ir quad cost estimate status marc kaducak 02-nov-2012 ir quad cost estimate - m. kaducak1
TRANSCRIPT
IR Quad Cost Estimate - M. Kaducak 1
IR Quad Cost Estimate Status
Marc Kaducak02-Nov-2012
IR Quad Cost Estimate Kickoff - M. Kaducak 2
Options Considered
Case # Description Qty. MQXF (Q1, Q2, Q3)
# 4m Coils
# 6.8m Coils
Comment
1 (aka 50%)
Q1 AND Q3 8 + 2 spare = 10 (20 “half length” cold masses)
80 0 Probably requires two labs.
2 (aka 25%)
Q1 OR Q3 4 + 1 spare = 5 (10 “half length” cold masses)
40 0 Possible with one lab.
3 (aka 100%)
Q1, Q2, AND Q3 16 + 4 spare = 20 80 40 Probably exceeds budget.
IR Quad Cost Estimate Kickoff - M. Kaducak 3
Scope for Case #1
• All units are 150mm aperture ~4m length cold masses for Q1/Q3, cold tested and delivered to CERN
• Two(2) ~4m prototypes (one at each of two labs)• Twenty(20) production units (ten at each of two labs)• L2 managers included, but no overall project
management or project controls.• Cost estimates in this presentation do not include
mirror, practice coils, short models. These are being prepared separately.
IR Quad Cost Estimate Kickoff - M. Kaducak 4
Assumptions and Parameters Used
• FNAL overhead rates used for all except cold mass assembly from LBNL and cable from BNL. FNAL labor rates used for all.
• CD-3 and production unit start is 01-Mar-2017• LBNL bladder and key design• Yield is 8/9, total of 5 prototype and 45
production coils fabricated at each lab.
IR Quad Cost Estimate Kickoff - M. Kaducak 5
Scheme
• Two labs producing in parallel, synchronously• Single test facility• Two(2) reaction ovens at each lab• Three(3) sets of winding and
reaction/impregnation tools at each lab• Additional set of prototype winding/curing and
reaction/impregnation tools at each lab• First ten(10) production units at each lab take
twice as long to fabricate as remaining
IR Quad Cost Estimate Kickoff - M. Kaducak 6
Basis of Estimate
• Coil fabrication based on LQ, 11T experience (Ambrosio, Nobrega, Bossert, Yu).
• Magnet assembly from LBNL (Prestemon, Felice, Cheng, Hafalia).
• Cable from BNL (Ghosh)• Testing from FNAL MTF (Carcagno)
IR Quad Cost Estimate Kickoff - M. Kaducak 7
Summary Schedule including R&D
IR Quad Cost Estimate Kickoff - M. Kaducak 8
Coil Fabrication Schedule Building Block @ Max Production Rate
Assume that next coil can start when outer coil curing begins.
IR Quad Cost Estimate Kickoff - M. Kaducak 9
Coil Production at Max Rate
IR Quad Cost Estimate Kickoff - M. Kaducak 10
Learning curveAssumed all activities for first 10 coils took 2x longer than the rest (except for fixed times in ovens)
Outcome: First coil starts 01-Mar-2017, last coil finished 16-Oct-2020. Even with learning curve this is probably optimistic.
IR Quad Cost Estimate Kickoff - M. Kaducak 11
Cost Summary (50% case)
FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22Total w/o
Contingency Contingency %Total incl.
ContingencyMaterials $0 $2,925,781 $2,928,765 $12,508,399 $11,763,772 $19,147,062 $15,972,425 $2,088,088 $152,992 $0 $67,487,284 30% $87,733,469Labor $0 $4,603,682 $5,276,569 $4,505,920 $6,566,141 $7,829,077 $9,489,099 $8,701,869 $6,273,794 $724,747 $53,970,897 30% $70,162,166Total $0 $7,529,463 $8,205,333 $17,014,319 $18,329,913 $26,976,140 $25,461,524 $10,789,956 $6,426,785 $724,747 $121,458,181 30% $157,895,635
IR Quadrupole (MQXF) Cold Mass Estimate using 150mm aperture, "half-length" coils. Production of two(2) full length prototypes and twenty(20) production cold masses using FNAL Rates. Overall project management not included. At-
year dollars and all burdens included.DRAFT 31-Oct-2012
NOTE: Short Models and Mirror not accounted for in this version.
IR Quad Cost Estimate Kickoff - M. Kaducak 12
M&S Summary (sorry for font)Phase PrototypeCMs complete 2 4 8 6 2
2013 2014 2015 2016 2017 2018 2019 2020 2021FNAL M&S O verhead Rate 20.390% Escalation 102.7% 105.5% 108.3% 111.2% 114.2% 117.3% 120.5% 123.7% 127.1%
Base Mtl.Tooling FY12 $ NOTES:
$ ea Qty $ OH AdderWinding and Curing tooling $214,509 6 $1,287,054 120.390% $1,723,646.70Winding, Curing prototype tooling $214,509 2 $429,018 120.390% $559,467Winding machine $0 $0Curing MoldCuring press $0 $0Coil handling / storage $181,000 4 $724,000 120.390% $969,594.09 BNL Estimate
New Reaction Oven $600,000 2 $1,200,000 120.390% $1,607,062.03 A. Nobrega ($250k in 2006) + ancillaryImpreg station $100,000 4 $400,000 120.390% $535,687.34 BNL EstimateReaction and Impregnation tooling $300,222 6 $1,801,329 120.390% $2,412,373.07Reaction, Impregnation prototype tooling $300,222 2 $600,443 120.390% $783,016.45Cold mass assembly tooling $70,825 2 $141,650 100.000% $153,435 LBNL Estimate (includes M&S OH)Collaring fixture $0 0 $0 120.390% $0 BNL EstimateYoke alignment fixture $0 0 $0 120.390% $0 BNL EstimateTest Cryostat $151,018 1 $151,018 120.390% $196,937Test Facility Modifications 441,935$ 1 $441,935 120.390% $576,311Subtotal Tooling and Equipment $2,132,304 $6,734,513
Qty tested 2 4 8 6 2Parts Qty Coils 5 10 22 32 26
Qty Cold mass 2 4 8 6 2$
Coil Parts Production - set $50,580 90 $4,552,208 120.390% $677,378 $1,530,421 $2,286,083 $1,907,631Coil Parts full length Prototype $50,580 10 $505,801 120.390% $659,597Cable $277,404 100 $27,740,411 100.000% $2,925,781 $3,085,843 $6,971,942 $10,414,416 $8,690,350 BNL estimate (Includes OH)Mirror parts $361,000 0 $0 120.390% Mirror in R&DCold mass parts $663,155 22 $14,589,410 100.000% $1,475,387 $3,030,353 $6,224,108 $4,794,213 $1,641,176 LBNL EstimateTesting materials production $34,000 18 $612,000 120.390% $394,558 $303,900 $104,034 LBNL Estimate (includes M&S OH)Testing materials prototype $68,000 2 $136,000 120.390% $187,046Testing materials first two production units $46,750 2 $93,500 120.390% $132,061Ship to CERN $16,000 22 $352,000 120.390% $0 $21,427 $44,011 $90,395 $185,674 $143,012 $48,957 BNL estimate
Totals 2014 2015 2016 2017 2018 2019 2020 2021Material with Overheads $67,487,284 $0 $2,925,781 $2,928,765 $12,508,399 $11,763,772 $19,147,062 $15,972,425 $2,088,088 $152,992
Contingency 30% $20,246,185 $877,734 $878,629 $3,752,520 $3,529,132 $5,744,119 $4,791,727 $626,426 $45,897 totalTotal Material $87,733,469 $3,803,515 $3,807,394 $16,260,919 $15,292,904 $24,891,181 $20,764,152 $2,714,514 $198,889 $87,733,469
Production
IR Quad Cost Estimate Kickoff - M. Kaducak 13
Labor Costs (sorry again for font)Prototype
2 4 8 6 2
FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 Cumulative $AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
$AY Incl. Burden
FTE per Hour 1768
L2 ManagementScientist $0.00 $424,160.88 $435,617.52 $447,365.88 $459,432.48 $471,870.36 $484,599.96 $497,700.84 $511,173.00 $524,989.92 $4,256,911Engineer $0.00 $161,400.72 $165,767.68 $170,231.88 $174,819.84 $179,549.24 $184,402.40 $189,379.32 $194,506.52 $199,757.48 $1,619,815
DesignEngineer $0 $1,291,206 $1,326,141 $0 $0 $0 $0 $0 $0 $0 $2,617,347Design/Drafter $0 $284,772 $389,985 $0 $0 $0 $0 $0 $0 $0 $674,757Drafter $0 $167,394 $229,239 $0 $0 $0 $0 $0 $0 $0 $396,633Coil FabricationTechnician $0 $0 $0 $866,674 $1,780,022 $2,437,577 $2,503,488 $2,571,096 $1,320,342 $0 $11,479,200Technician Supervisor $0 $0 $0 $473,011 $485,776 $498,894 $512,366 $526,228 $540,442 $0 $3,036,717Engineer $0 $0 $0 $1,361,855 $1,048,919 $1,077,295 $1,106,414 $1,136,276 $1,167,039 $0 $6,897,799Designer $0 $0 $0 $200,244 $205,654 $105,603 $0 $0 $0 $0 $511,500
QAQC (incoming inspection) $0 $0 $277,877 $190,254 $195,382 $100,334 $103,039 $42,329 $43,475 $0 $952,690QA (Production) $0 $274,942 $423,551 $434,981 $446,703 $305,864 $314,121 $161,303 $165,670 $0 $2,527,135Conductor QC
ToolingEngineer $0 $322,801 $663,071 $340,464 $0 $0 $0 $0 $0 $0 $1,326,336Designer $0 $94,924 $194,993 $0 $0 $0 $0 $0 $0 $0 $289,917Drafter $0 $55,798 $114,619 $0 $0 $0 $0 $0 $0 $0 $170,418
CM AssemblyEngineer (FNAL Estimate) $0 $0 $0 $0 $699,279 $718,197 $737,610 $757,517 $778,026 $0 $3,690,629Designer (LBNL Estimate) $0 $0 $102,913 $0 $40,804 $83,812 $172,155 $132,600 $45,396 $0 $577,680Tech (LBNL Estimate) $0 $0 $0 $19,489 $319,038 $655,341 $1,346,122 $1,036,856 $709,946 $0 $4,086,791Engineer (LBNL Estimate) $0 $0 $113,143 $1,351 $120,709 $247,949 $509,302 $392,286 $134,302 $0 $1,519,042
TestingTest CryostatEngineer $0 $484,202 $165,768 $0 $0 $0 $0 $0 $0 $0 $649,970Design/Drafter $0 $284,772 $194,993 $0 $0 $0 $0 $0 $0 $0 $479,764Technician $0 $0 $82,732 $0 $0 $289,531 $594,720 $458,086 $156,828 $0 $1,581,897Test Stand $0Engineer $0 $582,065 $0 $0 $0 $0 $0 $0 $0 $0 $582,065Design/Drafter $0 $175,244 $0 $0 $0 $0 $0 $0 $0 $0 $175,244Technician $0 $0 $396,159 $0 $0 $0 $0 $0 $0 $0 $396,159Testing Operations $0Technician $0 $0 $0 $0 $268,480 $327,446 $566,400 $436,272 $149,360 $0 $1,747,958
Shipping PreparationTechnician $0 $0 $0 $0 $14,834 $15,235 $31,294 $32,139 $16,504 $0 $110,005
Measurement/AnalysisScientist $0 $0 $0 $0 $306,288 $314,580 $323,067 $331,801 $340,782 $0 $1,616,518
TOTAL $0 $4,603,682 $5,276,569 $4,505,920 $6,566,141 $7,829,077 $9,489,099 $8,701,869 $6,273,794 $724,747 $53,970,897
Phase
Burdened Labor in $AY
Quantity of Cold Masses CompleteProduction
IR Quad Cost Estimate Kickoff - M. Kaducak 14
FNAL and BNL comparison(based on 02-Jul-2012 BNL estimate)
Item BNL FNAL
Mirror, Test Coils Yes No
Yield 4/5 8/9
Total Schedule Start->Finish FY15->FY20 FY14->FY21
Production Schedule FY17->FY20 FY17->FY21
Project Management, Controls
Yes No
Winding, Curing Tooling 2nd Mandrel at each lab 3 sets at each lab + prototype tooling
Reaction, Impregnation Tooling and Equipment
5 sets at each lab, oven for 5 coils
3 sets at each lab + prototype, one additional oven (clone of existing)
Cable cost $208k/UL $277k/UL
CM parts $361k $663k
IR Quad Cost Estimate Kickoff - M. Kaducak 15
25% Option Cost Summary
FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22Total w/o
Contingency Contingency %Total incl.
ContingencyMaterials $0 $1,462,891 $1,851,007 $6,264,913 $5,881,886 $9,639,562 $7,986,212 $1,044,044 $76,496 $0 $34,207,011 30% $44,469,114Labor $0 $4,310,901 $4,625,162 $2,433,612 $3,283,070 $3,948,007 $4,760,197 $4,367,004 $2,967,662 $362,374 $31,057,988 30% $40,375,385Total $0 $5,773,791 $6,476,169 $8,698,525 $9,164,957 $13,587,569 $12,746,409 $5,411,047 $3,044,158 $362,374 $65,264,999 30% $84,844,499
IR Quadrupole (MQXF) Cold Mass Estimate using 150mm aperture, "half-length" coils. Production of one(1) full length prototype and ten(10) production cold masses using FNAL Rates. Overall project management not included. At-year
dollars and all burdens included.DRAFT 30-Oct-2012
NOTE: Short Model and Mirror not accounted for in this version.
IR Quad Cost Estimate Kickoff - M. Kaducak 16
Conclusions
• Production scheme is aggressive and still requires more study and optimization
• Despite different approaches and some different boundary conditions, BNL and FNAL estimates are in fair agreement for this phase.
IR Quad Cost Estimate Kickoff - M. Kaducak 17
Backup
CERN 10-y plan
LHC baseline plan for the next ten years. In terms of energy of the collisions (upper line) and of luminosity (lower lines). The first long shutdown 2013-14 is to allow design parameters of beam energy and luminosity. The second one, 2018, is for secure luminosity and reliability as well as to upgrade the LHC Injectors.
18
From Lucio Rossi
IR Quad Cost Estimate Kickoff - M. Kaducak 19
LHC Dipole Learning Curve (P. Fessia)