investment in renovation and modernization of state-level coal … · 2011-02-05 · investment in...

35
PwC Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private Partnership (PPP) Structuring Opportunities

Upload: others

Post on 13-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

PwC

Investment in Renovation and Modernization of state-level coal fired power plants in India

Public-Private Partnership (PPP) Structuring Opportunities

Page 2: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Agenda/Contents

Utility-led Renovation and Modernisation (R&M) in India

Consideration of Transaction Options• Rehabilitate – Operate – Maintain (ROM)• Invest – Rehabilitate – Operate – Transfer• Invest – Rehab/Replace – Operate – Transfer• Variations in ownership structures

Page 3: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Agenda/Contents

Utility-led Renovation and Modernisation (R&M) in India

Consideration of Transaction Options• Rehabilitate – Operate – Maintain (ROM)• Invest – Rehabilitate – Operate – Transfer• Invest – Rehab/Replace – Operate – Transfer• Variations in ownership structures

Page 4: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 4PricewaterhouseCoopersMay 2009

Deployment of unit sizes in India

1950s 1960s 1970s 1977 1984/85 2008

30 MW

60 MW

100/120/140 MW

200 MWLMZ

200/210/500 MW KWU

660 MW/ 800 MW Super -Critical

Source: CEA presentation

Slide 4R&M Overview

Page 5: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 5PricewaterhouseCoopersMay 2009

Distribution and age of units

73 77

5

101

6 8 10

37

48

1023

0

50

100

150

200

Up to 100 MW 100-200 MW 200-210 MW 250 MW 500 MW

Unit Size

No.

of U

nits

> 20 yrs 15-20 yrs <15 yrs

Over 25,000 MW is due for R&M over 11th and 12th five year plan periods; Estimated requirement of over $7 Bn in investments

Slide 5R&M Overview

Page 6: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 6PricewaterhouseCoopersMay 2009

Lack of life-cycle accountability!

• Approvals/ financing constraints leads to delays between Design &Bidding • Surprises at Execution Stage often results in higher than benchmark costs• R&M low on priority because of subsisting energy deficits, lack of

institutional capacity, comparable attractiveness of green-field projects, etc. • Underperformance over O&M phase leads to sustainability issues

Utility-led Renovation and Modernisation in India

Design Stage

R&M Execution O&M

Design Consultant

• Energy Audit, RLA Study

• Cost Benefit Analysis

• Specifying R&M actions

• Bid Process; OR

• Negotiated award to BHEL in some cases

• Implementation of R&M actions

• Re-commissioning of Assets

R&M Vendor

Selection

External Financiers (Multilaterals, IFIs, ECA etc) R&M Vendor

Utility Owned Candidate R&M

Plant

Distribution Utility

Supplies Power at Regulated Tariffs

RLA & specifications, Execution Phase Review & Project Management Support

Renovates Asset (max LE of 10-15 yrs)

Debt financing – requires insurance & guarantees

Utility ( Internal Resource, State Government )

Design Consultant /

Project Implementation

ConsultantEquity financing

Utility OEM Vendor Utility

Page 7: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 7PricewaterhouseCoopersMay 2009

Phases of R&M – PSP Opportunities across the life-cycle!

Design Stage R&M Execution O&M

Design Consultant

• Energy Audit, RLA Study

• Cost Benefit Analysis

• Specifying R&M actions

• Bid Process; OR• Negotiated award to

BHEL in some cases

• Implementation of R&M actions

• Re-commissioning of Assets

R&M Vendor

Selection

Utility OEM Supplier Utility

Slide 7R&M Overview

R&M concessionaire

R&M entrepreneur

Page 8: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 8PricewaterhouseCoopersMay 2009

PPP – As a means of improving accountability- 1995 GoI guidelines on R&M

• Policy advocates 3 options - Lease, rehabilitate, operate and transfer (LROT) - Outright sale of plant and - Joint venture between SEB's and private companies

• Draft CEA Revised Guidelines on R&M of Power Stations indicate a similar strategy to be adopted by Utilities

Utility-led Renovation and Modernisation in India

Page 9: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Agenda/Contents

Utility-led Renovation and Modernisation (R&M) in India

Consideration of Transaction Options• Rehabilitate – Operate – Maintain (ROM)• Invest – Rehabilitate – Operate – Transfer• Invest – Rehab/Replace – Operate – Transfer• Variations in ownership structures

Page 10: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Case – 1: Rehabilitate – Operate – Maintain Contract

Page 11: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Case – 1: Rehabilitate – Operate – Maintain Contract

Page 12: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 12PricewaterhouseCoopersMay 2009

Case 1: 4-stage pit-head power plant

• Staged CHP offers independent measurement and management of fuel input.• In-house capacity expansion offers better redeployment options for utility

employees – makes older units amenable to PPP options for proposed R&M.• We discuss a simple PPP concept applicable to Stage 1 and Stage 2 keeping

utility and State Government considerations in mind:- Private R&M vendor to be responsible for O&M for a 10 year period post

R&M (with flexibility to extend term of contract)

Consideration of Transaction Options

4 x 210 MW 2 x 500 MWStage -1 Stage -2 Stage -4

2 x 500 MW

Under

Construction

Stage -31 x 500 MW

Stage 1 & Stage 2 proposed for R&M

Page 13: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 13PricewaterhouseCoopersMay 2009

Rehabilitate-Operate-Maintain (ROM) Contract

• Investment made by the Utility but executed by the R&M vendor along with responsibility for O&M- Will ensure better

accountability across the execution and O&M Phases

• ROM Contract to be structured to incentivise the private party over O&M phase subject to achievement of efficiencies.

• O&M Phase with - Guaranteed Availability - Station Heat Rate

Benchmarks- Forced Outage Rate - Performance guarantees

from the Vendor

Z

Plant Owner

O&M Vendor

Performance Contract

Stipulations

Energy Generation

Levels

Additional Generation by

reducing Scheduled Preventive

maintenance

Additional RoE / Incentive shared on mutually agreed basis Achieved

Gen. Level

Target Gen. Level

Savings in O&M expenses

Reduction in O&M costs passed on to

vendor

Achieved Gen. Level

Target Breakdown Maintenance Costs

Achieved Breakdown Maintenance Costs

Target Preventive Maintenance Costs

Achieved Preventive Maintenance Costs

Variable Cost Performance

Fuel Cost savings

allowed to be retained by Regulator

Achieved SHR

Target SHR

• National Power Corporation , Philippines adopted an ROM Approach for the 650 MW Malaya Thermal Power Station Complex

Consideration of Transaction Options

Page 14: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 14PricewaterhouseCoopersMay 2009

Rehabilitate-Operate-Maintain (ROM) Contract

• Good design stage studies is essential starting point of the bidding process• Proposed Bid Parameter

- (1) Cost of R&M and (2) O&M for 1st contract year (to be escalated for 10 years as per CERC index)

- NPV of (R&M + O&M) to be used for selection of vendor- O&M for 1st contract yr can be capped as a %age of cost of R&M to

prevent transfer between non-escalable & escalable elements- Prior power plant development and operation experience is essential

• Regulatory process- Regulators are open to benchmark regulations

• will be ready to adopt successful bidder’s capital cost (which is within preset benchmarks, e.g., set with inputs from CEA) for the purpose of tariff setting

• subject to competitiveness of R&M procurement process• and open to consideration of any major surprises post award

Consideration of Transaction Options

Page 15: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 15PricewaterhouseCoopersMay 2009

Conclusions on ROM Contracting

• Appropriate for projects where utility is capable of making investments in R&M

• Less effective than other forms of PPP but improves accountability across the execution and O&M phases- Few R&M vendors has been a concern in India; O&M stage

incentives crucial to attract more bidders• Requires regulatory action to set benchmarks for R&M

investments and subsequent adoption of tendered out cost of R&M, if within such benchmarks- Regulators have also been open to considering major

surprises post-award subject to prudence check & approval

Consideration of Transaction Options

Page 16: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Case – 2: Invest - Rehabilitate – Operate – Transfer Contract

Page 17: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 17PricewaterhouseCoopersMay 2009

Case 2: Three-stage pit-head power plant

• The entire plant (840 MW) has a common Coal Handling Plant (CHP), control room and generation switchyard

• Overall station performance has been low; utility has very weak institutional capacity

• Although only 2 units in Stage 3 have been proposed for R&M, this is guided more by investment considerations than R&M eligibility norm

• State has limited ability to finance green or brown-field expansions.

Consideration of Transaction Options

4 x 50 MW 2 x 100 MW 4 x 110 MW

Room

for

expa

nsion

Only 2 units in this stage proposed for R&M

Stage -1 Stage -2 Stage -3

Page 18: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 18PricewaterhouseCoopersMay 2009

Case 2: Three-stage pit-head power plant

• Stage-1 should ideally be decommissioned but hasn’t been proposed yet because of deficit considerations and over-dependence of the state on this plant.- Can be replaced with an efficiently sized unit when station availability

improves• Open to consider R&M for the entire plant, provided supply issues are

appropriately addressed. • Project offers significant room for further expansion, although these have not

been fully planned out by the utility• State open to PPP options, in view of limited in-house capability

Consideration of Transaction Options

4 x 50 MW 2 x 100 MW 4 x 110 MW

Can bereplaced with sets ofhigher rating

Room

for

expa

nsion

Only 2 units in this stage proposed for R&M

Stage -1 Stage -2 Stage -3

Page 19: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 19PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

• In a PPP structure, important to distinguish between legal ownership & contractual rights

• Legal ownership may have to continue with State Government because of public sensitivities- Option of transferring control and operation through long-

term contracts (e.g. franchised operation); OR- State Govt made Joint Venture partner with or without (in

lieu of land & other infrastructure) equity contribution.• Where less sensitive, a sale of asset will also be considered

as an option

Consideration of Transaction Options

Page 20: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 20PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

Term of concession• Concession with respect to refurbished assets to last for a

minimum of 15 years post-R&M; assets to be transferred back to utility at the end of this term.

• Concession for any capacities added in the station (including replacement of existing units) to last for a minimum of 25 years from the date of commissioning.

Consideration of Transaction Options

Plant Operates without R&M Plant Shutdown Re-commissioned Plant Operation

LoA R&M Procurement Stage R&M Execution O&M Phase

PPA on old basis No supply PPP as per successful bid parameters

Page 21: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 21PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

Expected R&M outputs in the RFP• To be established through technical assessment studies

- Period of R&M OR Outer date for re-commissioning; can allow for incentives in RFP for earlier commissioning

- Expected net capacity of the plant – gross capacity should preferably be restricted to rated unit capacities (840 MW in this case) with up-rating benefits left to investor for sale on merchant basis

- Output from capacity / units added (beyond 840 MW) to be left to the discretion of the developer

- Expected min efficiency of the plant; SHR to be a bid parameter for stations where coal is supplied by procurer

- RFP to specify schedule of charges for lease and shared services, where applicable

Consideration of Transaction Options

Page 22: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 22PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

Bidding Parameter• Option 1: Bid out on the basis of lowest capex quote to

rehabilitate; such capex to be adopted by the Regulator in normative tariff determination

• Option 2: Bid out on the basis of lowest levelised tariff quote;such tariff to be adopted by the Regulator

Policy / Regulatory Support• Guidelines from MoP u/s 63 for adoption of discovered capex /

tariff by Regulator

Consideration of Transaction Options

Page 23: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 23PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

Upfront Payment to Generation Utility• Is required to compensate for loss of returns over the remaining life of the

assets transferred• Gets factored into bids by the bidder and therefore will be subject to

scrutiny of Regulator- CERC ruling on sale of Tanda power plant sets the depreciated book

value as the transfer value for purpose of tariff determination• Depreciated Book Value of assets is a transparent measure of upfront

paymentTreatment of Land • State Govts would prefer land to be leased out instead of being transferred

regardless of ownership structures, as it is for public purpose and doesn’t reflect market value in the books of utilities.

• Land lease charges for new capacities added at the plant site, should be at market-determined rates

Consideration of Transaction Options

Page 24: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 24PricewaterhouseCoopersMay 2009

Case 2 – Proposed OptionInvest-Rehabilitate-Operate-Transfer (IROT) Contract

End-of-concession Transfer Value – often a debatable issue in PPP transactions!• Public authorities are uncomfortable in making payments at end of a concession

- require however that assets be transferred back in sound operating condition - zero transfer value may remove concessionaire’s incentives to invest in asset

upkeep• Zero end-of-concession transfer value is most commonly adopted as a clean &

transparent structure for sufficiently long concession contracts. - Not the most efficient solution for contracts which are over shorter contract

periods (say 15-20 years), as lack of transfer value gets loaded into bid value• Not advisable to “value” assets at the end of the concession period, as these would

link the utility back to inputs (investments) made by the concessionaire• For shorter concession terms, say less than 20 years, transfer value can simply be

equated to the Upfront Payment made by the successful bidder- May not completely obviate under-recoveries getting loaded on to quoted tariffs. - A transfer value, although not equal to the market value of assets, will act as an

incentive to invest periodically in the upkeep of assets.

Consideration of Transaction Options

Page 25: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 25PricewaterhouseCoopersMay 2009

Conclusions on IROT Option

• Very effective option for improving accountability across the life-cycle.- untapped expansion potential, if any, adds to the attractiveness- structure needs to allow for untapped expansion to be at reasonable

discretion of the investor over the useful life; and- for any up-rating benefits to be at investor’s discretion

• Structure permits selection u/s 63 (guidelines require due amendment)- reduces any regulatory risk perception of investors; and - offers inherent incentives for efficiencies across the life-cycle

• Transfer of legal ownership not essential, provided full rights for commercial exploitation are appropriately transferred- Need openness to consider alternative ownership structures

Consideration of Transaction Options

Page 26: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Case – 3: Invest – Rehabilitate / Replace – Operate – Transfer Contract

Page 27: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 27PricewaterhouseCoopersMay 2009

Case 3: Three-stage pit-head power plant

• Entire Plant (1,142.5 MW) has a common Coal Handling Plant (CHP)• Stage 2 and Stage 3 are due for R&M• Stage 1 is to be decommissioned and replaced with a 600 MW unit• Option of considering the entire plant to be offered on PPP basis,

which combines R&M for stage 2 & 3 with decommissioning and addition of new capacity at Stage 1

Consideration of Transaction Options

5 x 62.5 MW 200 MW 2 x 210 MW

Proposed for R&M

To be de-commissioned

Stage -1 210 MW

Stage - 2 Stage - 3

Due for R&M over 12th Plan

Page 28: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 28PricewaterhouseCoopersMay 2009

Case 3 – Proposed OptionInvest – Rehab / Replace -Operate-Transfer (IR/ROT) Contract

Expected outputs in the RFP- Gross capacity of Stage-2 and 3 of 830 MW (to be specified as net

capacity) to be re-commissioned (say) maximum of 2 years from LoA• can allow for incentives in RFP for earlier commissioning• up-rating benefits to be left to investor for sale on merchant basis

- Stage 1 replacement capacity of 600 MW to be commissioned (say) maximum of 48 months from LoA

- Output from units added beyond these three stages to be left to the discretion of the developer

- Min efficiency of the R&M plants; SHR to be a bid parameter for stations where coal is supplied by procurer

- RFP to specify schedule of charges for lease and shared services, where applicable

Consideration of Transaction Options

Page 29: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 29PricewaterhouseCoopersMay 2009

Case 3 – Proposed OptionInvest – Rehab / Replace -Operate-Transfer (IR/ROT) Contract

Expected support from the utility- Addition of new capacity is similar to Case-2 bidding

conditions and therefore should follow MoP guidelines on preparatory activities to be undertaken by the utility prior to bidding, viz with regards to• Land acquisition (where applicable), environmental

clearance, water and fuel arrangements and necessary data for DPR

- Allowing part of the capacity to be un-contracted for sale on merchant basis should be considered• Likely to lower tariff offered to utility and will improve

project attractiveness for investor

Consideration of Transaction Options

Page 30: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 30PricewaterhouseCoopersMay 2009

Case 3 – Proposed OptionInvest – Rehab / Replace -Operate-Transfer (IR/ROT) Contract

Bidding Parameter• Bid out on the basis of lowest levelised tariff quote; such tariff

to be adopted by the Regulator - Bundling replacement capacity would require adherence

with Case-2 bidding framework

Policy / Regulatory Support• Guidelines from MoP u/s 63 for adoption of discovered tariff by

Regulator

Consideration of Transaction Options

Page 31: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 31PricewaterhouseCoopersMay 2009

Conclusions on IR/ROT Option

• Benefits similar to IROT option. • Preparatory activities for replacement capacity would convey

seriousness to investors• MoP guidelines will require amendment to incorporate such an

option to be bid out u/s 63 of the Electricity Act

Consideration of Transaction Options

Page 32: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Variations depending on ownership

Page 33: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 33PricewaterhouseCoopersMay 2009

Variations depending on ownership

• Sale of plant- Cannot be at a premium, as the

same would get loaded on to tariff bids and will be disallowed by the regulator. • Effectively similar to the

Franchisee option- Land ownership is unlikely to be

transferred; any exploitation for untapped expansion should be at market-determined lease charges.

- Tax Considerations- Re-assignment of Fuel Supply

Agreement and Power Purchase Agreements would be required.

Consideration of Transaction Options

External Financiers

(Multilaterals, IFIs, ECA etc)

R&M Vendor

Utility

Distribution Company

Execution , Project Management Support Candidate R&M Plant

(Sold to Investor)

Debt Financing

Carves out and Sells Asset to Private Player

Reassigned PPA

Reassigned linkages, clearances, etc.

Page 34: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

Slide 34PricewaterhouseCoopersMay 2009

Variations depending on ownership

• Joint Venture - Requires the creation of an SPV

with carved out candidate plant- Preferable to some State Govts;

viewed with caution by investors- Offers flexibility for transfer of full

legal ownership rights to the SPV- State Govt equity participation

should ideally not exceed 26% and could be offset against upfront payment and land acquisition charges

- Selection of bidder should be on the basis of competitive bidding (on capex or tariff as in options discussed)

Consideration of Transaction Options

External Financiers

(Multilaterals, IFIs, ECA etc)

R&M Vendor

Utility

Distribution Company

Execution , Project Management Support

Candidate R&M Plant (Separate Legal Entity)

Debt Financing

Reassigned PPA

Investor

26% equity

74% equity

Can be a win-win for utility and investor (non-adversarial arrangement)

• Utility continues to have a stake in asset

• Investor doesn’t have to make large upfront payment

Page 35: Investment in Renovation and Modernization of state-level coal … · 2011-02-05 · Investment in Renovation and Modernization of state-level coal fired power plants in India Public-Private

© 2009 PricewaterhouseCoopers. All rights reserved. “PricewaterhouseCoopers” refers to the network of member firms of PricewaterhouseCoopers International Limited, each of which is a separate and independent legal entity. *connectedthinking is a trademark of PricewaterhouseCoopers LLP (US).

PwC

Thank You