Elmira High School IRM #2 Construction Overview
Community Safety Environmental Protection
Protection of EHS Property
IRM Area of Excavation
Haul Roads mid-June through the end of August
EHS to MSA - 30-40 loads per day
Loading Area for Materials to be Disposed
Offsite Transport and Disposal - 35 loads per day
Dust Monitoring Ambient Air Monitoring
Worker Protective Equipment: Safety glasses, hard hat, steel toe boots, gloves, high-viz, training
Piling will be used to protect structures and ensure soil removal to design limits
Traffic control on/off Main Street Geophysical survey to protect underground
utilities
Dust Control
Excavated soil is covered prior to proper disposal
All equipment is decontaminated before leaving site
Storm sewers protected from debris during construction
Worker Safety