International Space Station Program Overview Michael Suffredini Manager, ISS Program November 2012 1

Upload: vankhanh

Post on 25-Mar-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

International Space Station Program Overview

Michael Suffredini Manager, ISS Program

November 2012

1

Page 2: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

ISS Program Restructure

The ISS achieved assembly complete in 2011. With assembly tasks completed, the ISS Program took the opportunity to fine tune its organizational structure to better focus on achieving the full scientific capabilities of the ISS. Previously, all utilization aspects were managed within one office. This included managing the needs of utilization customers, managing the utilization hardware and software facilities on-orbit and managing the day-to-day utilization activities on-orbit. The ISS organizational deployment now:

The Utilization Office (OZ) remains the steward of the utilization customers needs ensuring they are integrated into the appropriate ISS processes that yield utilization results in the shortest life cycle time possible. The Vehicle Office (OB) now maintains all hardware on-board the ISS including utilization hardware which allows for greater efficiency in planning and executing maintenance and repair with a priority on utilization. The Avionics and Software Office (OD) now maintains all avionics and software related services needed for the execution of utilization on-board which allows for greater efficiency in planning and executing avionics and software maintenance with a priority on utilization. The Mission Integration Office (OC) now plans and executes all on-orbit activities which allows for greater efficiency in planning and executing operations and responding to anomalies in daily activities with a priority on utilization.

2

Page 3: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

MRM2

MRM1

(SM Zenith)

(FGB Nadir)

DC-1/ MLM/

SM-Aft

Node-2 Zenith

Node-2 Nadir

N2 Fwd

Port Utilization

2012 2013 2014 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

127 / 125

31S

11/18 GMT

143 / 141

32S

10/25 3/15

146 / 144

33S

12/21 5/14

167 / 165

34S

3/30 9/11

166 / 164

35S

5/30 11/10

168 / 166

36S

9/27 3/12

170 / 168

37S

11/27 5/14

174 / 172

38S

3/28 7/20

9/16

172 / 170

39S

5/30

180 / 167

ATV4

5/1 10/15 180 / 172

ATV5

4/20

3R (MLM) 12/20

HTV4

7/20 8/19

HTV5

7/6 8/5

SpX-1

10/10 10/28

SpX-2

3/3 4/2

SpX-3

10/2 11/1

SpX-4

1/15 2/14 SpX-5

4/8 5/8

Orb-D1

4/10 5/7 Orb-1

8/16 9/15

Orb-2

12/11 1/10

48P

2/11

49P

10/31 4/15

50P

2/14 4/23

51P

4/26 7/23

52P

7/26 12/18

53P

10/18 4/9

54P

2/7 3/25

55P

4/30 7/17

56P

8/1

10/23 32S

N°707 TMA-06M

12/19 33S

N°704A TMA-07M

3/28 34S

N°708 TMA-08M

5/28 35S

N°709 TMA-09M

9/25 36S

N°710 TMA-10M

11/25 37S

N°711 TMA-11M

3/26 38S

N°712 TMA-12M

5/28 39S

N°713 TMA-13M

4/18 ATV4

4/12 ATV5

12/11 3R

MLM

NET 7/15 HTV4

7/1 HTV5

10/8 SpX-1

3/1 SpX-2

9/30 SpX-3

1/13 SpX-4

4/6 SpX-5

8/8 SpX-6

12/17 Orb-TF

4/5 Orb-D1

8/13 Orb-1

12/8 Orb-2

10/31 49P

N°417 M-17M

2/12 50P

N°418 M-18M

4/24 51P

N°419 M-19M

7/24 52P

N°420 M-20M

10/16 53P

N°421 M-21M

2/5 54P

N°422 M-22M

4/28 55P

N°423 M-23M

7/30 56P

N°424 M-24M

R-32

Apr

R-33

Jun

R-34, 35

Aug

R-36

Oct

R-37

Dec

R-38, 39

Jan U-21, 22

R-40,41,42

Apr

R-43,44,45

Jun

R-46

Aug

11/03 -11/11 12/31 -01/10 06/01 -06/11 08/01 -08/09 11/02 -11/09 12/30 -01/09 05/31 -06/07

Inc 33 Inc 34 Inc 35 Inc 36 Inc 37 Inc 38 Inc 39 Inc 40 In

SpX-2: HRSGF (2) HTV4: MBSU, UTA, STP-H4

SpX-3: HDEV, OPALS SpX-5: CREAM HTV5: CALET, CATS

N (31S)

R (31S)

J (31S)

N K. Ford(CDR-34) 143 days (32S)

R O. Novitskiy 143 days (32S)

R E. Tarelkin 143 days (32S)

C C. Hadfield (CDR-35) 146 days (33S)

R R. Romanenko 146 days (33S)

N T. Marshburn 146 days (33S)

R P. Vinogradov (CDR-36) 167 days (34S)

R Misurkin 167 days (34S)

N Cassidy 167 days (34S)

R F. Yurchikhin (CDR-37) 166 days (35S)

N K. Nyberg 166 days (35S)

A L. Parmitano 166 days (35S)

R O. Kotov (CDR-38) 168 days (36S)

R S. Ryazansky 168 days (36S)

N M. Hopkins 168 days (36S)

J K. Wakata (CDR-39) 170 days (37S)

N R. Mastracchio 170 days (37S)

R M. Tyurin 170 days (37S)

N S. Swanson (CDR-40) 174 days (38S)

R A. Skvortsov 174 days (38S)

R O. Artemyev 174 days (38S)

R M. Suraev (CDR-41) 172 days N R. Wiseman 172 days E A. Gerst 172 days

Crew Rotation

Stage EVAs Stage S/W

Soyuz Lit Landing

Launch Schedule

Solar Beta >60 External Cargo

~11/14 ~12/26 ~1/12 ~2/20 ~3/20 ~4/18

~11/17 ~1/15 ~3/22

U-20

#3-80

For current baseline refer to SSP 54100 Multi-Increment Planning Document (MIPD)

#3-8 #3-8 #3-8 #3-8

4/29 – 5/26 ATV4

6/17 -19 7/1 – 7/26 ATV4

8/15, 17-18

#3-76

DO01: DO02:

30 days 30 days

30 days

18 days 30 days 30 days

30 days

#3-8

27 days

~5/23

~5/25

30 days 30 days

07/30 - 08/07

SpX-6

9/9 8/10 30 days

#3-7 (Beta)

SpX-4: RapidScat

4/5 Orb-3

Orb-3

4/8 5/8 30 days

#3-75

9/30 40S

#3-79

Near GMT midnight 11/19GMT Landing

11/1 u/r

X2R12 2/18u/r

ICU 2/25 u/r

X2R12.1 3/15

X2R13 9/1

ISS Flight Plan Flight Planning Integration Panel (FPIP)

NASA Official: John Coggeshall Prepared by: Scott Paul

Chart Updated: November 13th, 2012 SSCN/CR: 13526 (Baseline)

Page 4: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Expedition 33 Overview

Akihiko Hoshide Yuri Malenchenko Sunita Williams – Exp 33 CDR (Soyuz TMA-05M)

Evgeny Tarelkin Oleg Novitskiy Kevin Ford – Exp 34 CDR (Soyuz TMA-06M) 4

Page 5: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

SpX-1 28 Oct Unberth

Stage 34-6 (84 Days)

Stage 34-3 (33 Days)

50P

MRM1 MRM2

SM Aft

N2 Nadir

FE-2 – S. Revin FE-3 – J. Acaba

CDR – G. Padalka

30S

Oct 12 Sep 12 Nov 12 Dec 12 Jan 13 Feb 13

Updated October 24, 2012

(16-Sep)

Mar 13

Stage 33-6 (24 Days)

Stage 33-3 Stage 33-6 Stage 34-3 Stage 34-6

Berth SpX-1 Prep for 32S arrival Prep for ATV3 undock

• Dock 32S & 49P • Undock 31S • Prep for 49P arrival • Unberth SpX-1

• Prep for 33S arrival • Prep for Orb-D1 arrival

• Dock 33S & 50P • Undock 32S & 48P • Unberth Orb-D1 • Berth & Unberth SpX-2

Utilization

Energy (E) Circadian Rhythms (E) • MSPR Commissioning–AQH (J) Integrated Cardiovascular (N) Sprint (N) VO2Max (N) ACE-1 (N)

• Reversible Figures (E) • Thermolab (E) • Resist Tubule (1st time,J) • Hicari (J) • Pro-K (N) • Elite-S2 (N) • InSPACE-3 (N) • Micro-6 (1st time, N) • Medaka Osteoclast1 (1st

time, J)

• SOLAR (E) • TRITEL (1st time, E) • Nano Step (J) • NanoRacks (N) • MDCA / FLEX-2 (N) • I-SERV (1st time, N) • RRM (N)

• SOLAR (E) • Microflow 1 (1st time, C) • RADI-N2 (1st time, C) • IMMUNO (E) • MARES c/o (E) • EPO10 / ED-Blue Earth Gazing (1st time, J) • Spinal Ultrasound (1st time, N) • Seedling Growth-1 (1st time, N) • CSLM-3 (N) • Cell Bio Tech Demo (1st time, N) • NLP Vaccine-18&21 (N)

EVA, Resupply & Outfitting and Maintenance

• Calibrate IPOMs • USOS EVA#20 – bypass

PVTCS Radiator

• JEMRMS SFA Ground control demo • SPCU Heat Exchanger R&R

Software /

Avionic Updates

Node CDRA Air Seletor Valve R&R OGA ACTEX Pre-flush & R&R

• UPA 6.2 transition

• Transition to iAPS 6.3 and X2R12 • Ku-Band Comm Sys (ICUs 1&2) install & c/o • Install & C/O Columbus HDVCA • Nodes 1 & 2 WAP swap • WPA firmware upgrade • Convert APSs to iAPS spares

E33 FE-3 /E34 CDR – K. Ford (25/155) (130/153)

E33/E34 FE-1 – O. Novitskiy (25/155) (130/153)

E33/E34 FE-2 – E. Tarelkin (25/155) (130/153)

E33 CDR – S. Williams (58/118)

E33 FE-4 – Y. Malenchenko (58/118)

E33 FE-6 – A. Hoshide (58/118)

E34 FE-4 – R. Romanenko (102/160)

E34 FE-5/E35 CDR – C. Hadfield (102/160)

E34 FE-6 – T. Marshburn (102/160)

21-Dec 33S 32S 25-Oct

18-Nov 2-Aug

Increment 33 Increment 34

Stage 33-3 (39 Days)

Te

relk

in

N

ovits

kiy

F

ord

Vehicle Traffic

SpX-2

20 Jan Berth

19 Feb Unberth N2 Zenith

31 Soyuz Crew

H

oshi

de

M

alen

chen

ko

W

illia

ms

48P 11-Feb

15-Mar

32 Soyuz Crew

33 Soyuz Crew

Mar

shbu

rn

Rom

anen

ko

H

adfie

ld

18-Apr 31-OCT 49P 23-Apr

14-May 14-Feb

17-Jul 31S

ATV3 28-Sep

10 Oct Berth

2-Aug DC-1/MLM

SSCN 13526 (under review) moves Orb-D1 to 4/2013 launch.

US EVA #20

Page 6: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Expeditions 33 & 34 Objectives (September 2012 – March 2013)

Perform a minimum average of 35 hrs/week for payload investigations Perform first time payload operations of Robotic Refueling Mission (RRM) fluid transfer, deploy and activate JAXA Small Satellite Orbital Deployer (J-SSOD) and then Cubesat (completed) commission JAXA Aquatic Habitat for first use - Medaka (fish) osteoclast Execute ESA SOLAR full sun rotation viewing Perform demonstration of ground control of JEM RMS Small Fine Arm (SFA) Perform SpaceX-1 (completed), SpaceX-2 and Orbital-Demo1 rendezvous and berthing, attached operations, unberthing and departure Perform SpaceX, Orbital, Soyuz & Progress cargo operations Perform ATV-3 undock operations (completed) Complete Russian vehicle operations including 32-Soyuz and 33-Soyuz docking; 31- and 32-Soyuz undock and landing; 48- and 50-Progress undocking; and 49-, 50- and 51-Progress docking

J-SSOD Aquatic Habitat

Robotic Refueling Mission

Space-X Dragon capsule approaching and berthed to the ISS

6

Page 7: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

0.00

100.00

200.00

300.00

400.00

500.00

600.00

700.00

800.00

900.00

1000.00

0

10

20

30

40

50

600 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Cum

ulat

ive

Sche

dule

d Cr

ew T

ime

(Hou

rs)

Wee

kly

Crew

Tim

e (H

ours

)

OOS Planned USOS Executed 35 Hrs/Wk Avg RequirementOOS Planned Cumulative USOS Cumulative Executed

OC/OZ

reconciliation is complete through

Week 6.

Increment 33_34 Utilization Crew Time

SpX-1 SpX-2

Orb-D1 ATV3

Executed through Increment Wk (WLP week) 6 = 6.8 of 25.8 % through the Increment

USOS IDRD Allocation: 868.0 hours OOS USOS Planned Total: 865.5 hours

USOS Actuals: 177.68 hours 20.5 % through IDRD Allocation 20.5 % through OOS Planned Total

Total USOS Average Per Work Week: 26.13 hours/work week Voluntary Science Totals to Date: 4.25 hours (Not included in the above totals or graph)

3-Crew 6- Crew 3-Crew 6-Crew 3-Crew 6-Crew 3-Crew 6-Crew

Increment 33 Increment 34 Sept Oct Nov Dec Jan Feb Mar

US EVA #20

work weeks 26.36

Page 8: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Total ISS Consumables Status: Total On-orbit Capability 18-October-12 49P SORR, 49P (Dock 2-Nov-12)

T1: Current Capability with no resupply T2: Current Capability with 49P

Consumable – based on current, ISS system status Date to Reserve Level Date to zero supplies Date to Reserve Level Date to zero supplies

Food – 100% (1) May 11, 2013 July 2, 2013 (2) June 24, 2013 August 8, 2013

KTO March 29, 2014 May 13, 2014 May 23, 2014 July 10, 2014 (2)

Filter Inserts July 4, 2014 August 18, 2014 August 18, 2014 October 10, 2014 (2)

Toilet (ACY) Inserts (2) February 27, 2014 April 21, 2014 April 2, 2014 May 21, 2014

EDV (UPA Operable) (3) (4) May 11, 2013 July 29, 2013 (2) June 12, 2013 August 23, 2013

Consumable - based on system failure

EDV (UPA Failed) (2) (3) February 20, 2013 April 14, 2013 March 1, 2013 March 18, 2013

May 28, 2013

Water, if no WPA (Ag & Iodinated) (5) April 27, 2013 June 18, 2013 (2) June 7, 2013 July 22, 2013

O2 if Elektron supporting 3 crew & no OGA (2) (6) March 6, 2013 August 1, 2013 April 3, 2013 August 14, 2013

O2 if neither Elektron or OGA (6) December 9, 2012 February 12, 2013 (2) December 22, 2012 February 19, 2013

LiOH (7) (CDRAs and Vozdukh off)

~ 5.8 days ~19.8 days ~ 5.8 days ~19.8 days

Dock Dates: 32S / 25-OCT-12 49P / 2-NOV-12 (1) Includes food on Soyuz; after RS goes to zero, both sides share USOS food. (2) Reserve level to Zero is different than 45 days due to varying crew size. (3) Progress tanks included in assessment for urine dumping only. ATV tanks included in assessment for urine and brine dumping. (4) A-RFTA operations as of 8/6/12. Assumes 74% recovery rate and no RS urine processing. (5) RS processes all condensate in event of WPA failure. (6) Includes metabolic O2 for 45 day/6-crew reserve and the O2 for greater of CHeCs or 4 contingency EVAs. (7) LiOH Canisters will be used for CO2 removal from the ISS if the CDRAs are inoperable. Total LiOH Reserve Level is 14 days for 6 crew. (Reserve Level for USOS LiOH is ~13.3 days for 3 crew (20 canisters), and for RS LiOH is 15 days for 3 crew (15 canisters).)

8

Page 9: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

USOS ISS Consumables Status: USOS On-orbit Capability 18-October-12 49P SORR, 49P (Dock 2-Nov-12)

U1: Current Capability with no resupply U2: Current Capability with 49P

Consumable – based on current, ISS system status Date to Reserve Level Date to zero supplies Date to Reserve Level Date to zero supplies

Food – 100% (1) September 17, 2013 November 3, 2013 (2) September 23, 2013 November 7, 2013

KTO June 20, 2015 August 4, 2015 June 20, 2015 August 4, 2015

Filter Inserts July 17, 2015 August 31, 2015 July 17, 2015 August 31, 2015

Toilet (ACY) Inserts (2) March 25, 2015 May 11, 2015 March 25, 2015 May 11, 2015

EDV (UPA Operable) (2) (3) (4) July 13, 2013 January 29, 2014 July 13, 2013 January 29, 2014

Consumable – based on system failure

EDV (UPA Failed) (3) December 25, 2012 February 8, 2013 December 25, 2012 February 8, 2013

Water, if no WPA (Ag & Iodinated) (2) March 9, 2013 April 28, 2013 March 9, 2013 April 28, 2013

O2 if no OGA (2) (5) January 14, 2013 April 2, 2013 January 14, 2013 April 2, 2013

LiOH (6) (CDRAs off)

~11.3 days ~24.6 days ~11.3 days ~24.6 days

Dock Dates: 32S / 25-OCT-12 49P / 2-NOV-12

(1) Includes food on Soyuz. (2) Reserve level to Zero is different than 45 days due to varying crew size. (3) Progress tanks not included in assessment for urine dumping. ATV tanks are included in assessment for urine and brine dumping. (4) A-RFTA operations as of 8/6/12. Assumes 74% recovery rate and no RS urine processing. (5) Includes metabolic O2 for 45 day/3-crew reserve and the O2 for greater of CHeCs or 4 contingency EVAs. (6) LiOH Canisters will be used for CO2 removal from the ISS if the CDRAs are inoperable. Reserve Level for USOS LiOH supplies is ~13.3 days for 3 crew (20 canisters).

9

Page 10: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

USOS Challenges (1 of 3)

DC Switching Unit (DCSU) 3A Remote Bus Isolator (RBI) 1 Currently operating nominally. Tripped on 9/1/12, observed (negative) current

flowing from the DCSU toward the SSU. Hindsight buffer showed a fault current >250A out of RBI 1. Downstream DDCUs experienced a POR . Troubleshooting performed on 10/11/12, with no trip detected. On 10/17/12, untied channel 3A from 3B with no issues. On 10/18/12, all nominal downstream loads were connected to DCSU 3A. Channel 3A is operating nominally. Based on the observed signatures, the most likely cause of the trip was a component failure within the SSU.

Voltage Current Stabilizer (CHT) 21

[CHT21] is currently OFF. MCC-H is NO GO for reactivation. The [CHT] is believed to have caused MBSU2 RBI5 to trip off on GMT 206. The exact mechanism is unclear. Further testing on GMT 234 confirmed that erratic currents and temperatures in the primary power system correlate to [CHT21] operation. Operation has been stable while [CHT21] is deactivated. RSC-Energia and Boeing conducted independent testing in order to attempt to recreate the signature. A [CHT] spare arrived on 49P on 10/31/12. Future [CHT] operations will be discussed at the Bilateral Electrical Working Group (BEWG) TIM starting on 11/5/12.

10

Page 11: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

USOS Challenges (2 of 3)

Main Bus Switching Unit (MBSU) #1 Replacement During EVAs 18 and 19 Recovered, operating nominally. Bit errors in MBSU1 resulted in effective Loss of

Communications (LOC) to MBSU1. The bit errors were due to a known defect in the error correction code of the EEPROM memory chips. Several bit flips had occurred over time and eventually one bit flip caused the loss of comm. MBSU 1 and 2 are the only MBSU’s with this flaw. MBSU 2 is currently healthy. MBSU1 was replaced with a spare during EVAs 18 and 19. Removal and installation was difficult because the MBSU is sensitive to misalignment and the ACME bolt interface was galled due to difficult ground installation. The crew lubricated the bolt post interface and drove in a lubricated ACME bolt to chase the threads. The spare MBSU was then installed.

Photovoltaic Thermal Control System (PVTCS) 2B Ammonia Leak Starting in 2007, Channel 2B PVTCS exhibited a relatively constant leak rate of ~1.5

lbm/year. In June 2012, the leak rate increased to somewhere between 5.8 lbm/year and 9.5 lbm/year. EVA 20 was executed on 11/1/12 to substitute the Early External Active Thermal Control System (EEATCS) Photovoltaic Radiators (PVRs) for the P6 2B PVR. The PVR is considered the most likely leak source. Roughly 4 to 6 weeks of operation following the EVA are required to confirm whether the leak has been isolated to the P6 2B PVR. If the leak has not been isolated, another EVA to isolate the Pump Flow Control Subassembly will likely be executed.

11

Page 12: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

USOS Challenges (3 of 3)

RPCM LAP5 1A4A-A RPC 2 FET Hybrid Controller Failure (Lab RWS CEU Power Feed)

Currently troubleshooting. RPCM LAP51A4A-A RPC 2 tripped open on 9/22/12 due to a FET Hybrid Controller Failure. RPC 2 feeds the Lab Robotic Workstation (RWS) Controller Electronics Unit (CEU). Four Spare RPCMs were installed in the LAP5 1A4A-A location. All failed to establish communication with the upstream MDM. Root cause of the failure to establish communication the spares will require further investigation. The original failed RPCM was reinstalled and worked temporarily. However, after another trip of the RPCM on 10/4/12, the crew installed a jumper to power the CEU from RPC 3 on the same RPCM. Subsequent operation has been nominal. Fault tree in work on why comm with other spares installed at this location not successful.

EMU 3015 Cooling System EMU 3015 (EV2) exhibited a cooling anomaly during EVA 18. Late in the EVA, telemetry indicated a degradation of the suit’s cooling capability, with sublimator exit temperature trending up from 39’F to 74’F. Per EVA procedures, if a crewmember is not receiving adequate cooling the EVA would be terminated. EV2 reported adequate cooling toward the end of the EVA, so termination was not required. EMU 3015 is NO GO for EVA at this time. The EMU team is investigating the anomaly. The team has developed a fault tree and is working through the branches to determine the cause and to identify corrective actions needed to return EMU 3015 to service. A water sample was obtained from EMU 3015 and returned on SpX-1 to aid in troubleshooting. The three remaining EMUs on ISS are healthy. No issues were observed on EVA 20. 12

Page 13: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

HTV3 Abort Post-release

HTV3 performed 1.2 m/sec posigrade abort after release by SSRMS HTV onboard FDIR detected an off-nominal trajectory that would

have caused the HTV to be out of the “corridor” within 300 sec (time to nominal burn) Off-nominal trajectory was due to friction between the SSRMS LEE and the grapple fixture which effectively caused SSRMS to “pull” the HTV during its back-away from the grapple fixture

Real-time telemetry and reconstruction of abort post-flight showed no violations of structural or thermal limits Thermal loads and contamination analysis results have been shared with RSC-Energia specialists Dragon Departure Analysis

Dragon orientation at release does not require SSRMS to back-away

prior to vehicle separation Orbital mechanics pulls Dragon away from SSRMS avoiding the

roll seen on HTV 3 In case where Dragon does not drift out of SSRMS LEE carriage

may provide an impulse to Dragon This case has been analyzed and is bounded by other departure

scenarios

HTV Release Configuration

Dragon Release Configuration 13

Page 14: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

USOS System Enhancements

Pre-Determined Debris Avoidance Maneuver (PDAM) New capability that allows ISS to perform a DAM for late notification conjunctions up to Time of Closest Approach (TCA) – 5.5 hrs Software patch uplinked on 8/1/12 allows for Progress on DC1 Nadir PDAM Flight Rule updates and loads analysis is in work to support first demonstration of capability in November 2012 Additional capability supporting SM and aft vehicle PDAM planned for SM 8.07 software (early to mid 2013)

Obsolescence Driven Avionics Redesign (ODAR) Integrated Communications Unit (ICU) ready for activation in February 2013, doubling the downlink data rate to 300 Mbps Improved Payload Ethernet Hub Gateway (iPEHG) ready for activation in April 2013 – tenfold increase in medium rate onboard data communications to 100 Mbps 2 flight ICUs and 3 iPEHGs are on-orbit; 3rd flight ICU planned for launch on ATV4; fourth iPEHG launched on SpaceX-1

14

Page 15: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

SpX-1 Anomaly Summary

Falcon 9 First Stage Engine Anomaly Engine 1 was commanded to shutdown during launch

Engine 1 experienced a loss of pressure, but was not liberated Falcon 9 continued to operate nominally Dragon vehicle successfully berthed to the ISS SpaceX engine investigation team was formed with NASA participation

Fault tree analysis is underway Corrective action to address findings will be applied to future flights

Flight Computer (FC)-B

FC-B de-synced from A and C due to a suspected radiation hit FC-B was rebooted successfully, but not re-synced ISS departure successfully completed with FCs A & C (within flight rules)

Other Radiation Events

1 of 3 GPS units had a suspected radiation hit during free flight and was recovered after a power cycle and reincorporated While berthed, the Propulsion and Trunk computers and Ethernet switch had suspected radiation hits and were also recovered after a power cycle and reincorporated

Page 16: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

SpX-1 Anomaly Summary

Dragon Draco Thruster Sensor Anomalies Injector Resistance Temperature Detector (RTD) failure on Draco thruster 4 in quad 3.

Sensor not used for any Fault Detection, Isolation, and Recovery (FDIR) Pressure transducer drift in Draco thruster 3 in quad 3. Monitored for continued drift, but did not see any. Two sensor failures are needed to violate the FDIR requirements Pressure transducer failed low in Draco thruster 4 in quad 2. Two sensor failures are needed to violate the FDIR requirements

Splashdown Anomalies

Dragon lost all 3 coolant pumps after splashdown due to suspected water intrusion. The cabin fan continued to function and it is believed the cabin temperature stayed within limits. When Glacier was accessed (3 hours after splashdown) its temperature was -65 deg C (set point of -95 deg C), indicating a possible loss of power. Glacier data currently under investigation to determine duration and cause of power loss.

Page 17: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

New Research and Recent Results

Medaka Osteoclast: 32 fish delivered on 32S, all systems functioning within the Aquatic Habitat within Kibo module. Investigating the bone changes that occur in space through the multi-

generational breeding of fish will help us understand the impacts to crew health during long-duration flights, and aid in osteoporosis research on Earth.

Micro-6: A SpaceX-1 Sortie: Studying yeast (Candida albicans) for health

C. albicans exposure to microgravity may result in changes that tell us how this pathogen causes yeast infections on Earth, and help develop improved treatments and prevention.

VO2 MAX: Final subject in the study completed, marking end of the ISS investigation over 3 years

VO2 Max evaluates crewmembers’ cardiovascular and respiratory fitness by measuring oxygen and carbon dioxide exchange during intense exercise. Subject count required was 12. Fourteen subjects obtained total.

17

Presenter
Presentation Notes
Page 18: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Number of Utilization Investigations (Expeditions 0-30)

* Estimated † Draft

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

CSA ESA JAXA NASA Roscosmos

Biology andBiotechnologyEarth and SpaceScienceEducationalActivitiesHumanResearchPhysical Science

Technology

20 224 428 494 325*

Page 19: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

0

50

100

150

200

250

300

350

Inc 0-1 Inc 2-3 Inc 4-5 Inc 6-7 Inc 8-9 Inc 10-11 Inc 12-13 Inc 14-15 Inc 16-17 Inc 18-20 Inc 21-24 Inc 25-28 Inc 29-32φ

Research and Technology Investigations (December 1998 - September 2012)

NASA ESA CSA JAXA Roscosmos

*

* Post- Columbia

‡ Japanese investigation surge in protein crystal growth

**

** Shuttle Return to Flight φ Estimated Numbers

Sept 1998 - Mar 2001

Mar 2001 - Dec 2001

Dec 2001 - Dec 2002

Dec 2002 - Oct 2003

Oct 2003 - Oct 2004

Oct 2004 - Oct 2005

Oct 2005 - Sept 2006

Sept 2006 - Oct 2007

Oct 2007 - Oct 2008

Oct 2008 - Oct 2009

Oct 2009 - Sept 2010

Sept 2010 - Sept 2011

Sept 2011 - Sept 2012

Page 20: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Benefits of ISS Research

Discovery

Space Exploration

Earth Benefits

Julie A. Robinson, ISS Program Scientist

Research Benefits

Spinoffs

Page 21: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Major ISS Benefits from the Decade of Assembly

Discoveries MAXI black hole swallowing star

(Nature) Vision impacts and intracranial pressure (Opthalmology) Microbial virulence (Proc. Nat. Acad. Sci.)

NASA Exploration Mission Life support sustaining and

reliability Success in bone health maintenance resistive exercise (J. Bone Mineral Res.) Models for Atomic Oxygen erosion in orbit

Results with potential Earth benefit Candidate vaccines for Salmonella

and MRSA Candidate treatment for prostate cancer Candidate treatment for Duschenne’s muscular dystrophy

Technology Spinoffs Robotic assist for brain surgery

TiO2 for filtering bacteria from the air in daycares Remotely-guided ultrasound for maternal care in remote areas

Page 22: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Use of ISS to Prepare for Exploration

All ISS partners are actively conducting exploration preparatory activities on the ISS to prepare for future roles Partners seeking collaboration opportunities which maximize return on investment

Four main focus areas Exploration technology demonstrations

On-orbit demonstration or validation of planned and candidate technologies

Maturity and reliability demonstrations of critical exploration systems, such as life support systems Driving evolution in capabilities supporting the ISS today to meet future

challenges - high reliability, high efficiency, low mass, low power Human health management for long duration space travel

Research to understand the main risks to human health and performance Validation of strategies for keeping the crew healthy and productive

Operations simulations and techniques demonstrations Furthering our understanding of future operations challenges

Gaining information which will enable efficient and effective mission design and operations approaches

22

Page 23: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Media Outreach Strategy

ISS Program Communications Plan Draft now being incorporated into Agency- and Center-level plans

Grass-roots: ISS Ambassadors has reached over 2000 NASA Employees

Web and social media Research stories on nasa.gov had 3.6 million page views in 2012 (down from 8

million in 2011 with last Shuttle flights) 75,000 views of ISS Research Blog entries >22,000 followers of @ISS_Research

Traditional media ~20 press interviews and 7 media events on ISS research in 2012

~5,000,000 Impressions of stories through 24-7 redistribution service SpaceX pre-launch press events on ISS research replace Shuttle pre-launch events

23

Page 25: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

One Year Expedition

Four Russian cosmonauts have spent 365 days or more in low earth orbit (Mir station)

Vladimir Titov, Musa Manarov 366 days Dec 87 – Dec 88 Valery Polyakov 438 days Jan 1994 – Mar 95 Sergei Avdeev 380 days Aug 98 – Aug 99

Significant advances in habitability, countermeasures, physiologic understanding since then

Also sharper focus on next generation exploration programs Medical and human research infrastructure across ISS Partners enables a robust joint science program around year long flights Many Human Health and Performance activities facilitate this program

From other side, year long flight program is a forcing function to complete Human Health and Performance objectives

25

Page 26: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

One Year Expedition

NASA Human Research Program would realize significant value in one year flights Investigations and countermeasures data with 6 month flight heritage can be compared more meaningfully with extended durations (the extended time alone becomes the variable) Operational medical metrics continued beyond 6 months will help identify potential long duration risks and guide research and exploration medical ops Focus would be on Mars / NEA mission related risks Validation of physical countermeasures

Bone density and strength, muscle mass and strength, aerobic capacity, postural tolerance – ability of current countermeasures to maintain bone, muscle, fitness for 1 year

Look for threshold effects in health and performance metrics beyond 6 months Serial assessments of vision/intracranial pressure and other microgravity effects

Establish trend of progression vs. plateau effect

Three options studied and NASA and the Partners settled on a one year Expedition for one Roskosmos cosmonaut and one NASA astronaut starting in Spring 2015

26

Page 27: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Briz-M Breakup Event

On 16 October 2012 a Proton Briz-M upper stage with approximately 10 metric tons of residual propellant exploded. Stage had malfunctioned soon after launch on 6 August 2012

Orbit of stage at time of event: 265 km by 5010 km, 50 degree inclination Dry mass of stage: 2.6 metric tons

Initial U.S. Space Surveillance Network assessment of large pieces (~10

cm and greater) was in excess of 700. 101 debris officially cataloged as of 7 November

The estimated initial number of debris posing a potential critical risk to

ISS was ~65,000. ~85% of the debris posing a critical risk to ISS is expected to reenter the atmosphere within one year.

Page 28: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Briz-M ISS Risk Assessment through 2012

Page 29: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Rate of Decay of Briz-M Debris

29

Page 30: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

ISS MMOD Risk Status

The following chart provides a status of ISS micrometeoroid and orbital debris (MMOD) risks These are 10 year MMOD assessments using the ORDEM 2000 orbital debris model and the MEM meteoroid model

The new debris model, ORDEM 3.0, will be released later in the year, and we will require 6-8 months to evaluate ISS MMOD risks due to modifications to ISS shielding performance equations required to account for steel impactors

The assessments are based on using Soyuz and Progress vehicles predominately in future ATV & HTV included, but US commercial vehicles are not included

As commercial crew and cargo vehicles replace Soyuz/Progress vehicles, ISS MMOD risks will improve

Briz-M breakup is not included in these numbers

30

Page 31: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

ISS MMOD Risk Projected for next 10 years using ORDEM2000 debris model & MEM meteoroid model

ISS MMOD Risks 10-year future time period, updated with latest NASA results documented in JSC-65837 and JSC-66198

Date Penetration Risk Loss-of-crew (LOC) Risk Evacuation Risk

Requirement ≤ 24% (PNP=0.76)

≤ 5% *Goal, not a requirement

(PNCF=0.95)* NA

ISS Risk as of March 2012 March 2012 52% (PNP=0.48) 8.0% (PNCF=0.920) 16.1% (PNevac=0.839)

With partial implementation of Progress enhancement beginning

with 47P April 2012 49.0%

(PNP=0.510) 7.6% (PNCF=0.924) 14.4% (PNevac=0.856)

With above and Soyuz enhancement beginning with 30S May 2012 34.5%

(PNP=0.655) 5.2% (PNCF=0.948) 14.3% (PNevac=0.857)

Above and 5 SM debris panels installed on RS EVA 31 (Current Configuration)

August 2012 33.9% (PNP=0.661) 5.1% (PNCF=0.949) 13.7% (PNevac=0.863)

Above and full implementation of Progress enhancement beginning

with 57P

September 2014

28.0% (PNP=0.720) 4.6% (PNCF=0.954) 11.0% (PNevac=0.890)

Above and commercial crew vehicles beginning in 2017 (reduce

Soyuz flights) 2017 26.5%

(PNP=0.735) 4.4% (PNCF=0.956) 11.0% (PNevac=0.890)

October 2012

Page 32: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

PRA, V 2.5 Results (6 months)

DISCLAIMER To verify these are the latest results, contact the ISS Risk Team. (v2.5) Michael Lutomski, 281-244-8181

32

Page 33: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

ISS Top Program Risk Matrix Post November 09, 2012 PRAB

Risks (L x C) continued 1 3 1

1 5

3 1 2

4

L I K E L I H O O D

5

4

3

2

1

1 2 3 4 5

Score: 2 x 2

6347 - Temporary Urine and Brine Stowage System Catastrophic leak of a Tox-2 Fluid - (OB) - (C,S,T,Sa)

6198 - ODAR HRCS/ICU Cost Growth - SSCN#11372 - (OD) - (S,T)

6032 - On-Orbit Stowage Short-Fall (Pressurized Volume) - (OC) - (T,Sa)

5184 - USOS Cargo Resupply Services (CRS) Upmass Shortfall - 2010 through 2016 - (ON) - (C,S,T,Sa)

Corrective/Preventative Actions None

Watch Items None

Continual Improvement None

CONSEQUENCE

Low Medium High

C – Cost S – Schedule

T – Technical Sa – Safety

– Top Program Risk (TPR)

Added: 6404, 6402, 6399, 6393, 6368, 6367, & 6277

Removed: 5456 – ISS Budget & Schedule, 6093 – OGA Functionality, and 6262 – NORS Shortfall

Rescored: 5184 & 6347

Risks (L x C) Score: 5 x 5

6352 - Overlap in Commercial Crew & Soyuz Launch Services - (OH) - (C,S,T,Sa)

Score: 5 x 4 6370 - ISS Pension Harmonization - (OH) - (C) 6344 - ISS Operations Budget Reduction - (OH) - (C) 6234 - Institutional Gaps (Formally Loss of Constellation

funding) - (OH) - (C,S,T,Sa)

Score: 4 x 4 6399 - ISS Budget and Schedule - (OH) - (C,S,T) 6393 - Channel 2B PVTCS Ammonia Leak Increasing -

(OB) - (C,S,T,Sa) 6372 - Full ISS Utilization - (OZ) - (S) 6367 - NASA Docking System (NDS) Qualification Cost

and Schedule - (OG) - (C,S,T,Sa) 6169 - Visual Impairment / Intracranial Pressure - (SA) -

(C,S,T,Sa)

Score: 3 x 5 5688 - ISS Solar Array Management Operations

Controls and Constraints - (OM) - (C,S,T,Sa) 2810 - Russian Segment (RS) capability to provide

adequate MM/OD protection - (OM) - (C,S,T,Sa)

Score: 5 x 3 6402 - SpaceX Dragon splash down - water intrusion /

power outage - (ON) - (S,T)

Score: 3 x 4 6404 SpaceX Falcon 9 Engine Failure - (ON) - (S,T)

Score: 4 x 3 5269 - The Big 12 Contingency EVA's - (OB) - (S,T,Sa)

Score: 3 x 3 6368 - Development of ISS On-Orbit Nitrogen and

Oxygen Recharge Capability - (OG) - (C,S,T,Sa) 6277 - Loss of utilization flexibility based on CRS

capabilities - (OZ) 6096 - Urine Processing Function - (OB) - (C,T)

33

Page 34: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Backup Slides

34

Page 35: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Soyuz & Progress: Enhanced Shielding Region Maps

Soyuz Soyuz

Soyuz Orbital Module Enhanced MMOD Shielding Area

(yellow region)

Progress

Progress Cargo Module Enhanced MMOD Shielding Area

(yellow region) 35

Page 36: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Soyuz Orbital Module Enhanced Shielding Region Maps

Soyuz Orbital Module Enhanced MMOD Shielding Area

(yellow regions) 36

Page 37: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Progress Cargo Module Enhanced Shielding Region Maps

Progress Cargo Module Enhanced MMOD Shielding Area

(yellow regions) 37

Page 38: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Soyuz Orbital Module MMOD Shield Enhancements

Soyuz:

Addition of a 0.5mm thick aluminum bumper at a 15mm distance from the existing Orbital module pressure shell First use on Soyuz flight 30S, 15 May 2012 (vehicle #705) Used on all subsequent Soyuz vehicles

Current Status: implementation complete

38

Page 39: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Progress Cargo Module MMOD Shield Enhancements

Progress: (Phase 1 of 2) Addition of 0.5mm thick bumper and 15mm standoff First use on Progress flight 47P, 20 April 2012 (vehicle #415)

Current Status: implementation complete

39

Page 40: International Space Station Program Overview - NASA... · 14.11.2012 · International Space Station Program Overview ... all utilization aspects were managed within one ... activate

Progress Cargo Module MMOD Shield Enhancements

Progress: (Phase 2 of 2) Addition of a 0.2mm thick aluminum plate Addition of a fiberglass cloth layer on both sides of the 0.2mm thick aluminum plate First use on Progress flight 57P, September 2014

Current Status: awaiting implementation

40