Page 1: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

https://investvietnam.vn

Page 2: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

CONTENT

1. Renewable Energy in Vietnam

2. Power Demand in Quang Tri up to 2035

3. Project Overview

4. Geographical Location

5. Project Progress

6. Investment Effects

7. Investment Procedure

8. Contact

IP

AV

IE

TN

AM

Page 3: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

RENEWABLE ENERGY IN VIETNAM

One of the most dynamic emerging market in

South East Asia

Installed capacity of approximately 43,000MW

with an increasing need of electrification

moving forward

Very high power demand growth rate of 11.5%

per annum over the last decade 2005-2015

Power demand growth rate in coming years is

forecasted to be between 10-12% per annum

The planned power volum expansion in the

revised master plan VII includes:

- 2020: 850MW

- 2025: 4,000MW

- 2030: 12,000MW

IP

AV

IE

TN

AM

Map of wind energy

Page 4: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

POWER DEMAND IN QUANG TRI UP TO 2035IP

AV

IE

TN

AM

Average demand growth per year

2021 - 2025 2026 - 2030 2031 - 2035

11.70% 9.10% 8.00%

Power demand in the whole province

2020 2025 2030 2035

166 MW 288 MW 445 MW 654 MW

Page 5: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

PROJECT OVERVIEWIP

AV

IE

TN

AM

Location: Huong Hoa District, Quang Tri Province, Vietnam

Capacity scale: 48MW

Land area: 339.1 ha

Total estimated investment capital: USD 85 million

Implementation schedule: Q.4/2019 –> end of 2020

Expected first year electricity output: 181,654 MWh

Cooperation plan: maximum 50% shares of total investment capital

Page 6: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

GEOGRAPHICAL LOCATIONIP

AV

IE

TN

AM

Coordinates: 16°44'25.6"N 106°41'14.5"E

Wind speech: 7.49 m/s

Land situation: mountain terrain

- Agricultural land: 5.38 ha

- Regenerated trees: 19.16 ha

- Planted woods: 0.31 ha

- Other planted forest: 70.09 ha

- Empty land: 244.14 ha

Page 7: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

PROJECT PROGRESSIP

AV

IE

TN

AM

1. Wind measurement: completed

2. Add to the master plan: completed

3. FS and basic design: nearly completed

4. Site clearance and construction design: 7/2019 - 12/2019

5. Infrastructure construction: 1/2020 - 6/2020

6. Equipment import: 1/2020 - 7/2020

7. Erection of turbines: 8/2020 - 5/2021

8. Acceptance and operation: 6/2021 - 7/2021

Page 8: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

INVESTMENT EFFECTSIP

AV

IE

TN

AM

Total land area 339.1 Hectares

Total investment 1,745 Billion VND

Capacity 48 MW

Annual output 181,654.0 MWh/Year

PPA rate $8.5 Cents/KWh

Index Unit Economic Analysis Financial Analysis

IRR % 19.1 26.51

NPV Bil VND 1,384.46 753.35

Payback Year 9 8

Page 9: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

INVESTMENT PROCEDURE : 3 PHASESIP

AV

IE

TN

AM

Phase 1 - Investment Registration

1. Obtaining approval of Pre- Feasibility Study

2. Obtaining the approval of supplement into the power planning of

provinces, MOIT or Prime Minister (as case may be) if the Project

has not been included in the relevant planning yet

3. Obtaining investment policy decision for the Project

4. Obtaining Investment Registration Certificate

5. Obtaining Enterprise Registration Certificate

Page 10: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

INVESTMENT PROCEDUREIP

AV

IE

TN

AM

Phase 2 - Construction

1. Obtaining approval of Feasibility Study

2. Working with EVN and reaching an agreement with EVN on connection point,

the design of SCADA/EMS…

3. Negotiating and signing the power purchase agreement (PPA) with EVN

4. Obtaining approval for the environmental impact assessment report (EIA)

5. Obtaining the land lease or allocation decisions

6. Approval of permissible heights of construction works

7. Obtaining the construction permits for the construction works

Page 11: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

INVESTMENT PROCEDUREIP

AV

IE

TN

AM

Phase 3 - Power Operation

1. Obtaining the power operation permit from the competent authority

2. Approval & work permits for foreign employees and other documents relating

to labour issues

3. Application, documents for declaration, payment and finalization of taxations

Page 12: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

The 1st market intelligence & e-bidding platform

Page 13: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand
Page 14: investvietnam - Belt and Road Summit€¦ · M POWER DEMAND IN QUANG TRI UP TO 2035 Average demand growth per year 2021 - 2025 2026 - 2030 2031 - 2035 11.70% 9.10% 8.00% Power demand

CONTACTIP

AV

IE

TN

AM

Vietnam Investment Promotion and Associates Corporation

R.605, Toyota My Dinh Building, 15 Pham Hung St, Hanoi, Vietnam

Hotline: +84-83-555-3388 I Email: [email protected]

Website: www.investvietnam.vn l Skype: fdiconsult