![Page 1: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/1.jpg)
-1-
Intermodal Parking Facilities
And Enhancements Design-Build Project
![Page 2: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/2.jpg)
Presentation
• Foothill Extension
• Phase 2A – Pasadena to Azusa
– Three Design-Build Projects
– Intermodal Parking Facilities and Enhancements
Design-Build Project: Scope of Work
• Procurement and Evaluation
• Q&A
![Page 3: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/3.jpg)
Completing the Vision
![Page 4: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/4.jpg)
Creation/Powers of the Authority • SB 1847 sponsored by State Senator (now Congressman) Adam Schiff effective January 1, 1999
updated October 2011 – AB706, sponsored by State Assembly
member Norma Torres
• Scope included current Metro Gold Line from Union Station to East Pasadena, and any fixed guide way to Claremont (now Montclair) • SB 1847 also provides the necessary powers to complete the project:
the ability to acquire right-of-way
issue debt
enter into joint development agreements
relocate utilities
accept grants, fees and allocations from all funding sources
enter into design build contracts
![Page 5: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/5.jpg)
Strategic Partnership w/Metro
• We are not LACMTA / Metro • General Relationship
– Construction Authority plans, designs and builds the line (per Metro’s design/safety guidelines and specifications)
– Metro operates and maintains the line following construction
• Both agencies play a role in public safety planning and education
• Master Cooperative Agreement – Formalizes roles and responsibilities – MCA for Pasadena to Azusa and Azusa to Montclair segments
signed March 2010
![Page 6: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/6.jpg)
Building by Phase
![Page 7: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/7.jpg)
Planning/Construction Phases
• Pasadena to Azusa Extension – Fully Funded by Measure R – 11.5 Miles, 5 Cities, 6 Stations/Completion Anticipated 2015
Pasadena-Azusa Azusa-Montclair Airport Ext.
• Azusa to Montclair Extension - Proposed – 12.6 Miles, 6 Stations/Estimated Funding Needed is $550 Million
• Ontario Airport Extension - Proposed – Approximately 8 Miles/Unfunded
![Page 8: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/8.jpg)
• Pasadena to Azusa comprises three design-build project packages: – Package 1 – Iconic Freeway Structure (I-210 Bridge) – Package 2 - Alignment Contract (11.5 miles) – Package 3 - Intermodal Parking Facilities and Enhancements
Pasadena-Azusa
Status: Pasadena to Azusa
![Page 9: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/9.jpg)
Design-Build Packages
• Package 1: Iconic Freeway Structure over I-210 (approx. 584 linear feet)
• Package 2: Phase 2A Alignment, includes: Rail Track Alignment, Bridges, Crossings, Stations, Utilities, Systems, Signals (and related items), as well as a Maintenance & Operations Facility
• Package 3: – Intermodal Parking Facility at five of the six stations:
four multi-level parking structures and one surface parking lot.
– Intermodal Enhancements, including: bus pads and shelters, bike lockers and racks, sidewalks, ramps, enhanced crosswalks, trees and tree wells, pedestrian street lights, traffic signals and roadway improvements.
![Page 10: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/10.jpg)
Package 1: Iconic Freeway Structure
![Page 11: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/11.jpg)
Package 2: Phase 2A Alignment
Package 2 includes: Rail Track Alignment, Bridges, Crossings, Stations, Utilities, Systems, Signals, and Maintenance & Operations Facility.
Structures
Stations
Track
Crossings
![Page 12: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/12.jpg)
Package 3: Intermodal Parking Facilities and Enhancements
Package 3 includes: parking structures, a surface parking lot, fencing, traffic signals, bus pads and shelters, bike racks and lockers, retaining walls, sidewalks, ramps, enhanced crosswalks, landscaping, trees and tree wells, pedestrian street lights, roadway improvements, other related work.
![Page 13: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/13.jpg)
-13-
Intermodal Parking Facilities
And Enhancements Design-Build Project:
Scope of Work
![Page 14: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/14.jpg)
Scope of Work: • Design-Build Project Quality Control
o Inspections o Testing
Quality Assurance • Public Agency Project Construction Work Plans
• Coordinate with: Cities Utility Owners Third Parties Alignment (DB2)
Contractor Metro (via Authority)
![Page 15: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/15.jpg)
Intermodal Parking Facilities Five parking facilities:
Four parking structures
One surface parking lot
Utility Relocations
Retaining walls
SUSMP Requirements
Ventilation system, when required
![Page 16: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/16.jpg)
Intermodal Enhancements Bike lockers and racks Bus pads and shelters Sidewalks, ramps and curb ramps Enhanced crosswalks Street trees and tree wells Pedestrian street lights Traffic signal and roadway improvements
![Page 17: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/17.jpg)
Relocation of utilities Vacation of existing street Demolition of existing buildings/facilities
Arcadia Site
![Page 18: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/18.jpg)
2-level Parking Structure with approx. 300 spaces Intermodal Enhancements on Santa Clara Street & 1st Ave
Arcadia
![Page 19: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/19.jpg)
Multi-level Parking Structure with approx. 350 spaces
Monrovia
![Page 20: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/20.jpg)
Surface Parking Lot with approx. 125 spaces Intermodal Enhancements on Duarte Rd and Highland Ave
Duarte
![Page 21: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/21.jpg)
Retaining walls required Relocation of overhead utilities Relocation of drainage pump station
Irwindale Site
![Page 22: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/22.jpg)
3-level Parking Structure with approx. 350 spaces Intermodal Enhancements on West Avenida Padilla
Irwindale
![Page 23: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/23.jpg)
Intermodal Enhancements on Santa Fe Ave Joint Venture Parking Structure (not included in scope)*
Azusa-Alameda
![Page 24: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/24.jpg)
3-level Parking Structure with approx. 200 spaces Intermodal Enhancements at Station Area & on Citrus Ave and Foothill Blvd
Azusa-Citrus
![Page 25: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/25.jpg)
-25-
Procurement Process
![Page 26: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/26.jpg)
Request for Statements of Qualifications
1. Goal: To create a shortlist of most-qualified teams
2. Evaluation Criteria: Related Project Experience (50 points) Staffing and Organization (35 points) Legal & Financial Qualifications (15 points)
3. Evaluation Criteria: Forms
4. Questions and Answers: Form E
5. Only Addenda are Binding
6. Single Point of Contact; No Ex Parte Communications§3.2
![Page 27: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/27.jpg)
RFQ Procurement Milestones
RFQ MILESTONES ANTICIPATED DATES
Issue RFQ March 19, 2012
Pre-submittal Conference March 22, 2012
Questions Due April 16, 2012
Authority Response April 25, 2012
Statements of Qualification Due May 15, 2012
Interview Dates (if any) June 4-5, 2012
Announce Shortlist June 8, 2012
![Page 28: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/28.jpg)
Recommend Award
Discussions (if any)
SOQ s received
5/15
Shortlist of Design-Build
Teams
6/8
Industry Review Draft Release
6/8
Industry Review Comments & Technical
One-on-Ones
7/9 – 7/30
8/29
Revised / Final Proposals
(if any)
10/24
RFQ Issued
1/9/13
Proposals Due
RFP Issued
2/27/13
3/19
11/15
Procurement: The Big Picture
![Page 29: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/29.jpg)
Next Steps
Last Day for Submitting Written Questions April 16, 2012
Proposals Due May 15, 2012
Interview Date (if required) June 4-5, 2012
Shortlist Announced June 8, 2012
![Page 30: Intermodal Parking Facilities And Enhancements Design ...foothillgoldline.org/images/uploads/files/2012_03...1. Goal: To create a shortlist of most-qualified teams 2. Evaluation Criteria:](https://reader035.vdocument.in/reader035/viewer/2022071213/603362770b0288117117ffda/html5/thumbnails/30.jpg)
-30-