Page 1: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

ISTANBUL STRAITIMMERSED TUNNEL

Considerations and Strategiesbehind

Design & Construction Requirements

ISTANBUL STRAITIMMERSED TUNNEL

Considerations and Strategiesbehind

Design & Construction Requirements

Bosphorus Rail TunnelIstanbul, Turkey

Page 2: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Christian IngerslevSenior Engineering Manager

Parsons BrinckerhoffNY, USA

Christian IngerslevSenior Engineering Manager

Parsons BrinckerhoffNY, USA

Page 3: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Prime DirectivesPrime Directives

• Design-build project• Performance based• Fit for purpose• Standards & Codes of Practice

• Turkish• USA, British, EuroCode, Japanese

Page 4: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Depth IssuesDepth Issues• Deepest immersed tunnel, 58 m deep

• BART in San Francisco is 40 m deep

Page 5: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Depth Issues - Limit LeakageDepth Issues - Limit Leakage

• Construction Care• Watertight design: ignore waterpr’fing• Mandatory waterproofing membrane• Leakage below membranes

• Use of anchoring ribs in concrete• Compartmentalize surface (10 m² max)

Page 6: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Tunnel TypeTunnel Type

Fort McHenry Tunnel, USA,Steel Double Shell

Bay Area Rapid Transit (BART), USA,Steel Single Shell

Naha Port & Kobe Port, JapanSteel Sandwich Type

Airport Rail Tunnel, HK,Concrete

Phot

o so

urce

unk

now

n

Phot

o co

urte

sy o

f Wal

ter G

rant

z

Page 7: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Currents in StraitCurrents in Strait

• Currents• Surface south• Deep north• Turbulent layer

• Simulation model• Calibration

• Tunnel placing risks• Model test• Temporary access

Page 8: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Seismic Issues – Fault NearbySeismic Issues – Fault Nearby

Detail

• North Anatolian Fault• 7.5 Richter in 35 yrs• Tsunami

Page 9: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Seismic Issues – ApproachSeismic Issues – Approach

• DBE = FEE = SEE for this project• Facility to remain operational• Bedrock ground-motion time history• Req’d detailed analysis methodology• More boreholes

© Steen Lykke

Page 10: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Seismic Issues – TreatmentSeismic Issues – Treatment

• Site response analysis• Liquefaction analysis

• Shaking loads• Hydrodynamic loads

• Ground improvement• Post-earthquake loads & deformation• Fill type

Page 11: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Seismic Issues – SafetySeismic Issues – Safety

• Longitudinal analysis• Transverse racking analysis• Ductility in the overload range• Seismic

joints• Floodgates

Page 12: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Geotechnical DataGeotechnical Data

Immersed Tunnel now Terminates at Rock Faces

Page 13: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Geotechnical ChallengesGeotechnical Challenges

• Contractor to decide:• Immersed length • TBM to immersed connection

• Required excavation/fill analyses defined

• Long-term and post-seismic analyses• Estimate installation level• Internal space checks

Page 14: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Cross-SectionCross-Section

• 1985 BART-type concept

• 2002 Client concept for bid

• 2004 Contractor’s Design

Page 15: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Current TGN DesignCurrent TGN Design

• Construction method partially afloat • Reinforced concrete except collars• Steel plate on sides & base• Ease of construction

Figure after that in

the Basic Design by Taisei-Gama-Nurol JV

Page 16: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Unusual Features – Terminal JointsUnusual Features – Terminal Joints• Terminal joints in deep water• Bored tunnels to enter immersed tunnel

Skinplate of TBM

Flexible joint

Segmental lining

Immersed tunnel Sleeve pipe

Reinforced concrete section

Figure from the Basic Design by Taisei-Gama-Nurol JV

Page 17: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Unusual Features – Terminal JointsUnusual Features – Terminal Joints• Bored tunnels to enter immersed tunnel• Only done once before, in HK

MTRC Contract 103, HK

Page 18: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Construction SequenceConstruction Sequence

• Lay tunnel from Asian side• Temporary access shaft by Leander’s

tower• Backfill for end zones to be watertight• Bore directly out of rock into end of

immersed tunnel.

Page 19: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Fire Resistance - SafetyFire Resistance - Safety

• Provide fire insulation over ceiling & walls

• No spalling of concrete beneath insulation

• Concrete & reinforcement temperatures limited.

Page 20: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Fire ProtectionFire Protection

• Freight as well as passengers • Two-hour 100 MW fire rating for the

Rijkswaterstaat hydrocarbon curve • Four hour rating for the harmonized

curve.

0; 30

3; 890

5; 114010; 120030; 1300 60; 1350 90; 1300

120; 1200

0200

400600800

1000

12001400

0 20 40 60 80 100 120 140 160 180 200 220 240

Time (min)

Tem

pera

ture

°C

Rijkswaterstaat hydrocarbon Harmonized hydrocarbon

Page 21: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Other ChallengesOther Challenges

• Seabed level to remain unchanged• Excavating & backfilling in current

• Great depth• How to control location of operations

• Fish migration may limit operations• Environmental issues• Control of international waterway

Page 22: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Notice to Mariners – Phase 4Notice to Mariners – Phase 4

http://www.shodb.gov.tr/ilanlar/marmaray_ing.htm

Page 23: ISTANBUL STRAIT IMMERSED TUNNEL Considerations and

Safeguarding the EnvironmentSafeguarding the Environment