introduction to break-out groups draft questionnaire for ... fileecologic institute ecologic.eu...
TRANSCRIPT
Ecologic Institute
ecologic.eu
Introduction to break-out groups
&
draft questionnaire for case study
inter-comparison
Eleftheria Kampa, Ecologic Institute
Ecologic Institute
ecologic.eu
2 breakout groups for discussion
2
Group
Case studies
Moderator
Rapporteur Room
A
CS1. Low head run-of-river HPP with water abstraction and ponding effect
CS4. High head HPP with storage in (artificial) lake reservoir in high altitude mountains
Veronika Koller Kreimel,
AT
E. Kampa, Ecologic Small room
B
CS2. Low head run-of-river in-stream HPP with ponding (impoundment)
CS3. Large scale HPP with storage in lake reservoir with discharge into river
Jo Halleraker, NO
Sebastian Döbbelt-Grüne,
DE
J. Rouillard, Ecologic Plenary room
Ecologic Institute
ecologic.eu
Aim of breakout groups
Share knowledge and experience on measures
which are considered relevant to mitigate impacts in
storage-affected stretches
Exchange views on relevant criteria and issues being
considered for selecting & ruling out mitigation
measures (e.g. due to significant effects on use)
Identify gaps in the information provided so far on the
case studies and items which should be added to the
draft country questionnaire on mitigation measures
for defining GEP
3
Ecologic Institute
ecologic.eu
Workplan of breakout groups
Different CS addressed but similar impacts discussed
in both groups
Discussions with active contribution from all
participants (approach & material explained in groups)
Day 1 (1,5h): Focus on CS1 & CS2
Day 2 (2 x1,5h): Focus on CS4 & CS3 and
summarise key conclusions from group discussion
Day 2 (13:30): Rapporteur from each group will
present briefly key conclusions in plenary
4
Ecologic Institute
ecologic.eu
Some questions for discussion on each case
1. Which MM would you take into account to significantly
improve a situation similar to the case study?
2. Would the MM be relevant in all cases or be dependent
on scale and other physical factors?
3. Which MM would you rule out (e.g. due to significant
adverse effects on use or wider environment) and why?
4. What information do you need from the case study to
explain your reasons for ruling out specific measures?
5. How do you consider cost- effectiveness, environmental
benefits and sustainability of measures?
6. What questions / criteria to add to draft questionnaire to
cover all possible reasons for selecting & ruling out MM?
5
Ecologic Institute
ecologic.eu
Draft county questionnaire on GEP measures
To collect information from countries on:
How their methods for general definition of GEP are used to
select & ruling out MM for situations similar to the case
studies on storage
Which ecological improvements are expected from MM
selected
Which reasons are used for ruling out MM for different
impacts
First draft questionnaire circulated to you on 7 Feb 2017
Draft questionnaire to be further developed after the
workshop taking into account discussions in Vienna
Next discussion of questionnaire at ECOSTAT, 4-6 April
2017
6
Ecologic Institute
ecologic.eu
Linkage of draft questionnaire to case studies
A separate questionnaire to be filled for each case study
relevant to storage impacts & situations in your country
7
Ecologic Institute
ecologic.eu
Questions for each stretch of case study
Q1. Which mitigation measures would you select and which
mitigation measures would you rule out in the stretches
impacted by water storage in this specific case study?
Impact on use - scenario 1, 2, 3
Q2. Which improvement to ecological functions is
expected from the measures selected for GES or GEP
achievement (even if measure is not implemented due
to disproportionate costs)?
Q3, 4 …tbd
Fore example: would the selected measure not be
implemented due to disproportionate costs?
Costs- scenario 1, 2, 3
8
Ecologic Institute
ecologic.eu
9
Go to spreadsheet
columns for stretch 1
Example
Ecologic Institute
ecologic.eu
One response possible (drop-down list):
1. Selected to achieve GES
2. Selected for GEP
3. Not selected because another measure is preferred to
deliver the same ecological function
4. Ruled out due to technical infeasibility
5. Ruled out due to significant adverse effect on use or wider
environment (fill in also Qx - tbd)
6. Ruled out due to another reason (please explain in next
column)
7. Excluded due to disproportionate costs (fill in also Qy -tbd)
8. Measure not relevant (impact not present or no fish zone)
10
Q1. Which mitigation measures would you select and which mitigation
measures would you rule out in the stretches impacted by water storage
in this specific case study?
Ecologic Institute
ecologic.eu
Question should be answered also for measures which
are not implemented due to disproportionate costs
Open-ended response (qualitative or quantitative
description of ecological improvement)
Expected improvement to ecological functions should be
indicated for each affected BQE
11
Q2. Which improvement to ecological functions is expected from the
measures selected for GES or GEP achievement?
Ecologic Institute
ecologic.eu
12
Example
Ecologic Institute
ecologic.eu
Further development of questionnaire…
Pending to develop sheets with questions and response
options on:
Ruling out of measures due to significant adverse
effects on use or wider environment
Exclusion of measures due to disproportionate
costs
Information exchange on relevant criteria and aspects
to be considered in this workshop
Existing questions and response options in draft
questionnaire may also be revised after workshop
13
Ecologic Institute
ecologic.eu
Ecologic Institute
Pfalzburger Str. 43/44
10717 Berlin
Germany
Tel. +49 (30) 86880-0
ecologic.eu
Thank you for your attention
Dr. Eleftheria Kampa
14