Government of India Department of Space ISRO Satellite Centre Bengaluru – 560017 Phone: +91-080-2508 4370, Fax: +91-080-2520 5283/84 No. ISAC/PUR/EOI/AIT of Satellites/2016 June 16, 2016 INVITATION FOR EXPRESSION OF INTEREST [EoI] FOR SYSTEMS ASSEMBLY, INTEGRATION AND TESTING OF STANDARD ISRO SATELLITES THROUGH INDUSTRY ISRO Satellite Centre [ISAC] of Indian Space Research Organization [ISRO] under Department of Space, Government of India is the lead centre of ISRO for Design, Development, Fabrication and Testing of all Indian made Satellites. As a sequel to its mandate of spacecraft realisation, the Centre is engaged in the development of cutting-edge technologies of relevance to its Satellite Building Activities and setting up of infrastructure for Design, Development, Fabrication and Testing of Spacecraft. The proposal is to invite Expression of Interest and to enter into Contract with Industry for Systems Assembly, Integration and Testing [AIT] of Standard ISRO Satellites at ISAC. The Brief Description, Scope of Work, Tenure of Work, Manpower Estimation, Safety Precautions, Non-Disclosure Agreements, etc., forming part of the AIT Activity is available in the EoI Document which can be downloaded from our Websites www.isac.gov.in and/or www.isro.gov.in under “Tenders” and submit along with the Document fee Rs. 573/- in the form of Demand Draft drawn in favour of Accounts Officer, ISAC, Bengaluru before the specified date and time. Interested Vendor[s] having sufficient know-how, experience/expertise and sound financial background are invited to express their interest for Systems Assembly, Integration and Testing of Standard ISRO Satellites at ISAC. Along with the “Expression of Interest”, please furnish the following information related to Vendor[s]:- 1. Registered address with Phone, Fax, Email, Web etc. 2. Company Status (Proprietary / Partnership / Private Ltd. etc.) with Name and Address of Proprietor, Partners, Board of Directors, etc. 3. Associates : (a) Indian (b) Foreign 4. List of Major Customers with full address and their Contact Persons. 5. Details of other Contracts, if any now in hand. Contd... 2/-

Upload: others

Post on 18-Jan-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

Government of India Department of Space

ISRO Satellite Centre Bengaluru – 560017

Phone: +91-080-2508 4370, Fax: +91-080-2520 5283/84

No. ISAC/PUR/EOI/AIT of Satellites/2016 June 16, 2016

INVITATION FOR EXPRESSION OF INTEREST [EoI] FOR SYSTEMS ASSEMBLY, INTEGRATION AND TESTING OF STANDARD ISRO SATELLITES

THROUGH INDUSTRY ISRO Satellite Centre [ISAC] of Indian Space Research Organization [ISRO] under Department of Space, Government of India is the lead centre of ISRO for Design, Development, Fabrication and Testing of all Indian made Satellites. As a sequel to its mandate of spacecraft realisation, the Centre is engaged in the development of cutting-edge technologies of relevance to its Satellite Building Activities and setting up of infrastructure for Design, Development, Fabrication and Testing of Spacecraft. The proposal is to invite Expression of Interest and to enter into Contract with Industry for Systems Assembly, Integration and Testing [AIT] of Standard ISRO Satellites at ISAC. The Brief Description, Scope of Work, Tenure of Work, Manpower Estimation, Safety Precautions, Non-Disclosure Agreements, etc., forming part of the AIT Activity is available in the EoI Document which can be downloaded from our Websites www.isac.gov.in and/or www.isro.gov.in under “Tenders” and submit along with the Document fee Rs. 573/- in the form of Demand Draft drawn in favour of Accounts Officer, ISAC, Bengaluru before the specified date and time. Interested Vendor[s] having sufficient know-how, experience/expertise and sound financial background are invited to express their interest for Systems Assembly, Integration and Testing of Standard ISRO Satellites at ISAC. Along with the “Expression of Interest”, please furnish the following information related to Vendor[s]:-

1. Registered address with Phone, Fax, Email, Web etc. 2. Company Status (Proprietary / Partnership / Private Ltd. etc.) with Name and

Address of Proprietor, Partners, Board of Directors, etc. 3. Associates : (a) Indian (b) Foreign 4. List of Major Customers with full address and their Contact Persons. 5. Details of other Contracts, if any now in hand.

Contd... 2/-

Page 2: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

: 2 :

6. Copy of latest Annual Report. 7. Financial Capacity / Credit facilities available. 8. Name and Address of Bankers. 9. Trade Association to which you belong to. 10. Establishment / Sales / Service Tax Registration Number. 11. Nature of Business. 12. Any other information you consider relevant.

Pre – EoI Conference:

1. A Pre-EoI meeting for Expression of Interest is arranged at ISRO Satellite Centre, Bengaluru in order to have a better understanding of our Invitation to EoI document, clarify doubts if any and other allied technical details of Systems Assembly, Integration and Testing of Standard ISRO Satellites at ISAC.

2. The interested Vendor[s] are hereby requested to take part in the Pre-EoI

meeting on the Date, Time and Venue mentioned here below:-

3. Date of Pre-EoI Meeting : July 12, 2016

4. Time : 10.00 Hrs, IST

5. Focal Point & Venue of Pre-EoI Meeting : Shri. Belgaonkar. P. V Head, GIS-4/GID System Integration Group

ISRO Satellite Centre, HAL Airport Road, Vimanapura Post, Bengaluru – 560 017. Contact No. 23027159 E-mail: [email protected]

6. Last date for submission of EoI : August 02, 2016 at 14.00 Hrs.

7. Opening date of EoI : August 02, 2016 at 15.00 Hrs

8. Interested Vendor[s] may please provide the details of the representative[s] taking part in the Pre-EoI meeting for Expression of Interest well in advance in order to arrange for Security clearance.

9. Please note that request for “preponement/postponement of Pre-EoI meeting

for Expression of Interest” will not be entertained under any circumstances.

Contd... 3/-

Page 3: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

: 3 :

10. The Vendor[s] who do not participate in the Pre-EoI Meeting for Expression of Interest will not be considered and shall be disqualified.

11. In the event if the Vendor[s] are unable to attend the Pre-EoI Meeting for

Expression of Interest physically, a Pre-EoI Meeting for Expression of Interest through Video Conference / Skype / Conference Call shall be arranged by ISRO Satellite Centre, Bengaluru upon the request from Vendor[s], if mutually agreeable.

12. Data required for Security Clearance for Pre-EoI Conference on or

before July 11, 2016:

a. Name of the visitor: b. Mobile Number: c. Nationality: d. Date of Birth: e. Place of Birth: f. Gender: g. Passport Number, Validity, Date and Place of Issue [Photocopy of Passport is

to be attached]: h. Business Visa Number and validity [Photocopy of Business Visa is to be

attached]: i. Occupation: j. Name and Address of Organization/Company:

“Expression of Interest” with all the above information shall reach the undersigned, Quoting above Reference Number on or before August 02, 2016 at 14.00 Hrs. This proposal is initiated as a Pre-EoI Qualification. ISAC reserves the right to accept or reject all or any such “Expression of Interest”; without assigning any reasons what so ever.

Sd/- Head, Purchase & Stores

Page 4: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

Government of India Department of Space

ISRO Satellite Centre Bengaluru – 560017

Phone: +91-080-2508 4370, Fax: +91-080-2520 5283/84

No. ISAC/PUR/EOI/AIT of Satellites/2016 June 16, 2016

INVITATION FOR EXPRESSION OF INTEREST [EoI] FOR SYSTEMS ASSEMBLY, INTEGRATION AND TESTING OF STANDARD ISRO SATELLITES

THROUGH INDUSTRY

ISRO Satellite Centre [ISAC] of Indian Space Research Organization [ISRO] under Department of Space, Government of India is the lead centre of ISRO for Design, Development, Fabrication and Testing of all Indian made Satellites. As a sequel to its mandate of spacecraft realisation, the Centre is engaged in the development of cutting-edge technologies of relevance to its Satellite Building Activities and setting up of infrastructure for Design, Development, Fabrication and Testing of Spacecraft. The proposal is to invite Expression of Interest and to enter into Contract with Industry for Systems Assembly, Integration and Testing [AIT] of Standard ISRO Satellites at ISAC. The Brief Description, Scope of Work, Tenure of Work, Manpower Estimation, Safety Precautions, Non-Disclosure Agreements, etc., forming part of the AIT Activity is available in the EoI Document which can be downloaded from our Websites www.isac.gov.in and/or www.isro.gov.in under “Tenders” and submit along with the Document fee Rs. 573/- in the form of Demand Draft drawn in favour of Accounts Officer, ISAC, Bengaluru before the specified date and time.

Pre – EoI Conference:

1. Date of Pre-EoI Meeting : July 12, 2016

2. Time : 10.00 Hrs, IST

3. Last date for submission of EoI : August 02, 2016 at 14.00 Hrs.

4. Opening date of EoI : August 02, 2016 at 15.00 Hrs

Page 5: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

p

Invitation for Expression of Interest (EoI)for Systems Assembly, Integration &Testing of Standard ISRO Satellites

through Industry

Page 6: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class
Page 7: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 1

Table of Content

Sl No. Chapter Page No

1. INTRODUCTION 3

2. SCOPE OF WORK 15

3. TENURE OF WORK 27

4. MANPOWER ESTIMATION 33

5. SAFETY PRECAUTIONS 37

6. CONFIDENTIALITY AND NON-DISCLOSURE 41

7. GENERAL TERMS AND CONDITIONS 45

8.GENERAL INSTRUCTION FOR SUBMISSION OF EOIPROPOSAL

51

9. RESPONSE FORMAT 57

Page 8: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 2

This page is intentionally left blank

Page 9: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 3

1. INTRODUCTION

Page 10: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 4

This page is intentionally left blank

Page 11: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 5

1. INTRODUCTION

1.1 ISRO Satellite Centre

ISRO Satellite Centre (ISAC) is one of the lead Centres of the Indian Space

Research Organisation (ISRO) responsible for design, development,

assembly & integration of satellites for various applications.

ISAC main campus is spread across a 32 acre campus at Old Airport Road,

Vimanapura in Bengaluru. To cater to the growing demand for satellite

applications, ISRO Satellite Integration & Testing Establishment (ISITE), a 110

acre campus which is about 8 km away from the main campus was also

established. ISAC/ISITE house state-of-the-art design, fabrication, and test

facilities and large cleanrooms for the assembly, integration and testing of

various types of satellites. Laboratory for Electro-Optics Systems (LEOS),

situated at Peenya Industrial Estate, Bangalore is engaged in design,

development and production of Electro-Optic sensors and camera optics for

satellites and launch vehicles.

The ISAC main campus and ISITE campus are hereinafter collectively

referred to as ‘ISAC’.

The specialised teams of scientists, engineers and technicians at ISAC have

built more than 80 complex and advanced satellites for various applications in

areas of telecommunications, television broadcasting, VSAT services, tele-

medicine, tele-education, navigation, weather forecasting, disaster warning,

search & rescue operations, earth observations, natural resource

management, space science and interplanetary missions

Programme at ISAC is categorized into:

etc. The Satellite

Geo-Stationary Satellite Programme

Satellite Navigation Programme

Page 12: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 6

Earth Observation Programme

Microwave and Remote Sensing Programme

Space Science and Planetary exploration Programme

Small Satellite Programme

Based on the mass and power generation, communication satellites are

classified into mainly four major bus platform:

I-1K Bus Satellite – 1 to 1.5 ton class satellite

I-2K Bus Satellite – 2 to 2.3 ton class satellite

I-3K Bus Satellite – 3 to 3.5 ton class satellite

I-4/6K Bus Satellite – 4 to 6.5 ton class satellite

Likewise, the remote sensing and small satellite are classified into IRS Bus

Satellite, IMS-1 Bus and IMS-2 bus depending upon the mass and

configuration of the satellite

ISAC is presently engaged in the challenging task of building future

generation advanced communication, remote sensing,navigation and

space science satellites. ISAC has set the target of building about 10-12

satellites per year to cater to the growing demand for satellite based

applications. In order to meet this huge demand, ISAC is striving for

increasing collaboration and contribution from Indian

satellites. Presently, vendors are involved in various

vendor to build

satellite building

activities such as electronic and mechanical subsystem parts

manufacturing, subsystem fabrication and testing, etc. There is a huge

opportunity for vendor to contribute in the field of space by building

satellites and the scope of vendor participation is bound to increase, both

in terms of volume and complexity. Vendor participation on

Page 13: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 7

a large scale is required not only to meet goals of ISAC but also for self-

reliance resulting in higher throughput.

After successfully completing the vendor’s participation in subsystem level

fabrication and testing, ISAC is seeking to extend the scope of vendor

participation to spacecraft level assembly, integration and testing activities.

On successful completion of these tests, the spacecraft will be shipped to

the launch base for launch. The vendors which are interested in

collaborating with ISAC to assemble integrate and test satellites as per

ISAC’s procedures and guidelines shall express their interest for the same.

The details of ISAC’s requirements from vendors are

subsequent chapters.

provided in the

Page 14: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 8

S

L

S

1.2 Satellite Subsystem:

Satellite is an amalgamation of multiple disciplines of engineering and science

streams such as mechanical, electrical, electronics, computer science,

information technology etc. Typically a satellite can be broadly classified into

mainframe subsystem, payload subsystem and other subsystems as shown in

the figure below.

ATELLITE SUBSYSTEM

MAINFRAMESUBSYSTEM

PAYLOADSUBSYSTEM

ACTIVITY

STRUCTURE COMMUNICATIONMISSION PANALYSIS

ANNING &

THERMAL NAVIGATION RELIABILITY &

MECHANISM REMOTE SENSINGQUALITY A

ASSEMBLY

SURANCE

PROPULSION

POWER

TTC-Baseband

AOCS

SENSORS,ACTUATORS

INERTIAL SYSTEMS

COMMUNICATIONSYSTEM

INTEGRATION &TESTING

Fig 1: Satellite Subsystems

The mainframe subsystem comprises of many tangible subsystems such as

structural system, propulsion system, deployment mechanisms, thermal control

system, digital system, attitude orbit & control system, sensor systems, inertial

Page 15: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 9

systems, power system, communication system etc. Payload subsystems are

mission specific and application dependent such as communication, navigation,

remote sensing and space science etc. Besides these subsystems, mission

planning & analysis, reliability & quality assurance and Assembly integration &

testing activity are also integral part of satellite system. The other activities

involved are procurement, system engineering, project management and

documentation.

A Typical Disassembled view of a spacecraft is shown below:

PROPELLANT &PRESSURANTTANKS

FNORTH SOLAR ARRAY u

HeOx

TTC ANTENNA

TTCHORN

EARTH SENSOR

WEST PANELKUSHAPEDREFLECTOR

KuBANDTWTA SOUTH PANEL

NORTH PANEL

EAST PANEL

KUSHAPEDREFLECTOR

MOMENTUMWHEELS

LAM MAINSTRUCTURE

SOUTHSOLARARRAY

BATTERY PANEL

Fig 2: Typical Disassembled view of a spacecraft

The major subsystem of a typical satellite is discussed in brief in the subsequent

section

Page 16: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 10

1.2.1 Structural System

Structural subsystems includes Primary central cylinder

made of CFRP face skin and aluminium honey comb core,

shear webs and equipment panels. It provides the basic

shapes, strength and rigidity to the satellite.

1.2.2 Thermal Control Systems:

The function of the thermal control system is to keep the temperature of

the payloads and mainframe subsystems housed in the satellite within the

specified limits throughout the mission life. Thermal management is done

through thermal

elements such

control elements employing passive and active thermal

as optical solar

reflectors (OSR), multi layer

insulation (MLI)

sinks, surface

blankets; heat

coatings, paints,

tapes, filler material, heaters, heat pipes etc.

1.2.3 Mechanism System:

Mechanisms are employed to stow and hold down

the appendages

hold-down and

of the satellite. These include

release systems, deployment

mechanisms, reflector mechanisms and other

special mechanisms as required by the mission.

Typically a satellite has two wings; each wing consists

solar panels on the north and south sides of satellites

of one yoke and

Page 17: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 11

1.2.4 Propulsion system:

Propulsion system is required for orbit raising and orbit maintenance

operations throughout the mission phase of the

satellite. The propulsion system of the satellite is a

unified bi-propellant propulsion system using

mono-methyl hydrazine (MMH) as fuel, mixed

oxides of nitrogen (MON3) as oxidizer and

gaseous helium as pressurant. The satellite employs thrusters for station

keeping. It also employs a liquid apogee motor for orbit raising operations.

1.2.5 Power System:

The power system comprises of the solar panels used to generate the

required power, batteries to store and make available the required power

for eclipse support and the electronics to manage, control and distribute

the power throughout the satellite.

1.2.6 Attitude and Orbit Control System:

The Attitude and Orbit Control (AOCS) Subsystem

computer that integrates Telecommand, telemetry, sensor

processing, thermal control, and spacecraft autonomous

is the onboard

Page 18: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 12

operations. It comprises of software and hardware deliverable system. It

helps in Orientation of the spacecraft axes with respect to an inertial

reference frame and provides stable platform for the mission. Together with

the propulsion subsystem, AOCS provides the capability of 3-axis attitude

control with thrusters in the transfer orbit in addition to orbit rising and fine

orbit adjustment. The satellite carries Sensors such as Sun Sensor, Star

Sensor and the Inertial Reference Unit (IRU) based on Dynamically Tuned

Gyros that provides attitude data.

1.2.7 Telemetry & Telecommand Base band systems:

Telemetry and Telecommand (TTC-Baseband) system

based on processor, HMCs and FPGA’s is configured to

serve the requirements of spacecraft health monitoring through Telemetry

and commanding for control during all the phases of the Mission.

1.2.8 Communication System:

TTC-RF system provides the link

between the spacecraft and ground

station. The primary function of the subsystem is command reception,

telemetry transmission. The elements of the communication system are

Transmitters, Receivers and antenna systems.

1.2.9 Payload Systems:

Payload subsystems are mission specific and are intended to perform the

desired mission objective. The different kind of payloads depending upon

the missions is given below.

Page 19: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 13

Table1: Different Types of payloads

Type of Satellite Payload subsystems

CommunicationSatellite

Transponders in S, C, Ext C,Ku, Ka band

Navigation Satellite Navigation payload

Remote SensingSatellite

Application specific payloads like camera,Scatterometer, imager, sounder, SAR, PANcamera etc

Space Science Scientific instruments like Telescopes, IRCameras etc.

Interplanetary Missions Probes , Orbiters & Rovers

1.2.10 Mission planning & Analysis:

Besides these tangible deliverables, the first and the foremost activity for a

satellite building is the mission planning & analysis. It includes, mission

planning and operation, Orbit selection and Local time studies, ground

segment software suite, Pre launch, launch and post launch operation.

1.2.11 Reliability & Quality Assurance:

A satellite works in a hostile space environment and therefore it calls for

high reliability and quality of satellite systems. It is utmost essential to

ensure the quality assurance of components, parts, materials and process

so that satellite perform its intended on-orbit operations. Stringent reliability

analysis and quality assurance procedures are adopted at all stages of

satellite building to meet the space reliability and quality standards.

1.2.12 Assembly Integration & Testing (AIT):

The qualified spacecraft subsystem hardware flows into the AIT Cleanroom

for electrical & mechanical integration activity in a sequential manner. The

Page 20: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 14

completely integrated/assembled satellite undergoes a series of tests

including Thermovac test, Vibration test, Acoustic test, Compact antenna

ranging test, physical parameter measurements, Dynamic tests etc that

ultimately qualifies the spacecraft for launch.

Page 21: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSTRY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 15

2. SCOPE OF WORK

Page 22: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 16

This page is intentionally left blank

Page 23: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 17

2. SCOPE OF WORK

It is proposed to carry out the assembly, Integration and testing (AIT) activities of

two number of ISRO Standard bus satellites with the participation of the

prospective vendor. The entire activity is planned to be carried out in two phases

viz Phase-1 and Phase-2. During Phase-1, the AIT activities of the first satellite

will be done by ISAC while on-the-job training will be given to the vendor. The AIT

activities of the second satellite will be carried out by the selected vendor under

the supervision of ISRO/ISAC in phase-2.

After successful completion of Phase-2, potential vendors may be invited to take

up satellite fabrication activities on an end-to-end basis and/or carry out assembly,

integration and testing of spacecraft at ISAC/ISITE campus which is beyond the

scope of this EoI.

The Vendor shall take up the activity within ISAC premises at ISITE (ISRO

Satellite Integration and Test Establishment) campus, Marathalli, Bangalore. ISAC

will provide all necessary infrastructures & facilities to facilitate vendor to carry out

Assembly, Integration and Testing of ISRO Standard bus satellites.

The scope of work involved in each phase is discussed in brief below:

2.1 Phase 1: FirstTraining):

ISRO Standard bus satellite realization (On-the-Job

A project team with

constituted after the

members from ISAC and selected

selection of the qualified vendor. The

vendor shall be

required skilled

manpower from the vendor shall be inducted and provided an orientation training

programme on satellite systems and associated systems engineering concepts.

During the realization of first ISRO Standard bus satellite; the vendor will get on-

the-job training on the assembly, integration and testing activities of the satellite.

The flight mainframe subsystems, payload, harness and all the other supporting

infrastructure/facilities, equipment, resources and accessories shall be provided

by ISAC. The vendor shall also be responsible in bringing out necessary

Page 24: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 18

p

p

p

documentation for system assembly, integration and testing activities. All the

activities mentioned will be carried out using ISAC facilities/Infrastructure

Fig 3: First ISRO Standard bus satellite RealizationThe Scope of Work during Phase-1 is summarized below:

Table 2: Scope of Work - Phase 1Sl.No Activities ISAC Vendor

2.1.1 SatelliteSubsystem

Prime responsibilityOrientation trainingprogramme

Partici ation in theOrientation training

Readiness programmeDocumentation

2.1.2 Satelliteassembly andintegrationactivities

PrimeresponsibilityOn-the-job training

Participation underISAC supervisionDocumentation

2.1.3 SpacecraftTesting –

PrimeresponsibilityOn-the-job training

Partici ation underISAC supervision

Facilities/Infrastructure

Documentation

2.1.4 ProjectManagement

PrimeresponsibilityOn-the-job training

Documentation eg:checklist, statusreport, time linecharts

2.1.5 QualityManagement

PrimeresponsibilityOn-the-job training

Partici ation underISAC supervisionDocumentation

Page 25: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 19

2.1.1 Satellite Subsystem Readiness:

ISAC will be responsible for the delivery of satellite subsystem to

cleanroom realized through external vendors, other ISRO work Centres

and in-house agencies during this phase. The vendor manpower shall be

provided orientation training programme in the area of Configuration

Management, Systems Engineering, Subsystem fabrication and testing,

test and evaluation and QA/QC aspects.

2.1.2 Satellite Assembly and Integration Activities:

ISAC will be responsible to carry out the spacecraft assembly and

integration activities while the vendor will be imparted training

programme and on-the-job training and shall actively participate in all the

AIT activities. The vendor shall be provided with orientation training

programme and on-the-job training in order to get acquainted with the

satellite building activities. Exposure to the system engineering aspects,

subsystem design, fabrication and testing, spacecraft level AIT activities,

project management, quality management, facility management etc shall

be provided so that the vendor can take up the entire AIT activities as

listed below during the second phase.

Table 3: List of major AIT Activities

1. Receipt Inspection of Structure, Positionining on Fixture

2. Receipt Inspection of Propulsion System

3. Receipt Inspection of Equipment Panel & Assembly

4. Propulsion System Integration & testing

5. Thermal implementation Activities on Structure,Propulsion elements & Panels

6. Harness installation on panels and patch brackets

7. Receipt Inspection of Subsystem Hardware and payload

Page 26: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 20

Table 3: List of major AIT Activities

8. Assembly & Integration of Subsystems and payload

9. Disassembled Mode IST

10. Preparation of Panels for Closure

11. Panel closure

12. Assembled Mode IST

13. Preparation for Thermo-vacuum Test

14. Containerisation of Satellite, Movement to Thermo-vacuum Chamber, Satellite Removal, Assembly intoChamber

15. Satellite Thermo-vacuum Test

16. Removal of Satellite from Chamber, Containerisation,Movement to Clean Room, Positioning on Fixture

17. EMI/EMC test

18. Alignment of Various Subsystem Hardware

19. End-to-end polarity test

20. Appendages integration & testing

21. Measurement of Physical Parameters of Satellite (CG,MI, Mass)

22. LAM deck assembly & testing

23. Preparation for Satellite Dynamic Test

24. Satellite Fit Check with Launch Vehicle Adaptor

25. Containerisation of Satellite, Movement to Vibration Lab,Satellite Removal, Assembly onto Shaker

26. Vibration Test

Page 27: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 21

Table 3: List of major AIT Activities

27. Removal of Satellite from Shaker, Positioning onFixture, Movement to Acoustic Test Facility, Position onFixture

28. Acoustic Test

29. CATF test

30. SP-1 IST

31. Removal of Satellite from Fixture, Containerisation,Movement to Launch Base

2.1.3 Spacecraft Testing- Infrastructure/Facilities:

ISAC is equipped with state-of-the-art facilities/infrastructure for the

design, development, assembly, integration and testing of satellites

under one roof. Some of the major capital intensive

facilities/infrastructure includes 1 lakh class cleanroom, mechanical

ground support equipment, electrical ground support equipment,

handling and positioning fixture, thermovac chamber, vibration test

facility, Acoustic test facility, Compact antenna test facility, physical

parameter measurement machine, appendages deployment zero g

fixture etc. In this phase, while ISAC will be primarily responsible to

operate the facilities and conduct the test, the vendor shall be provided

with necessary training to actively participate during the tests.

2.1.4 Project Management:

Budget planning, systems engineering, contract management,

configuration management, procurement management, inventory

management etc are the major component of satellite project

management. Training in the relevant project management aspects that

facilitate the smooth and seamless execution of the AIT phase shall be

imparted to the vendor. The vendor shall be provided with adequate

Page 28: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 22

exposure to prepare required documents during this phase. Necessary

documentation such as status report, checklist shall be generated by the

vendor will the support of ISAC during this phase.

2.1.5 Quality Management:

ISAC shall be primarily responsible for the quality and reliability aspects

during this phase. Quality control/ quality assurance plan and procedure

will be worked out by ISAC in order to ensure the compliance of satellite

system/ subsystem/part/component to the space grade quality and

reliability standards of ISAC. Necessary documentation such as test

procedures, test results, inspection report, audit report, failure analysis

report, non-conformance report etc shall be generated at each stage of

the satellite life cycle. The vendor shall be provided with necessary

training and shall actively participate in all the quality management

aspects of satellite AIT activities

2.2 Phase 2: Second satellite Realization:

Based on the knowledge and expertise gained by the vendor during the

realization of the first ISRO Standard bus satellite, the Vendor will now be

geared up to further expand their scope of participation in the satellite AIT

activities. During phase-2, ISAC shall be responsible to realize and deliver

spacecraft systems, payload, harness, checkout systems, mechanical ground

support equipment, electrical ground support equipment etc to the clean room.

With the availability of spacecraft subsystems, the vendor shall be completely

responsible to carry out the assembly, integration and testing of the spacecraft

under the supervision of ISAC. The overall project management is the

responsibility of ISAC. Quality control and assurance is the primary

responsibility of the vendor while the auditing responsibility is of ISAC. The

Page 29: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 23

v

e

vendor will be responsible for necessary documentation during all the stages

of system assembly, integration and test activities.

Fig 4: Second ISRO Standard bus satellite RealizationThe Scope of Work during Phase-2 is summarized below:

Table 4: Scope of Work - Phase 2Sl.No Activities ISAC Vendor2.2.1 Satellite Subsystem

ReadinessPrime responsibility Deliverable check-

listDocumentation

2.2.2 Satellite assembly andintegration acti ities

Supervision Prime responsibilityDocumentation

2.2.3 Spacecraft Testing –Facilities/Infrastructure

Operation andsupervision

UtilizationDocumentation

2.2.4 Project Manag ment Prime responsibility ParticipationDocumentation

2.2.5 Quality Management Audit Prime responsibilityDocumentation

2.2.1 Subsystem Readiness:

ISAC will be responsible for the delivery of satellite subsystem to

cleanroom realized through external vendors, other ISRO work Centres

Page 30: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 24

and in-house agencies during this phase. The vendor manpower shall

prepare a subsystem deliverable check-list and submit the report to

ISAC. Subsequent to the clearance of the checklist report by ISAC focal

point, the vendor shall initiate the spacecraft assembly and integration

activities.

2.2.2 Spacecraft Assembly And Integration Activities:

The vendor shall carry out the spacecraft assembly and integration

activities as per approved assembly sequence plan of ISAC as

summarized below. All the activities mentioned will be carried out using

ISAC facilities/Infrastructure.

Table 5: List of major AIT Activities1. Receipt Inspection of Structure, Positionining on Fixture

2. Receipt Inspection of Propulsion System

3. Receipt Inspection of Equipment Panel & Assembly

4. Propulsion System Integration & testing

5. Thermal implementation Activities on Structure, Propulsion elements& Panels

6. Harness installation on panels and patch brackets

7. Receipt Inspection of Subsystem Hardware and payload

8. Assembly & Integration of Subsystems and payload

9. Disassembled Mode IST

10. Preparation of Panels for Closure

11. Panel closure

12. Assembled Mode IST

13. Preparation for Thermo-vacuum Test

Page 31: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 25

Table 5: List of major AIT Activities14. Containerisation of Satellite, Movement to Thermo-vacuum Chamber,

Satellite Removal, Assembly into Chamber15. Satellite Thermo-vacuum Test

16. Removal of Satellite from Chamber, Containerisation, Movement toClean Room, Positioning on Fixture

17. EMI/EMC test

18. Alignment of Various Subsystem Hardware

19. End-to-end polarity test

20. Appendages integration & testing

21. Measurement of Physical Parameters of Satellite (CG, MI, Mass)

22. LAM deck assembly & testing

23. Preparation for Satellite Dynamic Test

24. Satellite Fit Check with Launch Vehicle Adaptor

25. Containerisation of Satellite, Movement to Vibration Lab, SatelliteRemoval, Assembly onto Shaker

26. Vibration Test

27. Removal of Satellite from Shaker, Positioning on Fixture, Movementto Acoustic Test Facility, Position on Fixture

28. Acoustic Test

29. CATF test

30. SP-1 IST

31. Removal of Satellite from Fixture, Containerisation, Movement toLaunch Base

The total assembly shall be carried out with the vendor on-line Q.C

while ISAC QA/QC team will audit the activity at each stage. The vendor

shall report all anomalies/non-conformance related to AIT activities to

ISAC as and when observed. The vendor shall proceed to next stage

only after the clearance from the ISAC QA team. The vendor shall submit

Page 32: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 26

AIT check-list, cleanroom log history sheet, inspection and assembly

report, Non conformance report etc to ISAC as and when required.

2.2.3 Spacecraft Testing – Facilities/Infrastructure

The spacecraft level testing activities such as thermovac test,vibration

test, acoustic test, antenna test and associated test will be carried out by

the vendor. In this phase, vendor shall be provided with all the necessary

infrastructure/facilities to carry out the testing activities under ISAC

supervision. The operation of the infrastructure/facilities shall be the

responsibility of ISAC.

2.2.4 Project Management:

The overall planning, execution and monitoring of the spacecraft AIT

activities of the second satellite as per the defined scope of work and

within the prescribed time schedule is the primary responsibility of the

vendor in this phase. ISAC shall provide the necessary support and

guidance as and when necessary for the smooth completion of this

phase.

2.2.5 Quality Management:

Quality control and assurance shall be the primary responsibility of the

vendor during this phase while the auditing responsibility is of ISAC. The

vendor shall follow the test plan and procedure, guidelines as defined by

the QA/QC team of ISAC. The vendor shall generate all necessary

documentation in to order to ensure the compliance of the satellite

systems with the space grade quality and reliability standards of ISAC

Page 33: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 27

3. TENURE OF WORK

Page 34: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 28

This page is intentionally left blank

Page 35: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 29

3. TENURE OF WORK:3.1 Phase -1 & Phase-2 Tenure of work

The first ISRO Standard bus satellite is required to be ready for shipment to

launch base by 8 months from the date of work order release. The second ISRO

Standard bus satellite shall be ready 10 months after the readiness of the first

satellite. The overall schedule is depicted below:

Fig 5: Overall Tenure of work

The Overall Realization Schedule plan of the first ISRO Standard bus satellite is

given below:

Page 36: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 30

Fig 6: First Satellite Overall Realization ScheduleThe Overall Realization Schedule plan of the second ISRO Standard bus satellite is

given below:

Fig 7: Second Satellite Overall Realization Schedule

Page 37: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 31

3.2 Long Term Business Plan:

In view of growing demand of satellite based services, there will be a continuous

load of realizing 10-12 satellites in a year. The future requirement of satellite is

enormous and a suitable vendor nurtured by ISAC can take up the satellite

realization portfolio so that ISAC can focus on the core research and

developmental activities in satellite technology. The tie up with the selected

vendor may be broaden if required in the due course of time depending upon the

technical and managerial expertise and experience gained by the vendor in

satellite building activities, subsystem realization process, system engineering

,space grade quality and reliability standards and future project load. Looking

forward, the association with the vendor may be expanded for the realization of

an additional three ISRO Standard bus satellites as summarized below.

Fig 8: Overall Realization Schedule: Five ISRO Standard bus satellite

Page 38: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 32

This page is intentionally left blank

Page 39: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 33

4. MANPOWERESTIMATION

Page 40: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 34

This page is intentionally left blank

Page 41: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 35

4. MANPOWER ESTIMATION:

It is estimated that around 50 personnel are required from the vendor for a period of

about 18 months to realize the two ISRO Standard bus satellites. An approximate

manpower estimation with their qualifications required are as given below:

20 (8: mechanical, 12: electrical/electronic) engineers with a minimum

qualification of BE / BTech

15 technicians with a minimum qualification of Diploma

15 tradesmen with a minimum qualification of ITI

The man-power employed by the vendor shall have experience of working in

relevant / similar areas and must possess a minimum of first class pass marks /

percentage / grading with respect to their qualification. The vendor shall ensure that

the manpower provided by vendor shall be retained throughout the phase-1 and

phase-2 time period. The estimated manpower required to carry out the satellite AIT

activities depends upon the expertise and learning skill of the vendor manpower.

The above number may vary based on upon the spacecraft configuration and

complexity.

The vendor shall be provided with orientation and on-the-job training in order to get

acquainted with the satellite building activities during phase-1. An orientation

training programme for the vendor manpower shall be provided wherein, they will be

introduced to satellite subsystem, system engineering aspects, project

management, and subsystem fabrication and testing, spacecraft level AIT etc.

It will be followed by on-the-job training in the AIT activities of the first ISRO

Standard bus satellite such as thermal fabrication and implementation, propulsion

integration and test activities, subsystem assembly, integration and testing,

integrated spacecraft level testing, checkout operations, In other words, the vendor

man power shall participate in AIT activities with ISAC team to realize the first ISRO

Standard bus satellite. After the completion of the AIT activities of the first ISRO

Standard bus satellite, the manpower will be work on the second ISRO Standard

Page 42: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 36

bus satellite. The on-the-job training will help vendor manpower to take up all

aspects of AIT activities of the second ISRO Standard bus satellite in phase-2.The

technical skill, competency and quality of the vendor manpower play a vital role in

the successful completion of the phase-1 and Phase-2.

Page 43: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 37

5. SAFETYPRECAUTIONS

Page 44: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 38

This page is intentionally left blank

Page 45: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 39

5. SAFETY PRECAUTIONS

The vendor should strictly adhere to the general work rules, procedures and

office timings followed at ISAC.

The personnel of vendor must adhere to all the safety guidelines while handling

components, cards, and packages during testing and transporting, particularly the

ESD protection measures such as wearing ESD overcoats, footwear, wrist bands,

grounding and other measures as per ISAC ESD protection guidelines.

Vendor is responsible to ensure the safe handling of the sub-

assemblies/equipment being used during the AIT of the satellite. The vendor shall

strictly conform to the safety and security procedures laid by ISAC.

Page 46: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 40

This page is intentionally left blank

Page 47: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 41

6. CONFIDENTIALITYAND NON-

DISCLOSURE

Page 48: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 42

This page is intentionally left blank

Page 49: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 43

6. CONFIDENTIALITY AND NON-DISCLOSURE

All documents prepared for fabrication, assembly, integration, test procedures,

log books, drawings, schematics and any other communication, codes revealed

during the satellite realization will be exclusive property of ISAC and vendor shall

have no right whatsoever on them.

These documents are to be strictly confidential and should not be reproduced,

copied/ transmitted to any media without explicit permission of ISAC.

Further, the vendor must not quote any of these works in any publications or to

any of their customers without explicit permission from ISAC and adhere to strict

confidentiality.

Page 50: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 44

This page is intentionally left blank

Page 51: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 45

7. GENERAL TERMSAND CONDITIONS

Page 52: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 46

This page is intentionally left blank

Page 53: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 47

7. GENERAL TERMS AND CONDITIONS

7.1 This EoI is not an offer and is issued with no commitment. ISAC reserves

the right to withdraw the EoI and change or vary any part thereof at any

stage. ISAC also reserves the right to disqualify any vendor/proposal,

should it be so necessary at any stage.

7.2 Timing and sequence of events resulting from this EoI shall ultimately be

determined by ISAC

7.3 By submitting a proposal, each vendor shall be deemed to acknowledge

that it has carefully read all chapters of this EoI, and has fully informed

itself as to all existing terms and conditions.

7.4 The proposal and all correspondence and documents shall be written in

English.

7.5 The vendor shall not subcontract the work related to satellite assembly,

integration & testing to any other third party without the permission of

ISAC.

7.6 Vendor shall compulsorily fill up the Response format and compliance

matrix (Part- I & Part- II) as given in chapter 9 in the EoI

7.7 Vendor shall be prepared to work beyond working hours and on holidays

to meet the project schedules, if necessary

7.8 The cost of components/systems damaged due to

negligence/mishandling by the vendor shall be recovered from the

vendor’s payment

Page 54: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 48

7.9 Minor rework and testing thereon required due to the above shall be

done by the vendor without any financial implications.

7.10 ISAC shall provide the necessary infrastructure/equipment while the

Vendor shall ensure the availability of all necessary resources and

logistics support required for the execution of the work at ISAC

7.11 Vendor shall ensure the minimum wage guidelines like salary, ESI, PF

and Insurance etc. for their manpower as per the wages act and produce

the evidence documents when required

7.12 Start of project will be decided and communicated by ISAC through work

order by ISAC focal point

7.13 Orientation training Programme shall be provided by ISAC to the vendor

7.14 Vendor shall be prepared to accept any short closure of the work order

decided by ISAC.

7.15 The Vendor must be a registered company under the Companies Act,

1956 or a partnership firm registered under Partnership Act or a

Proprietorship firm. The Vendor should be registered with the concerned

departments [Service Tax, Sales Tax, VAT etc] for legally carrying out its

business activities. The Vendor should also have a valid PAN. The

Vendor should submit Self attested copy(ies) of the Certificates of

Incorporation and other certificates that are legally required for carrying

out its business activities. The certificates should be valid at the time of

EoI submission and should be certified by an authorized signatory. A

copy of PAN Card should also be submitted.

Page 55: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 49

7.16 The Vendor shall provide the details of the ownership of the company

and details of owners / directors along with complete addresses of the

owners / directors and their other activities. If the company is owned by

another company similar details of the owner should be provided.

7.17 Not be insolvent, in receivership, or being wound up, not have its affairs

administered by a court or a judicial officer, not have its business

activities suspended, not have been blacklisted, defaulted and must not

be the subject of legal proceedings for any of the foregoing reasons;

7.18 Not have, and their directors and officers not have, been convicted of any

criminal offence related to their professional conduct or the making of

false statements or misrepresentations as to their qualifications to enter

into a procurement contract within a period of three years preceding the

commencement of the procurement process, or not have been otherwise

disqualified pursuant to debarment proceedings;

7.19 Not have a conflict of interest in the EoI in question as specified in the

EoI document

Page 56: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 50

This page is intentionally left blank

Page 57: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 51

8. GENERALINSTRUCTION FOR

SUBMISSION OFPROPOSAL

EoI

Page 58: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 52

This page is intentionally left blank

Page 59: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 53

8. GENERAL INSTRUCTION FOR SUBMISSION OF EoI PROPOSAL

Vendor participation is going to be a major steering factor in order to aid ISAC/ISRO in

meeting the objective of building 10-12 satellites per year. Presently many public and

private companies are directly or indirectly involved in satellite building activities. The

demand for space application is growing manifold across the globe and ISRO/ISAC is

keen to provide vendors opportunities to expand their contribution in satellite realization

activities. With this backdrop, it is now proposed to carry out satellites AIT activities

through an external vendor. In order to achieve this target, one major capable vendor

will be selected to build satellites.

8.1 Steps for selecting the potential vendor:

The following flowchart depicts the steps for selecting the potential vendor. The

process begins with the call for Expression of Interest (EoI). The interested

vendors shall submit the EoI proposal clearly indicating the details required in

chapter 9 Response format with supporting documents. A Pre-EoI

Conference with interested vendors would be conducted at ISAC campus before

the submission of EoI. The purpose of the conference is to provide vendors an

opportunity to seek clarifications regarding any aspect of the EoI. The vendors

finally responding to the EoI shall be shortlisted based on their compliance with

the EoI requirement. Subsequently a pre-bid meeting between ISAC and the

shortlisted vendors will be held at ISAC wherein detailed presentations on the

scope of work, roles and responsibilities and modalities of engagement will be

Page 60: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 54

made. A visit to vendor’s campus may be conducted for assessment of the

capabilities stated in the EoI. The vendors shortlisted (based on EoI and

assessment of their potential to carry out the proposed work) would be issued

Request for Proposal, inviting their technical and commercial bids at a later date.

Subsequently, based on the response to RFP, a potential vendor will be selected

and order will be awarded.

Call for Expression ofInterest

Pre-EoI Conference

EoI-ResponseSubmission

Shortlisting of Vendors

Pre -Bid Meeting

Release of RequestFor Proposal (RFP)

Selecting the Vendor

Placing the Order forSatellite Realization

Fig 8: Steps of selecting the potential vendor

Page 61: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 55

8.2 Guidelines for EoI submission:

The objective of this EoI is to solicit proposals from the interested vendor for

participation in the satellite AIT activities as discussed in the scope of work. The

interested vendor are expected to examine all instructions, scope of work, tenure

of work, manpower estimation, safety precautions, confidentiality and non-

disclosure, general terms and conditions, submission guidelines and other details

in the EoI documents. Failure to furnish complete information as mentioned in the

EoI documents or submission of a proposal not substantially responsive to the EoI

documents in every respect will be at the Vendor's risk and may result in rejection

of the proposal. The EoI is not an offer and is issued with no commitment. ISAC

reserves the right to withdraw the EoI and change or vary any part thereof at any

stage, if it determines that such action is in the best interest of the Government of

India. ISAC also reserves the right to disqualify any proposal, should it be so

necessary at any stage.

The proposal should be submitted as an Expression of Interest (EoI), clearly

providing the details requested below with documentary proof/supporting

documents.

The vendor has to provide the information as per the formats prescribed inchapter 9 Response Format. The overall compliance matrix as per section9.9 should also be submitted as per of the EoI proposal. All these inputsmay be furnished in MS word document neatly typed in the said formats.The proposal andEnglish.

all correspondence and documents shall be written in

Page 62: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 56

This page is intentionally left blank

Page 63: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 57

9. RESPONSE FORMATS

Page 64: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 58

This page is intentionally left blank

Page 65: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 59

9. RESPONSE FORMATS9.1 Cover Letter

(Company letterhead)

[Date]

To,

HEAD, PURCHASE & STORESISRO Satellite CentreHAL Airport Road, Vimanapura PostBangalore -560017Karnataka

Dear Sir,

Ref: “Expression of Interest for systems assembly, integration &

testing of standard ISRO satellites through Industry”

Having examined the Expression of Interest (EoI), the receipt of which is hereby duly

acknowledge, we, the undersigned, intend to submit a proposal in response to the

Expression of Interest (EoI).

We attach hereto the response as required by the EoI, which constitutes our proposal

Primary and Secondary contacts for our company are:

Primary Contact Secondary Contact

Name:

Title:

Company Name:

Address:

Phone :

Page 66: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 60

Primary Contact Secondary Contact

Mobile:

Fax :

E – mail :

We confirm that the information contained in this response or any part thereof,

including its exhibits, and other documents and instruments delivered or to be

delivered to ISAC is true, accurate, verifiable and complete. This response includes

all information necessary to ensure that the statements therein do not in whole or in

part mislead ISAC in its short-listing process.

We fully understand and agree to comply that on verification, if any of the information

provided here is found to be misleading the short listing process, we are liable to be

dismissed from the selection process or termination of the contract during the

realization of Phase-1 and Phase -2 , if selected to do so.

We agree for unconditional acceptance of all the terms and conditions set out in the

EoI document.

It is hereby confirmed that I / We are entitled to act on behalf of our company/

corporation/ firm / organization and empowered to sign this document as well as

such other documents, which may be required in this connection.

Dated this

(Signature)

(Name)

(In the capacity of)

Duly authorized to sign the EoI Response for and on behalf of :

(Name and Address of Company)Seal / Stamp of Vendor

Page 67: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 61

Witness Signature :

Witness Name :

Witness Address:

CERTIFICATE AS TO AUTHORIZED SIGNATORIES

I, …………………………………………., the Company Secretary of

……………………………….., certify that

………………………………………………………………. Who signed the above EoI is

authorized to do so and bind the company by authority of its board / governing body.

Date :

(Company Seal)

Signature :

Page 68: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 62

9.2 General Details of the Vendor

9.2.1 Name of the Vendor

9.2.2Year of Establishment

9.2.3Brief profile and core capabilities

of the vendor

provide details in 1-2 pages

(enclose separate sheet )

9.2.4Type of Vendor

Government/Public sector

Undertaking/Private/Others

9.2.5 Head office location and address:

9.2.6 Local address in Bangalore if any:

9.2.7 Corporate website URL:

9.2.8Quality certification (such as

MIL/ISRO/DRDO/Aerospace):

9.2.9 Vendor’s Quality Standards

Page 69: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 63

e

9.3 Aerospace/Space Related Activities

9.3.1 In case the

January 01,

vendor is having/had any Purchase

2012 onwards) from ISRO Centres or

order/Contract (from

aerospace Industry.

provide the following details:

Sl

No.

Name of the ISRO

Centre/Aerospac

Industry

Statement

of Work

Date of release:

Purchase order

/Contract

Present

Status

Remark

s

1.

2.

3.

4.

5.

6.

9.3.2 List of sub-contractor involved in executing the Purchase order/Contract

(from January 01,2012 onwards) from ISRO Centres or aerospace industry

if any.

9.3.3 At present ISAC has qualified vendors for various satellite related activities.

If required, is the vendor willing to form a consortium with these vendors to

enable successful completion of the scope of work as defined in chapter 2-

Scope of work? Yes/No

Page 70: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 64

9.4 Vendor Expert Manpower

9.4.1 Management structure of the vendor

9.4.2 Manpower Strength as on 1st June 2016

Stream Total no. of Engineers (Engg.) Total no. of Technicians

(Tech.)

Mechanical

Electronics

Computer

Science

Others

9.4.3 Years of Experience as on 1st June 2016

Experience Mechanical Electronics Computer Sci. Others

Engg. Tech. Engg. Tech. Engg. Tech. Engg. Tech.

0 to 2 years

>2 to 5

years

>5 to 10

years

>10 years

Page 71: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 65

9.4.4 Is the vendor willing to deploy their manpower to work in ISAC /ISITE

campus Yes/No

9.4.5 The vendor shall ensure that the manpower provided by vendor shall be

retained throughout the phase-1 and phase-2 time period. Yes/No

9.4.6 Is the vendor willing to work in regular shift (8 hrs shifts), two shift or three

shift mode operation if required depending upon the phase of the project.

Yes/No

9.4.7 The vendor shall provide all logistics support to its manpower for the

execution of the work at ISAC Yes/No

9.4.8 Please provide risk management plan to handle unforeseen situations such

as attrition etc?

Page 72: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 66

9.5 Infrastructure Capabilities

9.5.1 List of major infrastructure presently available to build systems/subsystem

related to either satellite or launch vehicle or aerospace related systems

such as cleanroom, electronic fabrication facility, mechanical fabrication

facility, environment test chambers etc.(facilities used to execute orders

from ISRO Centres or aerospace vendors)

Sl.No Name of

Infrastructure/Facility

Year of

commissioning

Brief

specifications

1.

2.

3.

4.

5.

9.5.2 Is the vendor willing to invest in resources-

manpower/equipment/facilities/infrastructure? Yes/No

Page 73: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 67

9.6 Financial Details:

9.6.1 Financial Information

FY 2012-13 FY 2013-14 FY 2014-15 FY 2015-16

Revenue (in

INR Crores)

Profit before

Tax(in INR

Crores)

Revenue from

services(in

INR Crores)

9.6.1.1 Mandatory Supporting Documents

9.6.1.1.1 Auditor certified statements for the last four years 2012-

13,2013-14,2014-15 and 2015-16 (please includes only the

sections on profit and loss , revenue,and assets, not the entire

balance sheet)

9.6.1.1.2 Unaudited certified statements certified by the company

auditors for the latest year 2015-16(in case auditor certified

statement for 2015-16 is not available

9.6.1.1.3 Certification by the company auditors supporting the revenue

break up.

Page 74: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 68

9.7 Legal Aspects

9.7.1 The Vendor must be a registered company under the Companies Act, 1956

or a partnership firm registered under Partnership Act or a Proprietorship

firm. The vendor should be registered with the concerned departments

[Service Tax, Sales Tax, VAT etc] for legally carrying out its business

activities. The vendor should also have a valid PAN. The Vendor should

submit Self attested copy(ies) of the Certificates of Incorporation and other

certificates that are legally required for carrying out its business activities.

The certificates should be valid at the time of EoI submission and should be

certified by an authorized signatory. A copy of PAN Card should also be

submitted.

Page 75: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 69

9.8 Others

9.8.1 The Vendor shall provide the details of the ownership of the company and

details of owners / directors along with complete addresses of the owners /

directors and their other activities. If the company is owned by another

company similar details of the owner should be provided.

9.8.2 Not be insolvent, in receivership, or being wound up, not have its affairs

administered by a court or a judicial officer, not have its business activities

suspended, not have been blacklisted, defaulted and must not be the

subject of legal proceedings for any of the foregoing reasons

9.8.3 Not have, and their directors and officers not have, been convicted of any

criminal offence related to their professional conduct or the making of false

statements or

procurement

misrepresentations as to their qualifications to enter into a

contract within a period of three years preceding the

commencement of the procurement process, or not have been otherwise

disqualified pursuant to debarment proceedings

9.8.4 Not have a conflict of interest in the EoI in question as specified in the EoI

document

Page 76: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 70

9.9 Compliance Matrix to be filled by Vendor9.9.1 Part- I Compliance Matrix

Refer

Chapter

No

DescriptionCompliance

(Yes/No)Remark

2 Acceptance to Scope of work

3 Acceptance to Tenure of work

4 Acceptance to Manpower Estimation

5 Acceptance to Safety precautions

6Acceptance to Confidentiality and

non-disclosure

7 Acceptance to General Terms and

Conditions

8.Acceptance to General instruction for

submission of EoI proposal

9Acceptance to Response Format

Page 77: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 71

9.9.2 Part- II Compliance Matrix

Chapt

er NoDescription

Compliance

(Yes/No)Remark

Supporting

Document

9.1.Covering Letter

9.2. General Information

9.2.1. Data provided as per 9.2.1

9.2.2. Data provided as per 9.2.2

9.2.3.Attached separate sheet as per

9.2.3

9.2.4. Data provided as per 9.2.4

9.2.5. Data provided as per 9.2.5

9.2.6. Data provided as per 9.2.6

9.2.7. Data provided as per 9.2.7

9.2.8. Data provided as per 9.2.8

9.2.9. Data provided as per 9.2.9

9.3. Aerospace/Space Related

Activities

Page 78: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 72

p

Chapt

er NoDescription

Compliance

(Yes/No)Remark

Supporting

Document

9.3.1.All details & supporting documents

as per 9.3.1 attached?

9.3.2.List of sub-contractor as per 9.3.2

attached?

9.3.3.Acceptance to 9.3.3

9.4. Vendor Expert Man ower

9.4.1. All details as per 9.4.1 attached?

9.4.2. All details as per 9.4.2 attached?

9.4.3.All details & supporting documents

as per 9.4.3 attached?

9.4.4. Acceptance to 9.4.4

9.4.5. Acceptance to 9.4.5

9.4.6. Acceptance to 9.4.6

9.4.7. Acceptance to 9.4.7

9.4.8. Acceptance to 9.4.8

Page 79: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 73

Chapt

er NoDescription

Compliance

(Yes/No)Remark

Supporting

Document

9.5. Infrastructure Capabilities

9.5.1.List of major infrastructure as per

9.5.1 attached?

9.5.2. Acceptance to 9.5.2

9.6. Financial Details

9.6.1.All details & supporting documents

as per 9.6.1

9.7. Legal aspects

9.7.1.All details & supporting documents

as per 9.7.1

9.8. Others

9.8.1.All details & supporting documents

as per 9.8.1

9.8.2.All details & supporting documents

as per 9.8.2

9.8.3.All details & supporting documents

as per 9.8.3

Page 80: ISRO Satellite Centre · Based on the mass and power generation, communication satellites are classified into mainly four major bus platform: I-1K Bus Satellite 1 to 1.5 ton class

SYSTEMS ASSEMBLY,INTEGRATION & TESTING OFSTANDARD ISRO SATELLITESTHROUGH INDUSRTY

ISRO SATELLITE CENTRE,BENGALURU

Expression of Interest 74

Chapt

er NoDescription

Compliance

(Yes/No)Remark

Supporting

Document

9.8.4.All details & supporting documents

as per 9.8.4

The vendor has to provide the information as per the formats prescribed in

chapter 9 Response format 9.1 to 9.8. The overall compliance matrix as per

section 9.9 should also be submitted as per of the EoI proposal. All the above

inputs may be furnished in MS word document neatly typed in the above said

formats.