  • 7/27/2019 IPS1000 for TMIC Project.10

    1/20

    HUAWEI TECHNOLOGIES CO., LTD.

    www.huawei.com

    Huawei Confidential

    Security Level:2009-8-15

    IPS1000 Power Distribution

    Installation and Connection(For TMIC project P02)

  • 7/27/2019 IPS1000 for TMIC Project.10

    2/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 2Huawei Confidential

    BMU

    ATS

    ACDB

    IPS1000

    INTERNAL FUNCTION OF IPS1000:

  • 7/27/2019 IPS1000 for TMIC Project.10

    3/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 3Huawei Confidential

    Work Principle of 1+0 Energy System

    D.G Starts to

    powers the BTS

    and charges the

    Battery

    D.G. stops and

    Battery discharges

    to power the BTS

    About 6hrs

    Battery is

    fully charged

    Battery discharges to

    a setting residualcapacity(40%)

    Depended on the consumptionof the site and batterys age.

    Remark: For some 1+0 sites which have EDC, the site will use the EDC first , if the EDC is off , the DG and battery wil l cycle

    like the sites which have no EDC, anytime the EDC is available, the system will switch to EDC to supply for the site.

  • 7/27/2019 IPS1000 for TMIC Project.10

    4/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 4Huawei Confidential

    SITE POWER CONNECTION CHART FOR OUTDOOR GREEN FIELD:

    Power cableAlarm cable

    ACDB Guard Room

    Lighting

    SocketBY CIVIL WORK SUB-CON

    IPS1000

    BTS

    Battery (-48V)

    (Mini shelter)

    TE

    equipment

    Gen-set

    Mains

    (DG2)

    optional

    Done by CW Sub-con

    Done by TE Sub-con

    Done by DG Supplier

  • 7/27/2019 IPS1000 for TMIC Project.10

    5/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 5Huawei Confidential

    DGS BATTERY CABLEDG START SIGNAL

    CABLE

    DGS POWER CABLE

    EDCSee next for the connection

    DETAIL CONNECTION FOR IPS

    ACDB

    L1 L2 L3 N

    From IPS

  • 7/27/2019 IPS1000 for TMIC Project.10

    6/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 6Huawei Confidential

    +

    -

    Current transformer DC power connection at APM30

    Alarm connector

    for Mini shelterFrom Mini sheltersdoor fan

    From Temperature

    sensor in Mini shelter

    Connect to Batt. temp

    in APM30

    From Door sensor of

    Mini shelter

    Connect to APM30

    door sensor

    (see next page)

    1

    2

    3

    4

    5

    67

    98

    1110

    12

    Mini Shelter

    SETAIL CONNECTION OF MINI SHELTER AND IPS

  • 7/27/2019 IPS1000 for TMIC Project.10

    7/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 7Huawei Confidential

    Take this short connector out and connect

    the door alarm cable from Mini shelter

    BTS

    CONTROL CONNECTION AT IPS

    (Done by DG supplier)

    M G + -

    From Current transformer

    (at min i shelter)

    -48V

    PGND

    To DG start

    To DG Battery

    + -

    BMU Fail SPD Fail

    (To APM30H)

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

    To mini shelter

    Bus bar

  • 7/27/2019 IPS1000 for TMIC Project.10

    8/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 8Huawei Confidential

    DG Installation(1.2)---EDC AC Power Cable

  • 7/27/2019 IPS1000 for TMIC Project.10

    9/20

    Instruction to change the AC power input from 1 to 3 phases

  • 7/27/2019 IPS1000 for TMIC Project.10

    10/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 10Huawei Confidential

    N

    L1

    L2

    L3From

    ACDB

    Take this out from the connector board

    APM30 Panel

    AC power input

    connector

    Instruction to change the AC power input from 1 to 3 phases

    supply for Green field BTS outdoor site

  • 7/27/2019 IPS1000 for TMIC Project.10

    11/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 11Huawei Confidential

    Battery Cabinet Installation(1)---Summay

    Chart

  • 7/27/2019 IPS1000 for TMIC Project.10

    12/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 12Huawei Confidential

    Battery Cabinet Installation(3)---

    Connection Between Battery and

    IPS/Power System

    Power System Battery Input PortIPS

    RTN -48V

    Fan Power Input

    M G

    1-2

  • 7/27/2019 IPS1000 for TMIC Project.10

    13/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 13Huawei Confidential

    Battery Cabinet Installation(2)---Install Current

    Sensor

    ! Make sure the connector is faced down to the floorotherwise the current transformer doesnt work.

  • 7/27/2019 IPS1000 for TMIC Project.10

    14/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 14Huawei Confidential

    DG Alarm Connection for (1+1) site

    APM30H

    LOW FUELGEN2 RUNGEN2 FAULT

    GEN1 RUN

    GEN1 FAULT

    1..81

    .

    .

    .

    .

    8

    1..8

    1

    .

    .

    .

    .

    8

    APM30H

  • 7/27/2019 IPS1000 for TMIC Project.10

    15/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 15Huawei Confidential

    APM30H

    BMU FAIL

    GEN1 RUN

    GEN1 FAULT

    1..8

    1

    .

    .

    .

    .

    8

    APM30H

    LOW FUEL

    DG Alarm Connection for (1+0) site

    BMU Fail

    IPS SET(2)

  • 7/27/2019 IPS1000 for TMIC Project.10

    16/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 16Huawei Confidential

    IPS SET(2)

    Note: During the commissioning, we only set:

    1. Batteries capacity (as the installed batteries)

    2. The date and t ime

    IPS St t U

  • 7/27/2019 IPS1000 for TMIC Project.10

    17/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 17Huawei Confidential

    When the power supply is coming the RUN led is blinked, if

    the power reached the terminals but the RUN light not

    ON:

    1. Check Switch (1) toAuto or not if not switch it toAuto

    2. Check the fuses (2) whether they are loose or not

    properly connected (take it out and check then put it inagain and check the RUN light if the light is OK wait

    about 10s the transfer switch will ON then the light on

    the front door is ON).

    1

    3

    Set to 0000 if site (1+0) means

    DG+Battery

    Power Indicator (front door)

    IPS Start Up

    Instruction

  • 7/27/2019 IPS1000 for TMIC Project.10

    18/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 18Huawei Confidential

    IPS SET(3)

    1Set the power switch of the BMU to OFF, disconnect the EDC

    inputif EDC is available, set the diesel generator to the

    automatic mode, then the diesel generator will start automatically.

    2Set the power switch of the BMU to ON, set the diesel

    generator to the Test Mode, selectATS Control, press the ENT

    button of control panel, select Close and press ENT button to

    stop the diesel generator.

    3Exit the Test Mode and the diesel generator will start to supplypower 3 automatically.

    4Connect the EDC inputif EDC is available, the IPS will

    start the EDC to supply power and the diesel generator will stop

    work a moment later automatically.5After the test, close the door of each cabinet and give the key

    to the person in charge for proper management.

  • 7/27/2019 IPS1000 for TMIC Project.10

    19/20

    HUAWEI TECHNOLOGIES CO., LTD. Page 19Huawei Confidential

    Accessories for IPS1000 (in the box)

    CT sensor

    Fire proofing Mud (use to close the hole of PG

    socket after finishing the installation)

    Control cables terminals

    Grounding Terminal

    (Note: dont forget to

    connect this cable)

    All the accessories in IPS1000s box

  • 7/27/2019 IPS1000 for TMIC Project.10

    20/20

    Thank youwww.huawei.com