario, an increased share of the additional load will be served by wind and solar energy. In the high load growth scenario, additional load is served first with wind and solar energy that was curtailed in the base case. On the other hand, lower than expected load will mean relatively more curtailment and less than expected production cost savings.
Scenarios with increased renewable energy will experience larger changes of overall curtailment given an equal change in load.
Overall, a high renewable scenario will mean less volatility in production cost given equal changes in system load.
6.2 Fuel Price Sensitivities
Another uncertainty in modeling future scenarios is the fuel price forecast. Historical experience has
shown significant volatility in fuel prices, which leads to volatility in production cost (fuel cost + VOM +
start cost) and electricity prices. This is especially true for Hawaii due to reliance on imported fuel and
the dominance of oil-fired generation resources. To account for this forecast uncertainty, sensitivity
analysis was performed by using a 10% and 20% increase and decrease on the assumed oil price
inputs. For this analysis, “oil price” includes all petroleum derivative products including residual oil,
distillate oil and diesel fuels.
Figure 6-4 shows the breakdown of total production cost by oil consumption, coal consumption,
VOM, and start costs for Scenario 1. Overall, 95% of the total system production cost is directly
related to oil consumption. The VOM and start cost component of production cost make up around
1% of the total. Because such a significant portion of overall production cost relies on the oil price, it
is likely that any increase or decrease in the oil price will lead to an equal percent change in the total
system production cost. For example, a 10% increase in fuel price will lead to a near 10% increase in
total production cost.
Figure 6-5 shows the elasticity of fuel price and production cost. This sensitivity analysis confirms
that fuel price and production cost are near unit elastic – a 1% change in fuel price will lead to a 1%
change in production cost.
![Page 112: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/112.jpg)
Hawaii Stage 2 Interconnection Study Sensitivity Analysis
GE Energy Consulting 97 Final Report 5/21/2013 Final Report 4/30/2013
Figure 6-4: Fuel Cost as a Component of Overall Production Cost
Figure 6-5: Elasticity of Fuel Prices and Production Cost
![Page 113: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/113.jpg)
Hawaii Stage 2 Interconnection Study Sensitivity Analysis
GE Energy Consulting 98 Final Report 5/21/2013 Final Report 4/30/2013
Figure 6-6 shows the change in production cost by sensitivity in Scenario 1 and Scenario 7 under
different fuel price assumptions. From the figure it can be determined that;
The change in production cost under different fuel sensitivities is less for the high renewable scenario (Scenario 7) than a scenario with less renewable energy. This is simply due to less overall fuel consumption as renewable penetration increases.
Larger amounts of wind, solar and firm renewable energy will decrease volatility in production cost when fuel prices change assuming the price for the renewable resources is not tied to the price of oil.
Figure 6-6: Change in Production Cost in Fuel Sensitivities
![Page 114: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/114.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 99 Final Report 5/21/2013 Final Report 4/30/2013
7 Energy Storage Options Whenever renewable energy is being evaluated the question always arises as to the efficacy of
Energy Storage devices to help mitigate the variability and minimize the amount of curtailment
required. In this analysis Energy Storage is evaluated over a range of sizes for two distinct operating
modes. In section 7.1 Energy Storage is examined as purely a reserve asset. Section 7.2 considers its
ability to shift energy from times of curtailment and low costs in order to offset oil fired thermal
generation at a later period. Section 7.3 compares the results of these two operating strategies.
The analysis in this section was based on the results for Scenario 7 which included 200 MW of wind
generation on Lanai, 200 MW of wind generation on Molokai and 100 MW of firm renewable energy
on Maui in addition to the existing resources. All recommended operating changes were also
incorporated. This included removing the fixed operating schedules on the Maui and Oahu baseload
generation and reducing the minimum power limits on the Oahu base load generation. In addition,
the analysis was considered to be technology neutral and demonstrate the benefits associated with
a generic energy storage device, however battery energy storage was assumed for the cost/benefit
analysis in Section 7.3. In both sets of analysis storage sizes from 50 MW to 200 MW were
considered.
7.1 Energy Storage as a Reserve Asset
The first analysis considered Energy Storage as an asset capable of providing contingency and
operating reserves. As has been described in previous sections the variability of the wind and solar
generation requires additional operating reserves to be carried. When thermal resources are
committed to provide these reserves they may not be able to shut down during low load or high
renewable periods thereby increasing the amount of renewable curtailment that must take place. An
energy storage device, such as a battery, could provide some of the necessary reserves without
introducing additional minimum generating requirements.
Figure 7-1 shows the operating and contingency reserve duration curves for Scenario 7 and the four
different levels of energy storage considered. The top curve is the same as was shown in Figure 3-8
with the addition of the 185 MW of contingency reserves. The storage device allows the reserves
from thermal generation to be reduced in all hours of the year. In order to do this the device can only
be used as a reserve asset and cannot simultaneously be used as an energy shifting device.
![Page 115: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/115.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 100 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-1: Operating and Contingency Reserve Duration Curves with Energy Storage
The annual operation of the system was simulated for these four new sensitivities. Figure 7-2 shows
the total production cost (fuel cost + VOM + start cost) and the average benefits of the storage
devices in $/KW. These values, and the total savings, are also shown in Table 7-1. While the overall
benefits continue to increase with increasing amounts of storage it is with diminishing returns. The
maximum value was with 50 MW of storage and was worth roughly $250/KW/yr.
Reserv
e R
eq
uir
em
en
t Scenario 7
50mw Storage
100mw Storage
150mw Storage
200mw Storage
![Page 116: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/116.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 101 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-2: Annual Production Cost Savings with Energy Storage as a Reserve Asset
Table 7-1: Annual Production Cost Savings with Energy Storage as a Reserve Asset
The source of this value can be seen in Table 7-2. As energy storage provides increasing amounts of
reserves the amount of wind and solar curtailment drops from 192 GWh to only 133 GWh. With
relaxed operating reserves and 200 MW of energy storage reducing the reserves, nearly 95% of the
available wind and solar generation is captured.
Scenario
Total
Production
Cost (M$)
Savings
(M$)
Average
Benefits
($/KW)
Scenario 7* 751.5
50mw Storage 739.0 12.5 250.00
100mw Storage 730.0 21.5 215.00
150mw Storage 722.7 28.9 192.67
200mw Storage 715.9 35.6 178.00
*Assumes Modified Operating Practices
![Page 117: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/117.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 102 Final Report 5/21/2013 Final Report 4/30/2013
Table 7-2: Delivered Wind and Solar Energy with Energy Storage as a Reserve Asset
Table 7-3 shows how the energy generation shifted by generation type by island. Not surprisingly
the generation in Maui County did not change significantly. In Oahu, however, the base load thermal
generation increased along with the delivered wind energy while the cycling units backed down by
almost an order of magnitude.
Table 7-3: Energy Generation by Island with Energy Storage as a Reserve Asset
Reducing reserve requirements while also modifying operating practices will ultimately decrease the number of baseload units online during each hour of the year. With 200 MW less reserve requirement on the system, less baseload units will be committed to serve load and provide reserves. Figure 7-3 shows the impact of reduced reserves on the operation of Oahu’s baseload units.
ScenarioTotal Wind &
Solar (GWh)
Additional
Wind (GWh)
Curtailment
(GWh)
Delivered
Energy (%)
Scenario 7* 2,335 - 192.4 92%
50mw Storage 2,365 30.0 162.4 94%
100mw Storage 2,379 44.6 147.8 94%
150mw Storage 2,386 51.4 141.0 94%
200mw Storage 2,394 59.5 132.9 95%
*Assumes modified operating practices
Base50mw
Storage
100mw
Storage
150mw
Storage
200mw
Storage
OAHU 7,589 7,597 7,602 7,604 7,604
BASELOAD 5,364 5,413 5,458 5,494 5,512
CYCLING 210 144 90 50 25
PEAKING 11 7 6 5 5
SOLAR 180 180 180 180 180
WIND 1,823 1,852 1,867 1,874 1,882
MAUI 1,674 1,671 1,671 1,671 1,672
BASELOAD 1,333 1,332 1,332 1,332 1,333
CYCLING 4.6 4.2 4.2 4.5 5.1
PEAKING 4.7 3.6 3.0 2.7 2.3
SOLAR 25 25 25 25 25
WIND 307 307 307 307 307
LANAI 0.6 0.4 0.3 0.3 0.3
MOLOKAI 2.7 1.9 1.7 1.4 1.2
![Page 118: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/118.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 103 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-3: Oahu Baseload Unit Operating Impacts with Reduced Reserve Requirement
![Page 119: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/119.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 104 Final Report 5/21/2013 Final Report 4/30/2013
7.2 Energy Storage as an Energy Shifting Asset
When the energy storage device is modeled to shift energy it is assumed that charging will take
place, storage levels allowing, whenever renewable energy is being curtailed or the AES coal plant is
being operated below its maximum rating. First preference is given to charging with curtailed
energy. Further, it is assumed that the storage device will generate energy whenever there is an
opportunity to displace oil-fired thermal generation and there is available down-range on the system.
In this way the energy is used as soon as it is economically attractive in order to make room for
additional charging as soon as possible. In some instances it may be possible to displace slightly
higher cost generation later in the day. However, there is no significant variation in the marginal cost
among the various oil-fired generators so the incentive to delay usage is small. The storage device is
assumed to be located on Oahu for the purpose of calculating DC cable flows.
In addition to varying the capacity of the storage device from 50 MW to 200 MW this analysis also
varied the size of the “reservoir” from 2 hours up to 100 hours. When the energy storage device is
being used to shift energy the storage size in MWh is a critical parameter. The value of the
generation provided is based on the spot price of the generation displaced minus the cost of
charging from the AES plant. Curtailed wind energy is assumed to be available at no charge. Round
trip efficiency of the storage is 80%.
Figure 7-4 shows the value of an energy storage device that is used to shift zero cost curtailed or low
cost thermal energy to a more desirable time frame.
Figure 7-4: Value of Energy Storage as an Energy Shifting Device
The most significant reductions to production cost are achieved with storage capabilities up to 12
hours. Adding storage levels beyond that increases the value only slightly. Increased capacities
beyond 50 MW provide slightly diminished returns. Figure 7-5 shows the utilization of the energy
storage for a 200 MW device with 6 hours of storage. Using the AES plant to supplement the
charging increased its value by 66%, as compared to charging only with curtailed energy.
![Page 120: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/120.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 105 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-5: Utilization of Energy Storage Device to Shift Energy
Figure 7-6 shows the average utilization by time of day for the same example. Almost all of the
charging is done overnight and the bulk of the generation (discharging) is done during the morning
load rise, although some generation is done later in the day.
Figure 7-6: Utilization of Energy Storage by Time of Day
Note: assumes 200MW asset with 6 hours of storage
Total Value: $23.9 million Total Value: $14.4 million
![Page 121: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/121.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 106 Final Report 5/21/2013 Final Report 4/30/2013
The graph on the left of Figure 7-7 shows the reduction in the renewable curtailment duration curve
for the same 200 MW asset. The curve on the right illustrates the increased utilization of the AES
plant.
Figure 7-7: Impact of 200MW, 6hr Storage Device on Renewable Curtailment and Coal Generation
7.3 Comparison of Energy Storage Results
Figure 7-8 shows the relative value (reduction in dispatchable thermal generation and production
cost) of a 2-hour storage device used for either energy shifting or reserve displacement as a function
of the storage charge/discharge rating. Regardless of the size, the reserve storage function provides
greater value. But while the value of the energy storage when used as a reserve asset will not
change as more hours of storage are added the previous charts have shown that the value of energy
shifting will increase.
![Page 122: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/122.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 107 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-8: Comparison of Savings for a 2-hour Storage Device
Figure 7-9 examines the value (reduction in dispatchable thermal generation and production cost) of
a 200 MW energy storage device. The diamond and horizontal dotted line show the value of the
device when used to provide spinning reserve. Increasing the hours of storage beyond one hour
adds no value to a device operated in this mode. The solid line shows the value when the device is
used for shifting energy within the week, and this does increase with increasing hours of storage.
This would seem to imply that a device with over 3 hours of storage would provide greater value
when used for energy shifting. However, the increased hours of storage come at an increased cost.
For a one-hour battery storage system roughly 50% of the cost is for the power conversion
equipment and the other half is for the storage. A two-hour battery will double the storage cost but
have no impact on the power conversion costs. In fact, the storage costs will continue to increase
linearly with the number of hours. In this way an Incremental Benefit can be calculated as:
(7-1)
As an example consider 3 hours of storage. The value when used for reserves is $12.4 M. When used
for energy shifting the value is $18.4 M. However, the relative cost for the 3-hour device is:
0.5 + 3(0.5) = 2 per unit
So that the incremental benefit = $18.4M / 2 = $9.2M. In this way it can be seen that the device used
for reserves, which only requires a single hour of storage, is still the better value. If this is continued
for all hours of storage the dotted curve labeled “Incremental Benefit of Energy Shifting” in Figure 7-9
is obtained. It can now be seen that no matter how many hours of storage are added it will never be
more economic than a one hour battery used to provide spinning reserve.
![Page 123: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/123.jpg)
Hawaii Stage 2 Interconnection Study Energy Storage
GE Energy Consulting 108 Final Report 5/21/2013 Final Report 4/30/2013
Figure 7-9: Comparison of Storage Options
Figure 7-10 extends this analysis across all four values of capacity (50MW, 100MW, 150MW and
200MW) for a range of storage sizes from 1 to 15 hours. Regardless of the capacity, no matter how
many hours of storage are added the energy shifting operation does not provide as much value as a
single hour of storage used to provide spinning reserve.
Figure 7-10: Comparison of Storage Options for a Range of Sizes
Assuming a 200MW asset, with different amounts of storage (MWh)
![Page 124: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/124.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 109 Final Report 5/21/2013 Final Report 4/30/2013
8 Cost-Benefit Analysis Prior to this section, much of the analysis has concentrated on the benefits (production cost savings)
of an interconnected Oahu and Maui County electricity grid with increased renewable penetration.
The production cost analysis includes all of the variable costs of generating electricity (fuel, variable
operations and maintenance, and start costs). It does not capture the fixed or capital costs necessary
for operating a power system or constructing new renewable energy sources. In order to adequately
plan for future scenarios and an interconnected system, it is important to also analyze the capital
costs required to achieve the production cost savings. This section compares the study scenarios
using a traditional cost-benefit analysis comprised of four steps;
1. Develop capital cost assumptions for each technology from external sources, 2. Apply capital cost assumptions to the renewable capacity and transmission additions and
calculate an estimated range of total capital costs for each scenario, 3. Calculate benefits (production cost savings) for each scenario. 4. Compare costs and benefits across the scenarios.
8.1 Capital Cost Data
Total plant capital cost depends on several variables, including equipment and site characteristics
which are unknown at this stage in the planning process. Rather than use a single capital cost
assumption, this analysis uses a potential range of assumptions for each technology. The range of
capital cost assumptions was developed using a sample of third-party, publicly available reports
deemed by the project team as reasonably accurate and current. Table 8-1 shows the capital cost
assumptions ($/KW) for onshore wind, photovoltaic solar, and geothermal resources across six
different sources (See Chapter 11 for references). For the purposes of the cost-benefit analysis, the
firm renewable capacity discussed throughout the previous sections is considered here to be a
geothermal resource. This was done to allow a cost-benefit analysis similar to other resources (wind
and solar) where the variable fuel cost is zero. All costs in Table 8-1 represent total plant installation
costs for utility-scale applications.
Table 8-1: Capital Cost Data for Wind, Solar and Geothermal from External Sources ($/KW)
In order to simplify the range of capital costs, this analysis uses the minimum, maximum and
average capital costs for each technology, shown at the bottom of Table 8-1. Figure 8-1 shows a
box-plot of the range of capital costs by technology to allow for direct comparison across
Source Wind (Onshore) Solar PV Geothermal
EIA $2,438 $4,755 $4,141 - $5,578
NREL $1,762 $6,051 $3,661
Black & Veatch $1,980 $2,357 $5,940
Big Wind $2,600 $7,100
EPRI Low $2,120 $3,725
EPRI High $2,825 $5,050
Melbourne ERI $1,925 $3,408
Minimum $1,762 $2,357 $3,661
Average $2,236 $4,635 $4,830
Maximum $2,825 $7,100 $5,940
![Page 125: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/125.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 110 Final Report 5/21/2013 Final Report 4/30/2013
technologies. The capital cost assumptions are lowest for wind and, on average, highest for
geothermal. However, solar PV has the largest range of cost estimates. This reflects the uncertainty
surrounding prices of future solar installations across the industry.
Figure 8-1: Capital Cost Assumptions by Technology
The cost-benefit analysis also includes the cost of the DC cables with a 1x200 MW configuration for
Scenarios 1-4 and a 2x200 MW configuration for Scenarios 5-10. The price for the transmission
upgrades is assumed to be $1,200/KW and is based on previous analysis in the Economics of Big
Wind study conducted for proposed wind projects on Lanai and Molokai. It includes the costs of the
DC cables and any infrastructure required to interconnect the systems. As a result, the total cost of
transmission interconnection is $480 million for scenarios with a single DC cable and $960 million for
two DC cables. This cost is added to the total cost of each scenario and is not assigned to the cost of
an individual project.
An estimate of the AC cable infrastructure capital cost is also included. Initial estimates from the
Interisland Transmission Interconnection Capital Cost Estimate1 suggest additional capital costs
between $601 million and $830 million for three undersea AC cables to interconnect Maui, Molokai,
and Lanai. For the purpose of this study, a central estimate of $715 million was assumed for the tri-
cable configuration. However, Scenarios 1-4 may not require all three cables and it might be possible
to implement some scenarios with fewer AC cables. Scenarios 1-4 are assumed in this analysis to
only require a single AC link between Lanai and Maui. This is because there is only a single DC link
between Lanai and Oahu and the quick-start capabilities are only needed from either Lanai or
Molokai, but not both. As a result, the assumed capital cost for the single AC cable in Scenarios 1-4 is
assumed to be 33% of the full estimate, or $238 million.
1 Interisland Transmission Interconnection Capital Cost Estimate.” Prepared for IRP 2013. HECO Transmission Planning
Division, revised March 20, 2013. Reference: TPD 2013-05-Rev1.
![Page 126: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/126.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 111 Final Report 5/21/2013 Final Report 4/30/2013
8.2 Capital Costs for Study Scenarios
Using the minimum, average and maximum capital cost data from Section 8.1, a total capital cost is
calculated for each scenario and shown in Table 8-2. The total capital cost (in millions of dollars)
includes the cost of all wind, solar and geothermal additions along with the necessary AC and DC
transmission upgrades to interconnect the island systems.
For example, Scenario 1 includes the 200 MW Lanai wind addition, along with a single DC cable
configuration and a single AC cable configuration. Therefore, the minimum capital cost estimate is
equal to the wind capacity addition (200,000 KW) multiplied by the minimum wind cost assumption
from Table 8-1 (1,762 $/KW). As a result, the cost of the wind addition (using the minimum cost data)
is $352.4 million, plus the cost of the DC transmission upgrades ($480 million) and the AC
transmission upgrades ($239 million), for a total capital cost of $1,071 million. This process was
replicated for each scenario using the minimum, average and maximum capital cost data. Estimated
capital costs range from a low of $1.1 billion to a high of $3.7 billion depending on the capital cost
assumptions used and the scenario selected. For a more complete breakdown of each scenario’s
capital cost assumptions, see Section 12.3.
Table 8-2: Total Estimated Capital Cost by Scenario (M$)
In order to compare these costs with production cost savings (benefits) discussed throughout the
report, the total capital costs must be annualized. The annualized value represents the annual capital
recovery required ($/year) for a given year. In order to calculate this, the total capital cost is
multiplied by the fixed charge rate (FCR) per Equation 8-1. The FCR captures the expected debt
service, equity and income tax associated with an investment. The FCR, which is defined in Equation
8-2, was not calculated specifically for the purposes of this study. Instead, a range of potential FCRs
was used between 12% and 16%, representing typical rates for an investor owned utility. Owners
with easier access to capital will be able to borrow money and fund the project with less return on
investment required, translating to a lower FCR. In turn, this will drive down overall costs associated
with funding a new renewable energy project.
(8-1)
(8-2)
Table 8-3 shows the total annual capital recovery required for each scenario, assuming a 14% FCR
and the total capital cost assumptions in Table 8-2. Each scenario’s annual capital recovery required
Minimum Average Maximum
Scenario 1 1,071 1,166 1,284
Scenario 2 1,254 1,407 1,581
Scenario 3 1,437 1,649 1,878
Scenario 4 1,684 2,371 3,130
Scenario 5 2,381 2,570 2,806
Scenario 6 2,564 2,812 3,103
Scenario 7 2,747 3,053 3,400
Scenario 8 2,557 2,794 3,089
Scenario 9 2,740 3,035 3,386
Scenario 10 2,923 3,277 3,683
Total Capital Cost (M$)
![Page 127: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/127.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 112 Final Report 5/21/2013 Final Report 4/30/2013
was also analyzed using a 12% and 16% FCR, the results of which will be shown later in this chapter.
These values now represent annualized costs associated with renewable capacity additions and can
be directly compared to the benefits (production cost savings) attributed to each scenario.
Table 8-3: Annual Capital Recovery Required ($/Year) by Scenario using a 14% FCR
Note: Annual capital costs represent the cost of the Scenario’s “bundle” of new renewable additions, AC and DC cables.
8.3 Annual Benefits with Existing Operating Practices
The annual benefits used in the cost-benefit-analysis are the total operating cost savings associated
with each scenario. The total operating cost includes the production costs from dispatchable thermal
units as well as the existing PPA costs from renewable electricity sources. It does NOT include any
cost from new renewable sources, which is addressed later in Section 0. Table 8-4 outlines the
existing PPA prices assumed in this analysis.
Table 8-4: Existing PPA Prices by Plant
All scenarios are compared back to a non-interconnected system without any additional renewable
energy or DC cables. This represents an additional MAPS sensitivity on the Base Cases without the
Lanai wind plant (referred to as the “Existing System”). The additional sensitivity was required to
estimate the change in production costs from the installation of the Lanai wind plant. The results of
Minimum Average Maximum
Scenario 1 150 163 180
Scenario 2 176 197 221
Scenario 3 201 231 263
Scenario 4 236 332 438
Scenario 5 333 360 393
Scenario 6 359 394 434
Scenario 7 385 427 476
Scenario 8 358 391 432
Scenario 9 384 425 474
Scenario 10 409 459 516
Annual Capital Cost (M$)
Plant Name PPA Assumptions
On Peak: $130.72/MWh
Off Peak: $123.08/MWh
Tier 1 (up to 42 GWh): $241.99/MWh
Tier 2 (42 - 62 GWh): $186.80/MWh
Tier 3 (over 62 GWh): $53.07/MWh
Tier 1 (up to 83 GWh): $209.14/MWh
Tier 2 (over 83 GWh): $53.07/MWh
Kawailoa Wind (Oahu 70 MW Wind) $212.65/MWh
Kahuku Wind (Oahu 30 MW Wind) $220.87/MWh
Maui 15 MW Distributed Solar $210.00/MWh
Oahu 60 MW Central Solar $210.00/MWh
Oahu 40 MW Distributed Solar $210.00/MWh
On Peak: $166.1/MWh for the first 28.23 GWh per month, $105.8/MWh after
Off Peak:$161.4/MWh for the first 7.62 GWh per month, $63.5/MWh after
Auwahi Wind (Maui 21 MW Wind)
H Power
Kaheawa Pastures Wind #1 (Maui 30 MW Wind)
Kaheawa Pastures Wind #2 (Maui 21 MW Wind)
![Page 128: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/128.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 113 Final Report 5/21/2013 Final Report 4/30/2013
this additional sensitivity included a total production cost of $1,161 million. All of the future scenarios
were then compared back to this sensitivity to calculate both a total production cost savings (M$)
and additional delivered wind, solar and geothermal energy (GWh).
Table 8-5 shows the annual benefits by scenario, represented in two ways;
1. Total Reduction in Operating Cost (M$/Year) in Column 7. This is the change in total operating cost (thermal production cost plus existing PPA cost) between each scenario and the “Existing System.”
2. Reduction in Operating Cost ($/MWh) in Column 8. This is the change in total operating cost between each scenario and the “Existing System,” divided by the increase in wind, solar and geothermal energy delivered.
Table 8-5: Annual Benefits by Scenario with Existing Operating Practices
8.4 Annual Capital Recovery Required
Comparing the costs with the benefits illustrates the overall economics associated with each
scenario. Although each scenario has different levels of wind, solar, and geothermal capacity, this
analysis allows for direct comparison to one another. Figure 8-2 provides a visual representation of
the cost and benefits associated with each scenario. The grey bar on the bottom represents the AC
cable cost with a single cable for Scenarios 1-4 and three cables for Scenarios 5-10. The tan bar
represents the DC cable cost with a single cable for Scenarios 1-4 and two cables for Scenarios 5-10.
The blue bars represent the annual capital cost requirements for the renewable energy additions
using the minimum, average and maximum capital cost assumptions presented in Section 8.1. The
annual benefits are represented by the yellow markers. For a scenario to be economically attractive,
the benefits (yellow marker) must exceed the cost (blue bars).
For example, in Scenario 2, the benefit is about the same as the cost when using the minimum
capital cost assumptions. However, costs exceed benefits when using the average or high cost
assumptions. Therefore, Scenario 2 is economically viable if the additional renewable energy is built
at or below the minimum cost assumptions, but unattractive otherwise.
Delivered
Renewable
Energy
(GWh)
Total
Production
Cost
(M$/yr)
Existing PPA
Cost
(M$/yr)
Operating Cost
of Existing
Resources
(M$/yr)
Additional
Renewable
Energy
Delivered
(GWh)
Reduction in
Operating Cost
(M$/yr)
Reduction in
Operating Cost
($/MWh)
Existing System* 1,553 $1,161 $243 $1,404
Scenario 1 2,371 $1,035 $248 $1,283 818 $120 $147.06
Scenario 2 2,730 $982 $245 $1,228 1,177 $176 $149.35
Scenario 3 3,066 $938 $239 $1,178 1,513 $226 $149.24
Scenario 4 2,804 $972 $248 $1,220 1,251 $183 $146.51
Scenario 5 2,896 $970 $248 $1,219 1,343 $185 $137.71
Scenario 6 3,198 $928 $245 $1,173 1,645 $230 $139.94
Scenario 7 3,471 $893 $239 $1,133 1,918 $271 $141.30
Scenario 8 3,118 $948 $248 $1,196 1,565 $208 $132.62
Scenario 9 3,383 $910 $245 $1,156 1,830 $248 $135.35
Scenario 10 3,623 $880 $239 $1,119 2,070 $284 $137.26
*Existing System represents an additional MAPS sensitivity. It includes the isolated system cases, but does not include the Lanai wind plant.
**Operating cost includes production cost from thermal generating units, plus PPA cost for existing renewable energy plants
![Page 129: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/129.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 114 Final Report 5/21/2013 Final Report 4/30/2013
Figure 8-2: Cost-Benefit Analysis (M$/Year) by Scenario Using Different Capital Cost Assumptions
and Assuming a 14% FCR
Using the results of Figure 8-2, the following conclusions can be made;
When comparing the ten scenarios to one another, it becomes evident that the scenarios with three AC cables and two DC cables (Scenarios 5 – 10) are less economically favorable than the scenarios with single cables due to the increased capital cost associated with the additional cables and the increased level of curtailment. The increased curtailment in the later scenarios weakens the economic attractiveness of the renewable additions due to decreasing marginal benefits associated with the new capacity additions.
The most economically attractive scenarios are Scenarios 1 – 3 because there is limited curtailment and no additional cost associated with a second DC cable or the full tri-island interconnection in Maui County. When the firm renewable generation (geothermal) is added to Scenario 1, the economics become even more favorable. Under these scenarios, the economic benefits associated with the geothermal additions outweigh to capital costs using all but the highest capital cost assumptions.
Assuming minimum capital costs and existing operating practices, only Scenarios 2 and 3 are economic. All other scenarios do not cover the capital cost with the production cost savings.
![Page 130: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/130.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 115 Final Report 5/21/2013 Final Report 4/30/2013
In addition to using a range of capital cost assumptions, it is also illustrative to analyze a range of
different FCRs. Figure 8-3 shows the same cost-benefit analysis as before, but under a range of FCRs.
In this analysis, the average capital cost assumptions are held constant and the FCR is varied to
include 12%, 14% and 16%. The capital costs of the AC and DC cables are still included, but are not
colored separately. The annual benefits do not change as they are not affected by the FCR.
Interestingly, the range of FCR assumptions from 12% to 16% is similar to the range of different
underlying capital costs. Because the differences are minimal between these two approaches, the
underlying conclusions do not change significantly.
Figure 8-3: Cost-Benefit Analysis (M$/Year) by Scenario Using Different FCR Assumptions and
Assuming Average Capital Costs
![Page 131: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/131.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 116 Final Report 5/21/2013 Final Report 4/30/2013
Because the specifications and costs of the AC cable system are not fully understood at this point in
time, the break-even cost of the AC cable was also calculated. For this part of the analysis, the AC
cable cost is not included in the overall capital costs for each scenario. Instead, the surplus benefit
(total operating cost minus the capital cost of the DC cables and renewable additions) is calculated
for each scenario under a high, medium and low capital cost assumption. Columns 2 – 4 of Table 8-6
show the surplus benefit for all scenarios. A negative number represents a scenario where total
annualized costs exceed annual benefits (reduction in operating costs). A positive number represents
a scenario where the annual benefits exceed the costs.
In scenarios where surplus benefits are positive, a break-even cost can be calculated for the AC
cable network by taking the annual surplus benefit and dividing by a 14% FCR. This cost represents
the price that the AC cable network would need to be built in order for the scenario’s annual benefits
to cover the annualized costs.
Table 8-6: Break Even Cost of the AC Cable Network Assuming a 14% FCR
For example, results from Section 4.1 show that the AC cable interconnection between Maui, Lanai
and Molokai will reduce total operating cost by $8 million per year with no additional renewable
capacity or DC cables. Assuming a 14% FCR, the AC cable cost would need to be built for $57 million
in order to break even in the Maui County Base Case. The only other scenarios to have a positive
surplus benefit are Scenarios 2 and 3 under the minimum and average capital cost assumptions. For
these scenarios, the break even costs for the AC cables are between $30 million and $357 million
depending on the scenario and capital cost assumption.
In general, the break-even costs shown in Table 8-6 are significantly lower than the initial estimates
from the Interisland Transmission Interconnection Capital Cost Estimate. However, there are
significant benefits associated with the AC interconnection beyond the economic benefits from
reduced operating costs. These ancillary benefits include increased reliability and the ability to build
additional renewable capacity on Maui to be used for the Maui, Oahu, Lanai and Molokai grids.
Surplus
Benefit M$
(Min)
Surplus
Benefit M$
(Avg)
Surplus
Benefit M$
(Max)
Break Even
Cost M$
(Min)
Break Even
Cost M$
(Avg)
Break Even
Cost M$
(Max)
Maui County Base Case 8 8 8 57 57 57
Scenario 1 -4 -18 -34 N/A N/A N/A
Scenario 2 26 4 -20 183 30 N/A
Scenario 3 50 20 -12 357 146 N/A
Scenario 4 -27 -123 -229 N/A N/A N/A
Scenario 5 -56 -83 -116 N/A N/A N/A
Scenario 6 -36 -71 -112 N/A N/A N/A
Scenario 7 -21 -64 -113 N/A N/A N/A
Scenario 8 -58 -91 -133 N/A N/A N/A
Scenario 9 -44 -85 -134 N/A N/A N/A
Scenario 10 -33 -82 -139 N/A N/A N/A
![Page 132: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/132.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 117 Final Report 5/21/2013 Final Report 4/30/2013
8.5 Cost of Renewable Electricity (COE)
Another method of comparing costs and benefits across scenarios is conducting a cost of electricity
(COE) analysis. To do this, all of the costs and benefits are levelized based on the amount of additional
renewable energy delivered. This provides values in terms of dollars per MWh of energy delivered,
rather than total annual capital cost (Equation 8-3). Results of this calculation can be found in the last
column of Table 8-5.
(8-3)
Figure 8-4 shows the costs and benefits on a $/MWh basis under different capital cost assumptions
and a 14% FCR. Using these results, a variety of conclusions can be made;
Benefits in each scenario do not vary significantly and remain close to $150/MWh. This is because the benefits associated with additional renewable energy are equal to the amount of thermal energy it is displacing. Although the actual unit displacement varies across the scenarios, in general the displaced energy is oil or diesel fired generation. As a result the overall benefits of displaced thermal energy do not vary significantly.
When additional amounts of geothermal resources are added, the overall cost in $/MWh decreases.
When incremental geothermal capacity is added, there is no change in the number of DC cables, but the overall delivered renewable energy increases dramatically due the resource’s high capacity factor.
Overall, the cost of electricity method highlights similar findings as the annual capital recovery
requirement method. Scenarios 1 – 3, which contain only a single AC & DC cable configuration, are
more economically viable than the later scenarios which include a second DC cable and experience
increased curtailment. In addition, the COE methodology favors technologies with higher capacity
factors. For example, scenarios which add the geothermal and firm capacity are more attractive
relative to the cases without them.
![Page 133: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/133.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 118 Final Report 5/21/2013 Final Report 4/30/2013
Figure 8-4: Cost Benefit Analysis ($/MWh) Based on Delivered Renewable Energy
8.6 Cost-Benefit Analysis with Modified Operating Practices
As described in Chapter 5, operating practices have a significant impact on variable operating cost.
Although the capital costs in this analysis don’t change, the annual benefits (production cost savings)
change dramatically when operating constraints are relaxed. This is because curtailment is reduced
and delivered renewable energy increases. Total capital costs do not increase in this analysis
because the incremental capital costs associated with required upgrades to modify operating
practices (retrofits on existing thermal units, synchronous condensers, etc.) are not included in this
study. The feasibility and cost to achieve these modified operating practices need to be evaluated
and capital costs added to the analysis in the future.
Table 8-7 shows the annual benefits (product cost savings) for each scenario, this time with modified
operating practices. The new benefits values are plotted against the same capital cost assumptions
in Figure 8-5. In addition, the benefits are also plotted against the capital costs on a $/MWh basis,
using the increased delivered renewable energy. Note that the existing PPA costs are the same in all
scenarios. This is because modified operating practices allow the system to take all available energy
from the existing renewable plants listed in Table 8-4.
![Page 134: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/134.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 119 Final Report 5/21/2013 Final Report 4/30/2013
Table 8-7: Annual Benefits by Scenario with Modified Operating Practices
Figure 8-5: Cost-Benefit Analysis (M$/Year) with Modified Operating Practices
Delivered
Renewable
Energy
(GWh)
Total
Production
Cost
(M$/yr)
Existing PPA
Cost
(M$/yr)
Operating Cost
of Existing
Resources
(M$/yr)
Additional
Renewable
Energy
Delivered
(GWh)
Reduction in
Operating Cost
(M$/yr)
Reduction in
Operating Cost
($/MWh)
Existing System* 1,553 $1,161 $243 $1,404
Scenario 1 2,511 $984 $250 $1,234 958 $169 $176.60
Scenario 2 2,939 $912 $250 $1,162 1,386 $241 $174.01
Scenario 3 3,359 $847 $250 $1,097 1,806 $306 $169.70
Scenario 4 2,966 $910 $250 $1,160 1,413 $243 $172.02
Scenario 5 3,200 $885 $250 $1,136 1,647 $268 $162.56
Scenario 6 3,597 $822 $250 $1,072 2,044 $331 $161.96
Scenario 7 3,977 $765 $250 $1,016 2,424 $388 $159.98
Scenario 8 3,541 $844 $250 $1,095 1,988 $309 $155.40
Scenario 9 3,915 $785 $250 $1,036 2,362 $368 $155.62
Scenario 10 4,267 $733 $250 $984 2,714 $420 $154.73
**Operating cost includes production cost from thermal generating units, plus PPA cost for existing renewable energy plants
*Existing System represents an additional MAPS sensitivity. It includes the Oahu and Maui County base cases, but does not include the Lanai wind plant.
![Page 135: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/135.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 120 Final Report 5/21/2013 Final Report 4/30/2013
Figure 8-6: Cost-Benefit Analysis ($/MWh) Based on Delivered Renewable Energy with Modified
Operating Practices
Figure 8-5 and Figure 8-6 show the added value associated with changes to the operating practices.
These practices include;
Relaxed fixed operating schedules for existing Oahu and Maui baseload units
Reduced minimum power limits on Oahu baseload units
Assuming the modified operating practices are achievable, the additional benefits captured through
the changes to operating practices are large enough to reverse some of the findings from the
previous cost-benefit analysis under the base assumptions. As a result, the following conclusions can
be drawn;
When operating practices are modified, the annual benefits exceed the costs in 3 of the 10 scenarios, even under the highest capital cost assumptions.
The solar scenario (Scenario 4) begins to be cost competitive if solar equipment costs are near the low end of assumed values.
Modifications to the existing thermal fleet will increase utilization of the wind and solar assets, improving their economic value.
The added benefits arise from reduced curtailment when baseload units can be turned down lower
or turned off all together. This demonstrates that the importance of operating practices can be equal
to, or greater, than the overall capital cost assumptions associated with new renewable capacity
additions. However, the costs and feasibility of achieving the operational modifications need to be
assessed to fully capture the cost-benefit analysis.
![Page 136: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/136.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 121 Final Report 5/21/2013 Final Report 4/30/2013
Similar to the results shown in Section 8.3, the break even costs are also provided for each scenario
with Modified Operating Practices. Table 8-8 shows the surplus benefits and break even costs for
Scenarios 1 – 10 under minimum, average and maximum capital cost assumptions. With modified
operating practices most scenarios are economic and therefore more break even costs can be
computed for the AC cable network. In addition, the break even cost for the AC cable cost now
exceed $600 million and are closer to the initial estimates provided in the Interisland Transmission
Interconnection Capital Cost Estimate report.
Table 8-8: Break Even Cost of the AC Cable Network Assuming a 14% FCR and Modified
Operating Practices
Surplus
Benefit M$
(Min)
Surplus
Benefit M$
(Avg)
Surplus
Benefit M$
(Max)
Break Even
Cost M$
(Min)
Break Even
Cost M$
(Avg)
Break Even
Cost M$
(Max)
Scenario 1 49 35 19 347 252 134
Scenario 2 95 73 49 678 525 352
Scenario 3 135 105 73 962 750 521
Scenario 4 37 -60 -166 262 N/A N/A
Scenario 5 31 4 -29 219 29 N/A
Scenario 6 68 34 -7 488 240 N/A
Scenario 7 99 57 8 710 404 57
Scenario 8 47 14 -27 337 100 N/A
Scenario 9 80 39 -10 573 277 N/A
Scenario 10 107 57 1 764 410 4
![Page 137: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/137.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 122 Final Report 5/21/2013 Final Report 4/30/2013
8.7 Total Cost Including PPA Costs
Another method for analyzing total system costs is to use estimated PPA costs for delivered
renewable energy rather than using the estimated capital costs of new construction. Publicly
available PPA costs were used as available for existing facilities, and assumptions were made for
future capacity additions throughout the later scenarios.
Table 8-4 shows the PPA assumptions for each existing plant on the interconnected system. For
some of the existing PPA structures, a tiered approach was used where energy is priced differently
depending on the overall extent of annual generation. Other plants assume an on-peak and off-peak
PPA structure where prices are dependent on time of generation.
The existing PPA prices found in Table 8-4 do not include an estimate for new or proposed renewable
resources evaluated across the different scenarios in this study. Instead, this section will assume a
range of potential prices per MWh of renewable electricity. The low price assumption is $110/MWh,
the medium price assumption is $165/MWh and the high price assumption is $220/MWh. The price
assumptions are technology neutral and applied to each of the new renewable sources evaluated in
the future scenarios. Including rough estimates of the future renewable generation, while applying
the cost of existing PPA resources, provides a high-level perspective of total operating costs for an
interconnected Oahu and Maui County grid.
Figure 8-7 shows the total system cost under existing operating practices, including PPA payments,
for each scenario. Using the PPA pricing assumptions highlighted in Table 8-4, a total operating cost
was calculated for each scenario. The total operating cost is equal to the production cost for thermal
resources (grey bars) plus the exisiting PPA cost of the renewable generation (red bars), plus the PPA
cost of new construction renewable generation (range of green bars). The individual cost (M$) of each
component is listed at the production cost and existing PPA cost segments. The total operating cost,
assuming high future PPA costs is highlighted on top of each bar. The PPA cost is included for
renewable assets only. It does not capture the PPA cost for thermal IPP units which are already
accounted for in the production cost.
![Page 138: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/138.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 123 Final Report 5/21/2013 Final Report 4/30/2013
Figure 8-7: Total Operating Cost by Scenario (M$)
The following conclusions can be drawn from Figure 8-7;
Total production cost (mostly fuel costs) decreases throughout the scenarios as renewable energy increases.
In the Base Case, 24-29% of total operating cost is paid to external PPAs. In the highest renewable scenario (Scenario 10), this share of renewable PPA cost increases to 35-44%.
If future renewable energy is purchased at the higher end of the range considered here, ($165 - $220/MWh), total system operating costs increase as renewable penetration increases. This occurs when PPAs are more expensive than the variable operating cost of existing thermal assets which they displace. As a result, future high penetration renewable scenarios and changes to existing operating practices will actually increase total system operating cost. However, the cost of future renewable resources will not be tied to the price of oil and will therefore be less variable and not expected to increase as quickly as oil prices.
If future renewable energy is purchased at the low end of the range ($110/MWh) total system operating cost is reduced with increased renewable penetration.
![Page 139: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/139.jpg)
Hawaii Stage 2 Interconnection Study Cost-Benefit Analysis
GE Energy Consulting 124 Final Report 5/21/2013 Final Report 4/30/2013
Figure 8-8 shows the total operating cost by scenario, comparing each scenario with existing
operating practices and modified operating practices. By comparing the total system cost between
different operating practices, additional conclusions can be drawn;
The modified operating practices leads to decreased utilization of the thermal fleet due to decreased minimum power limits and reducing the fixed operating schedule. This causes production cost for the thermal units to decrease in each scenario.
Total PPA cost increases because the reduced thermal output is replaced by previously curtailed, higher cost, renewable energy.
Future PPAs should continue to follow a tiered structure or share benefits of reduced curtailment
similar to existing PPAs for the KWP, Auwahi and H Power units. Without the tiered structures,
changes made to operating practices in order to reduce curtailment could actually increase total
system costs if the PPA prices were higher than $165/MWh. This increase to total system cost will
occur even though there is no increase to variable cost for the additional renewable energy.
Figure 8-8: Comparison of Total Cost (M$) with Existing and Modified Operating Practices
![Page 140: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/140.jpg)
Hawaii Stage 2 Interconnection Study Observations & Conclusions
GE Energy Consulting 125 Final Report 5/21/2013 Final Report 4/30/2013
9 Observations & Conclusions This analysis investigated the interconnected operation of the combined Oahu and Maui County
power grids with a variety of renewable generation additions. The primary conclusions are:
Interconnection offers a variety of benefits. It enables sharing of reserves and more efficient operation of the existing thermal fleets. In addition, it positions the system to accept more renewable generation and access to better sites for wind and geothermal generation.
Operating changes and reductions in the minimum power levels of baseload generation are very beneficial with the interconnected system and become more valuable as renewable penetration increases.
Energy storage is more attractive as a reserve asset than as an energy shifting device.
PPAs for renewable energy, especially wind and central solar resources, should have a tiered structure so that reducing curtailment benefits the utility and rate payer as well as the developer. Other structures are also possible, but the key aspect is that benefits of reduced curtailment should be shared in a manner that benefits all participants in a fair manner. In addition, the procurement of the renewables should be separate from the access to the DC cables.
The DC cables should be a system asset, not tied to any single renewable asset. This improves overall grid efficiency and available capacity on the cables can be used for additional future renewable energy sources. The nominal 200 MW rating of the cables was not found to be limiting in most cases, even with additional renewable sources.
![Page 141: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/141.jpg)
Hawaii Stage 2 Interconnection Study Future Research
GE Energy Consulting 126 Final Report 5/21/2013 Final Report 4/30/2013
10 Future Research When the study scope was developed, it was decided to calculate the value of the interconnection
with existing operating practices. The additional value of modified operating practices were then
determined on the interconnected system only, as part of a sensitivity and mitigation strategy
analysis.
However, the modified operating practices add value to the scenarios, even if the systems are not
interconnected. In fact, it is likely that much of the value of the modifications is a direct result of the
interconnection and some of the benefits would not be captured if the systems remained isolated. So
there is an open question; what is the value of the interconnection (grid-tie vs. gen-tie) if the
operating practices are modified before the interconnection is implemented? It is likely that the
modified operating practices will increase the value of the interconnection, and thus provide a
greater incentive to choose a grid-tie transmission plan rather than a gen-tie configuration for new
renewable capacity.
In order to appropriately assign value to the interconnect versus the modified operating practices,
several new simulations should be run. These include the following cases;
1. Base Cases with modified operating practices 2. Future scenarios with modified operating practices in a grid-tie only transmission
configuration.
Figure 10-1: Determining the Incremental Value of Interconnection vs. Modified Operating
Practices
![Page 142: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/142.jpg)
Hawaii Stage 2 Interconnection Study Future Research
GE Energy Consulting 127 Final Report 5/21/2013 Final Report 4/30/2013
In addition, there is an open question about the order in which the modified operating practices take
place. In the original project scope system modifications were made in the following steps:
1. Remove Maui fixed operating schedules 2. Step 1 + Reduce Oahu minimums 3. Step 1 + Step 2 + Remove Oahu fixed operating schedules
Although the final end-point will remains unchanged with all three modifications in place, the
economic benefits for each incremental step will change if the order of its implementation changes.
For example, the original Stage 2 analysis shows that reduced Oahu minimums provides the most
incremental value, even though it is implemented after the removal of the Maui fixed operating
schedules. It is possible that if the Oahu minimums were reduced first, the economic value would be
even greater. By running additional simulations with different implementation schedules, HECO will
have a better understanding about the relative benefits associated with each modification in
isolation. This will aid in decision making about which modifications provide the largest economic
benefit.
The following additional simulations are suggested in order to appropriately assign value to the
system modifications in isolation;
1. Remove fixed operating schedules on all Maui units (already run in Stage 2 study) 2. Remove fixed operating schedules on individual Maui units, one at a time, to determine which
units will provide the most economic benefit. 3. Reduce minimum power limits on all Oahu units 4. Reduce minimum power limits on individual Oahu units, one at a time, to determine which
units will provide the most economic benefit 5. Remove fixed operating schedules on all Oahu units 6. Remove fixed operating schedules on individual Oahu units, one at a time, to determine
which units will provide the most economic benefit.
HNEI and GE Energy Consulting are preparing to conduct this analysis. When it is completed, the
results will be documented in a new report.
![Page 143: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/143.jpg)
Hawaii Stage 2 Interconnection Study References
GE Energy Consulting 128 Final Report 5/21/2013 Final Report 4/30/2013
11 References
11.1 Previous Studies
[1] “Hawaii Solar Integration Study; Summary Technical Report”, GE Energy Consulting, December
2012
[2] “Hawaii Solar Integration Study; Final Technical Report for Oahu”, GE Energy Consulting,
December 2012.
[3] “Hawaii Solar Integration Study; Final Technical Report for Maui”, GE Energy Consulting,
December 2012.
[4] M. Brower, P. Beaucage, J. Frank, “Development of a Cloud Model to Generate High-Frequency
Solar Irradiance and Power Data”, 2nd International Workshop on Integration of Solar Power
into Power Systems, Paper SIW12-48, Lisbon, Portugal, November 12-13, 2012.
[5] “KWP2 Wind Integration Study - Final Report”, GE Energy, June 2010.
[6] “Oahu Wind Integration Study – Final Report”, GE Energy Consulting, December 2010. Available at:
http://www.hnei.hawaii.edu/sites/web41.its.hawaii.edu.www.hnei.hawaii.edu/files/story/2011/03/
Oahu_Wind_Integration_Study.pdf
11.2 Capital Cost Assumptions
[7] U.S. Energy Information Agency. Updated Capital Cost Estimates for Electricity Generation Plants.
Washington, D.C. November 2010.
http://www.eia.gov/oiaf/beck_plantcosts/pdf/updatedplantcosts.pdf
[8] National Renewable Energy Laboratory. Energy Technology Cost and Performance Data. July
2010. http://www.nrel.gov/analysis/costs.html
[9] Black & Veatch. Cost and Performance Data for Power Generation Technologies, Prepared for the
National Renewable Energy Laboratory. February 2012. http://bv.com/docs/reports-studies/nrel-
costreport.pdf
[10] National Renewable Energy Laboratory. Energy Technology Cost and Performance Data. July
2010. http://www.nrel.gov/analysis/costs.html
[11] Electric Power Research Institute. Generation Technology Options in a Carbon-Constrained World.
EPRI Report 1022782. 2011.
http://globalclimate.epri.com/doc/Generation_Technology_Options_in_a_Carbon-
Constrained_World.pdf
[12] Hearps, Patrick and Dylan McConnell. Renewable Energy Technology Cost Review. University of
Melbourne, Energy Research Institute. March 2011. http://www.garnautreview.org.au/update-
2011/commissioned-work/renewable-energy-technology-cost-review.pdf
![Page 144: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/144.jpg)
Hawaii Stage 2 Interconnection Study Appendix
GE Energy Consulting 129 Final Report 5/21/2013 Final Report 4/30/2013
12 Appendix
12.1 GE MAPS Description
Production cost modeling of the NSPI system was performed with the GE’s Multi Area Production
Simulation (MAPSTM) software program. This commercially available modeling tool has a long history
of governmental, regulatory, independent system operator and investor-owned utility applications.
The production cost model provides the unit-by-unit production output (MW) on an hourly basis for
an entire year of production (GWh of electricity production by each unit). The results also provide
information about the variable cost of electricity production, emissions, fuel consumption, etc.
The overall simulation algorithm is based on standard least marginal cost operating practice. That is,
generating units that can supply power at lower marginal cost of production are committed and
dispatched before units with higher marginal cost of generation. Commitment and dispatch are
constrained by physical limitations of the system, such as transmission thermal limits, minimum
spinning reserve, as well as the physical limitations and characteristics of the power plants.
The primary source of model uncertainty and error for production cost simulations, based on the
model, consist of:
o Some of the constraints in the model may be somewhat simpler than the precise situation dependent rules used by HECO.
o Marginal production-cost models consider heat rate and a variable O&M cost. However, the models do not include an explicit heat-rate penalty or an O&M penalty for increased maneuvering that may be a result of incremental system variability due to as-available renewable resources (in future scenarios).
o The production cost model requires input assumptions like forecasted fuel price, forecasted system load, estimated unit heat rates, maintenance and forced outage rates, etc. Variations from these assumptions could significantly alter the results of the study.
o Prices that HECO pays to IPPs for energy are not, in general, equal to the variable cost of production for the individual unit, nor are they equal to the systemic marginal cost of production. Rather, they are governed by PPAs. The price that HECO pays to third parties is reflected in the simulation results insofar as the conditions can be reproduced.
The simulation results provide insight into hour-to-hour operations, and how the commitment and
dispatch may change subject to various changes, including equipment or operating practices. Since
the production cost model depends on fuel price as an input, relative costs and change in costs
between alternative scenarios tend to produce better and more useful information than absolute
costs. The results from the model approximate system dispatch and production, but do not
necessarily identically match system behavior. The results do not necessarily reproduce accurate
production costs on a unit-by-unit basis and do not accurately reproduce every aspect of system
operation. However, the model reasonably quantifies the incremental changes in marginal cost,
emissions, fossil fuel consumption, and other operations metrics due to changes, such as higher
levels of wind power.
![Page 145: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/145.jpg)
Hawaii Stage 2 Interconnection Study Appendix
GE Energy Consulting 130 Final Report 5/21/2013
12.2 Maintenance and Outage Schedule
Table 12-1: Maui County Weekly Maintenance and Outage Schedule
UNIT NAME 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
X1 RO RO RO RO PS PR
X2 RO PS RO PR RO RO
M1 FD FD FD PF RO PR RO RO RO
M2 RO PF FD FD PF RO RO PR RO
M3 PF FD FD FD FD FD FD FD PF RO PR RO RO
M4 PR PS
M5 PS PR
M6 PS PR
M7 PR PS
M8 PS PR
M9 PR PS
M10 PF FD FD FD FD FD FD PF PR
M11 PR PF FD FD FD FD FD FD FD
M12 PR PS
M13 PR PS
M141516 PF FD PF FD PF PR
M1718 PR PF FD PF
M171819 PR PF FD PF FD PF
K1 PR PF FD FD FD PF
K2 FD FD FD FD PF PR
K3 FD FD FD PF PR
K4 PF FD FD FD PF PR
GEN_LAN1 PR PS RO
GEN_LAN2 RO PS PR
GEN_LAN3 RO PR PS
GEN_LAN4 RO PS PR
GEN_LAN5 PS PR RO
GEN_LAN6 PS PR RO
GEN_LAN7 PR PS RO
GEN_LAN8 PS PR RO
GEN_LANM RO PR PS
GEN_MOL1 PR PS RO
GEN_MOL2 PS PR RO
GEN_MOL3 RO PS PR
GEN_MOL4 PS PR RO
GEN_MOL5 PS PR RO
GEN_MOL6 PS RO PR
GEN_MOL7 RO PR PS
GEN_MOL8 PS RO PR
GEN_MOL9 PS RO PR
GEN_MOLS PR PS RO
Key: RO = Random Outage PR = Partial Random Outage FD = Fixed Daily Maintenance PF = Partial Fixed Maintenance PS = Partial Scheduled Maintenance
Week of Year -->
![Page 146: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/146.jpg)
Hawaii Stage 2 Interconnection Study Appendix
GE Energy Consulting 131 Final Report 5/21/2013
Table 12-2: Oahu Weekly Maintenance and Outage Schedule
UNIT NAME 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53
HONH8 PR PF FD FD FD FD FD FD FD PF RO RO RO RO RO RO
HONH9 PR PF FD PF RO RO RO RO RO RO RO
WAIW3 PR RO RO PF FD PF RO RO RO RO RO
WAIW4 PR RO RO PF FD PF RO RO RO RO
WAIW5 RO PF FD FD PF PR RO
WAIW6 RO PR RO PF FD FD PF
WAIW7 PF FD PF PR RO RO
WAIW8 RO PR RO PF FD FD FD FD FD PF
WAIW9 RO RO RO PR RO RO PF RO
WAIW10 RO RO PF FD FD FD FD FD FD PF PR RO RO RO
KAHK1 PF FD PF RO PR
KAHK2 PF FD PF RO PR
KAHK3 RO PR PF FD FD FD FD FD FD FD FD FD FD FD FD FD FD PF
KAHK4 PR RO PF FD FD FD PF RO
KAHK5 PF FD FD FD FD FD FD FD FD FD FD FD FD FD FD FD FD FD PF PR RO
KAHK6 PF FD PF RO PR
KALKAL1 PF FD PF PR
KALKAL2 PF FD FD FD PF PR
KALKAL3 PF FD FD FD FD PF PR
AES PR
CIPCT1 RO RO RO PF PF RO RO RO RO PR
AIRDSG8
Key: RO = Random Outage PR = Partial Random Outage FD = Fixed Daily Maintenance PF = Partial Fixed Maintenance PS = Partial Scheduled Maintenance
Week of Year -->
![Page 147: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/147.jpg)
Hawaii Stage 2 Interconnection Study Appendix
GE Energy Consulting 132 Final Report 5/21/2013
12.3 Detailed Capital Cost Assumptions
Table 12-3: Capital Cost Calculator using Minimum Cost Assumptions
Table 12-4: Capital Cost Calculator using Average Cost Assumptions
Capital Cost Assumption Used: Min
Include AC Cable Cost (Y/N)? Yes
RE & Transmission Resources - Capital Cost
1,762 2,357 3,661 2,400 716 0.14
$/kW $/kW $/kW $/kW $/M FCR
Scenario
RE
Delivered
(GWh)
RE
Delivered
(%)
VOC
($M/yr)
Existing
PPA Cost
($M/yr)
Total Cost
($M/yr)
Wind
(MW)
Solar
(MW)
Geother
mal
(MW)
HVDC
(MW)
Wind
($M)
Solar
($M)
Geothermal
($M)
HVDC &
Oahu Grid
Upgrades
($M)
AC Maui
County
Upgrades
($M)
Total Cost
($M)
Add'l RE
Delivered
(GWh)
Add'l Capital
Cost ($M)
Annual Capital
Recovery Req
($M)
COE ($/MWh)
Change in
Total Cost
($M/yr)
Reduction in
VOC ($/MWh)
BASE 1553 17% 1161 243 1404
1 2371 26% 1035 248 1283 200 200 352 0 0 480 239 1071 818 1071 150 $183 -120.3 $147
2 2730 30% 982 245 1228 200 50 200 352 0 183 480 239 1254 1177 1254 176 $149 -175.8 $149
3 3066 33% 938 239 1178 200 100 200 352 0 366 480 239 1437 1513 1437 201 $133 -225.8 $149
4 2804 30% 972 248 1220 200 260 200 352 613 0 480 239 1684 1251 1684 236 $188 -183.3 $147
5 2896 31% 970 248 1219 400 400 705 0 0 960 716 2381 1343 2381 333 $248 -184.9 $138
6 3198 35% 928 245 1173 400 50 400 705 0 183 960 716 2564 1645 2564 359 $218 -230.2 $140
7 3471 38% 893 239 1133 400 100 400 705 0 366 960 716 2747 1918 2747 385 $200 -271.0 $141
8 3118 34% 948 248 1196 500 400 881 0 0 960 716 2557 1565 2557 358 $229 -207.6 $133
9 3383 37% 910 245 1156 500 50 400 881 0 183 960 716 2740 1830 2740 384 $210 -247.7 $135
10 3623 39% 880 239 1119 500 100 400 881 0 366 960 716 2923 2070 2923 409 $198 -284.1 $137
MAPS Simulation Results Comparison to Base Case (Not Interconnected)Additional Capital CostsPPA Costs Capacity Additions
Capital Cost Assumption Used: Average
Include AC Cable Cost (Y/N)? Yes
RE & Transmission Resources - Capital Cost
2,236 4,635 4,830 2,400 716 0.14
$/kW $/kW $/kW $/kW $/M FCR
Scenario
RE
Delivered
(GWh)
RE
Delivered
(%)
VOC
($M/yr)
Existing
PPA Cost
($M/yr)
Total Cost
($M/yr)
Wind
(MW)
Solar
(MW)
Geother
mal
(MW)
HVDC
(MW)
Wind
($M)
Solar
($M)
Geothermal
($M)
HVDC &
Oahu Grid
Upgrades
($M)
AC Maui
County
Upgrades
($M)
Total Cost
($M)
Add'l RE
Delivered
(GWh)
Add'l Capital
Cost ($M)
Annual Capital
Recovery Req
($M)
COE ($/MWh)
Change in
Total Cost
($M/yr)
Reduction in
VOC ($/MWh)
BASE 1553 17% 1161 243 1404
1 2371 26% 1035 248 1283 200 200 447 0 0 480 239 1166 818 1166 163 $200 -120.3 $147
2 2730 30% 982 245 1228 200 50 200 447 0 241 480 239 1407 1177 1407 197 $167 -175.8 $149
3 3066 33% 938 239 1178 200 100 200 447 0 483 480 239 1649 1513 1649 231 $153 -225.8 $149
4 2804 30% 972 248 1220 200 260 200 447 1205 0 480 239 2371 1251 2371 332 $265 -183.3 $147
5 2896 31% 970 248 1219 400 400 894 0 0 960 716 2570 1343 2570 360 $268 -184.9 $138
6 3198 35% 928 245 1173 400 50 400 894 0 241 960 716 2812 1645 2812 394 $239 -230.2 $140
7 3471 38% 893 239 1133 400 100 400 894 0 483 960 716 3053 1918 3053 427 $223 -271.0 $141
8 3118 34% 948 248 1196 500 400 1118 0 0 960 716 2794 1565 2794 391 $250 -207.6 $133
9 3383 37% 910 245 1156 500 50 400 1118 0 241 960 716 3035 1830 3035 425 $232 -247.7 $135
10 3623 39% 880 239 1119 500 100 400 1118 0 483 960 716 3277 2070 3277 459 $222 -284.1 $137
MAPS Simulation Results Comparison to Base Case (Not Interconnected)Additional Capital CostsPPA Costs Capacity Additions
![Page 148: Interconnection of Grid Systems for Maui and Oahu Counties · 2019-11-08 · Acknowledgement: This material is based upon work supported by the United States Department of Energy](https://reader033.vdocument.in/reader033/viewer/2022050413/5f8a3e6ccc941b561226387f/html5/thumbnails/148.jpg)
Hawaii Stage 2 Interconnection Study Appendix
GE Energy Consulting 133 Final Report 5/21/2013
Table 12-5: Capital Cost Calculator using Maximum Cost Assumptions
Table 12-6: Capital Cost Assumptions for the DC Cable Interconnections
Capital Cost Assumption Used: Max
Include AC Cable Cost (Y/N)? Yes
RE & Transmission Resources - Capital Cost
2,825 7,100 5,940 2,400 716 0.14
$/kW $/kW $/kW $/kW $/M FCR
Scenario
RE
Delivered
(GWh)
RE
Delivered
(%)
VOC
($M/yr)
Existing
PPA Cost
($M/yr)
Total Cost
($M/yr)
Wind
(MW)
Solar
(MW)
Geother
mal
(MW)
HVDC
(MW)
Wind
($M)
Solar
($M)
Geothermal
($M)
HVDC &
Oahu Grid
Upgrades
($M)
AC Maui
County
Upgrades
($M)
Total Cost
($M)
Add'l RE
Delivered
(GWh)
Add'l Capital
Cost ($M)
Annual Capital
Recovery Req
($M)
COE ($/MWh)
Change in
Total Cost
($M/yr)
Reduction in
VOC ($/MWh)
BASE 1553 17% 1161 243 1404
1 2371 26% 1035 248 1283 200 200 565 0 0 480 239 1284 818 1284 180 $220 -120.3 $147
2 2730 30% 982 245 1228 200 50 200 565 0 297 480 239 1581 1177 1581 221 $188 -175.8 $149
3 3066 33% 938 239 1178 200 100 200 565 0 594 480 239 1878 1513 1878 263 $174 -225.8 $149
4 2804 30% 972 248 1220 200 260 200 565 1846 0 480 239 3130 1251 3130 438 $350 -183.3 $147
5 2896 31% 970 248 1219 400 400 1130 0 0 960 716 2806 1343 2806 393 $293 -184.9 $138
6 3198 35% 928 245 1173 400 50 400 1130 0 297 960 716 3103 1645 3103 434 $264 -230.2 $140
7 3471 38% 893 239 1133 400 100 400 1130 0 594 960 716 3400 1918 3400 476 $248 -271.0 $141
8 3118 34% 948 248 1196 500 400 1413 0 0 960 716 3089 1565 3089 432 $276 -207.6 $133
9 3383 37% 910 245 1156 500 50 400 1413 0 297 960 716 3386 1830 3386 474 $259 -247.7 $135
10 3623 39% 880 239 1119 500 100 400 1413 0 594 960 716 3683 2070 3683 516 $249 -284.1 $137
MAPS Simulation Results Comparison to Base Case (Not Interconnected)Additional Capital CostsPPA Costs Capacity Additions
Electranix Report: HVDC cost is $533M ($1,333/kW) for 2x200MW HVDC lines, Oahu-Molokai & Oahu-Lanai (OWITS config B1-2); no data for ac upgrades
Docket 2009-0162 HVDC and AC upgrade costs itemized as follows:
$533 M HVDC cable cost, 2x200MW rating
$95 M Lanai & Molokai infrastructure
$188 M Project management, engineering, contingency
$142 M Oahu transmission infrastructure
$958 M Total installed cost for 400 MW HVDC system to Lanai & Molokai wind plants, rounded to $1B in the docket ($2,400/kW)