it infrastructure transformation agency coordination with rpb mainframe and server migration
DESCRIPTION
IT Infrastructure Transformation Agency Coordination with RPB Mainframe and Server Migration. December 6, 2007. Messaging Services. Desktop. Help Desk. Mass Desktop Refresh Projects Network Printer Consolidation and Refresh Enterprise Desktop Management Systems. - PowerPoint PPT PresentationTRANSCRIPT
1
Data Center Migration Update
IT Infrastructure TransformationAgency Coordination with RPB Mainframe and Server Migration
December 6, 2007
2
Data Center Migration Update
Help DeskDesktopMessaging Services
Enterprise Exchange/Outlook Email
Enterprise Collaboration toolsActive Directory, DNS
Mass Desktop Refresh ProjectsNetwork Printer Consolidation and RefreshEnterprise Desktop Management Systems
New IBM and Unisys Mainframes in new Data Center Consolidation and refresh of servers
Migration of servers to the data center
Enterprise Help Desk in Lebanon and MeadowvilleField Based agents and technicians for Level 3
Enterprise Help Desk System (Peregrine)
New Data Center/Office Building in MeadowvilleNew Disaster Recovery Center and Help Desk
in Lebanon/Russell County
New Commonwealth-wide MPLS Core WANLAN upgrades to local switches/routers as needed
Network Re-addressing of IP, DHCP
Voice over IP Network optimized for voice and video traffic
Enterprise Security Operations CenterComputer Security Incident Respon
CenterSecure Internet Gateway
Security
NetworkVoice / Video
Mainframe and Servers
Facilities Tier 3 and Tier 2
Reliable, High Performance,Enterprise-Wide IT Infrastructure
“People – Processes – Tools”
3
Data Center Migration Update
Server Transformation and Move Introduction
Project Description
Relocating all Data Center operations for the current Data Center located in the Richmond Plaza Building to the new Commonwealth Enterprise Solutions Center (CESC).
Consolidating/Virtualization of servers at RPB to reduce overall foot-print and better facilitate the relocation effort
Consolidation of multiple SAN/Disk subsystem to a single new SAN/Disk infrastructure to facilitate the relocation effort and improve operations efficiency
The Data Center Relocation is scheduled to start in early June 2007 and continue through November 2007. The Relocations will be scheduled during weekend periods to minimize the impact to agency operations.
Purpose and Benefits
• Easier Maintenance through server virtualization
• Quicker response time to agency change requests
• Better utilization of server hardware
• Better utilization of SAN/Disk infrastructure
4
Data Center Migration Update
RPB to CESC Server Move Status (12/6/2007)
Move Group 1 (DCG, DFP, SCB) Complete
Move Group 2 (VGIN, DOF) Complete
Move Group 3 (SBE, DPB) Complete
Move Group 4 (DGS, DSS, DVS) Complete
Move Group 5 (DEQ, VEC Partial) Complete
Move Group 6 (GOV, VDACS, IDC tentative) Complete
Move Group 7 (TAX, DSS, VEC, DCJS, VITA) Complete
Move Group 8 (IDC, VITA) Complete
Move Group 9 (VDH, VITA) Complete
Move Group 10 (VITA LAB) Complete
5
Data Center Migration Update
Project Description
• Upgrade tape processing.
• Consolidate mainframe print centers to a central location using new printers that will deliver both continuous form or cut sheet output.
• Implement disk that will be shared by IBM and Unisys mainframes.
• Move mainframes and related equipment to the new data center in Chesterfield.
Purpose and Benefits
• Expand the use of tape robotics to improve data access performance, minimize manual tape mounts, and reduce floor space for racked tapes.
• Upgrade to current disk technology will enable data replication of virtual tape and disk to the disaster recovery center in Lebanon.
• Minimize mainframe printing cost by using current technology
• Migration to a Tier 3 datacenter
Mainframe Transformation and Migration Introduction
6
Data Center Migration Update
Summary of Cutover Time-Line
• Friday, Dec. 14 – 10 a.m. - Go or no-go decision for executing change.
– 6 p.m. – Mainframes unavailable. Begin move.
• Saturday, Dec. 15– 4 a.m. to 5 a.m. – CESC Internet connectivity outage.
– 4 p.m. – Agency mainframe application testing begins
7
Data Center Migration Update
Summary of Cutover Time-Line• Sunday, Dec. 16
– 6 a.m. - Summary of all test results, current problem, status from agencies
– 8 a.m. - Earliest point that applications will be available for general use
– 8 a.m. - Final go or no-go decision
– 12 noon - Begin execution of back out if required
• Monday, Dec. 17– 6 a.m. – End of change window. All applications available