Introduction to The Trans Bay Cable Project

Upload: dangdang

Post on 07-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Introduction to

The Trans Bay Cable Project

Page 2: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

We’ve come a long way…

1

Page 3: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

2

But thanks to the advances of two men and…

Page 4: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

The Battle of Currents…

3

Page 5: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Utilities are able to choose

the most effective and

efficient means for their

unique power transmission

challenges.

4

Page 6: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

HVDC Basics

Page 7: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Uses of HVDC

− HVDC has two main purposes

– Back-to-back interconnections

• Useful for connecting mismatched AC Networks

• Can convert 50-60 Hz

– Point-to-point connections

• Connects remote generation to load centers

• Bulk power transmission over long distances

6

Page 8: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

LCC (Line Commutated

Converter)

− Thyristor (Turn on

capability only)

− Active Power Control

Only

− AC Filters

− No Black Start Capability

− Higher Capacity

− Large Footprint

VSC (Voltage Sourced

Converter)

− IGBT (Turn on/off)

− Active and Reactive

Control

− No AC Filtration

− Black Start Capable

− More Flexible

− Small Footprint

7

LCC vs. VSC

Page 9: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Why TBC

− Post the 1998 blackout event and part of the CAISO long term plan, the CAISO

put into place a team called the San Francisco Stakeholder Study Group

(SFSSG).

− The CAISO and the SFSSG proposed the following long term projects to meet

the need of the energy demands of San Francisco:

− Status Quo

− Upgrade and replace existing facilities

− Trans Bay Cable Project

− Moraga-Potrero 230 kV Line

− Tesla-Potrero 230 kV Line

− In summary Trans Bay Cable was a fast, affordable, effective solution to solve

the long term energy needs of San Francisco.

Page 10: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

– TBC was originally

slated to be an LCC

facility

– Available land in the

city proved

challenging

– Smaller footprint of

VSC reduced amount

of land required and

cut costs

9

Page 11: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

− TBC Selected

Siemens’ Modular

Multilevel Converter

HVDC PLUS

− Smoother waveform

− Each module is a

discrete voltage

source

− Each arm has 216

sub-modules (16

spares)

10

Page 12: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

11

Page 13: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in
Page 14: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Pittsburg Converter

Station

Potrero Converter

Station

+200-kV DC Cable

-200-kV DC Cable

PG&E Pittsburg 230-kV

Substation

PG&E Potrero 115-kV

Substation

POI POI Po

trero

11

5-k

V

AC

Ca

ble

Sy

stem

Pit

tsb

urg

2

30

-kV

A

C C

ab

le S

yst

em

Simplified Project One-Line Diagram

Page 15: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

DC Cable Route

Pittsburg

(Potrero) San Francisco

Page 16: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Pittsburg Converter Station

Page 17: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Pittsburg Converter Station

Transformers

Converter Hall

DC Reactors AC Reactors

Control & Protection

Room Condensers (cooling

fans)

Page 18: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Potrero Converter Station

Page 19: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

TBC_OP_INS_11.PPTX(EMD)

Potrero Converter Station

Transformers

Converter Hall

DC Reactors AC Reactors

Control & Protection

Room Condensers (cooling

fans)

Page 20: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Operational Performance

Page 21: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Operational Performance

SEU FEU Avail Utilization

2011 2.8% 0.2% 97.0% 92.8%

2012 1.55% 0.81% 97.64% 96.92%

2013 3.23% 0.48% 96.3% 86.4%

• Utilization is based on average MW per day

• CAISO has recently started to aggressively use TBC for power flow management within SF and

peninsula – lower MW average per day – leverages flexibility and agility of VSC system

Page 22: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Technology Operations

Page 23: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

AC – DC Converter Hall

Page 24: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Trans Bay Cable Specifics

Active power is controllable between 0MW and 400MW in increments

of 1MW.

Reactive power can be generated/absorbed within limits at each

Converter Station, independent of the other Converter Station.

±145MVAr at Pittsburg (at full active power)

±170MVAr at Potrero (at full active power)

Smoother waveform, lower harmonics, less filtering, smaller

“footprint”

Low system losses.

Independent and fully controllable reactive power

Page 25: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

P Delivered to Potrero POI (MW) P Extracted from Pittsburg POI

(MW)

Q D

eli

ve

rer

d t

o P

OI

(MV

Ar)

(+400,+170

)

(+400,-170)

(+400,0

)

(0,+300

)

(0,-300) (0,-300)

(0,+300

)

(-418,0)

(-418,+145)

(-418,-145)

P/Q at Pittsburg

POI

P/Q at Potrero

POI

Project Real and Reactive Power

Capability

Q A

bs

orb

ed

fro

m P

OI

(MV

Ar)

Q D

eli

ve

rer

d t

o P

OI

(MV

Ar)

Q

Ab

so

rbe

d f

rom

PO

I (M

VA

r)

Operation in RED AREA

Available at Expense of Real

Power Transmission

Operation in RED AREA

Available at Expense of Real

Power Transmission

Page 26: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

OPERATOR

Page 27: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Project O&M Structure

26

TBC LLC owner

Siemens Operator

TBC Operations LLC 24hr Site O&M

Page 28: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

CABLE

Page 29: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

28

XLPE Cable Fibre Optic Cable

• 53 miles

• Burial depth 6ft

• Follows deep water channel

• Numerous infrastructure crossings

• Interfaces with multiple bay agencies

Page 30: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Hydroplow

Ship: Giulio Verne (Deep Water Cable Installer)

Page 31: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Submarine cable laying ship

Page 32: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Submarine cable laying

Page 33: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Details Re: Shipping Lanes In Area

32

Asset Monitor

Page 34: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Change in Utilization?

33

Page 35: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

34

TBC Utilization

Page 36: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

2013 Accumulated and Monthly Ramping

35

Page 37: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

TBC’s Plans for the Future

Page 38: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

− Siemens currently using Inelfe Project (Spain – France

Interconnect) as base design

− Upgrade to address lose of PG&E Martin substation

− Will bring Black Start functionality to the Trans Bay Cable

− Allows TBC to support up to ~350 MW of critical load in San

Francisco

− Scheduled for Q3 2016 completion

37

Quick Start Upgrade

Page 39: Introduction to The Trans Bay Cable Project - · PDF file− Will bring Black Start functionality to the Trans Bay Cable − Allows TBC to support up to ~350 MW of critical load in

Questions?

38