internal audit's value addition approach - a study in the dallas-fort worth area - dallas

47
2011 Internal Audit's Value Addition Approach - A Study in the Dallas-Fort Worth Area The Research Committee of the Dallas Chapter of the IIA 2011 - The IIA Research Foundation

Upload: narendra-reddy-lokireddy

Post on 07-Dec-2015

221 views

Category:

Documents


3 download

DESCRIPTION

Internal Audit's Value Addition

TRANSCRIPT

  • 2011

    Internal Audit's Value Addition Approach - A Study in the Dallas-Fort Worth Area The Research Committee of the Dallas Chapter of the IIA

    2011 - The IIA Research Foundation

  • The Dallas Chapter of the Institute of Internal Auditors

    Internal Audits Value Addition Approach

    Worth Area

    Contents

    Introduction ................................Value Addition ApproachesSurvey Design ................................Project Plan ................................Participants Profile ................................Represented Organizations ProfileRepresented Internal Audit Departments ProfileArea Specific Observations

    Project Management ................................Enterprise Risk ManagementCorporate Governance ................................Social and Sustainability Audits and ConsultationStrategy Audits and Consultation

    Data Analysis ................................Conclusions and ImplicationsLimitations and Future OpportunitiesAcknowledgements ................................Appendix I: Statistical TablesAppendix II: Interpreting Correlation Coefficients and CovarianceAppendix III: Pre-Interview QuestionnaireAppendix IV: Interview QuestionnaireReferences ................................

    The Dallas Chapter of the Institute of Internal Auditors

    Internal Audits Value Addition Approach- a Study in the Dallas

    ................................................................................................

    Value Addition Approaches .........................................................................................................................................................................................

    ................................................................................................

    ................................................................................................

    Represented Organizations Profile ................................................................Represented Internal Audit Departments Profile .......................................................Area Specific Observations .......................................................................................

    ..............................................................................................

    ise Risk Management ...........................................................................................................................................................

    Social and Sustainability Audits and Consultation................................Strategy Audits and Consultation ................................................................

    ................................................................................................

    Conclusions and Implications ....................................................................................Limitations and Future Opportunities ................................................................

    ................................................................................................

    Appendix I: Statistical Tables .....................................................................................Appendix II: Interpreting Correlation Coefficients and Covariance ............................

    Interview Questionnaire ................................................................Appendix IV: Interview Questionnaire ................................................................

    ................................................................................................

    2

    a Study in the Dallas-Fort

    .................................................. 3 ......................... 6

    ............................................. 9 ............................................... 10

    .................................... 10 ........................................... 13

    ....................... 15

    ....................... 17 .............................. 18

    ................................................. 21 ........................... 26

    .................................................. 30 ........................................... 33

    ............................................. 35 .................... 35

    ......................................... 36 .................................... 37

    ..................... 38 ............................ 39

    ................................. 40 ........................................ 42

    ................................................ 47

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Introduction

    As Richard Chambers observed, from the back room to the board roominternal auditors to provide additional value to the organizationthan everii. The objective of thisthe efforts of internal audit organizations in this endeavor. committee (committee) leveragedAUDIT SURVEY- Characteristics of an emerging focus areas in which internal auditors could add valueinnovative approaches. From this foundation, whether the internal audit departments these emerging focus areas.

    The hypothesis for this studywill experience a push to increasingly focus below) and to generate additionalor financial audit areas. The committees for focused research and conducting area to evaluate the level of experience local internal auditemerging audit areas. Keeping in perspective that the study is a chapter research project, the committee focusedperceived by the committee as and that can be performed by size. Based on these criteria, Table-1 for study from the 2010 IIA Global Internal Audit Survey: Characteristics of an Internal Audit Activity- Report I

    The Dallas Chapter of the Institute of Internal Auditors

    As Richard Chambers observed, the internal auditing profession and its rom the back room to the board roomi is being closely watched. The demand for

    internal auditors to provide additional value to the organizations they servethis study is to identify the factors that contribute to or inhibit

    the efforts of internal audit organizations in this endeavor. To that end, the leveraged the results of the 2010 IIA GLOBAL INTERNAL

    Characteristics of an internal audit Activityiii as a basis to identify in which internal auditors could add value using nontraditional or

    From this foundation, the committee sought to determine the internal audit departments in the Dallas/Fort Worth Metroplex are

    for this study is that internal audit departments (respondentswill experience a push to increasingly focus on certain emerging types of audits (noted

    additional value outside the traditional operational, compliance The committees approach involved identifying the audit areas

    conducting targeted interviews with Audit Executives in the to evaluate the level of experience local internal audit departments have with these

    . Keeping in perspective that the study is a chapter research ed on a selection of internal audit activities that

    ommittee as unique and innovative, that were emerging in popularityerformed by a wide variety of audit functions, regardless of industry or

    Based on these criteria, the committee selected the five focus areas2010 IIA Global Internal Audit Survey: Characteristics of an

    Report I.

    3

    profession and its journey is being closely watched. The demand for

    s they serve is higher is to identify the factors that contribute to or inhibit

    he research the results of the 2010 IIA GLOBAL INTERNAL

    as a basis to identify using nontraditional or

    sought to determine in the Dallas/Fort Worth Metroplex are active in

    respondents) ging types of audits (noted

    operational, compliance identifying the audit areas

    with Audit Executives in the have with these

    . Keeping in perspective that the study is a chapter research udit activities that were

    emerging in popularity, regardless of industry or

    areas noted in 2010 IIA Global Internal Audit Survey: Characteristics of an

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Table 1 Focus Areas Activity Levels and Ranking

    Focus Area

    1 Audits of enterprise risk management

    processes

    2 Project management assurance/

    audits of major projects

    3 Corporate governance reviews

    4 Reviews addressing linkage of

    strategy and company performance

    5 Social and sustainability audits

    The above areas were considered to meet the Committees selection criteria based our review of the Global Internal Audit Survey. According to the Survey:

    The areas were not traditionaldepartments, with activity amount

    There was a fairly even distribution of operational, governance and strategic areas.

    The selection included emerging issues such as environmental sustainability and strategy audits.

    The aspects considered by the committee through this study

    How many respondents had begun to integrate these areas into their audit plans, and what percentages of resources were

    Have these engagements added value the progress being measured?

    For organizations not performing these engagements, what are the main roadblocks and concerns?

    If these activities are not performed currently, what is the timeframe for adoption? What challenges are facing internal auditors in their attempts to add value in their

    organizations in these areas?

    The Dallas Chapter of the Institute of Internal Auditors

    Focus Areas Activity Levels and Ranking

    Activity Rank

    Audits of enterprise risk management 56.6% 8

    Project management assurance/

    audits of major projects

    55.4% 9

    Corporate governance reviews 44.5% 13

    Reviews addressing linkage of

    strategy and company performance

    25.3% 19

    and sustainability audits 19.6% 22

    considered to meet the Committees selection criteria based our review of the Global Internal Audit Survey. According to the Survey:

    traditional focus areas by the majority of internal audit vity amounting to less than 60%.

    There was a fairly even distribution of operational, governance and strategic

    The selection included emerging issues such as environmental sustainability and

    by the committee through this study included the following:

    How many respondents had begun to integrate these areas into their audit plans, percentages of resources were being allocated?

    these engagements added value to their organizations, and if sothe progress being measured? For organizations not performing these engagements, what are the main roadblocks and concerns? If these activities are not performed currently, what is the timeframe for adoption?

    enges are facing internal auditors in their attempts to add value in their organizations in these areas?

    4

    Rank

    considered to meet the Committees selection criteria based on

    internal audit

    There was a fairly even distribution of operational, governance and strategic

    The selection included emerging issues such as environmental sustainability and

    the following:

    How many respondents had begun to integrate these areas into their audit plans,

    eir organizations, and if so, how is

    For organizations not performing these engagements, what are the main

    If these activities are not performed currently, what is the timeframe for adoption? enges are facing internal auditors in their attempts to add value in their

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Methodology For the purposes of the study, the committee use

    as the framework to evaluate the level of maturity of thedepartment as well as its maturity and experience level related to each specific area. The Capability Maturity Model is a continuum used to evaluate the maturity of a process, department or organization, with the stages

    Initial: No sustainable repeatable capabilities (little or no internal audit department or process exists)Infrastructure: Sustainable and repeatable procedures (compliance audits)Integrated: IA management and professional practices uniformly applied (advisory services) Managed: Integrates information from across the organization to improve governance and risk management (overall assurance on Governance, Risk Management and control)Optimized: IA learning from inside and outside the organization for continuous improvement (internal a

    First, the committee asked each respondent to maturity level of their overall internal overall evaluation was to provide a evaluation for each specific audit area.activity areas, the respondentslevel with respect to that particularthe assessment of maturity levels of the organization versus the maturity level of focus areas.

    The Dallas Chapter of the Institute of Internal Auditors

    of the study, the committee used the Capability Maturity as the framework to evaluate the level of maturity of the respondents internal audit department as well as its maturity and experience level related to each specific area. The Capability Maturity Model is a continuum used to evaluate the maturity of a process, department or organization, with the stages of maturity defined as follows:

    No sustainable repeatable capabilities (little or no internal audit department or process exists)

    Sustainable and repeatable internal audit (IA) practices and procedures (compliance audits)

    IA management and professional practices uniformly applied

    Integrates information from across the organization to improve governance and risk management (overall assurance on Governance, Risk Management and control)

    IA learning from inside and outside the organization for continuous audit recognized as key agent of change)

    ommittee asked each respondent to in their opinion nternal audit department. The purpose of obtaining this

    provide a basis against which to compare the maturity evaluation for each specific audit area. Then, for each of the above identified audit

    ondents were asked to assess their internal audit teams to that particular area. The committee then studied the maturity levels of the organization versus the maturity level of focus

    5

    Maturity Model respondents internal audit

    department as well as its maturity and experience level related to each specific focus area. The Capability Maturity Model is a continuum used to evaluate the maturity of a

    of maturity defined as follows:

    No sustainable repeatable capabilities (little or no internal audit

    practices and

    IA management and professional practices uniformly applied

    Integrates information from across the organization to improve governance and risk management (overall assurance on Governance, Risk

    IA learning from inside and outside the organization for continuous

    evaluate the . The purpose of obtaining this

    against which to compare the maturity or each of the above identified audit

    their internal audit teams maturity the differences in

    maturity levels of the organization versus the maturity level of focus

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Value Addition Approaches As mentioned previously, five value addition approaches were selected. A brief

    description of each value addition approach follows. These descriptions were to each respondent:

    1) Project Management refers to the activities performed by the or consulting support for the organizations project management initiatives. Some organizations/companies may not have a dedicated Project Ma(PMO) or Project Management (PM) framework. Internal audits engagement may include the following types of activities:

    Post Implementation R Consultative services Implementation verification

    2) Enterprise Risk Management (ERM)and processes used by organizationopportunities by embedding risk awareness into the strategyERM is different from audit risk assessment, seeking to accomplish the broader initiatives of linking risks to strategic objectives, responses, and managing risk to within risk appetite on an enterpriseInternal audit departments however, the Institute of the acceptable roles internal auditobjective of our study was to determine the extent to which to support ERM implementation while Figure 1iv.

    The Dallas Chapter of the Institute of Internal Auditors

    e Addition Approaches As mentioned previously, five value addition approaches were selected. A brief

    description of each value addition approach follows. These descriptions were

    Project Management Audit and Consultation activities refers to the activities performed by the internal audit department to provide audit or consulting support for the organizations project management initiatives. Some organizations/companies may not have a dedicated Project Management Office (PMO) or Project Management (PM) framework. Internal audits engagement may include the following types of activities:

    Post Implementation Reviews Consultative services during the design and implementation phaseImplementation verification and validation

    Enterprise Risk Management (ERM) ERM generally refers to the methods and processes used by organizations to strategically manage risks and leverage

    by embedding risk awareness into the strategy-setting process. rent from audit risk assessment, seeking to accomplish the broader

    of linking risks to strategic objectives, developing appropriate risk responses, and managing risk to within risk appetite on an enterpriseInternal audit departments could be involved in a number of ways in this processhowever, the Institute of internal auditors has established guidelines surrounding

    internal auditors can take on with respect to ERMobjective of our study was to determine the extent to which internal

    support ERM implementation while staying within the boundaries as defined

    6

    As mentioned previously, five value addition approaches were selected. A brief description of each value addition approach follows. These descriptions were provided

    t and Consultation activities epartment to provide audit

    or consulting support for the organizations project management initiatives. Some nagement Office

    (PMO) or Project Management (PM) framework. Internal audits engagement

    during the design and implementation phase

    enerally refers to the methods manage risks and leverage

    setting process. rent from audit risk assessment, seeking to accomplish the broader

    developing appropriate risk responses, and managing risk to within risk appetite on an enterprise-wide level.

    ould be involved in a number of ways in this process; delines surrounding

    ors can take on with respect to ERM. An nternal audit is able

    within the boundaries as defined in

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    3) Corporate Governance:customs, policies, laws, and institutions affecting the way a corporation (or company) is directed, administered or contra significant role in assisting the board with corporate governance. According to the IIA Position Paper Organizational Governance: Guidance for Internal Auditors, Often, internal auditors can assist organizationboard of directors and executive management on needed improvements and changes in structure and design, not just whether established processes are operating. The type of activities performed by related to the maturity of the Governance Model in the organization, as the IIAs Internal Audit Governance Maturity Model of our study was to identify the level of maturity exhibited by respondents in providing the advisory support recommended by the IIA.

    The Dallas Chapter of the Institute of Internal Auditors

    Figure 1 Internal Audit Roles

    Corporate Governance: Corporate governance is the set of processes, customs, policies, laws, and institutions affecting the way a corporation (or company) is directed, administered or controlled. Internal audit departments play a significant role in assisting the board with corporate governance. According to the IIA Position Paper Organizational Governance: Guidance for Internal Auditors, Often, internal auditors can assist organizations better by advising the board of directors and executive management on needed improvements and changes in structure and design, not just whether established processes are operating. The type of activities performed by internal audit can typically be

    ated to the maturity of the Governance Model in the organization, as the IIAs Internal Audit Governance Maturity Model shows in the Figure 2v

    of our study was to identify the level of maturity exhibited by respondents in e advisory support recommended by the IIA.

    7

    Corporate governance is the set of processes, customs, policies, laws, and institutions affecting the way a corporation (or

    Internal audit departments play a significant role in assisting the board with corporate governance. According to the IIA Position Paper Organizational Governance: Guidance for Internal

    s better by advising the board of directors and executive management on needed improvements and changes in structure and design, not just whether established processes are

    udit can typically be ated to the maturity of the Governance Model in the organization, as the IIAs

    v. An objective

    of our study was to identify the level of maturity exhibited by respondents in

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 2

    4) Social and sustainability (Corporate social responsibility, environmental) audits: Social and sustainability initiatives include the pwhereby an organization integrates its social responsibilities and sustainable business practices. Social responsibilities might include activities to promote public interest, charitable, and/or philanthropic activities. Sustainabiinclude practices to promote environmentally friendly activities, prevent environmental disasters, or prevent misterm profits rather than for customer welfare.)initiatives are gaining significant prominence in business and government in recent years. The latest sustainability reporting trends indicate that 142 regulatory instruments addressing sustainability reporting exist in 30 countries and 65% of the standards from government, a series of challenges were noted in a survey by Deloittepart of our study objectives we sought to understand the rate of voluntary adoption of sustainability initiatives in the

    The Dallas Chapter of the Institute of Internal Auditors

    2 Internal Audit Governance Maturity Model

    Social and sustainability (Corporate social responsibility, environmental) Social and sustainability initiatives include the processes and practices,

    whereby an organization integrates its social responsibilities and sustainable business practices. Social responsibilities might include activities to promote

    interest, charitable, and/or philanthropic activities. Sustainabiinclude practices to promote environmentally friendly activities, prevent environmental disasters, or prevent mis-selling (e.g. selling of products for shortterm profits rather than for customer welfare.) Social and sustainability goals and

    itiatives are gaining significant prominence in business and government in recent years. The latest sustainability reporting trends indicate that 142 regulatory instruments addressing sustainability reporting exist in 30 countries and 65% of the standards are considered mandatoryvi. Even with significant push from government, a series of challenges were noted in a survey by Deloittepart of our study objectives we sought to understand the rate of voluntary adoption of sustainability initiatives in the DFW Metroplex, the extent of

    8

    Social and sustainability (Corporate social responsibility, environmental) and practices,

    whereby an organization integrates its social responsibilities and sustainable business practices. Social responsibilities might include activities to promote

    interest, charitable, and/or philanthropic activities. Sustainability might include practices to promote environmentally friendly activities, prevent

    selling (e.g. selling of products for short-Social and sustainability goals and

    itiatives are gaining significant prominence in business and government in recent years. The latest sustainability reporting trends indicate that 142 regulatory instruments addressing sustainability reporting exist in 30 countries

    . Even with significant push from government, a series of challenges were noted in a survey by Deloittevii. As part of our study objectives we sought to understand the rate of voluntary

    the extent of

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    respondents activities to support these initiatives, noted.

    5) Strategy Audits: The definition of business strategy is a long term plan of action designed to achieve a particular goal or set of goalmay be comprised of two types: 1) Assessing the adequacy of the strategy making process and subsequent monitoringof a business and comparing that to the planned direction as outlined istrategic plan. Strategy respondents to the Global Internal Audit Survey reporting that they are a significant part of their organizations audit plans. However, they important way for internalmeasurement and feedback on performance in association with achievement of strategic objectives. As the consultative partner, advising controls that impact achievement of strategic objectives and value creation, we sought to determine whether these audits are being performed in pursuit of this direction.

    Survey Design The committee contacted

    having at least 25 participants)audit executive uniquely represented one formally functioning internal audit department. During this process the committeeand organization sizes.

    The data was collected in two phases. In the first phase, the requested to complete a preliminary III). In the second phase, the reminutes to obtain additional informationquestionnaire (see Appendix- 25 respondents for this study.

    The Dallas Chapter of the Institute of Internal Auditors

    respondents activities to support these initiatives, and the particular challenges

    : The definition of business strategy is a long term plan of action designed to achieve a particular goal or set of goals or objectives. Strategy audits may be comprised of two types: 1) Assessing the adequacy of the strategy making process and subsequent monitoring, or 2) Assessing the actual direction of a business and comparing that to the planned direction as outlined istrategic plan. Strategy audits are not common, with less than 25% of respondents to the Global Internal Audit Survey reporting that they are a significant part of their organizations audit plans. However, they can be an important way for internal auditors to add value through providing independent measurement and feedback on performance in association with achievement of

    As the internal audit profession seeks to emerge as a consultative partner, advising management and the board on the risks and controls that impact achievement of strategic objectives and value creation, we sought to determine whether these audits are being performed in pursuit of this

    The committee contacted approximately 40 audit executives (with a goal of having at least 25 participants) in the DFW area for participation in this study

    uniquely represented one formally functioning internal audit department. During this process the committee attempted to cover a wide array of industry sectors

    The data was collected in two phases. In the first phase, the respondents were preliminary written data-gathering questionnaire

    In the second phase, the respondents were interviewed for approximatelyminutes to obtain additional information based on the responses provided in the initial

    IV). The committee was able to meet the goal of having for this study.

    9

    and the particular challenges

    : The definition of business strategy is a long term plan of action s or objectives. Strategy audits

    may be comprised of two types: 1) Assessing the adequacy of the strategy or 2) Assessing the actual direction

    of a business and comparing that to the planned direction as outlined in the are not common, with less than 25% of

    respondents to the Global Internal Audit Survey reporting that they are a can be an

    auditors to add value through providing independent measurement and feedback on performance in association with achievement of

    udit profession seeks to emerge as a oard on the risks and

    controls that impact achievement of strategic objectives and value creation, we sought to determine whether these audits are being performed in pursuit of this

    (with a goal of in the DFW area for participation in this study. Each

    uniquely represented one formally functioning internal audit department. wide array of industry sectors

    respondents were questionnaire (see Appendix

    approximately 30 based on the responses provided in the initial

    The committee was able to meet the goal of having

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Project Plan

    The research project was completed in three phases starting from Octhrough March 2011 as shown below:

    Figure 3 Project Plan

    Participants Profile The research committee solicited

    organizations that are based in DFW area. The parameters defined by the committee for the participants were as follows:

    Chief Audit Executive (CAE), the topequivalent department with the responsibility of providing

    Audit Executive (AE), an existinggroup who has a direct reporting relationship to a CAE

    The Dallas Chapter of the Institute of Internal Auditors

    The research project was completed in three phases starting from October 2010 through March 2011 as shown below:

    The research committee solicited audit executives in the DFW areabased in the DFW area or that have significant operations in the

    he parameters defined by the committee for the participants were as

    Chief Audit Executive (CAE), the top-most person in the internal auditequivalent department with the responsibility of providing internal auditAudit Executive (AE), an existing member of the internal audit management

    who has a direct reporting relationship to a CAE.

    10

    tober 2010

    area who serve icant operations in the

    he parameters defined by the committee for the participants were as

    internal audit or internal audit services.

    internal audit management

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Ex-CAEs or Ex-AEs, who have served in audit management year, but are not currently em

    Other Director or higher level personnel in the audit organizationsufficient knowledge of internal audit activities of the organization.

    Professional Service Practitioners (PSP), Partnerservices firms who hafunctions. These categormajor clients as the representative organization for the purpose of the survey.

    Each participant represented a uniDFW area.

    The quality of the data is greatly dependent on the experience level of the participants and their tenure with the organization. The data cooverall experience levels of respondents respondents being the internal audithaving at least 10 years experiencethe experience levels of the respondents

    24%

    4%8%

    The Dallas Chapter of the Institute of Internal Auditors

    AEs, who have served in audit management rolesnot currently employees.

    higher level personnel in the audit organizationsufficient knowledge of internal audit activities of the organization. Professional Service Practitioners (PSP), Partner-level personnel in professional

    o have adequate knowledge of their clients. These categories of participants were requested to select one of their

    major clients as the representative organization for the purpose of the survey.Each participant represented a unique functional internal audit department in the

    Figure 4 Respondents' Profile

    The quality of the data is greatly dependent on the experience level of the participants and their tenure with the organization. The data collected indicated that the

    levels of respondents were high, with approximately twointernal audit leaders (CAEs) and 84% of the respondents experience. Figure-5 provides an overview of th

    the experience levels of the respondents.

    64%

    Respondents' Profile

    Chief Audit Executive

    (CAE)

    Audit Executive

    Ex-CAE

    Professional Services

    Partner

    11

    roles within the past

    higher level personnel in the audit organizations who have

    level personnel in professional adequate knowledge of their clients internal audit of participants were requested to select one of their

    major clients as the representative organization for the purpose of the survey. que functional internal audit department in the

    The quality of the data is greatly dependent on the experience level of the llected indicated that the

    two-thirds of the % of the respondents

    provides an overview of the distribution of

    Chief Audit Executive

    Professional Services

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Respondents' experience Figure-6. The data collected from the respondents (84%) of the respondents had at least organization and two audit calendar cycles of experience with the practices of the organization.

    Figure

    28%

    Overall Experience Levels

    28%

    16%

    Respondents' Experience with the

    The Dallas Chapter of the Institute of Internal Auditors

    Figure 5 Overall Experience Levels

    Respondents' experience with their respective organizations The data collected from the respondents indicated that a high proportion

    %) of the respondents had at least two or more years of tenure within their current audit calendar cycles of experience with the practices of the

    Figure 6 Experience with the Organization

    4%12%

    56%

    Overall Experience Levels

    Less than 5 years

    5 to 10 years

    10 to 25 years

    More than 25 years

    16%

    40%

    Respondents' Experience with the

    Organization

    Less than 2 years

    2 to 5 years

    5 to 10 years

    More than 10 years

    12

    is depicted in indicated that a high proportion

    f tenure within their current audit calendar cycles of experience with the practices of the

    Less than 5 years

    More than 25 years

    Less than 2 years

    More than 10 years

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Represented Organizations ProfileTo ensure the data was representative, t

    obtain data covering a wide variety of industries.NAICS as a reference to identify the were noted to operate in more than one industry sector. For example, operated in both the construction and manufacturing operated in both the transportation and information sectors. The committee noted thatoverall; the responding organizations represented all the NAICS industry sectorfully or partially.

    The data collected represented a wide variety of organizationemployees and revenue. Howeverorganizations (76%) achieved

    Figure

    In terms of employee countorganizations had at least 10,000 employeedistribution by number of employees.

    32%

    Revenue of Respondents'

    The Dallas Chapter of the Institute of Internal Auditors

    Represented Organizations Profile data was representative, the research committee attempted to

    obtain data covering a wide variety of industries. The research committee used the tify the major industry sectors. A number of organizations

    were noted to operate in more than one industry sector. For example, oneconstruction and manufacturing sectors while another respondent

    rtation and information sectors. The committee noted thatthe responding organizations represented all the NAICS industry sector

    The data collected represented a wide variety of organizational sizes in terms of owever, the majority of respondents reported that their

    achieved at least 1 billion or more in yearly revenue.

    Figure 7 Revenue of Respondents Organization

    count, it was noted that about half (48%) of the least 10,000 employees or more. Please see Figure

    by number of employees.

    8%

    12%

    4%

    44%

    Revenue of Respondents'

    Organization

    Less than $200 million

    $200 million to $500

    million

    $500 million to $1 billion

    $1 billion to $5 billion

    More than $5 billion

    13

    he research committee attempted to The research committee used the

    industry sectors. A number of organizations one respondent

    another respondent rtation and information sectors. The committee noted that,

    the responding organizations represented all the NAICS industry sectors either

    sizes in terms of respondents reported that their

    least 1 billion or more in yearly revenue.

    of the Please see Figure-8 for

    Less than $200 million

    $200 million to $500

    $500 million to $1 billion

    $1 billion to $5 billion

    More than $5 billion

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 8 Size of Respondents

    In terms of geography, operate internationally. Please see

    Figure

    20%

    20%

    8%

    Size of Respondents' Organization (By

    48%

    4%

    Respondents' Organization Type

    The Dallas Chapter of the Institute of Internal Auditors

    Size of Respondents Organization (by Employees)

    In terms of geography, about half (48%) of the respondents organizations Please see Figure-9 for distribution by organization type

    Figure 9 Respondents Organization Type

    12%

    40%

    8%

    Size of Respondents' Organization (By

    Employees)

    Less than 1000

    1,000 to 10,000

    10,000 to 50,000

    50,000 to 100,000

    100,000 +

    16%

    32%

    4%

    Respondents' Organization Type

    Regional

    National

    International/ Trans

    national

    Others and Not-

    Applicable

    14

    organizations by organization type.

    Less than 1000

    1,000 to 10,000

    10,000 to 50,000

    50,000 to 100,000

    International/ Trans-

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Represented Internal Audit Departments ProfileThe respondents audit

    respondents had departments half (56%) of the respondents reporting that their internal audit department consisted of at least 11 members.

    Figure

    In terms of maturity by respondents internal audit departments the majority of them (over 60%)Figure-11 for the distribution by the duration of operations of internal audit departments.

    36%

    12%

    8%

    Respondents' IA Department Size

    The Dallas Chapter of the Institute of Internal Auditors

    Represented Internal Audit Departments Profile audit departments were of various sizes. The majority

    had departments in the 11 to 25 members category and slightly more than half (56%) of the respondents reporting that their internal audit department consisted of

    Figure 10 Respondents IA Department Size

    In terms of maturity by the length of operation, the data indicated that 8departments have been operating for at least 5 years and

    (over 60%) have been in operation for over 10 years.by the duration of operations of internal audit departments.

    24%

    20%

    Respondents' IA Department Size

    Less than 5 members

    6 to 10 members

    11 to 25 members

    26 to 50 members

    More than 50 members

    15

    ajority of the and slightly more than

    half (56%) of the respondents reporting that their internal audit department consisted of

    ion, the data indicated that 80% of the have been operating for at least 5 years and

    have been in operation for over 10 years. Please see by the duration of operations of internal audit departments.

    Less than 5 members

    More than 50 members

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 11 Respondents IA Department's Duration of Operations

    In terms of the maturity of was noted that most (88%) of the organizations rated themselves aslevel of Integrated or Managed.level of the internal audit department.

    Figure 12 Overall Maturity Level as Assessed by Respondents

    60%

    Respondents' IA Departments'

    Duration of Operations

    48%

    Overall Maturity Level

    The Dallas Chapter of the Institute of Internal Auditors

    Respondents IA Department's Duration of Operations

    In terms of the maturity of internal audits process as rated by the respondents, it of the organizations rated themselves as having a maturity

    level of Integrated or Managed. Please see Figure-12 for distribution by overall internal audit department.

    Overall Maturity Level as Assessed by Respondents

    4%

    16%

    20%

    Respondents' IA Departments'

    Duration of Operations

    One year or less

    1 to 5 years

    5 to 10 years

    10 or more years

    4% 4%

    40%

    4%

    Overall Maturity Level

    Initial

    Infrastructure

    Integrated

    Managed

    Optimized

    16

    udits process as rated by the respondents, it having a maturity

    overall maturity

    One year or less

    5 to 10 years

    10 or more years

    Infrastructure

    Integrated

    Managed

    Optimized

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    In terms of the activities performed by the internal audit departments, the distribution pattern in Table 2 departments had higher involvement in audit and assurance activities and compliance activities.

    Table 2 Respondents Internal Audit Departments

    Level/ Activity A&A Activities

    No Time (0%) _ 0% to 10% _ 10% to 25% 2 26% to 50% 8 51% to 75% 14

    More than 75% 1

    Area Specific ObservationsAs touched on previously, the process of collecti

    was executed in two phases. In the first phase, respondents were asked to complete pre-interview questionnaires to provide a baseline understanding of thematurity and resource allocation rationale for each fowere then targeted to the responses provided in the preon the rationale that the information available from respondents would vary depending on the experience with that area. For example, a Cdepartments maturity in performing Strategy Audits as Initial would likely have limited input on the benefits of conducting such activities, but may be able to answer questions related to future plans in this area. Conversely,maturity as Optimized could offer additional information about the benefits and roadblocks in conducting such activities, and how value and continuous improvement programs are monitored and measured. For the complete list to Appendices III and IV.

    The Dallas Chapter of the Institute of Internal Auditors

    In terms of the activities performed by the internal audit departments, the was noted and the data indicated that most of the audit

    had higher involvement in audit and assurance activities and compliance

    Internal Audit Departments Time Allocation for Various Activities.

    Consulting Compliance Administration

    1 1 -

    9 8 13

    12 7 11

    3 8 1

    - 1 -

    - - -

    Area Specific Observations As touched on previously, the process of collecting the data for each focus area

    was executed in two phases. In the first phase, respondents were asked to complete interview questionnaires to provide a baseline understanding of their

    maturity and resource allocation rationale for each focus area. Follow-up interviews were then targeted to the responses provided in the pre-interview questionnaires based on the rationale that the information available from respondents would vary depending on the experience with that area. For example, a CAE or AE who assessed his departments maturity in performing Strategy Audits as Initial would likely have limited input on the benefits of conducting such activities, but may be able to answer questions related to future plans in this area. Conversely, a respondent who assessed the maturity as Optimized could offer additional information about the benefits and roadblocks in conducting such activities, and how value and continuous improvement programs are monitored and measured. For the complete list of survey questions, refer

    17

    In terms of the activities performed by the internal audit departments, the was noted and the data indicated that most of the audit

    had higher involvement in audit and assurance activities and compliance

    inistration Others

    12

    11

    2

    -

    -

    -

    ng the data for each focus area was executed in two phases. In the first phase, respondents were asked to complete

    experience, up interviews

    interview questionnaires based on the rationale that the information available from respondents would vary depending

    AE or AE who assessed his departments maturity in performing Strategy Audits as Initial would likely have limited input on the benefits of conducting such activities, but may be able to answer questions

    a respondent who assessed the maturity as Optimized could offer additional information about the benefits and roadblocks in conducting such activities, and how value and continuous improvement

    of survey questions, refer

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    A summary of the data and observationseach focus area is provided in the subsections below.

    Project Management

    The data collected in this area indicated that maturity level with about oneorganizations at this maturity level and 7see figure 13 for the distribution of the assessed maturity levels.

    Figure 13 Maturity Level (Project Management) as Assessed by Respondents

    About half of the respondentsdepartments internal audit time in respondents indicated that their internal audit department spends at least 5% or more of their departments time in this area.

    36%

    20%

    Maturity Level as Assessed by

    The Dallas Chapter of the Institute of Internal Auditors

    A summary of the data and observations (for the sample size of 25)each focus area is provided in the subsections below.

    The data collected in this area indicated that Integrated was the medianabout one-third (36%) of the respondents identifying their

    organizations at this maturity level and 76% at the Integrated level or below.for the distribution of the assessed maturity levels.

    Maturity Level (Project Management) as Assessed by Respondents

    respondents organizations (54%) spent less thaninternal audit time in the project management area. About 46%dicated that their internal audit department spends at least 5% or more of

    their departments time in this area.

    20%

    20%

    4%

    Maturity Level as Assessed by

    Respondents

    Initial

    Infrastructure

    Integrated

    Managed

    Optimized

    18

    (for the sample size of 25) relative to

    as the median of the respondents identifying their

    level or below. Please

    Maturity Level (Project Management) as Assessed by Respondents

    than 6% of their About 46% of the

    dicated that their internal audit department spends at least 5% or more of

    Infrastructure

    Integrated

    Managed

    Optimized

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 14

    Approximately half of the respondents noted that internal audit time on audit and assurance activities.

    Figure 15 Allocation of Time Between Consulting and Assurance Activities

    12%

    17%

    17%

    Time Spent for Project Management

    20%

    12%

    4% 4%

    Allocation of Time Between Consulting

    The Dallas Chapter of the Institute of Internal Auditors

    Time Spent for Project Management Activities

    Approximately half of the respondents noted that their departments spend 75% of n audit and assurance activities.

    Allocation of Time Between Consulting and Assurance Activities

    8%

    46%

    0%

    Time Spent for Project Management

    Activities

    No Time Spent

    0% to 5%

    6% to 10%

    11% to 15%

    16% to 25%

    More than 25%

    8%

    52%

    4%

    Allocation of Time Between Consulting

    and Assurance No consulting time (all audit/assurance)

    Some consulting (Less than 25%

    of time)

    Half consulting (Other 50% of

    time for audit/assurance)

    Mostly consulting (75% or more

    time)

    All consulting (no

    auidt/assurance)

    Not applicable

    19

    spend 75% of their

    Allocation of Time Between Consulting and Assurance Activities

    No Time Spent

    11% to 15%

    16% to 25%

    More than 25%

    Some consulting (Less than 25%

    Half consulting (Other 50% of

    Mostly consulting (75% or more

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    The vast majority of the respondentslevels were appropriate for the project management area

    Figure 16

    Some of the themes noted during the interviews are as follows: A number of respondent

    Information Technology (IT) initiatives (asmanagement activities such as construction projectetc.)

    A large number of organizations had department (mainly IT) framework.

    About 60% of the respondentsin project management type internal audit activitiesto be involved in this area in the near future.

    A large portion of the respondents indicated that there is not an organizationwide project management framework, indicating opportunity for management to streamline their project management activities across th

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Project Management Resource Allocation

    The Dallas Chapter of the Institute of Internal Auditors

    vast majority of the respondents (75%) felt that the allocations at the current for the project management area as noted below:

    16 Project Management Resource Allocation

    Some of the themes noted during the interviews are as follows: A number of respondents associated the term project management Information Technology (IT) initiatives (as opposed to business process management activities such as construction projects, process re

    number of organizations had a specially assigned project department (mainly IT) and a few organizations had a wider project management

    About 60% of the respondents organizations were noted to be currently involved in project management type internal audit activities, while 25% do

    be involved in this area in the near future. A large portion of the respondents indicated that there is not an organizationwide project management framework, indicating opportunity for management to streamline their project management activities across the organization.

    0 5 10 15

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Others

    Project Management Resource Allocation

    20

    allocations at the current as noted below:

    project management with opposed to business process

    , process re-engineering,

    a specially assigned project management project management

    noted to be currently involved 25% dont have plans

    A large portion of the respondents indicated that there is not an organization-wide project management framework, indicating opportunity for management to

    e organization.

    20

    Project Management Resource Allocation

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Some key observations from

    When asked how activities in this area added value to their organizations, and how the value was measured, many respondents stated that their consultative activities in this area provided substantioften not be quantified. For example, many respondents stated that they were regularly consulted to advise on project risks and make control recommendations in the planning stage of major projects. By identifying critical risks that threaten the success of the project and recommending mitigating controls before project implementation, these respondents believed internal auditproject initiatives. Additionally, some respondents stated that they were consulted to review process design within major projects and recommend improvements to streamline the process and gain efficiencies. These process improvement recommendations often resulted in reduced cost organization. Various roadblocks and challenges were noted by respondents related to their activities in this area. A small number of respondents stated that they lacked human resources and training for lowersupport. One respondent stated that occasionally independence can become an issue when process owners and project managers do not understand boundaries and the need to maintain independence. The retwo key methods of overcoming this issue are communication with the project team at the inception of the project planning phase to clearly define limiting internal audits involvement to advisory in the involvement in the implementation phase.

    Enterprise Risk Management

    The data collected in this area indicated that Integrated or lower level of maturity in this area with the

    The Dallas Chapter of the Institute of Internal Auditors

    Some key observations from interviews:

    When asked how activities in this area added value to their organizations, and how the value was measured, many respondents stated that their consultative activities in this area provided substantial value to the organization, although this value could often not be quantified. For example, many respondents stated that they were regularly consulted to advise on project risks and make control recommendations in the planning

    By identifying critical risks that threaten the success of the project and recommending mitigating controls before project implementation, these

    internal audit played a significant role in ensuring success of tionally, some respondents stated that they were consulted to

    review process design within major projects and recommend improvements to streamline the process and gain efficiencies. These process improvement recommendations often resulted in reduced cost of the overall project to the

    Various roadblocks and challenges were noted by respondents related to their activities in this area. A small number of respondents stated that they lacked human resources and training for lower-level staff to provide adequate Project Management support. One respondent stated that occasionally independence can become an issue when process owners and project managers do not understand boundaries and the need to maintain independence. The respondent also stated that two key methods of overcoming this issue are communication with the project team at the inception of the project planning phase to clearly define internal a

    udits involvement to advisory in the design phase, with less involvement in the implementation phase.

    Enterprise Risk Management

    The data collected in this area indicated that 75% of the organizations had an level of maturity in this area with the median in the

    21

    When asked how activities in this area added value to their organizations, and how the value was measured, many respondents stated that their consultative activities

    al value to the organization, although this value could often not be quantified. For example, many respondents stated that they were regularly consulted to advise on project risks and make control recommendations in the planning

    By identifying critical risks that threaten the success of the project and recommending mitigating controls before project implementation, these

    played a significant role in ensuring success of tionally, some respondents stated that they were consulted to

    review process design within major projects and recommend improvements to streamline the process and gain efficiencies. These process improvement

    of the overall project to the

    Various roadblocks and challenges were noted by respondents related to their activities in this area. A small number of respondents stated that they lacked human

    o provide adequate Project Management support. One respondent stated that occasionally independence can become an issue when process owners and project managers do not understand internal audits

    spondent also stated that two key methods of overcoming this issue are communication with the project team at

    audits role, and design phase, with less

    5% of the organizations had an in the Infrastructure

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    stages of adopting ERM processesby ERM process maturity.

    Figure 17 Maturity Level (ERM) as Assessed by Respondents

    The data collected indicated that all respondents spend atarea, with about one-third of internal audit dinvolvement (more than 10% of time)over assurance activities as compared to consulting activitiesFigure-19.

    Figure

    20%

    24%

    Maturity Level As Assessed by

    16%

    8%

    8%

    Time Spent for ERM Activities

    The Dallas Chapter of the Institute of Internal Auditors

    stages of adopting ERM processes. Please see figure-17 for the distribution of samples

    Maturity Level (ERM) as Assessed by Respondents

    The data collected indicated that all respondents spend at least some time in this internal audit departments having higher level of

    (more than 10% of time). The extent of involvement appears to be more over assurance activities as compared to consulting activities as noted in Figure

    Figure 18 Time Spent for ERM Activities

    24%

    28%

    4%

    Maturity Level As Assessed by

    Respondents

    Initial

    Infrastructure

    Integrated

    Managed

    Optimized

    36%

    32%

    8% 0%

    Time Spent for ERM Activities

    No Time Spent

    0% to 5%

    6% to 10%

    11% to 15%

    16% to 25%

    More than 25%

    22

    bution of samples

    least some time in this epartments having higher level of

    . The extent of involvement appears to be more in Figure-18 and

    Infrastructure

    Integrated

    Managed

    Optimized

    No Time Spent

    11% to 15%

    16% to 25%

    More than 25%

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 19 Allocation of Time to Consulting and Assurance Activities

    The data collected regarding the rationale for resource allocation and focus indicated that a vast majority of the respondents (75%) felt that the alcurrent levels were appropriate as noted below:

    28%

    4% 4% 0%

    Allocation of Time to Consulting and Assurance

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    ERM Resource Allocation

    The Dallas Chapter of the Institute of Internal Auditors

    Allocation of Time to Consulting and Assurance Activities

    The data collected regarding the rationale for resource allocation and focus indicated that a vast majority of the respondents (75%) felt that the allocation

    appropriate as noted below:

    Figure 20 ERM Resource Allocation

    20%

    44%

    0%

    Allocation of Time to Consulting and Assurance

    ActivitiesNo consulting time (all

    audit/assurance)

    Some consulting (Less than 25% of

    time)

    Half consulting (Other 50% of time for

    audit/assurance)

    Mostly consulting (75% or more time)

    All consulting (no auidt/assurance)

    Not applicable

    0 5 10 15

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Others

    ERM Resource Allocation

    23

    The data collected regarding the rationale for resource allocation and focus locations at the

    Allocation of Time to Consulting and Assurance

    Some consulting (Less than 25% of

    Half consulting (Other 50% of time for

    Mostly consulting (75% or more time)

    All consulting (no auidt/assurance)

    20

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    The themes noted during the interviews are as follows: A number of respondents indicated that internal audit is involved in co

    of the ERM initiatives at their organizations. In some instances, been asked to be the owner of the process as no other departments accepted the responsibility.

    A vast number of organizations indicated that they have a formal prplace (70%).

    About 25% of the respondents (among the organizations in early stages) indicated that they do not

    Independence was not identified as a concern in this area.

    Some key observations from

    According to the IIA, internal risk awareness within the organization. However, several respondents stated in interviews that a major barrier to getting ERM off the ground in their organizations is convincing executives of its beneficial impact.

    One respondent who has experience getting successful ERM implementations off the ground stated that implementing ERM is more an art than a science. Getting buy-in from top-level management can be a challengrespondent has developed several innovative approaches to address the issue while demonstrating the value of the initiative:

    - Proactively discuss risks with top level management in formal and informal discussions. Gain an understanding of what keeps management up at night and identify events that would negatively impact the achievement of objectives. In this effort, establish what the problems are, whether they are systemic or isolated, and begin to identify what the key controls are. Do the controls currently exist, or must they be designed? Where the key controls shouldprocess owners begin having to be accountable through the quarterly certification

    The Dallas Chapter of the Institute of Internal Auditors

    he themes noted during the interviews are as follows: A number of respondents indicated that internal audit is involved in coof the ERM initiatives at their organizations. In some instances, internal auditbeen asked to be the owner of the process as no other departments accepted

    A vast number of organizations indicated that they have a formal pr

    About 25% of the respondents (among the organizations in early stages) do not plan to increase their level of involvement.

    Independence was not identified as a concern in this area.

    Some key observations from interviews:

    nternal audit can and should be a champion of ERM and risk awareness within the organization. However, several respondents stated in interviews that a major barrier to getting ERM off the ground in their organizations is

    nvincing executives of its beneficial impact. One respondent who has experience getting successful ERM implementations

    off the ground stated that implementing ERM is more an art than a science. Getting level management can be a challenge due to various factors, and the

    respondent has developed several innovative approaches to address the issue while demonstrating the value of the initiative:

    Proactively discuss risks with top level management in formal and informal n an understanding of what keeps management up at night and

    identify events that would negatively impact the achievement of objectives. In this effort, establish what the problems are, whether they are systemic or isolated, and begin

    e key controls are. Do the controls currently exist, or must they be the key controls should be located to ensure optimization? As

    process owners begin having to be accountable through the quarterly certification

    24

    A number of respondents indicated that internal audit is involved in co-ordination internal audit has

    been asked to be the owner of the process as no other departments accepted

    A vast number of organizations indicated that they have a formal process in

    About 25% of the respondents (among the organizations in early stages) plan to increase their level of involvement.

    udit can and should be a champion of ERM and risk awareness within the organization. However, several respondents stated in interviews that a major barrier to getting ERM off the ground in their organizations is

    One respondent who has experience getting successful ERM implementations off the ground stated that implementing ERM is more an art than a science. Getting

    e due to various factors, and the respondent has developed several innovative approaches to address the issue while

    Proactively discuss risks with top level management in formal and informal n an understanding of what keeps management up at night and

    identify events that would negatively impact the achievement of objectives. In this effort, establish what the problems are, whether they are systemic or isolated, and begin

    e key controls are. Do the controls currently exist, or must they be be located to ensure optimization? As

    process owners begin having to be accountable through the quarterly certification

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    process for exceptions, less and less exceptions should occur over time. These results can then be presented to management as evidence of the success of the initiative, as it demonstrates effective results in reducing the risks that keep management up at night. This can solidify and increase support for a formal ERM effort built on continuous improvement. This approach allows adoption of ERM as an incremental effort, rather than an overnight implementation.

    - Develop a pilot of ERM for a single department, such as AccountRoll ERM out in that one department by identifying the departments objectives, linking them to risks, and developing risk responses and control activities. Self Assessment testing should be performed periodically to evaluate the success the successes and opportunities for improved implementation. Build on the knowledge learned to refine the process in that department. Present the results to senior management as a proposal for a phased implementation that is morbe more easily integrated into the business processes. If management understands that ERM doesnt have to be all at once, and doesnt have to be overcomplicated, buyis easier to achieve.

    Another respondent acknowledged that ERM wastage within his organization, but stated that this was intentional and that the company was where it wanted to be with respect to ERM with limited additional investment. With his approach, all the elements of tto link risks to strategy, increase risk awareness in the company, and increase process owner accountability for developing risk responses. benefit to his approach to ERM is that it has allowed and build risk awareness into the culture of the organization over time, without overwhelming process owners with the ERM terminology. In annual risk assessments, internal audit gains an understanding of the highest risks facing the organization. Then, when the audit plan is developed it is linked to the companys strategy risks are linked to strategic objectives and the audit plan is linked to strategy. These are key objectives within ERM and the respondent believes he is accomplishing them

    The Dallas Chapter of the Institute of Internal Auditors

    less and less exceptions should occur over time. These results can then be presented to management as evidence of the success of the initiative, as it demonstrates effective results in reducing the risks that keep management up at night.

    dify and increase support for a formal ERM effort built on continuous improvement. This approach allows adoption of ERM as an incremental effort, rather than an overnight implementation.

    Develop a pilot of ERM for a single department, such as AccountRoll ERM out in that one department by identifying the departments objectives, linking them to risks, and developing risk responses and control activities. Self Assessment testing should be performed periodically to evaluate the success of the initiative, noting the successes and opportunities for improved implementation. Build on the knowledge learned to refine the process in that department. Present the results to senior management as a proposal for a phased implementation that is more practical and can be more easily integrated into the business processes. If management understands that ERM doesnt have to be all at once, and doesnt have to be overcomplicated, buy

    Another respondent acknowledged that ERM was probably in the Initial or Infrastructure stage within his organization, but stated that this was intentional and that the company was where it wanted to be with respect to ERM with limited additional investment. With his approach, all the elements of the internal audit / compliance functions work together to link risks to strategy, increase risk awareness in the company, and increase process owner accountability for developing risk responses. This respondent believes that a key

    to ERM is that it has allowed internal audit to link risk to strategy and build risk awareness into the culture of the organization over time, without overwhelming process owners with the ERM terminology. In annual risk assessments,

    an understanding of the highest risks facing the organization. Then, when the audit plan is developed it is linked to the companys strategy risks are linked to strategic objectives and the audit plan is linked to strategy. These are

    y objectives within ERM and the respondent believes he is accomplishing them

    25

    less and less exceptions should occur over time. These results can then be presented to management as evidence of the success of the initiative, as it demonstrates effective results in reducing the risks that keep management up at night.

    dify and increase support for a formal ERM effort built on continuous improvement. This approach allows adoption of ERM as an incremental effort, rather

    Develop a pilot of ERM for a single department, such as Accounting or Finance. Roll ERM out in that one department by identifying the departments objectives, linking them to risks, and developing risk responses and control activities. Self Assessment

    of the initiative, noting the successes and opportunities for improved implementation. Build on the knowledge learned to refine the process in that department. Present the results to senior

    e practical and can be more easily integrated into the business processes. If management understands that ERM doesnt have to be all at once, and doesnt have to be overcomplicated, buy-in

    s probably in the Initial or Infrastructure stage within his organization, but stated that this was intentional and that the company was where it wanted to be with respect to ERM with limited additional investment. With

    he internal audit / compliance functions work together to link risks to strategy, increase risk awareness in the company, and increase process

    This respondent believes that a key udit to link risk to strategy

    and build risk awareness into the culture of the organization over time, without overwhelming process owners with the ERM terminology. In annual risk assessments,

    an understanding of the highest risks facing the organization. Then, in this manner,

    risks are linked to strategic objectives and the audit plan is linked to strategy. These are y objectives within ERM and the respondent believes he is accomplishing them

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    without creating a separate ERM effort. This helps gain the buyhe presents the audit plan, because management sees a risklinked to the company's core objectives, and it makes sense to them.

    A major benefit noted by various respondents was that the ERM implementation process resulted in positive changes to the risk culture of the organization. Often, the process of conducting risk assessments and discussing risks with management resulted in increased risk awareness and more accountability on the part of process owners and managers.

    Corporate Governance

    The data collected in this area maturity level with 32% of the respondents identifying their organizations at this maturity level and about two-thirds (64

    Figure 21 Maturity Level (Corporate Governance) as Assessed by

    More than half of the respondents (departments time was spent at least 1

    32%

    Maturity Level as Assessed by

    The Dallas Chapter of the Institute of Internal Auditors

    without creating a separate ERM effort. This helps gain the buy-in of management when he presents the audit plan, because management sees a risk-based audit plan that is

    the company's core objectives, and it makes sense to them. A major benefit noted by various respondents was that the ERM implementation

    process resulted in positive changes to the risk culture of the organization. Often, the sessments and discussing risks with management resulted

    in increased risk awareness and more accountability on the part of process owners and

    The data collected in this area indicated that Integrated was the median% of the respondents identifying their organizations at this maturity

    thirds (64%) below the Integrated maturity level or below.

    Maturity Level (Corporate Governance) as Assessed by Respondents

    More than half of the respondents (60%) indicated that their internal audit at least 10% or more in this area.

    12%

    20%

    32%

    4%

    Maturity Level as Assessed by

    Respondents

    Initial

    Infrastructure

    Integrated

    Managed

    Optimized

    26

    in of management when based audit plan that is

    A major benefit noted by various respondents was that the ERM implementation process resulted in positive changes to the risk culture of the organization. Often, the

    sessments and discussing risks with management resulted in increased risk awareness and more accountability on the part of process owners and

    as the median % of the respondents identifying their organizations at this maturity

    level or below.

    Respondents

    60%) indicated that their internal audit

    Infrastructure

    Integrated

    Managed

    Optimized

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Figure 22 Time Spent for Corporate Governance Activities

    Of the time spent in this areatheir internal audit departmentsthe Figure below.

    Figure 23 Allocation of Time between Consulting and Assuran

    24%

    28%

    Time Spent for Corporate

    Governance Activities

    4%4%

    4% 4%

    Allocation of Time Between Consulting and

    The Dallas Chapter of the Institute of Internal Auditors

    Time Spent for Corporate Governance Activities

    in this area, a majority (68%) of the respondents noted that their internal audit departments time spent is in assurance type activities as shown in

    Allocation of Time between Consulting and Assurance Activities

    4%

    20%

    16%

    8%

    Time Spent for Corporate

    Governance Activities

    No Time Spent

    0% to 5%

    6% to 10%

    11% to 15%

    16% to 25%

    More than 25%

    16%

    68%

    Allocation of Time Between Consulting and

    Assurance ActivitiesNo consulting time (all

    audit/assurance)

    Some consulting (Less than 25% of

    time)

    Half consulting (Other 50% of time

    for audit/assurance)

    Mostly consulting (75% or more

    time)

    All consulting (no auidt/assurance)

    Not applicable

    27

    the respondents noted that time spent is in assurance type activities as shown in

    ce Activities

    No Time Spent

    11% to 15%

    16% to 25%

    More than 25%

    Some consulting (Less than 25% of

    Half consulting (Other 50% of time

    Mostly consulting (75% or more

    All consulting (no auidt/assurance)

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    The data collected regarding the rationale for resource allocation and focus indicated that a vast majority of the respondentscurrent levels was appropriate as noted

    Figure 24

    Some of the themes noted during the interviews are as follows: A number of respondents indicated that

    key activity in this area. A large number of organizations in

    organizations are requested by management or activities in this area.

    Some key observations from

    A key roadblock noted by several respondents was that there is a laguidance on how to audit corporate governance. One respondent stated that this can result in difficulties developing the scope and objectives for corporate governance audits.

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Corporate Governance

    The Dallas Chapter of the Institute of Internal Auditors

    The data collected regarding the rationale for resource allocation and focus indicated that a vast majority of the respondents (85%) felt that the allocation at the current levels was appropriate as noted in Figure-24.

    24 Corporate Governance Resource Allocations

    Some of the themes noted during the interviews are as follows: A number of respondents indicated that the Entity-level controls review key activity in this area.

    number of organizations indicated that there are set procedures or their organizations are requested by management or the audit committee to perform

    Some key observations from interviews:

    A key roadblock noted by several respondents was that there is a laguidance on how to audit corporate governance. One respondent stated that this can result in difficulties developing the scope and objectives for corporate governance

    0 5 10 15 20

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Others

    Corporate Governance - Resource

    Allocation

    28

    The data collected regarding the rationale for resource allocation and focus 5%) felt that the allocation at the

    level controls review was the

    dicated that there are set procedures or their audit committee to perform

    A key roadblock noted by several respondents was that there is a lack of guidance on how to audit corporate governance. One respondent stated that this can result in difficulties developing the scope and objectives for corporate governance

    25

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Several respondents noted that a major benefit of performing these typeengagements is that they can help strengthen the corporate culture and ethical climate. This benefit can be achieved through identifying exceptions and following up to verify remediation, and also through making recommendations when deficiencies in tdesign of organizational governance processes are noted.

    A large healthcare services organization'sadopted a number of organization wreinforcement initiatives that appear to have been received well by the auditeesarea. Some of the key initiatives are as follows: * "Audit Trophy", an award given to the units that meet or exceed certain scor

    in the yearly rotational audits. * "Audit update newsletter", an email blast that is sent on a monthly basis to

    communicate the audit and governance initiatives. * "Quarterly audit webcasts", an online webinar inviting organization wide

    participants for education and discussions on hot topics. * "Data Analysis Dashboards",

    management to monitor business trends.

    The Dallas Chapter of the Institute of Internal Auditors

    Several respondents noted that a major benefit of performing these typeengagements is that they can help strengthen the corporate culture and ethical climate. This benefit can be achieved through identifying exceptions and following up to verify remediation, and also through making recommendations when deficiencies in tdesign of organizational governance processes are noted.

    A large healthcare services organization's CAE notes that internal audit has adopted a number of organization wide internal audit communication and other positive reinforcement initiatives that appear to have been received well by the auditees

    . Some of the key initiatives are as follows: * "Audit Trophy", an award given to the units that meet or exceed certain scor

    in the yearly rotational audits. * "Audit update newsletter", an email blast that is sent on a monthly basis to

    communicate the audit and governance initiatives. * "Quarterly audit webcasts", an online webinar inviting organization wide

    ts for education and discussions on hot topics. * "Data Analysis Dashboards", data summary reports for internal audit and

    management to monitor business trends.

    29

    Several respondents noted that a major benefit of performing these types of engagements is that they can help strengthen the corporate culture and ethical climate. This benefit can be achieved through identifying exceptions and following up to verify remediation, and also through making recommendations when deficiencies in the

    internal audit has ide internal audit communication and other positive

    reinforcement initiatives that appear to have been received well by the auditees in this

    * "Audit Trophy", an award given to the units that meet or exceed certain score

    * "Audit update newsletter", an email blast that is sent on a monthly basis to

    * "Quarterly audit webcasts", an online webinar inviting organization wide

    data summary reports for internal audit and

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Social and Sustainability Audits and Consultation

    The data collected in this area indicated that a majority of the respondents (7have not been involved in this area and were at the Initial

    Figure 25 Maturity Level (Social & Sustainability Audit) as assessed by Respondents

    The trend of involvement of with the amount of time spent involvement as noted in Figure 26 and Figure 27

    Figure 26 Time Spent for Social and Sustainability Related Activities

    12%

    8% 0%4%

    Maturity Level As Assessed by

    36%

    8%

    Time Spent for Social and

    Sustainability Audit Activities

    The Dallas Chapter of the Institute of Internal Auditors

    Social and Sustainability Audits and Consultation

    The data collected in this area indicated that a majority of the respondents (7have not been involved in this area and were at the Initial

    Maturity Level (Social & Sustainability Audit) as assessed by Respondents

    trend of involvement of internal audit departments in this area also coincided nt about half of the respondents did not have any

    in Figure 26 and Figure 27.

    Time Spent for Social and Sustainability Related Activities

    76%

    4%

    Maturity Level As Assessed by

    Respondents

    Initial

    Infrastructure

    Integrated

    Managed

    Optimized

    56%

    8% 0%0%0%

    Time Spent for Social and

    Sustainability Audit Activities

    No Time Spent

    0% to 5%

    6% to 10%

    11% to 15%

    16% to 25%

    More than 25%

    30

    The data collected in this area indicated that a majority of the respondents (76%) have not been involved in this area and were at the Initial maturity level.

    Maturity Level (Social & Sustainability Audit) as assessed by Respondents

    udit departments in this area also coincided the respondents did not have any

    Infrastructure

    No Time Spent

    11% to 15%

    16% to 25%

    More than 25%

    2011 - The IIA Research Foundation

    KRevelsText Box

  • The Dallas Chapter of the Institute of Internal Auditors

    Of the internal audit departments that spent time in this area, a large propo(87%) spent most of their time in assurance type activities as noted in the Figure 27.

    Figure 27 Spread of Time between Audit and Consulting Activities

    The data collected regarding the rationale for resource allocation andindicated that a vast majority of the respondentscurrent levels was appropriate below:

    Figure 28 Allocation of Resources to Soc

    8%0%0%

    40%

    Allocation of Time Between

    Consulting and Audit Activities

    We feel allocation is appropriate

    Area is not applicable for our business

    Area not a high risk to our business

    Budgetary constraints

    Business goals have not been defined

    Social and Sustainability Audits: Resource

    The Dallas Chapter of the Institute of Internal Auditors

    Of the internal audit departments that spent time in this area, a large propo(87%) spent most of their time in assurance type activities as noted in the Figure 27.

    Spread of Time between Audit and Consulting Activities

    T