Intro to Process Analysis IIIntro to Process Analysis II
Kristen’s Cookies
Gantt Charts
Resource conflicts
Batch size and setups
Economies of Scale
Getting more for your cookie, er, money!
The Big PictureThe Big Picture
Most of your investments—and a lot of your other costs—are due to resources (people, equipment, etc.)
By avoiding resource conflicts and exploiting economies of scale you can more efficiently use your resources.
Thus, you can either increase production or reduce costs.
Either way, ROI goes up.
KRISTEN’S PROCESS FLOW DIAGRAM
GANTT CHART(ORDER SIZE = 1 DOZ.)
5 10 15 20 25 30 35 40 45 50 55 60 65
oven
roommate
Kristen
pay
pack
cool
bake
mix/spoon
0
Q1. Rush order flowtime per order?
Q2. Process cycle time per order?
Q3. What is the process capacity?
Q4. If we start at 8 pm and end at Midnight, how many cookies can we make?
Let us look at a Gantt chart
Cookie Questions: 1 DozenCookie Questions: 1 Dozen
Q5. What is the labor content per order?
Q6. What is the labor utilization?
Q7. How many baking trays?
How many food processors?
Q8. Where should we add resources?
Add’l. Cookie QuestionsAdd’l. Cookie Questions
GANTT CHART(ORDER SIZE = 2 DOZ.)
0 5 10 15 20 25 30 35 40 45 50 55 60 65
oven
roommate
Kristen
pay
pack
cool
bake
mix/spoon
Q9. Suppose the order size increases.
Order Labor Bottle- System Cycle
ROFT
Size Content neck Capacity Time
1 dz. 12 mn. Oven 6 dz./hr. 10 mn. 26mn.
2 dz.
What happens to the order lead time?
Should we give a Price discount?
5
Suppose we have two ovens. . .
Mix
6 minper order
Cool5 min.
ReceivePayment
1 minper order
Pack2 min/dz
Oven10 min/dz.
Oven10 min/dz
Spoon2 min/dz
Performance with 2 OvensPerformance with 2 Ovens
Order Size
1 dz 2 dz
Kristen’sLabor Content
Room-Mates’Labor Content
Oven mins/order
Oven Cycle Time
Bottle-neck
System Capacity
What is the value of a second oven for order size = 1 dz.?
What is the impact if your roommate is out of town for order size = 1 dz.?
More Cookie QuandariesMore Cookie Quandaries
LESSONSLESSONS
1. Throughput time and Cycle time:
Implications for customers, managers:
Interrelationships:
10
OperatingSystem
ZeroLeadTime
CompleteCustomi-
zation
2. OM tension in the case:
11
3. Importance of process knowledge, learning, experimentation:
LESSONS (cont.)LESSONS (cont.)
The MessageThe Message
BEWARE
Even simple processes are very tricky.Analyzing them is far from simple.
A spreadsheet is not enough.Doing them in your head is not enough.
There is no substitute for using your OM tools.