ipts-2009-06-albert-enu

Upload: carlose123

Post on 23-Feb-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    1/6

    Presentation 6.1

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    PTL: A solid basis for building customized line protection test standards

    Eugenio Carvalheira / Michael Albert / Oliver Janke, OMICRON, Germany

    Introduction

    Relay testing has been changing over the years. The

    technological evolution of protective relays and test sets

    has driven these changes and the way how the tests

    are performed. Protective relays have evolved from the

    electromechanical to the multifunctional numerical

    technology. The test sets have also evolved along the

    time, from the passive to the solid state and dynamic

    test sets [2].

    Ten to twenty years ago the tests were performed by

    the testing personnel almost manually. The relay testquantities were hand calculated and a passive test set

    (comprised of resistive loads, mechanical phase shifters

    and variable autotransformers) was manually operated.

    The operating characteristics of electromechanical

    relays were shaped by resistor, inductor and capacitor

    networks while springs and levers defined the operating

    times. A small number of parameters had to be checked

    [4].

    Nowadays modern test sets include electronically

    regulated voltage and current sources and have the

    capability to run automated tests controlled by computer

    software [2]. This allows the realization of more

    sophisticated tests. With the appearance of modern

    multifunctional numerical relays the number of

    parameters and the complexity of protection functions

    have increased drastically. Knowledge about the relay

    algorithms and functions are required for testing [3].

    All this evolution of relays and test sets has a big impact

    on the testing practices and on the definition of testing

    standards. Which tests are necessary for our relay?

    How can we increase the effectiveness and quality of

    testing while saving time of protection engineers?

    These are some questions that should be done whendeveloping a customized testing standard. This paper

    will discuss how the use of the OMICRON Protection

    Testing Library (PTL) can help you to accomplish this

    target.

    Keywords: protection testing, test standards, auto

    reclosure, power swing.

    Possibilities for standardization

    As the diverse ways of testing has risen with moderntest equipment also the need for standardization

    increased. The reasons for that are different testing

    philosophies, historically grown testing approaches and

    not at least different knowledge, opinions and skills of

    the testing person. The advantages of a standardized

    way of testing are:

    - The test person saves time for developing a test.

    - As all test plans include the same tests, the testing

    quality can be better controlled and improved.

    - Working together as a team is easier, as everyone

    is working in a similar way. For example reading a

    colleagues test protocol is easier, if it is formatted

    in the same way and has the same order and

    content.

    - Company know-how can be added to the standard.

    However there are different levels where unifying ofrelay testing can be realized. Mainly two types of test

    standards can be differentiated on the field of

    application:

    - Standard for testing a dedicated protection function

    - Standard for testing a dedicated protection

    application (e.g. line protection for highest voltage)

    An example of a standard for testing a dedicated

    protection function is the definition of a test plan for

    testing the transformer differential protection function. A

    standard for testing this protection function can be:

    - Configuration or stabilisation test

    - Pickup test

    - Operating characteristic test

    - Trip time test

    - Harmonics blocking test

    The standard also should include the fault loops,

    transformer sides or combinations of transformer sides,

    which have to be tested. Additionally the number and

    position of test shots have to be defined.

    Within a company internal unification and standard-ization is getting more and more important. Additional to

    the "How to test" demand of a test standard some

    general points can be added:

    - A test plan can contain general text information like

    safety rules or telephone numbers.

    - The wiring of the test equipment can be

    standardized to fit for every relay of the protection

    application.

    - Announcement tests can also be integrated.

    - A test with circuit breaker is done.

    - The test protocol is unified.

    The development of a standard strongly depends on the

    testing philosophy of the test designer. As an example,

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    2/6

    Presentation 6.2

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    the standard way of testing a designated protection

    function will be different if defined by a relay

    manufacturer or by a utility engineer.

    Protection testing philosophies

    The testing practices and consequent definition of a

    testing standard, which states how the protective relay

    system should be tested, depends on different factors:

    - Testing purpose

    - Region / Company culture

    First of all the reason for testing should be considered.

    According to its purpose, the testing routines may be

    divided into three different stages:

    -

    Factory or Type tests- Commissioning tests

    - Maintenance or Routine tests

    The factory or type tests are realized by the device

    manufacturers or by the utilities when they select a new

    relay type for an intended application. In a type test, all

    the relay functions should be tested. It includes detailed

    tests of the relay characteristics and algorithms to verify

    that it works according to its specification.

    The commissioning tests are performed to prove the

    correctness of the protective relay system of an

    installation before setting it into operation. The

    requirement for detailed relay characteristic testing is

    reduced in comparison to type tests. Tests should be

    performed to check relay operation based on the setting

    values. The correct operation of the whole protection

    scheme logic should also be checked, e.g. through an

    end-to-end test or an automatic reclose test with the

    circuit breaker.

    Maintenance tests are performed periodically or after

    relay setting changes or firmware updates. The goal is

    to verify that the relay is operating correctly and

    minimize the risks of malfunction.

    A second factor that influences the development of a

    standardized test plan is the region or even company

    culture differences. These cultural differences result in

    different testing philosophies:

    - Test of discrete protection functions as single

    elements by re-routing their signal directly to a

    relay output or test of combined elements taking

    the resultant tripping characteristic of different

    elements [4].

    - A complete test should be performed after a relay

    firmware update; or is it sufficient to rely on the

    manufacturer information [4].

    - Incorporation of some tests based on the history of

    failures experienced by the company.

    Independent of the testing philosophy used by the test

    designer, the OMICRON Protection Testing Library

    (PTL) provides a good basis for designing new testing

    standards. The PTL items can be customized to fit thevariedly company requirements.

    Customizing PTL

    OMICRON provides preconfigured test plans for

    specific relay types. These test plans contain a XRIO

    converter to control the behavior of the template and to

    build up the characteristics out of the relay settings. All

    of these templates are summarized in the protection

    testing library (PTL). Every PTL item consists of an

    OCC file (called PTT, protection testing template) and aXRIO converter. The PTT contains tests for the main

    protection function and the most important backup

    functions [1] [3].

    The PTTs are OMICRON's suggestions how the relay

    can be tested. However customization may be required.

    The test plans of PTL are based on the standard

    features of the Test Universe software. Therefore the

    users have the possibility to adapt the test plans to their

    needs.

    Adapting the XRIO Converter

    The structure of the XRIO converters is shown in

    Picture 1.

    Picture 1: XRIO-Converter of the PTL.

    The XRIO converter is divided in five different parts,

    whereas the most important parts for customizing work

    are:

    - Relay parameter section

    - Additional Information

    - Template Controller

    The XRIO converter contains the relay settings in the

    same structure as in the relay manufacturer software.

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    3/6

    Presentation 6.3

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    The relay characteristics are automatically calculated at

    the given parameterization.

    The other parts of the XRIO converter must not be

    changed by the user. These blocks (RIOplus and RIO)

    are needed for the communication to the advanced test

    modules of the Test Universe software.

    Picture 1 shows the possibility to add a new block

    (Customer specific). This block can be used for entering

    additional data which is not recognized in the XRIO

    converter, e.g. settings of protection functions controlled

    by individual logic.

    Adapting the PTT

    The test plans provided by the PTL are prepared for

    testing different parameter settings of a relay. This

    automation is realized by using the LinkToXRIO

    functionality, predefined test shots and the visualization

    of the relay characteristic. To adapt the PTT to a test

    standard it will be necessary to change the range of the

    tests or the way of testing dedicated protection

    functions.

    Therefore the following mechanisms can very easily be

    used by every user without influence on the automation

    of other test modules in the test plan:

    - Deleting unnecessary test modules

    - Changing the predefined test shots- Copying test modules

    - Inserting new test modules

    The handling of the PTT does not differ from a general

    OCC-file. So every functionality of the Test Universe

    software can be used and it is possible to include every

    test module which is needed to fullfill the testing

    purpose.

    The use of the import filter

    Some relay manufacturer software supports the exportof the parameter settings. This export can be imported

    in the XRIO converters of the PTL by using the import

    filters also offered in the PTL. The customizing work

    has to consider the mode of operation of the import

    filters. These rules are recognized in the relay

    parameter section by entering the correct IDs or

    ForeignIDs of the relays.

    The following chapter shows how to change and adapt

    a given PTT to special needs.

    Examples for PTL Customization

    According to the user specifications or standards,

    customizations of the test plan may be necessary as

    illustrated in the following examples.

    1stExample: Schweitzer SEL-421

    This example shows the specification of a utility

    including tests of auto reclose function (ANSI 79) in

    their test plans for a SEL 421 distance relay.

    The protection functions covered by the available PTL

    item are [5]:

    - 21 Phase/Ground Distance protection

    - 50/67P Phase Instantaneous Overcurrent

    - 50/67G Residual Ground Inst. Overcurrent

    - 50/67Q Negative Sequence Inst. Overcurrent

    - 51 Time Overcurrent

    It is important to mention that the user may rearrange

    the complete test template, change the predefined test

    points or delete test modules if the test strategy does

    not fit his demands.

    Picture 2: Reclosing settings in converter

    As it is described above, testing of the auto reclose

    function is not supported. However, the user can find

    the complete relay settings in the converter, even the

    settings related to functions which are not supported

    (see Picture 2). With the necessary data and also the

    distance characteristic already available in the

    converter, the addition of the new test is simplified.

    Picture 3: Close Cmd signal in Hardware Configuration

    First of all, the Hardware Configuration should be

    checked to see if all necessary signals are available for

    the test. For the testing of the auto reclose function, the

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    4/6

    Presentation 6.4

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    close command signal from the relay is needed to

    evaluate the function's closing time. This signal should

    be added as a binary input in the Hardware

    Configuration and correctly routed to the relay during

    the test (see Picture 3).

    One option for this test is to use the State Sequencermodule to simulate a successful auto reclose cycle. The

    states necessary to simulate a 1-shot re-closure are:

    - Pre-Fault: simulates a nominal load condition; it

    should be run for a time enough to guarantee the

    auto reclose function goes to a reset stage.

    - Fault: simulates a Zone 1 trip condition. This state

    is triggered by the trip signal.

    - Pole open interval: circuit breaker opened

    condition; during this state the close command is

    expected from the relay, that will trigger the

    sequence to jump to next state.- Successful reclose: nominal load condition after the

    circuit breaker has been closed.

    The time between the circuit breaker opening and the

    receiving of the close command signal can be

    measured and automatically assessed by the module.

    Picture 4: State Sequencer with LinkToXRIO

    All the necessary testing parameters can be

    automatically set in the State Sequencer module using

    the LinkToXRIO functionality, as illustrated in Picture 4.

    These links are done to the relay settings that are

    already available in the converter. The definition of the

    fault condition (State 2) is very easy since the distance

    characteristic is already modeled by the converter. It is

    only necessary to define the fault location relative toZone 1 impedance.

    Picture 5: Detail and Impedance View of Fault state

    The new created modules can be added to the test

    template. The user can configure the module to be

    enabled only if the reclosing function is enabled at the

    specific site by using LinkToXRIO. If desired, other

    modules can be added to test the auto reclose function

    when it is used with two or more numbers of re-closure

    cycles.

    Picture 6: SEL 421 PTT with new Auto-Reclose tests

    As the XRIO converter of the SEL 421 supports the use

    of an import filter the tests of the auto reclose function

    integrated in the existing PTT can also make use of this

    feature. Changed relay settings will be updated

    immediately in all test modules of the test plan.

    2nd

    Example: Siemens 7SA6x

    In the second example the requirement of a utility to

    test the Power Swing function (ANSI 68) of the 7SA6distance relay is described. As in the previous example,

    the test will be based on the OMICRON PTT available

    for this relay to take all the advantages provided by the

    existing converter and template.

    The protection functions covered by the Siemens

    7SA6x PTT are [6]:

    - 21 Distance protection

    - 50/51/50N/51N Backup Overcurrent

    - Switch onto fault (SOTF)

    Testing of the 7SA6x Power Swing detection function is

    not implemented in the PTT. However, the relay

    settings for this function are built in the converter.

    Picture 7: Power Swing settings in converter

    The power swing detection in the 7SA6 relay allows theblocking of trips by the distance protection following

    dynamic events which result in an oscillatory behavior

    of the system. The power swing can also be set to trip

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    5/6

    Presentation 6.5

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    during unstable power swings, when system stability is

    lost. Then, both blocking and tripping should be tested.

    One option for implementing this test is to use the

    NetSim module (network simulation module). NetSim

    uses a numerical network model to simulate processes

    in an electric power network, enabling testing underclose to realistic conditions. Different network

    topologies are provided (called test cases). Two NetSim

    modules can then be added to our template with the

    correspondent test case for power swing blocking and

    tripping simulations.

    For the power swing blocking test, the test case "Power

    Swing Synchronous" should be used (shown in

    Picture 8).

    Picture 8: Power Swing Synchronous NetSim test case

    The line data necessary in the module is already

    available in the converter (Power System data in DIGSI

    software) and can be easily set using LinkToXRIO

    functionality. This can be seen in Picture 9.

    Picture 9: NetSim Line Data using LinkToXRIO

    The data of the two sources are not available in the

    relay settings. In this case, this data should be entered

    to allow a correct simulation. A new block in the XRIOconverter can be created by the user to store the

    additional data. Two new parameters are added to this

    block for entering the short-circuit power of the two

    source sides. Other three parameters are created to

    calculate the impedances of both sides which are

    necessary to be defined in NetSim. As shown in

    Picture 10, these parameters are blocked (dark gray),

    since formulas are defined to automatically calculate

    their values. The formulas are based on the powers

    defined in this block and other data already available in

    the converter (like voltage, CT and VT ratios). The

    resulting values are used in the sources tab(Picture 11).

    Picture 10: New System Data block in converter

    Picture 11: NetSim Sources Data using LinkToXRIO

    In this test case, three states are simulated: pre-fault,

    synchronous power swing and post-fault. During the

    power swing state, the slipping sources does not fall

    out-of-step and returns to a synchronous state.

    Picture 12 shows the voltages and currents over time

    while Picture 13 is showing the trajectory in the

    impedance plane.

    Picture 12: NetSim time signal view for power swing blocking

    Picture 13: Impedance trajectory for power swing blocking

    For the power swing tripping test, the test case "Power

    Swing Asynchronous (multiple turns)" should be used.

  • 7/24/2019 IPTS-2009-06-Albert-ENU

    6/6

    Presentation 6.6

    OMICRONelectronics GmbH 2009 International Protection Testing Symposium

    Picture 14: Power Swing Asynchronous NetSim test case

    The Line and Sources data are defined in this module

    using LinkToXRIO in the same way as in the blocking

    test. Also three states are simulated: pre-fault, unstable

    power swing and post-fault. In the power swing state, a

    complete pole slip (out-of-step) is simulated.

    Picture 15: Impedance trajectory for unstable power swing

    The 7SA6x PTL item is used as basis for the test plan

    and the two new NetSim modules are added to the test

    template as shown in Picture 16.

    Picture 16: 7SA6x PTT with new Power Swing tests

    An additional Pause module is also included to give the

    testing personnel prior testing instructions (see

    Picture 17).

    Picture 17: Power swing test information using Pause module

    The examples show that with a solid base it is possible

    to enhance and optimize the predefined test templates

    of the PTL and at the same time minimize the effort for

    preparing the test plan.

    Summary

    The protection functions of modern numerical relays aremore complicated than in the older ones and the

    number of functions is increasing with every new relay

    version.

    For this reason standardization of testing these

    functions is getting more important. The traceability and

    the interchangeability is an important factor for an

    effective work.

    With the PTL (Protection Testing Library), OMICRON

    offers a powerful tool to realize standardized protection

    testing within every company. As shown in two

    examples it is very easy to adapt a PTL item to specialneeds. Through the open structure of every PTL item, it

    is possible to change the given test plans to a

    customized standard for protection testing.

    Literature

    [1] Training material PTL.T270.1 "Testing with the

    OMICRON PTL (Protection Testing Library),

    OMICRON electronics Deutschland GmbH, July

    2009

    [2] A Survey of Relaying Test Practices, IEEE Power

    Systems Relaying Committee Report, January

    2002

    [3] B. Bastigkeit, OMICRON, How a library of Relay

    Specific Test Templates Can Support the

    Protection Engineer, OMICRON IPTS 2007,

    Austria

    [4] C. Araujo, F. Horvath, J. Mack, A Comparison of

    Line Relay System Testing Methods, by National

    Grid Co., FPL Seabrook Station, and Schweitzer

    Engineering Laboratories Inc., September 2006

    [5] SEL-421 Distance Protection Test Template User

    Manual, OMICRON electronics GmbH

    [6] 7SA6x Distance Protection Test Template User

    Manual, OMICRON electronics GmbH