island greenway bike path alternatives alternative “b“ (new license) alternative “a“ (new...
TRANSCRIPT
![Page 1: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/1.jpg)
Island Greenway Bike Path Alternatives
Alternative “B“(New License)
Alternative “A“(New License)
![Page 2: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/2.jpg)
Island Greenway Bike Path Alternatives
Alternative “C“(Existing Easement w/Amendments)
![Page 3: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/3.jpg)
Island Greenway Bike Path Alternatives• Alt. A – Bike Path on east side of retention pond
– License with no “consideration clause”– Condition of license requires construction of FE-6 fence (min) & 50-ft
clear zone; and maintenance for life of license (i.e. assuming multiple renewals)
• Alt. B – Bike Path on west side of retention pond– License contains “consideration clause” for fair market value (FMV) – Construction of FE-6 fence (min) & 50-ft clear zone ; and maintenance
as “consideration” in first term of license – FMV payment as “consideration” in the subsequent renewals
• Alt. C – No Bike Path– Amend easement to include as-builts for retention pond and require
construction of FE-6 fence (min) & 50-ft clear zone for public safety– No consideration requiredAssumption: Either license (Alt. A or Alt. B) conveys everything from west side
of “Greenway” to the MOTSU boundary to the east
![Page 4: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/4.jpg)
License Considerations• License include sufficient condition and
liability for the proposed use (bike path)• Any “new” use requires approval at Assistance
Chief of Staff for Installation Management (ACSIM) 60-90 day process
• Anything up to 20-yrs possible, longer terms risk non-approval.
![Page 5: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/5.jpg)
Independent Action Items
• Amend Easement #DACA21-2-03-3218 to reflect as-built conditions
• Address perceived encroachments• Determine appropriate fence that meets Army
needs
![Page 6: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/6.jpg)
Potential Alternative Fence
• We can approve the use of a higher-rated security fence that may be more aesthetically pleasing.
• Examples include ornamental fences referenced (with specifications) in Unified Facilities Criteria 4-022-03, dated 1 October 2013 (e.g./ drawings UFC 720 & 721).
![Page 7: Island Greenway Bike Path Alternatives Alternative “B“ (New License) Alternative “A“ (New License)](https://reader035.vdocument.in/reader035/viewer/2022062716/56649ddd5503460f94ad4eef/html5/thumbnails/7.jpg)
Ornamental Security Fencing Examples