ITEM 201 PRODUCTION OF HIGHWAY AGGREGATES - v02.2019 Note to Designer: If base, subbase and/or shoulder material are supplied from gravel or rock cuts, determine the quantity of CE/ SRE so used and deduct it from Column 13/ 18 for the stations of the source, so it is not taken into account in the Quantity Balance columns. Quantity to deduct = Tendered tonnes of aggregates bank unit weight (CE or SRE) x shrinkage or bulking factor, as follows: Material RD Col. to Deduct From Volume to Deduct for Crushing CE 13 (Compacted CE) tonnes 2.0 t/m 3 x 0.95 (typ.) SRE 18 (Bulked SRE) tonnes 2.6 t/m 3 x 1.3 (varies) In your specs include 201.2.1.1 below for gravel; or 201.2.1.1 and 201.2.1.2 for rock Replace 201.2.1.1 Gravel will be supplied under Item 106 at the point of excavation in the area of Station____ to / the location indicated on the Plans. OR 201.2.1.1 Rock will be supplied under Item 108 at the point of excavation in the area of Station __ to / the location indicated on the Plans. 201.2.1.2 Blending materials, if required, shall be supplied by the Contractor. If both common and rock cuts supply Base/Subbase Replace 201.2.1.1 Gravel will be supplied under Item 106 at the point of excavation in the area of Station to and/or as indicated on the Plans. 201.2.1.2 Rock will be supplied under Item 108 at the point of excavation in the area of Station to and/or as indicated on the Plans. Add 201.2.1.2.1 Blending materials, if required, shall be supplied by the Contractor. For Contracts Stockpiling Shoulder Material Page 1 of 93

Upload: others

Post on 23-Mar-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 201 – PRODUCTION OF HIGHWAY AGGREGATES - v02.2019

Note to Designer: If base, subbase and/or shoulder material are supplied from gravel or rock cuts, determine the quantity of CE/ SRE so used and deduct it from Column 13/ 18 for the stations of the source, so it is not taken into account in the Quantity Balance columns. Quantity to deduct = Tendered tonnes of aggregates bank unit weight (CE or SRE) x shrinkage or bulking factor, as follows:

Material RD Col. to Deduct From Volume to Deduct for Crushing CE 13 (Compacted CE) tonnes 2.0 t/m3 x 0.95 (typ.)SRE 18 (Bulked SRE) tonnes 2.6 t/m3 x 1.3 (varies)

In your specs include 201.2.1.1 below for gravel; or 201.2.1.1 and 201.2.1.2 for rock

Replace

201.2.1.1 Gravel will be supplied under Item 106 at the point of excavation in the area of Station____ to / the location indicated on the Plans.

OR

201.2.1.1 Rock will be supplied under Item 108 at the point of excavation in the area of Station __ to / the location indicated on the Plans.

201.2.1.2 Blending materials, if required, shall be supplied by the Contractor.

If both common and rock cuts supply Base/Subbase

Replace

201.2.1.1 Gravel will be supplied under Item 106 at the point of excavation in the area of Station to and/or as indicated on the Plans.

201.2.1.2 Rock will be supplied under Item 108 at the point of excavation in the area of Station to and/or as indicated on the Plans.

Add

201.2.1.2.1 Blending materials, if required, shall be supplied by the Contractor.

For Contracts Stockpiling Shoulder Material

Add

201.2.1.5 Processing of Shoulder material per 201.2.5.1 will include crushing.

For Contracts Stockpiling Sandstone Subbase in District 5

Replace

201.2.4.4.1.2 Sandstone Subbase shall have a maximum micro-Deval loss of 40% per test method MTO LS-618, and a maximum Plasticity Index (PI) of 5.

Page 1 of 68

Page 2: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

For Contracts Stockpiling 19 mm Aggregate Base

Add

201.2.7 Aggregate Base for Trails

201.2.7.1 Aggregate Base for NB Trail shall conform to the grading limits of Table 201-A.

Table 201-AGrading Limits – 19 mm Aggregate Base

ASTMSieve Size Percent Passing

25 mm 10019 mm 95 – 100

12.5 mm 67 – 869.5 mm 55 – 79

4.75 mm 37 – 642.36 mm 25 – 501.18 mm 16 – 37300 µm 5 – 1675 µm 0 – 7

Note to Designer: If the on-site pit and/or quarry area cited in 201.2.1.1 as a base/subbase source is not all of base/subbase quality, include the following:

Add

201.4.1.1.1 The Contractor may be required to excavate the material for Aggregate Base/Subbase at selected locations within the pit/quarry area identified in 201.2.1.1, as specified by the Engineer based on results of tests on samples taken by the Engineer before and during the course of the Work.

Note to Designer: If crushing in an on-site quarry is close enough to a highway such that dust from the operation could be dangerous, use the following:

Add

201.4.1.1.1 The Contractor shall take measures to control airborne dust from any crushing operation carried out in the area, so that such dust does not present a hazard to the safety of motorists on adjacent Route .

201.4.1.1.2 Materials to be crushed and stockpiled under this Item are as follows:Type of Material Size Specification Reference

Rock Base 31.5 mm Item 201, Table 201-2Rock Subbase 75 mm Item 201, Table 201-2Shoulder Material 31.5 mm Item 201, Table 201-6

201.4.3.3 By-products from production of any of the materials of 201.4.1.1.2 shall remain the property of the Owner and shall be reprocessed in the production of other crushed materials or stockpiled as directed by the Engineer.

Use 201.4.5.1.1 as appropriate

Add

201.4.5.1.1 Crushed aggregates shall be stockpiled at , or as approved by the Engineer.

January 28, 2021

Page 2 of 68

Page 3: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 203 – AGGREGATE BASE/SUBBASE - v04.2019

Note to Designer: Add haulage cost to unit price of each material. Use the latest haulage rates x 0.95 (per Item 932, 75% hauled by Private Trucks at full rates and 25% hauled by company trucks at 80% of rates, with no mark-up): Haulage = (0.75)(1.0) + (0.25)(0.8) = 0.95 of calculated figure.

Note to Designer: When material is not being provided in stockpile by the Owner, include Item 201 in the Particular Specifications using applicable library clauses from that Item. (See Note to Designer in Item 201)

Add

203.1.2 The Owner’s records indicate that the _______ pit / quarry at ___________ / on Route ___ / ___________ Road is an acceptable source for production of Aggregate Base/Subbase.

OR (if several established pits/quarries exist)

203.1.2 The Owner’s records indicate that several pits / quarries in the area of this Contract are acceptable sources for production of Aggregate Base/Subbase.

Note to Designer: If Base/Subbase is supplied from gravel or rock cuts, alter the RD sheet as described in Item 201 and include the statements below as appropriate:

For on-site gravel cuts, replace 203.2.1.1

Replace

203.2.1.1 Gravel will be supplied under Item 106 in the area of Station __ _ to and/or as indicated on the Plans.

For on-site rock cuts, replace 203.2.1.1 and add 203.2.1.1.1

Replace

203.2.1.1 Rock will be supplied under Item 108 in the area of Station __ _ to and/or as indicated on the Plans.

Add

203.2.1.1.1 Blending materials, if required, shall be supplied by the Contractor.

If both Common and Rock cuts supply Base/Subbase

Replace

203.2.1.1 Gravel will be supplied under Item 106 at the point of excavation in the area of Station to / the location indicated on the Plans.

Add

203.2.1.1.1 Rock will be supplied under Item 108 at the point of excavation in the area of Station to / the location indicated on the Plans.

203.2.1.1.2 Blending materials, if required, shall be supplied by the Contractor.

Page 3 of 68

Page 4: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

If DTI supplies some but not all the materials, replace 203.2.1.1 and add 203.2.1.1.1

Replace

203.2.1.1 Approximately t of Aggregate Base and t of Aggregate Subbase will be supplied by the Owner in stockpile at .

OR

203.2.1.1 Approximately t of RAP will be made available from Item 208 to be used as Aggregate Subbase.

AND

Add

203.2.1.1.1 All other materials shall be supplied by the Contractor.

If all of the Base/Subbase is available in stockpile

Replace

203.2.1.1 The Aggregate Base/Subbase will be supplied by the Owner in stockpile at __________.

Note to Designer: Subsequent to discussion and agreement with Construction Branch, if rock and gravel sources are both available, tender subbase as 203.075S and base as 203.0315B (or other sizes) and use the statement below. Do not select crushed gravel with prior approval.

Add

203.2.1.1.1 Aggregate Base/Subbase shall be crushed rock or crushed gravel.

For Contracts in Madawaska County Add

203.2.1.2.1                The Green River Quarries: Conrad Lavoie and Sons (Clearwater) Quarry (PID 3521078); St. Onge Forrest Products Quarry (PID 35236884) and Northern Construction Inc. Quarry (PIDs 35057363 and 35210285), formerly the Clarence Daigle and Sons Quarry, are not to be utilized in the production of Base and Subbase aggregate.

For Contracts in Charlotte County

Add

203.2.1.2.1               Rock from the J. Smith Excavating Quarry (PID 01239862) is not to be utilized in the production of Base and Subbase aggregate.

For Contracts with Sandstone Subbase in District 5

Add

203.2.1.2.1 Sandstone Subbase shall have a maximum micro-Deval loss of 40% per test method MTO LS-618, and a maximum Plasticity Index (PI) of 5.

Page 4 of 68

Page 5: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Note to Designer: If the subbase layer will be tendered as Rock Cap, see Item 108 (for rock from cuts) or Item 121 (for rocks from off site). See Item 121 for Sandstone Cap and Gravel Cap also.

Aggregate Base for Trails

Add

203.2.2 Aggregate Base for Trails

203.2.2.1 Aggregate Base for NB Trail shall conform to the grading limits of Table 203-A.

Table 203-AGrading Limits – 19 mm Aggregate Base

ASTMSieve Size Percent Passing

25 mm 10019 mm 95 – 100

12.5 mm 67 – 869.5 mm 55 – 794.75 mm 37 – 642.36 mm 25 – 501.18 mm 16 – 37300 µm 5 – 1675 µm 0 – 7

Note to Designer: If the on-site pit and/or quarry area cited in 201.2.1.1 as a base/subbase source is not all of base/subbase quality, as determined from the SP Sheet and/or Soils Engineer, include the following statement:

Add

203.4.1.1.1 The Contractor may be required to excavate the material for Aggregate Base/Subbase at selected locations with the pit/quarry area identified in 203.2.1.1, as specified by the Engineer based on results of tests on samples taken by the Engineer before and during the course of the Work.

Note to Designer: Use the following as appropriate (check paragraph numbers):

Add

203.4.1.1.1 Placement of Aggregate Base shall be to an average thickness of _____ mm, at an average width of ____ m and shall begin within ___ days of commencing the Work under Item 267.

203.4.1.1.1 The Aggregate Base/Subbase shall be placed at an average thickness of 50 mm as a levelling course upon completion of the Work under Item 267.

203.4.1.1.1 The Aggregate Base/Subbase shall be placed at ____________at Station .

Page 5 of 68

Page 6: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

For Culvert Replacement Areas

Add

203.4.1.1.1 Aggregate Base/Subbase shall be placed over the area of each cross culvert replacement performed under Item 140/141, at an average thickness of ___ mm and ___ mm, respectively.

203.4.1.1.1.1 The Contractor shall be responsible to maintain the Roadway at the cross culvert replacement/digout as directed by the Engineer.

Note to Designer: If calling Item 262 Partial Depth Recycling and with culvert replacements/digouts.

Add

203.4.1.1.1.1 The Contractor shall be responsible to maintain the Roadway at the cross culvert replacement/digout as directed by the Engineer.

203.4.1.1.2 RAP base shall be placed 200 mm thick at the culvert replacement area(s) no later than 2 days after the culvert replacement in each case, and prior to the Work under Item 262. The Work shall include removal and disposal of excess Aggregate Base from the culvert replacement area(s).

Note to Designer: If crushing in an on-site quarry is close enough to a highway such that dust from the operation could be dangerous, use the following:

Add

203.4.1.4 The Contractor shall take measures to control airborne dust from any crushing operation carried out in the area, so that such dust does not present a hazard to the safety of motorists on adjacent Route ____.

Note to Designer: For grading contracts with subbase to be placed, show the future guide rail locations on the Plans and add the following in the specs:

Add

203.4.2.5.1 At the locations of future guide rail installations by others, as shown on the Plans, the Aggregate Subbase shall be placed to a width that will allow for the guide rail installations, as staked by the Engineer.

Note to Designer: RAP used for Aggregate Base/Subbase Quantity > 5000 t

Add

203.4.2.15 The Contractor shall weigh all RAP used for Aggregate Base/Subbase from stockpile prior to placing on the Roadway.

February 22, 2021

Page 6 of 68

Page 7: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 204 – SHOULDER MATERIAL - v04.2019

If shoulder material is available from stockpile

Replace

204.2.1 Shoulder material will be supplied by the Owner in stockpile at ____________.

For Contracts in Madawaska County Add

204.2.1.1                   The Green River Quarries: Conrad Lavoie and Sons (Clearwater) Quarry (PID 3521078); St. Onge Forrest Products Quarry (PID 35236884) and Northern Construction Inc. Quarry (PIDs 35057363 and 35210285), formerly the Clarence Daigle and Sons Quarry, are not to be utilized in the production of Shoulder material.

For Contracts in Charlotte County

Add

204.2.1.1                   Rock from the J. Smith Excavating Quarry (PID 01239862) is not to be utilized in the production of Shoulder material.

Note to Designer: Use any of the following as appropriate.

If shoulder material is not RAP but all rock or all gravel (203.0315SM/R or 203.0315SM/G)

Add

204.2.2.1 Shoulder material shall be crushed rock or crushed gravel.

If shoulder material is not RAP but rock and gravel are both available (204.0315SM)

Add

204.2.2.1 Shoulder material shall be crushed rock or crushed gravel.

If both RAP and crushed rock/gravel are called, use 204.2.2.1 through 204.2.4 as noted

Add

204.2.2.1 Shoulder material shall be crushed rock or crushed gravel.

204.2.3.1.1 RAP will be made available under Item 208.

If requested/approved by Construction Branch, replace 204.2.3.3

Replace

204.2.3.3 The RAP shall be processed to have 100% of particles pass the 31.5 mm sieve per ASTM C136, and to have no lumps, clods or other deleterious materials.

Add

204.2.4 Material for driveways shall be crushed rock or crushed gravel.

Page 7 of 68

Page 8: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Add any of the following as needed, numbered as appropriate

Add

204.4.1.1 Approximately t of shoulder material will be required to be placed prior to fine grading the shoulders.

204.4.1.1 The tendered Quantity of crushed gravel or rock material shall be placed on the low shoulders prior to placing the RAP.

204.4.1.1 Approximately _________ t of crushed gravel or rock material shall be placed on the low shoulders prior to placing the RAP.

204.4.1.1 The RAP shoulder material shall be placed such that it extends an equal distance on each side of the roadway.

If a Table is Required

204.4.1.1 Shoulder material shall be placed as indicated in Table 204-A.

Table 204-APlacement of Shoulder Material

Roadway / Section

Quantity in TonnesShoulders Driveways Total

204.4.1.2 The Shoulder material shall be placed at a width of ____ m prior to rounding, per Standard Drawing 204-1.

Note to Designer: Use when Shoulder widths are < 800 mm:

Add

204.4.5.2 When shoulders are less than 800 mm in width, shoulder material shall be compacted to meet the requirements of 936.2.7.

204.4.5.2.1 The Contractor shall establish a rolling pattern using a nuclear gauge or equivalent. Upon completion of the rolling pattern the Contractor shall immediately submit a copy to the Engineer.

Note to Designer: Use when calling Item 262 or 263:

Replace

204.4.6.3 Shoulder material placement operation shall commence within 48 hours of the completion of Partial Depth / Full Depth Recycling.

204.4.6.3.1 Where the difference between the Partial Depth / Full Depth Recycling and the Shoulder exceeds 70 mm, the low shoulders shall be immediately signed as per the Work Area Traffic Control Manual.

Note to Designer: RAP used for Shouldering Material Quantity > 5000 t

Add

204.4.10 The Contractor shall weigh all RAP used for shouldering from stockpile prior to placing on the Roadway.

February 22, 2021

Page 8 of 68

Page 9: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 205 – FINE GRADING - v01.2019

When the pulverized or Aggregate Base surface will be chip sealed

Add

205.4.1.1 The Work shall be carried out immediately prior to the chip seal operation performed by the Owner, in coordination with the schedule of the chip seal crew.

OR

205.4.1.1 The Work shall be carried out immediately prior to the chip seal operation performed under Item 265.

Note to Designer: Include fine grading of shoulders that are to be paved. Use a combination of the statements below as applicable.

When only surface mix is to be placed (on existing or milled pavement):

Add

205.4.1.1 Prior to being paved, the shoulders / ____ shoulder shall be fine graded to be at the same elevation as the top of the adjacent existing / milled Pavement.

When base mix is to be placed (on new work/after milling) and then surface mix

Add

205.4.1.1 Prior to being paved, the shoulders shall be fine graded to be at the same elevation as the top of the abutting Asphalt Concrete Base lift.

Or, if more than one highway will have paved shoulder(s)

205.4.1.1 Prior to being paved, the shoulders on Route __ and the right shoulder of Route ___ shall be fine graded to be at the same elevation as the top of the ________ surface.

If pulverizing and not adding gravel/rock

Add

205.4.1.1 Fine grading shall be carried out following the Work under Item 267.

And when other areas are also to be fine graded, identify them

Add

205.4.1.2 Fine grading shall also be prior to paving culvert replacement areas, frost bump repair areas, and _________________________.

For Paving on a 4-Lane Highway and Interchange

Add

205.4.1.1 Prior to being paved, the right shoulder of the _____ lanes of Route ___ and the ______ ramps shall be fine graded to be at the same elevation as the top of the ___________________ surface.

February 25, 2016

Page 9 of 68

Page 10: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 208 – COLD MILLING - ASPHALT CONCRETE - v03.2019

Note to Designer: Use the following if milling consists of pre-milling before work under Item 262.

Add

208.1.1.1 The Work under this Item will consist of pre-milling the Roadbed prior to Partial Depth Recycling under Item 262 as required to improve cross-slope on tangents and superelevation on curves.

208.4.1.1 The Pavement shall be milled to a uniform cross-slope to depths from 0 to 50 mm maximum at locations as directed by the Engineer.

Note to Designer: Use the statements below, depending on the work required. Use other statements or a table to identify more than one depth or width.

1(a) For Partial Depth Milling – When Milling Within Paved Width

Add

208.4.1.1 The Pavement shall be milled to an average depth of mm and an average width of m.

1(b) Full Depth Milling - When Milling Extends Beyond Paved Width

208.4.1.1 Milling shall be performed to an average depth of ____ mm and an average width of ____ m, which will include ____ m of granular material on each side of the Pavement.

2(a) Full Depth Milling - When Asphalt Core Data Sheet is included

Add

208.4.1.1 The Pavement shall be milled full depth, at the thickness(es) interpreted from the Asphalt Concrete Core Data Sheet(s), and to an average width of ___ m.

2(b) Full Depth Milling - When no Asphalt Core Data Sheet is available

Add

208.4.1.1 The Pavement shall be milled full depth at an estimated average thickness of ___ mm and average width of m.

2(c) Full Depth Milling - In Place: Add the following after 208.4.1.1

208.4.1.2 The RAP from the Work under 208.4.1.1 shall be left in place on the Roadbed, then spread and compacted per Item __ and/or as directed by the Engineer.

3. If a table is required (cite actual width if constant, or range if width varies)

Milling on One Roadway only

Add

208.4.1.1 The Pavement shall be milled as indicated in Table 208-A.

Page 10 of 68

Page 11: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Table 208-ASchedule for Cold Milling Asphalt Concrete

Stations Depth (mm) Width (m)

Additional width of 3.7 m where there is another lane.

Milling on Multiple Roadways

Add

208.4.1.1 The Pavement shall be milled as indicated in Table 208-A.

Table 208-ASchedule for Cold Milling Asphalt Concrete

Locatio Stations Depth (mm) Width (m)

Additional width of 3.7 m where there is an extra lane.

Note to Designer: When guiderail remains in place, use the following:

Add

208.4.3.1.1 All material shall be removed from guide rail and delineators.  Damaged delineators shall be replaced at the Contractors expense.

Replace

208.4.3.2 Included in the Work under this Item, if a vertical cut is milled in the existing Pavement within the Work Area, the Contractor shall immediately construct with hot or warm mixed asphalt concrete a temporary smooth taper, as shown in Standard Drawing 261-1.

Note to Designer: If pre-milling prior to Partial Depth Recycling, use the following:

Replace

208.4.3.4 Before commencing the Work under this Item, the Contractor shall identify cross-slope on tangents and superelevation on curves of the existing Pavement and shall also submit the values of the expected cross-slopes and superelevation on curves prior to milling to the Engineer.

Note to Designer: Use the following when Item 576 is not included in the Contract.

Add

208.4.3.5 The Contractor shall apply temporary pavement markings for the milled surface in accordance with 576.2 and 576.4.

Replace

208.4.5 The Contractor shall provide adequate drainage of water from the cold milled area such that no water ponding shall occur.

Page 11 of 68

Page 12: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Note to Designer: RAP calculation: HRD 20% + 20% stockpile/moisture losses : HRB 35% + 20% stockpile/moisture losses

RAP for HRB/HRD is for use on the contract

208.4.6.2 The Contractor shall stockpile a maximum of XXX t of RAP for use under Item 261, which includes allowances for stockpile and moisture losses.

208.4.6.2.1 After the completion of Item 261, any RAP not incorporated in the mix shall be loaded, weighed and hauled to a location as directed by the Engineer.

208.4.6.2.1.1 Haulage of the RAP not incorporated into the mix will be paid under Item 801.

208.4.6.2.1.2 Stockpiling of the RAP, if required, shall be paid under Item 811.

Note to Designer: Use statements below as applicable.

Add

If all RAP is for use under Item 203 or 204

208.4.6.2 The Contractor shall stockpile all RAP for use under Item 203 / Item 204.

208.4.6.2.1 All RAP shall be processed as per 204.2.3.3.

208.4.6.2 The Contractor shall stockpile all remaining RAP for use under Item 203 / Item 204.

208.4.6.3 All RAP shall be processed as per 204.2.3.3.

208.4.6.3.1 The Contractor shall load and haul from stockpile all remaining RAP, after the shouldering operation is completed, and end dump on __________ Road at an average haul distance of ___ km from the Work Area.

208.4.6.3.2 The Contractor shall notify the Engineer at least 7 days in advance of performing the Work in 208.4.6.3.1.

OR

208.4.6.3.1 The Contractor shall load and haul from stockpile all remaining RAP, after the shouldering operation is completed, and stockpile at the Owner’s __________ Maintenance Depot.

208.4.6.3.2 The Contractor shall notify the Engineer at least 7 days in advance of performing the Work in 208.4.6.3.1.

Note to Designer: If all remaining RAP is to be end dumped

208.4.6.3 The Contractor shall end dump all remaining RAP on __________ Road at an average haul distance of ___ km from the Work Area, and shall notify the Engineer at least 7 Days beforehand.

OR, if all remaining RAP is to be stockpiled

208.4.6.3 The Contractor shall stockpile all remaining RAP at the Owner’s __________ Maintenance Depot and shall notify the Engineer at least 7 days beforehand.

Page 12 of 68

Page 13: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

OR, if some remaining RAP is to be end dumped and some stockpiled

208.4.6.3 The Contractor shall end dump approximately t of RAP on __________ Road at an average haul distance of ___ km from the Work Area.

208.4.6.4 The Contractor shall stockpile all remaining RAP at the Owner’s __________ Maintenance Depot.

208.4.6.5 The Contractor shall notify the Engineer at least 7 days in advance of performing the Work in each of 208.4.6.3 and 208.4.6.4.

Note to Designer: RAP used for Shouldering Material Quantity > 5000 t

Add

208.4.10 The Contractor shall weigh all RAP prior to stockpiling.

Note to Designer: When milling Bridge decks use the following: (Renumber if necessary)

208.4.10 Upon completion of the Bridge deck(s) milling, paving of the Bridge deck(s) shall be completed within 48 hours.

Note to Designer: Use only for Recaps:

Add

208.4.10 The Contractor shall supply any pilot vehicles with operator, and all other labour, Equipment and material required to convoy traffic through or around the Work Area.

February 25, 2021

Page 13 of 68

Page 14: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 210 – SHOULDER RUMBLE STRIPS - v01.2019

Note to Designer: Shoulder rumble strips apply only to four-lane roadways which have at least 0.8 m of the outside shoulder paved full depth. The criteria for their use are detailed in the item.

Add

210.4.2.1 Rumble strips shall be constructed from Station ____ to ____ (_____ bound) and Station _____ to ______ (______ bound).

OR, for multiple locations

210.4.2.1 Rumble strips shall be constructed at the locations indicated in Table 210-1.

Table 210-1Locations of Rumble Strips

____bound Stations ____bound Stations

December 2, 2010

Page 14 of 68

Page 15: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 259 – BITUMINOUS TACK COAT - v01.2019

Add

259.1.2 Tack Coat shall be a non-tracking emulsion.

Note to Designer: Choose the applicable clause below:

Add

259.1.2.1 Tack shall be applied on the existing asphalt surface.

OR

259.1.2.1 Tack Coat shall be applied on milled asphalt concrete surface.

OR

259.1.2.1 Tack Coat shall be applied on milled asphalt concrete surface and between lifts of newly placed asphalt concrete.

OR

259.1.2.1 Tack Coat shall be applied on Partial Depth Recycling surface.

OR

259.1.2.1 Tack Coat shall be applied on Partial Depth Recycling surface and between lifts of newly placed asphalt concrete.

Delete

259.2.2

Replace

259.2.3 Non-tracking emulsion shall meet the requirements of Table 259-1.

259.2.3.1 Non-tracking emulsion may be applied in dilute or concentrate form.

Add

259.2.3.1.1 When non-tracking emulsion is applied in dilute form, it shall be diluted with 40% water.

259.2.3.1.2 Dilution of the emulsion shall be permitted at the terminal only.

Replace

259.3.2 The Contractor shall submit, the manufacturer’s certification that the materials supplied meets the specified requirements as detailed in the Contract Documents.

Add

259.3.3 The Contractor shall submit, at the time of delivery to the Work Area, the delivery slip for each load of bituminous tack coat.

Page 15 of 68

Page 16: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Note to Designer: Use when there is Microsurfacing Only – No Paving

Add

259.4.1.1 The Work shall be carried out prior to microsurfacing.

Note to Designer: Use when there is Microsurfacing in Some Areas and Paving in Others

Add

259.4.1.1 The Work shall be carried out on the milled areas prior to paving, and on all areas to be microsurfaced.

Add

259.4.5.2 Bituminous tack coat shall only be applied when the temperature of the surface to be treated is a minimum of 0°C.

259.4.7.1 Non-tracking emulsion (Dilute) shall be applied at a minimum rate of 0.40 L/m2.

259.4.7.2 Non-tracking emulsion (Concentrate) shall be applied at a minimum rate of 0.24 L/m2.

259.4.9.1 Construction Equipment shall not be permitted on freshly applied bituminous tack coat until such time that is has been allowed to cure as approved by the Engineer.

259.4.11 After September 15th, Non-tracking emulsion shall not be diluted with water.

January 17, 2020

Page 16 of 68

Page 17: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 260 – ASPHALT CONCRETE – METHOD SPECIFICATION - v01.2019

260.1 DESCRIPTION

260.1.1 This Item consists of the supply and placement of hot mix asphalt concrete and warm mix asphalt concrete.

260.1.2 The asphalt concrete shall be identified by the following mix designations:

260.1.2.1 Hot mixed asphalt concrete base mix – B.

260.1.2.2 Hot mixed asphalt concrete base/surface mix – C.

260.1.2.3 Hot mixed asphalt concrete surface mix – D.

260.1.2.4 Warm mixed asphalt concrete base mix – WMA-B.

260.1.2.5 Warm mixed asphalt concrete base/surface mix – WMA-C.

260.1.2.6 Warm mixed asphalt concrete surface mix – WMA-D.

260.2 MATERIALS

260.2 .1 Material Properties

260.2.1.1 Asphalt Binder

260.2.1.1.1 Asphalt binder shall be supplied by the Contractor.

260.2.1.1.2 The asphalt binder grade shall be as specified in the Contract Documents.

260.2.1.1.3 Performance Grade (PG) asphalt binder shall meet the requirement of AASHTO

260.2.1.2 Coarse Aggregate

260.2.1.2.1 Coarse aggregate shall be supplied by the Contractor.

260.2.1.2.2 The coarse aggregate shall be prepared by crushing rock or gravel and shall consist of hard, sound, durable particles, free from adherent coatings, shale, clay, loam, schist and other soft or disintegrated pieces, or other deleterious substances.

260.2.1.2.3 Coarse aggregate is the portion retained on the 4.75 mm sieve, tested in accordance with ASTM C136, and shall meet the physical requirements of Table 260-1.

Page 17 of 68

Page 18: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Table 260-1Superpave Asphalt Concrete Mix Requirements

Sieve Size Type B/WMA-B Type C/WMA-C Type D/WMA-DASTM Designation % (by mass) Passing Each Sieve

Coarse Aggregate 25.0 mm 100.0 - -19.0 mm 84.0-98.0 - -16.0 mm 72.0-94.0 100.0 -12.5 mm 60.0-87.0 88.0-98.0 100.0 9.5 mm 51.0-75.0 68.0-90.0 76.0-98.0 6.3 mm 41.0-66.0 54.0-77.0 60.0-84.0

Fine Aggregate 4.75 mm 34.0-60.0 46.0-69.0 52.0-70.02.36 mm 22.0-50.0 28.0-58.0 36.0-65.01.18 mm 12.0-42.0 20.0-50.0 25.0-55.0 600 µm 6.0-32.0 13.0-40.0 16.0-44.0 300 µm 3.0-20.0 7.0-27.0 8.0-26.0 150 µm 2.0-8.0 3.0-10.0 4.0-12.0 75 µm 2.0-6.0 2.0-6.0 2.0-6.0

Physical Requirements For Asphalt ConcreteAir Voids % 3.0-5.0 3.0-5.0 3.0-5.0VMA % (min) 13.5 14.5 15.5Voids Filled with Asphalt % 70.0-75.0 70.0-75.0 70.0-77.0TSR (Average of Conditioned & Freeze/Thaw TSR values) %(min) ASTM D4867

80.0 80.0 80.0

Dust to Binder Ratio 0.6-1.2 0.6-1.2 0.6-1.2

Physical Requirements For Coarse AggregateFreeze/Thaw % (max) DTI Method

0.3 to < 3 million Design ESALs≥ 3 million Design ESALs

16.014.0

14.012.0

14.012.0

Micro-Deval %(max) MTO LS - 6180.3 to < 3 million Design ESALs

≥ 3 million Design ESALs20.018.0

16.015.0

16.015.0

Petrographic No.(max)* MTO LS - 6090.3 to < 3 million Design ESALs

≥ 3 million Design ESALs250230

200180

200180

Flat & Elongated Particle % (max @4:1) DTI Method

0.3 to < 3 million Design ESALs≥ 3 million Design ESALs

25.020.0

20.015.0

20.015.0

Crushed Particles DTI Method0.3 to < 3 million Design ESALs

≥ 3 million Design ESALs (min % by wt., one face) ≥ 3 million Design ESALs (min % by wt., two face)

609580

709580

709580

Absorption %(max) ASTM C 127 1.50 1.50 1.50Note: Not mandatory, the Owner reserves the right to obtain a Petrographic No.

Physical Requirements For Fine Aggregate Type B/WMA-B Type C/WMA-C Type D/WMA-DMicro-Deval % (max) MTO LS - 619

0.3 to < 3 million Design ESALs≥ 3 million Design ESALs

22.020.0

18.017.0

18.017.0

Uncompacted Void Content % (min) ASTM C1252 45.0 45.0 45.0Note: The allowable Micro-Deval surface Fine Aggregate shall be Max % Loss=19.0, if the Micro-Deval

on Coarse Aggregate is ≤12.0, provided that the Coarse Aggregate is from the same source.

260.2.1.2.4 For 3 million Design ESALs, coarse aggregate may be produced from pit run gravel by crushing the fraction retained on the 31.5 mm sieve, provided that no more than 10% of the retained material passes the 31.5 mm sieve, as determined by ASTM C136 and C117.

260.2.1.2.5 Coarse aggregate may also be accepted or rejected on the basis of past performance.

Page 18 of 68

Page 19: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.2.1.3 Fine Aggregate

260.2.1.3.1 Fine aggregate shall be supplied by the Contractor.

260.2.1.3.2 Fine aggregate shall be prepared by crushing rock or gravel or screening a manufactured sand and shall consist of hard, sound, durable particles free from adherent coatings, shale, clay, loam, schist and other soft or disintegrated pieces, or other deleterious substances.

260.2.1.3.3 Fine aggregate shall be the portion passing the 4.75 mm sieve, when tested in accordance with ASTM C117 and C136, and shall meet the physical requirements in Table 260-1.

260.2.1.3.4 For 3 million Design ESALs, fine aggregate may be produced from pit run gravel by crushing the fraction retained on the 6.3 mm sieve, provided that no more than 5% of the retained material passes the 6.3 mm sieve, as determined by ASTM C136 and C117.

260.2.1.3.4.1 Material produced as per 260.2.1.2.4 and passing the 4.75 mm sieve may be used as fine aggregate.

260.2.1.3.5 Fine aggregate may also be accepted or rejected on the basis of past performance.

260.2.1.4 Blending Sand

260.2.1.4.1 Blending sand shall be supplied by the Contractor.

260.2.1.4.2 Blending sand shall be used to obtain acceptable physical asphalt concrete mix properties as outlined in Table 260-1 and the source shall be approved by the Engineer before the material is incorporated into the asphalt concrete mix.

260.2.1.4.3 The maximum mass of blending sand to be used in the total asphalt concrete mix shall not exceed 10% of the total mass.

260.2.1.4.4 Blending sand shall have 100% passing the 9.5 mm sieve prior to the introduction into the cold feed at the plant.

260.2.1.5 Anti-stripping Admixtures

260.2.1.5.1 Anti-stripping admixtures shall be supplied by the Contractor.

260.2.1.5.1.1 The requirement for an anti-stripping admixture is determined at the asphalt concrete mix design stage.

260.2.1.5.1.2 The Owner has approved the anti-stripping admixtures listed in Table 260-2 for use in the Work.

Table 260-2Approved Anti-stripping Admixtures

ProductRedicote 82-S

Redicote C 3082Redicote C-2914Rediset LQ-1102

AD-here LOF 65-00AD-here 7700

Pave Bond T LiteTravcor 4505

Innovalt WEvotherm 3G

Cecabase RT 2N1Page 19 of 68

Page 20: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.2.1.5.2 The type and dosage of all asphalt binder anti-stripping admixtures shall be noted on the delivery slip.

260.2.1.6 WMA Materials

260.2.1.6.1 The Contractor shall supply all materials required for production of WMA.

260.2.1.6.2 The Contractor shall identify a facility to produce the WMA mix in accordance with the suppliers’ instructions for the use of their materials.

260.2.1.6.3 The Contractor shall obtain from the suppliers all information required for the proper preparation, handling, storage and use of their materials.

260.2.1.6.4 Other WMA materials and the mix composition shall be as specified for conventional mixes.

260.2.1.6.5 The Engineer has approved the following Warm Mix Technologies listed below for use in the Work:Evotherm 3G Sonne Warmmix Evotherm DAT Cecabase RTAdvera ALmix Foaming SystemsGencor Ultrafoam GX Meeker Foaming SystemsAstec Double Barrel Green Foaming Rediset LQCecabase RT 2N1

260.2.2 Production of Aggregates

260.2.2.1 Grading Requirements

260.2.2.1.1 Pit run gravel or quarried rock shall be crushed and separated into coarse and fine aggregates.

260.2.2.2 Washed Aggregates

260.2.2.2.1 Washed materials or materials excavated from underwater shall be stored for at least 24 hours to allow free water to drain from the aggregate and to allow the material to attain a uniform moisture content.

260.2.2.3 Blending Aggregates

260.2.2.3.1 Blending of aggregates shall be allowed only to meet the grading requirements and/or to increase the percentage of crushed particles.

260.2.2.3.2 Blending shall be performed at the asphalt plant cold feed units to produce a consistently graded product.

260.2.3 Composition of Asphalt Concrete Mix

260.2.3.1 Asphalt Binder Content

260.2.3.1.1 For the purpose of establishing the Unit Price for asphalt concrete the Bidder shall assume an asphalt binder content for the asphalt concrete mix as follows:

260.2.3.1.1.1 Asphalt concrete “B”: 4.8% of the total specified tonnage.

260.2.3.1.1.2 Asphalt concrete “C”: 5.7% of the total specified tonnage.

260.2.3.1.1.3 Asphalt concrete “D”: 6.0 % of the total specified tonnage.

260.2.3.1.1.4 Asphalt concrete “WMA-B”:4.8% of the total specified tonnage.

260.2.3.1.1.5 Asphalt concrete “WMA-C”:5.7% of the total specified tonnage.

260.2.3.1.1.6 Asphalt concrete “WMA-D”:6.0% of the total specified tonnage.Page 20 of 68

Page 21: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.2.3.2 Mix Design

260.2.3.2.1 Responsibility for Design Mix Formula

260.2.3.2.1.1 Preparation and submission of the asphalt Design Mix Formula (DMF) for the Owner’s approval is the responsibility of the Contractor.

260.2.3.2.1.1.1 The Contractor shall use Professional Engineering services and a qualified testing Laboratory to assess the aggregate materials proposed for use and to carry out the design of the asphalt concrete mix.

260.2.3.2.2 Requirements for Design Mix Formula

260.2.3.2.2.1 The Design Mix Formula is the Laboratory determination of the precise proportions of asphalt binder and aggregates to be blended together to meet the requirements in Table 260-1.

260.2.3.2.2.1.1 The asphalt concrete mix design shall follow AASHTO R35 Standard Practice for Superpave Volumetric Design for Hot-Mix Asphalt (HMA), AASHTO R30-02 Standard Practice for Mixture Conditioning of Hot-Mix Asphalt (HMA) and AASHTO T312 Standard Method for Preparing and Determining the density of Hot-Mix Asphalt (HMA) specimens by means of Superpave Gyratory Compactor.

260.2.3.2.3 Approval of Design Mix Formula / Aggregate Source Approval

260.2.3.2.3.1 All submissions shall include the Contract number.

260.2.3.2.3.2 The material samples shall be tagged and indicate the Contract number, the location of the source, pit/quarry ID number as indicated by the Engineer, the sample location, and the type/size of the material.

260.2.3.2.3.2.1 Sampling of the aggregates for the DMF/aggregate source approval for the asphalt concrete mix production for the year shall not be undertaken until:

260.2.3.2.3.2.1.1 At least 30% of each aggregate type is in stockpile, when the tendered Quantity for the mix designation is less than 10 000 t; or

260.2.3.2.3.2.1.2 At least 2 000 t of each aggregate type is in stockpile, when the tendered Quantity for the mix designation exceeds 10 000 t.

260.2.3.2.3.2.2 Sampling of the aggregate shall be done by the Contractor in the presence of the Engineer and delivered to the Owner’s Central Laboratory in Fredericton, during normal working hours.

260.2.3.2.3.3 The Contractor shall submit the DMF including the following information/materials to the Engineer for approval at a location(s) designated by the Engineer.

260.2.3.2.3.3.1 A list of all constituent materials, including aggregate source(s), blending sand source(s), asphalt binder source(s) and anti-stripping admixture source(s).

260.2.3.2.3.3.2 The average gradation of each aggregate to be used in the asphalt concrete mix.

260.2.3.2.3.3.3 The percentage by mass of each aggregate (including blending sand) to be used in the asphalt concrete mix.

260.2.3.2.3.3.4 The asphalt concrete mix design gradation of the combined aggregate (including blending sand).

260.2.3.2.3.3.5 Other characteristics of the combined aggregate specified in Table 260-1.Page 21 of 68

Page 22: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.2.3.2.3.3.6 All Superpave mix design characteristics, including bulk relative density specimen mass, graphs used in arriving at the final asphalt concrete mix design, the bulk relative density of each individual material and the combined aggregates, and the asphalt absorption of the combined aggregates.

260.2.3.2.3.3.7 Samples of the aggregate: (8)-18 kg samples of coarse aggregate, (10)-18 kg samples of fine aggregate, (2)-18 kg samples of blending sand, and 0.5 L of anti-stripping admixture, if necessary.

260.2.3.2.3.3.8 A sample of the asphalt binder (4 L/mix).

260.2.3.2.3.3.9 In order to calibrate the ignition oven, additional samples are required: (3)-18 kg samples of coarse aggregate, (3)-18 kg samples of fine aggregate, (1)-18 kg sample of blending sand, and 3 L/mix of asphalt binder, shall be required to be delivered to a lab designated by the Engineer.

260.2.3.2.3.4 The Engineer shall require up to 8 Days from the time of receipt of the DMF, for evaluation by the Owner’s Laboratory.

260.2.3.2.3.4.1 The evaluation period shall include verification of the asphalt concrete mix design, moisture sensitivity testing, and verification of the bulk relative densities of the coarse and fine aggregates and blending sand(s).

260.2.3.2.3.4.1.1 In case of discrepancy in the bulk relative density values of the aggregates or blending sand(s), the Engineer's results shall prevail.

260.2.3.2.3.5 If the DMF does not meet the requirements of Table 260-1 it shall be rejected.

260.2.3.2.3.5.1 The Engineer shall provide a written explanation to the Contractor that details why the DMF failed.

260.2.3.2.3.5.2 The Contractor shall then provide another complete DMF and re-submit it to the Engineer for approval.

260.2.3.2.3.6 The Engineer shall not accept any asphalt concrete mix produced prior to the Contractor receiving written approval of the DMF from the Engineer.

260.2.3.2.3.7 Once the DMF has been approved, the Engineer shall prepare samples of the combined aggregates and a sample of the asphalt binder for calibration of the ignition furnace to be used for the quality assurance.

260.2.3.2.3.7.1 The Engineer shall deliver the calibration samples to the quality assurance Laboratory.

260.2.3.2.3.7.2 The Engineer shall complete calibration of the ignition furnace within 3 Days of approval of the DMF.

260.2.3.2.3.8 The Contractor shall be responsible to pay the Owner’s associated costs if the Contractor submits for evaluation more than one asphalt concrete mix design per Contract conventional mix designation.

260.2.3.2.3.8.1 Testing costs incurred by the Owner shall be charged as per DTI Standard Laboratory Rate Schedule

260.2.3.2.4 Job Mix Formula

260.2.3.2.4.1 The Job Mix Formula (JMF) establishes the single definite percentage for the 4.75 mm and 75 µm sieve fractions of the aggregate and for the asphalt binder that shall produce the desired asphalt concrete mix properties under field conditions.

Page 22 of 68

Page 23: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.2.3.2.4.1.1 The JMF is established by producing one or more trial asphalt concrete mixes using the plant proposed for the Work.

260.2.3.2.4.2 The Design Asphalt Binder Content is the asphalt binder content established by the DMF.

260.2.3.2.4.3 The Approved Asphalt Binder Content is the asphalt binder content determined by the JMF.

260.2.3.2.4.4 The Actual Asphalt Binder Content is the asphalt binder content in the asphalt concrete mix as determined by ignition furnace results.

260.3 SUBMITTALS

260.3.1 The Contractor shall submit, in writing, the proposed source(s) of supply of coarse aggregate and fine aggregate for approval by the Engineer.

260.3.1.1 The Contractor shall be responsible to deliver all samples obtained for testing to the DTI Fredericton, NB Central Laboratory during normal working hours.

260.3.2 The Contractor shall notify the Engineer 3 Days in advance of the commencement of the production of the asphalt concrete mix.

260.3.3 The Contractor shall submit in writing, the proposed supplier of the asphalt binder.

260.3.3.1 The Contractor shall supply, upon request, a sample of the asphalt binder (2 L/mix) and a sample of any proposed admixtures, in a volume proportional to the asphalt binder sample.

260.3.3.2 The Contractor shall supply, upon request, the optimum mixing and compaction temperature, for PG asphalt binders.

260.3.3.3 The Contractor shall submit at the time of delivery to the plant the refinery certification and delivery slip for each tanker load of asphalt binder.

260.3.3.4 If the source of supply of the asphalt binder changes during the Work, the Contractor shall submit in writing, this proposed change prior to using the new asphalt binder supply in the Work.

260.3.4 Other submittals are required for this Item and are contained within the sections applicable to the specific phase of the Work being undertaken.

260.3.5 Submittals are required in accordance with any cross-referenced Item forming part of this Item.

260.4 CONSTRUCTION

260.4.1 General

260.4.1.1 The Contractor shall carry out the Work as indicated in the Contract Documents and/or as specifically directed by the Engineer.

260.4.2 Equipment

260.4.2.1 General

260.4.2.1.1 Equipment shall be on site and available for inspection, testing and approval before paving operations start.

260.4.2.1.2 The Contractor shall provide safe access to the plant and Equipment for purposes pertaining to the Work.

Page 23 of 68

Page 24: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.2.2 Mixing Plant

260.4.2.2.1 The asphalt mixing plant and its components shall meet the requirements of ASTM D995 and the Contract Documents.

260.4.2.3 Asphalt Binder Storage

260.4.2.3.1 Tanks for storage of asphalt binder shall be capable of heating the material and maintaining it within the range of 25°C from the optimum mixing temperature based on the temperature recommended by the asphalt binder supplier.

260.4.2.3.2 Heating shall be by a means such that no flame shall contact the asphalt binder.

260.4.2.4 Cold Bins

260.4.2.4.1 Cold bins shall be divided into not less than three compartments; each equipped with individual gate control to enable accurate and absolute proportioning of each size of cold aggregate.

260.4.2.4.2 Compartment dimensions shall be such as to promote free flow of material with a minimum gate opening of 50 mm.

260.4.2.4.3 An individual compartment shall be provided for each aggregate type (i.e. coarse, fine) and intermingling of aggregates shall not be permitted.

260.4.2.5 Thermometric Equipment

260.4.2.5.1 An armoured thermometer reading from 90°C to 200°C shall be fixed in the asphalt binder feed line near the discharge valve at the mixer unit and in each asphalt binder storage tank.

260.4.2.6 Dust Collectors

260.4.2.6.1 Plants shall be equipped with a Dust collecting system and this system must comply with all environmental regulations including but not limited to those initiated by the Government of Canada, the Province of New Brunswick, and/or municipal and/or local regulatory agencies having jurisdiction.

260.4.2.6.2 Plants equipped with a baghouse dust collection system shall be able to waste or uniformly return all or a portion of the fines as required to meet the ranges and tolerances indicated in Tables 260-1 and 260-3.

260.4.2.7 Safety and Inspection Requirements

260.4.2.7.1 Safe and adequate stairways, ladders and platforms shall be provided for access to trucks, mixer units and other plant units where inspection and sampling are required.

260.4.2.8 Additional Requirements for Batch Mix Plants

260.4.2.8.1 A rotary dryer designed for drying and heating mineral aggregates shall be provided.

260.4.2.8.2 The dryer capacity shall be sufficient to heat aggregates to the required temperatures.

260.4.2.8.3 Plant screens capable of efficient screening of aggregates to sizes required for proportioning each type of asphalt mix shall be provided.

260.4.2.8.3.1 Screens shall be kept clean and in good repair.

Page 24 of 68

Page 25: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.2.8.3.2 Aggregates shall be screened such that the stone portion (retained on the 4.75 mm sieve) is stored separately from the sand portion (passing the 4.75 mm sieve).

260.4.2.8.3.3 Carry-over for any mix, defined as the amount of stone which enters the sand bins and/or the amount of sand which enters the stone bins, in no case shall exceed 20% and shall not vary by more than ±5% from the established value.

260.4.2.8.4 Each plant shall contain a minimum of 2 hot storage bins.

260.4.2.8.4.1 Bins shall be divided into compartments of sufficient size to allow continuous operation of the plant.

260.4.2.8.4.2 Each hot storage bin shall contain a sensing device to indicate, at the control panel, when the aggregate level falls below one-third of the capacity of the bin.

260.4.2.8.4.2.1 When automatic batching controls are in use, batching shall not take place if the level of the aggregate, in any hot bin in use, falls below one third full.

260.4.2.8.4.3 Each compartment shall be provided with an overflow chute of such size and at such location to prevent backing up of material into other compartments.

260.4.2.8.4.4 Gates on hot storage bins shall be constructed to prevent leakage when closed.

260.4.2.8.4.5 Compartments shall be provided with suitable means of obtaining representative test samples as the aggregate is discharged.

260.4.2.8.5 Equipment shall include a means for accurately weighing aggregate from each bin in a weighing box or hopper of ample size to hold a full batch without running over.

260.4.2.8.6 Gates on the hopper shall be constructed to prevent leakage when closed.

260.4.2.8.7 Scales for weighing aggregate shall be accurate to 0.5% and for asphalt binder shall be accurate to 2.0% through the working range.

260.4.2.8.8 After plant set up and prior to batching materials and whenever deemed necessary by the Engineer, batching plant scales shall be tested for accuracy in the presence of the Engineer.

260.4.2.8.9 Satisfactory means shall be provided to deliver the required Quantity of asphalt binder to the mix at the specified temperature.

260.4.2.8.10 Asphalt binder shall be delivered to the mixer in a thin uniform sheet or in multiple streams over full length or width of mixer.

260.4.2.8.11 All plants shall be equipped with a recording thermometer or pyrometer to record the temperature of the aggregate at the drier discharge chute.

260.4.2.8.12 Plant shall include a batch mixer capable of producing a consistent and homogeneous mix.

260.4.2.8.12.1 The mixer shall be constructed to prevent leakage of contents until batch is discharged.

260.4.2.8.12.2 The mixer gate shall be equipped with a timing lock which shall lock the gate until the specified mixing time has elapsed.

260.4.2.9 Additional Requirements for Drum Mix Plants

260.4.2.9.1 Each cold feed bin shall have a variable speed belt feeder as well as an adjustable gate.

Page 25 of 68

Page 26: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.2.9.2 Plant control shall be such that aggregate feed shall have both individual and total proportional control.

260.4.2.9.2.1 Monitors indicating individual cold feed bin feeder speeds shall be required.

260.4.2.9.3 A means of warning the plant operator shall be provided on each aggregate bin so the flow of aggregate and asphalt binder can be stopped if the material from any aggregate bin should stop flowing.

260.4.2.9.4 Screens shall be installed on the conveyor system to prevent oversized materials from entering the drum.

260.4.2.9.5 The conveyor belt with a load cell shall be equipped with a belt cleaner to prevent build-up of material on the belt.

260.4.2.9.6 The total flow of aggregate shall be measured by an electronic weighing system.

260.4.2.9.6.1 The Contractor shall ensure, monitor and maintain the system so that the aggregate flow shall be interlocked with the asphalt pump and corrected for aggregate moisture content so that the proportions of aggregate and asphalt binder entering the mixer remain constant.

260.4.2.9.7 The weighing systems for aggregates and the metering system for asphalt binder shall have provision to enable easy sampling and calibration without having the material enter the drum.

260.4.2.9.7.1 Scales for weighing aggregate shall be accurate to 0.5% and for asphalt binder shall be accurate to 2.0% through the working range.

260.4.2.9.7.2 The asphalt binder system shall have provisions to compensate for fluctuations in temperature and relative density.

260.4.2.9.8 The heating of the asphalt mix shall be controlled to prevent the fracture of the aggregate and damage to the asphalt binder.

260.4.2.9.8.1 The system shall be equipped with automatic burner controls indicating the mix temperature at discharge.

260.4.2.9.8.2 The asphalt binder recovered by extraction from the asphalt mix shall meet the requirements of the Pressure Aging Vessel (PAV) as specified in AASHTO M320, Table 1 - Performance Graded Asphalt Binder Specification.

260.4.2.9.9 The mixing period and temperature shall be such as to produce a consistent and homogeneous mix at the required mix temperature.

260.4.2.9.10 The method used to transfer the mix from the drum mixer to the haulage units shall be designed, constructed and operated so that there shall be no segregation of, damage to or loss of the mix.

260.4.2.10 Surge Bins and Storage Silos

260.4.2.10.1 Surge bins and storage silos, and their components shall be designed so as not to damage or segregate the mix.

260.4.2.10.2 Storage silos equipped with a heating system shall be capable of maintaining the temperature without localized overheating.

260.4.2.10.2.1 Overnight storage in the silos shall not be permitted.

260.4.2.10.3 Surge bins and storage silos shall be equipped with mix level indicators.

Page 26 of 68

Page 27: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.2.10.4 When the plant is in continuous operation, the minimum level of mix in the silo must be maintained above the one-third capacity level.

260.4.2.11 Placing Equipment

260.4.2.11.1 Mechanical self-powered pavers shall be capable of spreading mix true to line, grade and cross-Slope.

260.4.2.11.2 Pavers shall be equipped with hoppers and distributing screws to place mix evenly in front of the screeds.

260.4.2.11.3 Pavers shall be equipped with vibrating screeds and shall be capable of spreading mixes, without segregation and with a smooth and uniform textured surface, to the required thickness and in widths from 3 to 5 m.

260.4.2.11.3.1 Screeds shall be equipped with heaters which are capable of preheating the entire screed and screed extensions.

260.4.2.11.4 The Contractor shall provide a 3 m straight edge with each paver.

260.4.2.11.5 Pavers shall be equipped with automatic screed controls for the control of longitudinal grade and transverse Slope.

260.4.2.11.5.1 The longitudinal grade control shall be equipped to operate from either side of the paver and be capable of providing longitudinal grade control as well as matching longitudinal joints.

260.4.2.11.5.2 The Contractor shall use a minimum 12 m ski/floating beam or an approved equivalent for longitudinal grade control.

260.4.2.11.5.2.1 A joint matching shoe may be used to control longitudinal grade of subsequent mats placed adjacent to the original mat.

260.4.2.11.5.3 A calibrated Slope indicator shall be installed in a readily visible location on each paver.

260.4.2.11.6 Longitudinal grade control shall be used on all lifts.

260.4.2.11.7 Vibrating hydraulic screed extensions and vibrating bolt-on screed extensions shall be used in placing mat widths greater than 3 m.

260.4.2.11.7.1 Hydraulic strike-off extensions are only acceptable when laying mats of irregular widths outside of the driving Lanes.

260.4.2.11.7.2 Screed cut off shoes may be used when placing widths less than 3 m.

260.4.2.12 Compaction Equipment

260.4.2.12.1 All rollers shall be of types specifically designed for asphalt compaction.

260.4.2.12.2 Rollers shall be in good condition and capable of reversing without backlash.

260.4.2.12.3 Steel wheeled rollers shall be equipped with a means of supplying a controlled flow of water to the wheels to prevent adhesion of the asphalt mix.

260.4.2.12.4 Pneumatic-tired rollers shall be self-propelled with a mechanical means of adjusting the tire inflation pressure.

260.4.2.12.5 All rollers with rubber tires shall be equipped with a means to prevent the asphalt mix from adhering to the rubber tires.

260.4.2.12.5.1 Hydrocarbon fuels or solvents shall not be used.

Page 27 of 68

Page 28: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.2.12.6 Compaction Equipment shall consist of at least one of each of the following:

260.4.2.12.6.1 Vibratory roller

260.4.2.12.6.2 Pneumatic tire roller

260.4.2.12.6.2.1 A combination steel-drum vibratory/pneumatic tire roller may be used in place of the vibratory and pneumatic rollers.

260.4.2.12.6.2.2 Paving in echelon on the driving lanes shall require the use of two pneumatic-tired rollers.

260.4.2.12.6.3 Steel-drum tandem finish roller

260.4.2.12.6.3.1 Use of a steel-drum finish roller on base courses shall be optional.

260.4.2.13 Material Transfer Vehicle (MTV)

260.4.2.13.1 Material transfer vehicles shall be self-propelled Equipment capable of transferring asphalt concrete from the hauling equipment into the paver, and shall have the following characteristics:

260.4.2.13.1.1 Minimum storage capacity of 20 t;

260.4.2.13.1.2 A conveyor system to transfer asphalt concrete from the hauling equipment to the paver hopper insert; and

260.4.2.13.1.3 An auger system in the MTV or paddle mixers in the hopper insert to remix the asphalt concrete prior to discharge from the hopper insert.

260.4.2.13.2 The Contractor has the option of using a material transfer vehicle for the placement of all asphalt concrete, with compensation per 260.5.4 herein.

260.4.3 Production and Placement of Asphalt Concrete Mix

260.4.3.1 Handling and Stockpiling Aggregates

260.4.3.1.1 The coarse aggregate, fine aggregate and blending sand shall each be stockpiled separately.

260.4.3.1.2 Stockpiles shall be placed on a level, well drained base and constructed in such a manner that segregation and contamination does not occur.

260.4.3.1.3 Segregated or contaminated stockpiles shall not be incorporated into the Work.

260.4.3.1.4 Production of asphalt concrete shall not commence until all of the aggregate types are produced and in stockpile, unless specifically designated otherwise in writing by the Engineer.

260.4.3.1.5 Aggregates shall be loaded into cold feed bins so as to prevent the intermixing of separate sizes.

260.4.3.1.6 Mixing of materials or loading of more than one type of material into a single bin shall not be permitted.

260.4.3.2 Physical Requirements for Asphalt Concrete

260.4.3.2.1 Once the JMF has been designated by the Engineer, the Contractor shall produce an asphalt concrete mix to the mix control tolerances as shown in Tables 260-1 and 260-3.

Page 28 of 68

Page 29: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Table 260-3Acceptance Criteria

Test Properties CriteriaAir Voids 2.50% – 5.00%Asphalt Binder Content JMF ± 0.40Percent Passing 4.75 mm Sieve JMF ± 6.0Percent Passing 75 µm Sieve JMF ± 1.0

260.4.3.2.2 For the plant mix, the TSR shall meet the requirements of Table 260-1.

260.4.3.3 Plant Calibration and Trial Mix

260.4.3.3.1 The Contractor shall provide to the Engineer a copy of the plant calibration.

260.4.3.3.2 A trial mix based on the Design Mix Formula shall be prepared by the Contractor for testing by the Engineer and shall only be carried out during normal working hours.

260.4.3.3.3 Continuous placement of asphalt concrete in the Work shall only be permitted after the Engineer is satisfied that the mix properties are in accordance with the applicable specified requirements.

260.4.3.3.4 Trial mixes are the property of the Contractor and shall be placed outside the Work Site, unless otherwise authorized by the Engineer for the purpose of padding or patching.

260.4.3.4 Mixing Times and Temperatures

260.4.3.4.1 For batch plants, the wet mixing time, beginning when the asphalt binder is introduced into the pugmill, shall be 35 seconds, longer if required, to produce a homogeneous mix where all of the aggregate is thoroughly coated with asphalt binder.

260.4.3.4.2 The mixing time for drum mix plants shall be such to produce a homogeneous mix where all of the aggregate is thoroughly coated with asphalt binder.

260.4.3.4.3 Mixing temperature for all types of plants shall be such that the temperature of the asphalt concrete mix when discharged from the mixer unit shall be controlled within ± 5°C of the temperature requirement of the DMF, unless otherwise authorized by the Engineer.

260.4.3.4.3.1 The maximum mixing temperature for Hot Mix Asphalt Concrete shall be 165°C or the temperature recommended by the asphalt binder supplier.

260.4.3.4.3.2 The maximum mixing temperature of the WMA mix shall be as specified by the WMA additive supplier.

260.4.3.4.4 During paving operations the Contractor shall produce only asphalt concrete mix(es) in the Contract.

260.4.3.5 Moisture Content

260.4.3.5.1 The maximum moisture content allowed in the asphalt concrete mix as it is discharged from the mixing unit shall not exceed 0.10%.

260.4.3.5.2 The aggregate shall be dried sufficiently so that visual evidence of moisture, such as, but not limited to: the presence of foaming, slumping or Stripping of the mix, does not occur.

Page 29 of 68

Page 30: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.3.6 Transportation of Asphalt Concrete

260.4.3.6.1 Trucks for transporting asphalt concrete mixes shall have tight, metal boxes free of foreign materials.

260.4.3.6.2 Loads shall be covered with tarpaulins of sufficient size to overhang the fully loaded truck boxes and be tied down on three sides and the front shall be tight to the box of the truck or shielded to prevent air infiltration.

260.4.3.6.3 Truck boxes may be lightly lubricated with an environmentally acceptable release agent, as required, but must be raised and drained after each application and before loading.

260.4.3.6.3.1 Hydrocarbon fuels or solvents shall not be used.

260.4.3.6.4 Tarpaulins shall be rolled back and the asphalt concrete shall be uncovered immediately prior to dumping the load into the material transfer vehicle or the paver.

260.4.3.7 Timing of Paving Operations

260.4.3.7.1 Paving operations shall not commence in the spring until the DTI Weight Restrictions are lifted or continue after the dates specified in Table 260-4 without written permission of the Engineer.

Table 260-4Cut-off Dates for Paving

County Surface mixes Base mixesGloucester, Madawaska,

Restigouche, VictoriaOctober 07 October 22

All others October 22 October 31

260.4.3.7.2 Paving operations shall only be conducted during Daylight hours unless specifically altered by written approval by the Engineer.

260.4.3.7.3 The placement of the new asphalt concrete mix shall commence within 14 Days of the commencement of the cold milling operation and shall continue on a daily basis until the entire milled surface has received a lift of asphalt concrete.

260.4.3.8 Placing Asphalt Concrete

260.4.3.8.1 The Contractor shall place asphalt concrete on a dry surface.

260.4.3.8.1.1 Asphalt concrete shall not be placed under adverse weather conditions of precipitation.

260.4.3.8.1.2 When placing asphalt concrete surface mix, the surface temperature of the material to be overlaid shall be a minimum of 5C.

260.4.3.8.2 When paving on an Aggregate Base, the Aggregate Base must be free from standing water and at least 300 m of prepared base shall be maintained ahead of pavers.

260.4.3.8.3 All prepared surfaces shall be cleaned of loose or foreign material prior to placing of the asphalt concrete.

260.4.3.8.3.1 Milled and aged asphalt concrete surfaces shall be treated with bituminous tack coat in accordance with Item 259 prior to the placing of asphalt concrete.

Page 30 of 68

Page 31: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.3.8.4 Existing approaches to railway crossings and bridges, or areas adjacent to paved surfaces or other Structures, shall be removed to the depths shown on the Contract Documents or as directed by the Engineer.

260.4.3.8.4.1 The removed materials shall be disposed of and the exposed surfaces shall be prepared as identified in the Contract Documents or as directed by the Engineer.

260.4.3.8.5 Contact edges of existing mats and contact faces of curb, gutters, manholes, Sidewalks and Bridge Structures shall receive an application of tack coat before placing the asphalt concrete.

260.4.3.8.6 The temperature of the hot mixed asphalt concrete shall be a minimum of 115°C prior to initial compaction.

260.4.3.8.7 The temperature of the warm mixed asphalt concrete shall be a minimum of 90°C prior to initial compaction.

260.4.3.8.8 The maximum temperature of the hot mixed asphalt concrete mix shall be 165°C or the temperature recommended by the asphalt binder supplier.

260.4.3.8.9 The maximum temperature of the warm mix asphalt concrete behind the screed shall be 125°C.

260.4.3.8.9.1 The allowable maximum temperature of the warm mixed asphalt concrete behind the screed may be increased for Work after October 1st, if approved by the Engineer.

260.4.3.8.9.2 The temperature shall be checked with a calibrated stem thermometer or temperature probe.

260.4.3.8.10 When laying base and/or surface course the alignment of the paver shall be controlled by an approved method, such as following a stringline, placed by the Contractor from an alignment designated by the Engineer.

260.4.3.8.11 Irregularities in alignment and grade along the outside edge of the asphalt concrete shall be corrected by the addition or removal of asphalt concrete before the edge is rolled.

260.4.3.8.12 The cross slope of the asphalt concrete surface shall be within ± 0.5 % (±15 mm when measured over 3 m, perpendicular to the centreline) of the cross slope specified in the Contract Documents or provided by the Engineer.

260.4.3.8.13 In narrow base widening, deep or irregular sections, intersections, turn-outs or driveways where it is impractical to spread and finish asphalt concrete by machine methods, the asphalt concrete shall be spread by hand in accordance with standard hand placement practices.

260.4.3.8.14 Paving of intersections, extra widths and other variations from standard Lane alignment and as defined in the Contract Documents, whether by hand spreading or machine laying, shall be carried out concurrently with the machine laying operation of the regular mat, unless otherwise approved by the Engineer.

260.4.3.8.14.1 Driveway entrances and aprons shall be paved concurrently or after the machine laying operation of the regular mat.

260.4.3.8.15 Spreading of asphalt concrete by hand shall be kept to a minimum and shall be carried out concurrently with the machine laying operation of the regular mat, unless otherwise approved by the Engineer.

Page 31 of 68

Page 32: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.3.8.16 Adjacent asphalt concrete mats, including those placed on shoulders, shall be completed to approximately the same location at the end of each Day's paving.

260.4.3.8.17 For ESAL counts equal to or greater than 3 million, no traffic shall be permitted on the newly placed asphalt concrete until finish rolling is complete, and the finished mat has been permitted to cool to 60°C.

260.4.3.8.17.1 Water required to lower the mat temperature shall be supplied in accordance with Item 191.

260.4.3.8.18 Damage to the mat as a result of contaminant spills from the Contractor's Equipment shall be immediately repaired by the Contractor to the satisfaction of the Engineer.

260.4.3.8.19 All placement, spreading, compacting and rolling shall occur only during Daylight hours, and any loads arriving at the Work Site such that these requirements cannot be met shall be rejected by the Engineer.

260.4.3.8.20 The speed of the paver shall be matched to the production of the asphalt plant to ensure continuous operation of the paver.

260.4.3.9 Padding

260.4.3.9.1 Material for padding shall be the same asphalt concrete mix designation as specified in the Contract Documents.

260.4.3.9.2 Asphalt concrete for padding shall be placed by means of a self-powered paver or by other means approved by the Engineer.

260.4.3.9.3 The compaction Equipment shall be in accordance with 260.4.2.12.

260.4.3.9.3.1 For padding, 260.4.5.1 and 260.4.5.2 shall not apply.

260.4.3.9.3.2 The Contractor shall establish a rolling pattern to achieve the maximum compaction of the asphalt concrete used for padding.

260.4.3.9.4 Padding is intended to be a separate operation and shall not be done as part of the construction of the subsequent lift of asphalt concrete.

260.4.3.10 Joints

260.4.3.10.1 General

260.4.3.10.1.1 Joints shall be constructed to ensure thorough and continuous bond and to provide a smooth riding surface.

260.4.3.10.1.2 Dirt or other foreign and loose material shall be removed from the faces against which joints are to be made.

260.4.3.10.1.3 The Contractor shall remove and dispose of waste materials, resulting from joint construction or other Work activity, outside the Work Site before the end of each week.

260.4.3.10.2 Transverse Construction Joint

260.4.3.10.2.1 A Transverse Construction Joint shall be constructed at the end of each Day’s Work and at other times when paving is halted for a period of time which shall permit the asphalt concrete to cool.

260.4.3.10.2.1.1 Below 115°C for hot mix asphalt concrete.

260.4.3.10.2.1.2 Below 90°C for warm mixed asphalt concrete.Page 32 of 68

Page 33: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.3.10.2.2 Where the asphalt concrete surface and/or base course has been terminated due to the conditions noted in 260.4.3.10.2.1; a smooth 1.5 m long taper shall be paved.

260.4.3.10.2.3 When paving resumes, tapers from surface courses previously laid shall be cut back to full mat thickness to expose fresh, straight vertical surfaces, free from broken or loose material and tacked in accordance with 259.2, 259.3 and 259.4.

260.4.3.10.3 Transverse Key Joint

260.4.3.10.3.1 When the elevation of the new asphalt concrete pavement is higher than the existing Pavement, a transverse key joint shall be constructed per Standard Drawing 260-1 between the existing and new asphalt concrete Pavement, at the beginning and at the paving limits and other locations, as determined by the Engineer.

260.4.3.10.3.1.1 If a transverse key is cut in advance of paving the joint area, the Contractor shall immediately construct with hot mixed asphalt concrete a smooth 1.5 m long taper at the joint area, as shown in Standard Drawing 260-1.

260.4.3.10.3.1.2 Prior to the placement of the asphalt concrete, all transverse key joint surfaces shall be cleaned of loose foreign material and a tack coat applied in accordance with 259.2, 259.3, and 259.4.

260.4.3.10.3.2 When the elevation of the new asphalt concrete Pavement is at the same elevation as the existing Pavement, a straight vertical surface equal to the thickness of the new asphalt Pavement shall be constructed between the new lift of Pavement at the beginning and at the end of the project and other locations where the new Pavement terminates against an existing Pavement.

260.4.3.10.4 Longitudinal Construction Joint

260.4.3.10.4.1 The following requirements shall apply when constructing longitudinal joints.

260.4.3.10.4.1.1 Widths of succeeding individual courses shall be offset by 50-100 mm.

260.4.3.10.4.1.2 Contractors using a one paver operation between May 15th and September 15th may leave an exposed longitudinal joint for up to one-half of the Day's production without an application of tack coat unless otherwise directed by the Engineer.

260.4.3.10.4.1.2.1 Before May 15th and after September 15th the Contractor shall be required to tack the longitudinal joint in accordance with 259.2, 259.3 and 259.4.

260.4.3.10.4.1.3 All longitudinal joints left exposed overnight or which are exposed to moisture shall receive an application of tack coat in accordance with 259.2, 259.3 and 259.4.

260.4.3.10.4.1.4 Longitudinal joints shall not be permitted between the edges of driving Lanes in the final lift of asphalt concrete.

260.4.3.10.4.1.5 Longitudinal joints shall be constructed to ensure that maximum compression under rolling is achieved.

260.4.3.10.4.1.6 On surface courses, the method of making joints shall be such that excess material is not scattered on the surface of the freshly laid mat and all excess material shall be carefully removed.

260.4.3.11 Compaction of Asphalt Concrete

260.4.3.11.1 Quality control testing shall be the responsibility of the Contractor.

Page 33 of 68

Page 34: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.3.11.2 Quality assurance testing shall be carried out in accordance with 260.4.5.

260.4.3.11.3 If damage to Highway components and/or adjacent property is occurring while using vibratory compaction Equipment, the Contractor shall immediately cease using this Equipment and proceed with the Work using static rolling Equipment.

260.4.3.11.4 Along curbs, manholes and similar Structures and places not accessible to full size rollers, the mix shall be compacted with either smaller compactive Equipment, such as vibrating plate tampers, or by hand tampers.

260.4.3.12 Additional Requirements for Bridge Deck Paving

260.4.3.12.1 The Contractor shall place asphalt concrete on the deck waterproofing system in accordance with the waterproofing manufacturer's recommendation and/or procedures.

260.4.3.12.2 The Contractor shall be responsible for all damage to the waterproofing membrane resulting from any aspect of the paving operation.

260.4.3.12.2.1 Should the membrane become damaged, paving operations shall be immediately stopped and repairs made, in accordance with the manufacturer’s instructions, before paving recommences.

260.4.3.12.3 Expansion joints and deck drains shall be protected from damage from Equipment passing over them.

260.4.3.12.3.1 The placing of the asphalt concrete at expansion joints shall be completed as indicated on Standard Drawing 260-2.

260.4.3.12.4 The Contractor shall submit a rolling pattern for the approval of the Engineer.

260.4.3.12.5 A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact pressure on compression roll of at least 3.0 kg/mm of drum width shall be the breakdown roller required for Bridge deck paving.

260.4.3.12.6 The breakdown roller shall be required to run off the deck to stop and turn.

260.4.3.12.7 After breakdown rolling, the mat shall be rolled with a pneumatic tired roller, taking care not to displace the mat when stopping or turning.

260.4.3.12.8 The mat shall be finish rolled to remove any marks.

260.4.3.12.9 For Bridge decks, 260.4.5.1 and 260.4.5.2 shall not apply.

260.4.4 Quality Control Testing

260.4.4.1 Sampling and Testing of Asphalt Concrete Mix

260.4.4.1.1 Asphalt concrete mix production shall be monitored throughout the period of the Work and shall be accepted or rejected on the basis of the testing performed by the Engineer.

260.4.4.1.2 The asphalt concrete mix being produced shall be sampled at a minimum frequency of once per shift.

260.4.4.1.2.1 Shift is defined as one production crew's daily work period.

260.4.4.1.3 The asphalt concrete mix shall be sampled and tested according to DTI Manual: Sampling and Testing of Asphalt Concrete Mix and Pavement Cores, Item 260.

Page 34 of 68

Page 35: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.4.1.4 The Contractor shall be provided a copy of all test results as soon as they are available and shall be notified if any test result indicates that materials are being produced outside of the specified limits.

260.4.4.2 Control of Asphalt Concrete Mix Production

260.4.4.2.1 Once a test result indicates that the material being produced does not meet the specified limits in Tables 260-1 and 260-3 the material shall be handled as follows:

260.4.4.2.1.1 The Engineer may suggest changes to the constituent materials to return test properties within the specified limits.

260.4.4.2.1.2 The Contractor may suggest changes to asphalt plant settings to return test properties within specified limits.

260.4.4.2.2 Regardless of any changes being made, a second mix sample shall be obtained from plant production and tested within one hour of notification that the asphalt concrete mix test results do not meet specified limits.

260.4.4.2.3 If the test result from the second sample indicates that the mix does not meet the specified limits, plant production may be suspended.

260.4.4.2.3.1 Plant production of asphalt concrete mix shall not resume until an acceptable trial mix is produced in accordance with 260.4.3.2 and 260.4.3.3.

260.4.4.2.4 The Engineer may request the asphalt concrete mix be removed if it is determined that asphalt concrete placed is not within the specified limits.

260.4.4.3 Compaction Testing

260.4.4.3.1 The Contractor shall be responsible for quality control testing for the compaction stage of the Work to ensure that the density conforms with the requirements of this Item.

260.4.5 Quality Assurance Testing and Adjustments

260.4.5.1 Asphalt Concrete Density

260.4.5.1.1 Compaction testing shall be based on a Lot average method.

260.4.5.1.2 A Lot is defined as the portion of the Work being considered for acceptance and is further defined as the following:

260.4.5.1.2.1 One Day's production and placement of 500 t or more of asphalt concrete, excluding the quantity used for padding and the quantity of surface mix placed in a single lift on granular Shoulders.

260.4.5.1.2.2 One Day's production and placement of less than 500 t of asphalt concrete, excluding the quantity used for padding and the quantity of surface mixed placed in a single lift on granular Shoulders, shall be evaluated as per 260.4.5.1.2.2.1 and 260.4.5.1.2.2.2.

260.4.5.1.2.2.1 The quantities for that Day and the next Day that meet the criteria of 260.4.5.1.2.1 shall be added together and the total shall be designated as a Lot.

260.4.5.1.2.2.2 If it is the last time the mix is produced meeting these criteria, that Day's quantity shall be included in the previous Day's Lot.

Page 35 of 68

Page 36: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.5.1.2.2.3 A separate Lot shall be established if, in the Engineer’s opinion, conditions of construction indicate that it is likely that a portion of a Day’s production and/or placement shall be significantly different from the remainder of the Day’s production and/or placement.

260.4.5.1.3 Pavement samples shall be taken on the road by coring at stratified random sample locations.

260.4.5.1.4 Sample locations shall be determined by the Engineer using stratified random sample procedures.

260.4.5.1.5 The Lot shall be divided into three segments of approximately equal length.

260.4.5.1.5.1 In each segment a test site shall be located by using random numbers to determine the longitudinal distance from the end of the segment and the lateral distance from the edge of the segment.

260.4.5.1.5.2 In no case shall a lateral distance be less than 0.3 m from the edge of the mat.

260.4.5.1.6 The following areas shall not be cored:

260.4.5.1.6.1 The Shoulder area where only a single lift of asphalt concrete surface mix is placed over granulars, for which the Contractor shall establish a rolling pattern to achieve the maximum compaction of the asphalt concrete.

260.4.5.1.6.2 Areas of obvious surface defects as indicated in 260.4.5.3, which shall be marked and repaired in accordance with 260.4.5.4.

260.4.5.1.6.3 Small areas such as tapers, aprons, Bridge approaches, gores and areas of handwork, and for asphalt mix used for isolated levelling and repair of failed areas.

260.4.5.1.6.4 Padding lifts.

260.4.5.1.7 Cores shall be obtained in accordance with ASTM D5361, within 24 hours after the placement of the Lot.

260.4.5.1.7.1 The maximum may be extended to include Saturdays, Sundays and holidays when applicable.

260.4.5.1.7.2 The Engineer may allow cores to be obtained within 12 hours after asphalt concrete placement.

260.4.5.1.8 The Contractor shall carry out the coring in the presence of the Engineer.

260.4.5.1.8.1 The cores shall be a nominal 100 mm diameter.

260.4.5.1.8.2 The Contractor shall reinstate the Pavement at each core sample location in conjunction with removal of the core by dewatering the core hole and filling it with hot mixed asphalt concrete in 50 mm lifts to the Pavement surface elevation, compacting each lift with 25 blows using a standard compaction device.

260.4.5.1.9 The Engineer shall be responsible for labelling the cores.

260.4.5.1.10 The Contractor shall be responsible for the storage and transportation of the cores to the Owner's Laboratory, within 2 hours of coring, for testing.

260.4.5.1.11 Mat densities shall be tested by the Engineer by core analysis throughout the course of the Work and shall conform to the density requirements indicated in Table 260-5.

Page 36 of 68

Page 37: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.5.1.12 The percent compaction of a Lot shall be determined by comparing the average of the core bulk densities, in accordance with ASTM D2726, with the average theoretical maximum density of the loose mix samples, in accordance with AASHTO T209.

260.4.5.1.13 The Engineer shall provide the Contractor with a copy of the results of acceptance tests within one working Day of their availability.

260.4.5.1.14 The procedure for dealing with an outlier test shall be as follows:

260.4.5.1.14.1 When an individual compaction test result from a Lot is questionable, the validity of the test result in question shall be determined in accordance with ASTM E178, Standard Practice for Dealing with Outlying Observations using a “t” test at a 5 percent significance level.

260.4.5.1.14.1.1 An appeal is required before the outlier test applies.

260.4.5.1.14.2 If the outlier test procedure shows that the challenged test result is valid then the test result shall be used in the calculations.

260.4.5.1.15 The conditions and procedures for an appeal of the Lot test results shall be as follows:

260.4.5.1.15.1 The Contractor may appeal the results of acceptance testing of the density for any rejected or penalized Lot only once.

260.4.5.1.15.2 Appeals shall be for all tests in the Lot.

260.4.5.1.15.3 Any attempt to improve density on the appealed Lot after the Engineer has tested the Lot for acceptance shall void the appeal and the original test results shall apply.

260.4.5.1.15.4 The Contractor shall serve notice of appeal to the Engineer, in writing, within 48 hours of receipt of the test results.

260.4.5.1.15.5 The Contractor shall take additional cores, in accordance with 260.4.5.1, at random locations, as determined by the Engineer, within 48 hours of the Contractor’s notice of appeal and these cores shall be tested by the Engineer.

260.4.5.1.15.6 The Contractor may have a representative present during the period of the testing; the Contractor’s representative shall comment on anything concerning the testing which he does not consider to be valid and the Engineer shall respond to all comments in order to resolve them.

260.4.5.1.15.6.1 Prior to leaving the testing Laboratory any unresolved comments regarding the testing procedures are to be given to the Engineer in writing.

260.4.5.1.15.6.2 Any comments, with respect to the testing procedures, which are made subsequent to the Contractor’s representative leaving the Laboratory, shall not be considered.

260.4.5.1.15.7 The test results from the original Lot shall be combined with the test results of the new samples.

260.4.5.1.15.7.1 A new sample mean for the combined test results shall be determined and this value shall be used for acceptance and Unit Price adjustment.

260.4.5.1.15.7.2 The new mean so obtained shall be binding on both the Contractor and the Owner.

Page 37 of 68

Page 38: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.5.2 Smoothness

260.4.5.2.1 General

260.4.5.2.1.1 The Profile requirements shall be specified in the Contract Documents.

260.4.5.2.1.2 The smoothness of the final lift of newly placed asphalt concrete Pavement shall be checked with a High Speed Profiler as soon as possible after final rolling.

260.4.5.2.1.3 The profile shall be checked along the outside wheel path in accordance with ASTM E950.

260.4.5.2.2 Bump/Dip Profile Requirement

260.4.5.2.2.1 Individual bumps/dips exceeding 8.4 mm as detected by the profiler shall be subject to payment adjustment as described in 260.5.3.

260.4.5.2.2.2 The Bump/Dip profile requirements shall apply to interchange ramps.

260.4.5.3 Surface Defects

260.4.5.3.1 The finished surface of any Pavement course shall have a uniform texture and be free of visible signs of poor workmanship and bumps and/or dips exceeding 3 mm as measured with a 3 m straight edge.

260.4.5.3.2 Any obvious defects, as determined by the Engineer, shall be cause for rejection of the Pavement course.

260.4.5.3.2.1 Multiple defects within a 10 metre section shall be considered as one defect.

260.4.5.3.2.1.1 If a defect is continuous beyond 10 metres it shall be considered as one defect.

260.4.5.3.3 Defects shall include but not necessarily be limited to the following:

260.4.5.3.3.1 Segregated areas;

260.4.5.3.3.2 Ravelling;

260.4.5.3.3.3 Roller marks;

260.4.5.3.3.4 Cracking or tearing;260.4.5.3.3.5 Improper matching of longitudinal and transverse joints;

260.4.5.3.3.6 Tire marks;

260.4.5.3.3.7 Sampling locations not properly reinstated;

260.4.5.3.3.8 Improperly constructed patches;

260.4.5.3.3.9 Contaminant on the mat;

260.4.5.3.3.10 Flushed areas; and

260.4.5.3.3.11 Pneumatic-tired roller pickup.

260.4.5.4 Repairs

260.4.5.4.1 General

Page 38 of 68

Page 39: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.4.5.4.1.1 Repairs to correct surface defects shall be carried out by removal and replacement as per 260.4.5.4.2 or routing and crack sealing. The method of repair shall be determined by the Engineer.

260.4.5.4.1.2 The asphalt concrete used to correct surface defects shall be the same asphalt concrete mix designation as that which is removed.

260.4.5.4.1.2.1 Any asphalt concrete which does not conform to the requirements of this Item shall not be incorporated in the Work.

260.4.5.4.1.3 Clause 260.6.7 shall also apply.

260.4.5.4.2 Removal and Replacement

260.4.5.4.2.1 The full thickness of the appropriate lift of rejected Pavement course shall be removed by cold milling or other means as approved by the Engineer.

260.4.5.4.2.2 All joints shall be tack-coated.

260.4.5.4.2.3 Repaired areas shall be retested for acceptance; those failing shall be rejected and shall require further repair.

260.4.5.4.2.4 Material removed shall become the property of the Contractor, who shall dispose of the material outside the Work Site.

260.5 MEASUREMENT FOR PAYMENT

260.5.1 General

260.5.1.1 The Quantity to be measured for payment shall be the number of tonnes of asphalt concrete placed, in accordance with this Item, subject to payment adjustments.

260.5.2 Payment Adjustment For Density

260.5.2.1 The Unit Price adjustment for density shall be as shown in Table 260-5.

260.5.2.2 The Unit Price adjustments of Table 260-5 shall not apply to asphalt concrete placed as padding, or as a single lift of surface mix on granular shoulders or Bridge decks.

260.5.2.3 If repairs are carried out by removal and replacement of the asphalt concrete, the Unit Price adjustment shall be based on quality assurance carried out on the repaired Lot.

Page 39 of 68

Page 40: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Table 260-5Unit Price Adjustment for Density

% of Theoretical Maximum Relative Density

Unit Price Adjustment

% of Theoretical Maximum

Relative Density

Unit Price Adjustment

Lot Average $ per Tonne Lot Average $ per Tonne93.0 +0.50 90.9 -2.4092.9 +0.40 90.8 -2.8092.8 +0.30 90.7 -3.2092.7 +0.20 90.6 -3.6092.6 +0.10 90.5 -4.0092.5 0.00 90.4 -4.4092.4 -0.10 90.3 -4.8092.3 -0.20 90.2 -5.2092.2 -0.30 90.1 -5.6092.1 -0.40 90.0 -6.0092.0 -0.50 89.9 -7.0091.9 -0.60 89.8 -8.0091.8 -0.70 89.7 -9.0091.7 -0.80 89.6 -10.0091.6 -0.90 89.5 -11.0091.5 -1.00 89.4 -12.0091.4 -1.20 89.3 -13.0091.3 -1.40 89.2 -14.0091.2 -1.60 89.1 -15.0091.1 -1.80 89.0 -16.0091.0 -2.00 <89.0 rejectcontinued next column

260.5.3 Payment Adjustment For Smoothness

260.5.3.1 Individual bumps and dips shall be assessed in accordance with the schedule set out in Table 260-6.

260.5.3.2 For asphalt concrete placed on Bridge decks, the payment adjustments as shown in Table 260-6 shall not apply.

Table 260-6Bump And Dip Penalty Schedule

Bump/Dip Penalty8.5 to 9.4 mm $ 100.009.5 to 10.4 mm $ 200.0010.5 to 11.4 mm $ 400.0011.5 to 12.4 mm $ 600.0012.5 to 13.4 mm $ 800.0013.5 to 14.4 mm $1000.0014.5 to 15.4 mm $1200.0015.5 to 16.4 mm $1400.0016.5 to 17.4 mm $1600.0017.5 to 18.4 mm $1800.00

18.5 mm $2000.00

260.5.4 Payment Adjustment for Use of Material Transfer Vehicle (MTV)

Page 40 of 68

Page 41: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

260.5.4.1 A unit price adjustment of +$3.00/t shall apply to the total quantity of asphalt concrete acceptably placed using a material transfer vehicle in accordance with this Item.

260.6 BASIS OF PAYMENT

260.6.1 Payment for Work under this Item shall include a separate Unit Price for each type of asphalt concrete, as identified under the Contract.

260.6.2 Compensation to the Contractor or the Owner for differences between the asphalt binder content, as determined by ignition furnace results and the assumed asphalt binder content specified in 260.2.3.1 for the total payable tonnage, will be as follows:

260.6.2.1 If the actual asphalt binder content is less than the assumed binder content, the Contractor shall reimburse the Owner using MTO's PG asphalt binder price index for the Month preceding the month of the tender opening.

260.6.2.2 If the actual asphalt binder content is higher than the assumed binder content, the Owner shall reimburse the Contractor the actual invoiced amount supplied by the Contractor.

260.6.2.3 Payments and credits shall be determined upon completion of the Work.

260.6.2.4 The asphalt binder content for each mix type will be calculated by obtaining a weighted average of all the ignition furnace results obtained throughout the contract.

260.6.3 Payment adjustment for change in the PG asphalt binder price shall be calculated in accordance with Item 821.

260.6.4 In the case that the Contractor initiates an appeal under 260.4.5.1.15, the following shall apply:

260.6.4.1 If the new test results after the appeal process indicate that a penalty no longer applies, then the testing costs incurred by the Owner during the appeal procedures for that Lot shall be borne by the Owner.

260.6.4.1.1 Payment to the Contractor shall be made for the sampling costs.

260.6.4.1.2 If the new test results after the appeal process verify that a penalty still applies or rejection remains valid for that Lot, the testing costs incurred by the Owner during the appeal procedure shall be charged, in accordance with Item 810, to the Contractor.

260.6.5 If the Contractor carries out repairs for surface defects, the smoothness shall be retested.

260.6.5.1 The Contractor shall be charged for the smoothness retesting in accordance with Item 810.

260.6.6 For each occurrence that paving is not performed per 260.4.3.7.3, the Contractor shall pay the Owner a penalty of $1000 for each Day after the 14th Day, until paving commences; and $1000 for each Day that paving is not continuous (stopped on any Day for more than 40% of the Contractor’s normal Work hours), until paving resumes.

260.6.6.1 The penalty shall not apply on Sundays or Statutory Holidays, or for Work time lost due to weather.

260.6.7 For each surface defect as per 260.4.5.3, the Contractor shall pay the Owner a penalty of $500.00 per defect.

Page 41 of 68

Page 42: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

January 15, 2019

Page 42 of 68

Page 43: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 261 – ASPHALT CONCRETE – END RESULT SPECIFICATION (ERS) - v03.2019

Note to Designer: Some specifications are required for all 261 work (including structures), though many

are dependent on the work category and other factors. These are various Notes to Designer with instructions on these, depending on the nature of the work, there may be conflicting spec numbering which will require adjusting.

Specifications specific to structures are highlighted in aqua for easier reference. Send structures contract specifications to Construction Branch prior to

finalizing the tender with the following information: asphalt quantity, limits of work for paving, any temporary detours, and asphalt placement.

Pay careful attention to the numbering and cross-reference the Standard Specifications manual – adjustments may be required.

Note to Designer: Chose appropriate Work Category. For Structures, use Work Category 4.

Work Category 1 > 8000 tWork Category 2 3000 t – 8000 tWork Category 3 1500 t – 3000 tWork Category 4 < 1500 t

Consult with Construction Branch before using Work

Category 4Add

261.1.1.5 For this Contract the Work Category will be Work Category 1, Work Category 2, Work Category 3 or Work Category 4.

261.1.1.6 For Route ___, the Design ESALs are ≥ 3 million / < 3 million.

OR

261.1.1.6 For the bridge deck surface or Route #, the Design ESALs are ≥ 3 million/ < 3 million.

Note to Designer: Use for Work Category 4 – Leveling only.

Add

261.1.1.5 For this Contract the Work Category will be Work Category 4 – Leveling.

For Work Category 4

Replace

261.1.2.5.1.3.1 One loose mix sample shall be taken from each lot unless otherwise directed by the Engineer.

Note to Designer: Use for Work Category 4 – Leveling only.

Replace

261.1.2.5.1.3 For Work Category 4 – Leveling – a Lot will be defined as 500 t.

261.1.2.5.1.3.1 One loose mix sample shall be taken from each lot unless otherwise directed by the Engineer.

Page 43 of 68

Page 44: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Table 261-1Superpave Asphalt Concrete Mix Requirements

Sieve Size Type WMA-DASTM Designation % (by mass) Passing Each Sieve

25 mm  12.5 mm 100%9.5 mm  

4.75 mm 66 – 73%

75 µm 4 – 7%

Physical Requirements for Asphalt Concrete (Levelling)

VMA (min) 14.50%Air Voids 3.5% - 4.5%

Physical Requirements for Coarse/Fine Aggregates

Freeze Thaw (max)20%

(Coarse Aggregate)Micro-Deval (max)

20%(Coarse Aggregate)Crushed Particles –

50%One Face (min)(Coarse Aggregates)Micro-Deval (max)

25%(Fine Aggregate)

For Work Category 1 Lot sizes < 2400 tonne. Add the following clauses:

Add

261.1.2.5.1.6 For this Contract, the Lot size for Asphalt Concrete ___ shall be less than 2400 tonne.

For Work Category 2 and 3 Lot sizes < 1500 tonne. Add the following clauses:

Add

261.1.2.5.1.6 For this Contract, the Lot size for Asphalt Concrete ___ shall be less than 1500 tonne.

Note to Designer: For Warm Mix Asphalt Concrete use the following and related paragraphs.

Add

261.2.1.1.2.1 The asphalt binder grade prior to combining with the WMA additive shall be PG _______.

Note to Designer: Consult with Construction to determine binder grade.

Add

261.2.1.1.2.1 The asphalt binder grade shall be PG - .

For Recycled Mixes

Page 44 of 68

Page 45: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Note to Designer: For HRB/WMA-RB:

261.2.1.1.2.1 For Asphalt Concrete HRB/WMA-RB, the asphalt binder grade shall be PG 52S-34.

Note to Designer: For HRD/WMA-RD:

261.2.1.1.2.2 For Asphalt Concrete HRD/WMA-RD, the asphalt binder grade shall be PG 58S-28.

Note to Designer: If calling HRB/WMA-RB and D mixes:

261.2.1.1.2.2 For Asphalt Concrete D, the asphalt binder grade shall be PG _____ - _____.

For Climbing Lanes, etc., where rutting is a serious concern (Per Construction Branch)

261.2.1.1.2.2 The asphalt binder grade for the lane from Station to shall be PG ____________.

Note to Designer: USE IN ALL CONTRACTS

Replace

261.2.1.1.3 Performance Grade (PG) asphalt binder shall meet the requirements of AASHTO M332, Table 1 – Performance Graded Asphalt Binder Specification and Table 261-1A.

Add

Table 261-1AMSCR % Recovery Requirements

Traffic Designation Jnr (@ 3.2 kPa)

% Recovery (min)

S ≤ 4.5 kPa-1 -H ≤ 2.0 kPa-1 30%V ≤ 1.0 kPa-1 35%

E ≤ 0.5 kPa-1 45%≤ 0.25 kPa-1 55%

Note to Designer: On contracts for Restigouche County or parts of Kings/Queens Counties, add the following as applicable:

Add

261.2.1.2.2.1 Coarse aggregate from Restigouche County shall be crushed rock.

261.2.1.2.5.1 Coarse aggregate from Rouse Quarry (Kings County)/ Squaw Cap Quarry / High Country Quarry (Restigouche County) is not acceptable based on past performance.

261.2.1.3.2.1 Fine aggregate from Restigouche County shall be crushed rock.

261.2.1.3.5.1 Fine aggregate from the Rouse Quarry (Kings County)/Squaw Cap Quarry / High Country Quarry (Restigouche County) is not acceptable based on past performance.

Page 45 of 68

Page 46: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Note to Designer: Use the following clauses for Contracts with Recycle Mix only.Check with Construction to determine the correction factor and burn temperature to be used.

Add

261.2.1.5.1.4 The asphalt binder content in the RAP shall be determined with an ignition furnace using a correction factor of ____% at a burn temperature of ____ºC.

261.2.1.5.2 RAP shall be free of contamination and shall be processed in such a manner that all particles pass the 50 mm sieve when tested in accordance with ASTM C136, unless otherwise approved by the Engineer.

Note to Designer: USE IN ALL CONTRACTS

Replace

261.2.1.7.1.2 The Owner has approved the following anti-stripping admixtures listed in Table 261-3A below for use in the Work:

Table 261-3AApproved Anti-Stripping Admixtures

Redicote 82-S Pave Bond T LiteRedicote C-3082 Travcor 4505Redicote C-2914 Innovalt WRediset LQ-1102 Evotherm M1AD-here LOF 65-00 Evotherm P25AD-here 7700 Cecabase RTZydex Zycotherm Road Science WarmGrip N1Zydex Zycotherm SP

261.2.1.8.3 The Owner has approved the following Warm Mix Technologies listed in Table 261-3B below for use in the Work:

Table 261-3BApproved Warm Mix Technologies

Evotherm M1 Evotherm P25Advera Sonne WarmmixGencor Ultraform GX Cecabase RTAstec Double Barrel Green Foaming ALmix Foaming SystemsCecabase RT 2N1 Meeker Foaming SystemsZydex Zycotherm Rediset LQZydex Zycotherm SP Road Science WarmGrip N1

Note to Designer: All Contracts shall be 75 gyrations.

Replace

261.2.2.1.1.1 Asphalt Concrete “B”: 5.0% of the total specified tonnage.

261.2.2.1.1.3 Asphalt Concrete “D”: 6.2% of the total specified tonnage.

261.2.2.1.1.6 Asphalt Concrete “WMA-B”: 5.0% of the total specified tonnage.

261.2.2.1.1.8 Asphalt Concrete “WMA-D”: 6.2% of the total specified tonnage.

AddPage 46 of 68

Page 47: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.2.2.2.1.1.2 Each DMF submission and resubmission shall be dated, stamped, and signed by a Professional Engineer.

261.2.2.2.2.1.2 Mix designs shall be completed by 75 gyrations of the gyratory compactor.

Note to Designer: For recycled mixes for HRB/WMA-RB use the following:

Add

261.2.2.2.2.2.1 The Contractor has the option of placing Asphalt Concrete B/WMA-B in lieu of Asphalt Concrete HRB/WMA-RB at no extra cost to the Owner, and if he chooses that option the following shall apply:

261.2.2.2.2.2.2 The cost of the additional asphalt binder required for the production of Asphalt Concrete B/WMA-B shall be the Contractor’s responsibility.

261.2.2.2.2.2.3 If Asphalt Concrete B/WMA-B is used in lieu of Asphalt Concrete HRB/WMA-RB, the binder grade shall be PG _______.

261.2.2.2.2.2.4 The Contractor shall base his Unit Price on an assumed asphalt binder content of 4.8% of the total tendered Quantity.

261.2.2.2.2.2.5 The Contractor may keep an equivalent amount of RAP, calculated at 30% of the tendered Quantity.

Note to Designer: For recycled mixes for HRD/WMA-RD use the following:

261.2.2.2.2.3.1 The Contractor has the option of placing Asphalt Concrete D/WMA-D in lieu of Asphalt Concrete HRD/WMA-RD at no extra cost to the Owner, and if that option is chosen the following shall apply:

261.2.2.2.2.3.2 The cost of the additional asphalt binder required for the production of Asphalt Concrete D/WMA-D shall be the Contractor’s responsibility.

261.2.2.2.2.3.3 If Asphalt Concrete D/WMA-D is used in lieu of Asphalt Concrete HRD/WMA-RD, the binder grade shall be PG _______.

261.2.2.2.2.3.4 The Contractor shall base the Unit Price on an assumed asphalt binder content of 6.0% of the total tendered Quantity.

261.2.2.2.2.3.5 The Contractor may keep an equivalent amount of RAP, calculated at 15% of the tendered Quantity.

Replace

261.2.2.2.3.3.2 The average gradation of each aggregate to be used in the asphalt concrete mix, including a summary of individual sieve results for each aggregate size.

Add

261.2.2.2.4.3 For each mix type specified in the Contract, the maximum number of JMF submission shall be as follows:

Tendered Quantity of Specified Mix (t)

Maximum Number of JMF Submissions

Page 47 of 68

Page 48: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

0 – 10000 210001 – 15000 315001 – 20000 420001 – 25000 5

> 25000 6

261.2.2.2.4.4 The Contractor shall submit the JMF using NBDTI’s ‘Item 261 - Job Mix Formula Contractor Submission Form’ posted at the following webpage: https://www2.gnb.ca/content/gnb/en/departments/dti/tenders_contracts.html

For Structures Only

Note to Designer: Use for Bridge Projects, if applicable (may not be required for Rehabs):

Add

261.2.3 Polymer modified bitumen strip joint sealer shall be Densoband or Royston Rel-Tape.

Note to Designer: USE IN ALL CONTRACTS

Replace

261.3.3.3 The Contractor shall submit, at the time of delivery to the plant, the manufacturer’s certificate of analysis and the delivery slip for each tanker load of asphalt binder.

Note to Designer: Describe paving work under the heading “261.4.1.2 – Details of the Work,” using the appropriate version for paving on the contract as follows. Be mindful of article numbering and adjust as required.

New Construction – paving on aggregate base or pulverized surface with Asphalt Concrete B & D

Padding or paving on milled surface, and/or paving over culvert replacements

Paving on New Chip Seal with Asphalt Concrete D / WMA-D Paving on a single roadway with Asphalt Concrete B / WMA-B and D /

WMA-D Paving on multiple roadways (variable widths and rates) with Asphalt

Concrete B / WMA-B / D / WMA-D Paving on Structures / Bridge Decks Only Driveways, aprons, crossroads, and railway crossing – Add as applicable

New Construction – paving on aggregate base or pulverized surface with Asphalt Concrete B/WMA-B & D/WMA-D

Add

261.4.1.2 Details of the Work

261.4.1.2.1 Asphalt Concrete B/WMA-B shall be placed ___m wide at a rate of ___ kg/m².

OR

261.4.1.2.1 Asphalt Concrete WMA-B shall be placed___m wide, in two lifts, at a rate of ___ kg/m² each.

OR

Page 48 of 68

Page 49: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.1.2.1 Asphalt Concrete B/WMA-B shall be placed at a rate of ___ kg/m², at the locations and widths indicated in Table 261-A.

OR

261.4.1.2.1 Asphalt Concrete B/WMA-B shall be placed at a rate of ___ kg/m² / in two lifts at a rate of ___ kg/m² each, at locations and widths as indicated in Table 261-A.

Table 261-ASchedule for Placement of Asphalt Concrete B/WMA-B

Station to Station Width (m)

Additional width of 3.7 m where there is an extra lane.

Or for multiple roadways and variable widths and application rates

261.4.1.2.1 Asphalt Concrete ____ shall be placed at locations and widths as indicated in Table 261-A.

Table 261-ASchedule for Placement of Asphalt Concrete _____

Roadway Station to Station Width(m)

Application Rate(kg/m2)

Additional width of 3.7 m where there is an extra lane.

Padding or paving on milled surface, and/or paving over culvert replacements (use articles as applicable; ensure article numbers are in sequence)

Add

261.4.1.2 Details of the Work

261.4.1.2.1 Approximately ____ t of the tendered Quantity of Asphalt Concrete __ is for padding.

OR (If existing pavement is badly distorted)

261.4.1.2.1 The tendered Quantity of Asphalt Concrete __ includes approximate quantities of padding as follows: t on the outside of the driving lanes to improve cross slope, followed by t to improve rideability.

AND (if there are culvert replacement areas)

261.4.1.2.2 In advance of the paving under 261.4.1.2.4, a lift of Asphalt Concrete B / WMA-B shall be placed m wide at a rate of kg/m² over the area of each culvert replacement within Days of its replacement / over the area of each culvert replacement completed by the Owner.

261.4.1.2.2.1 The Work shall include removal and disposal of excess aggregate base from the culvert replacement area, followed by fine grading per 205.4 to lines, grades, slope and tolerance as specified by the Engineer.

AND (if there are areas to be widened)

261.4.1.2.3 The existing Pavement shall be widened with Asphalt Concrete B / WMA-B by placing a slug approximately m wide on each side / the _____side in one lift at a rate of 120 kg/m² / two lifts at a rate of 120 kg/m² each.

Page 49 of 68

Page 50: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.1.2.3.1 Prior to the Paving with Asphalt Concrete D / WMA-D, the removal of the existing Shoulder Material and/or the preparation of the Shoulder Material shall be carried out to the approval of the Engineer.

Paving on New Chip Seal with Asphalt Concrete D / WMA-D

Add

261.4.1.2 Details of the Work

261.4.1.2.1 The Contractor shall schedule his paving operations to allow a minimum of two weeks for the chip seal surface to cure before commencing paving.

OR

261.4.1.2.1 The Contractor shall schedule his paving operations in coordination with the Owner’s chip seal schedule and shall allow a minimum of two weeks for the chip seal surface to cure before commencing paving.

261.4.1.2.2 All excess aggregate shall be swept from the chip seal surface before paving per 261.4.1.2.3.

261.4.1.2.3 Asphalt Concrete WMA-D shall be placed ___ m wide at a rate of ____ kg/m2. Paving on the chip seal surface shall not be performed when ambient temperature is higher than 25°C.

Paving on a single roadway with Asphalt Concrete B / WMA-B and D / WMA-D 261.4.1.2.4 Asphalt Concrete B / WMA-B shall be placed ___ m wide at a rate of ___

kg/m² / in two lifts at a rate of ___ kg/m² each, plus an additional width of 3.7 m where there is an extra lane.

OR

261.4.1.2.4 Asphalt Concrete B / WMA-B shall be placed at a rate of ___ kg/m² / in two lifts at a rate of ___ kg/m² each as indicated in Table 261-A.

Table 261-ASchedule for Placement of Asphalt Concrete B / WMA-B

Station to Station Width (m)

Additional width of 3.7 m where there is an extra lane.

261.4.1.2.5 Asphalt Concrete D/ WMA-D shall be placed ___ m wide at a rate of ___ kg/m², plus an additional width of 3.7 m where there is an extra lane.

OR

261.4.1.2.5 Asphalt Concrete D / WMA-D shall be placed at a rate of ___kg/m² at locations and widths as indicated in Table 261-B.

Table 261-BSchedule of Placement of Asphalt Concrete D / WMA-D

Page 50 of 68

Page 51: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Station to Station Avg. Width (m)

Additional width of 3.7 m where there is an extra lane.

Paving on multiple roadways (variable width and rates) with Asphalt Concrete B / WMA-B / D / WMA-D

261.4.1.2.4 Asphalt Concrete B / WMA-B shall be placed as indicated in Table 261-A.

Table 261-ASchedule for Placement of Asphalt Concrete B / WMA-B

Roadway Station to Station Average Width(m)

Application Rate(kg/m2)

Additional width of 3.7 m where there is an extra lane.

261.4.1.2.5 Asphalt Concrete D / WMA-D shall be placed as indicated in Table 261-B.

Table 261-BSchedule for Placement of Asphalt Concrete D / WMA-D

Roadway Station to Station Average Width(m)

Application Rate(kg/m2)

Additional width of 3.7 m where there is an extra lane.

Paving on Structures / Bridge Decks Only

Add

261.4.1.2 Details of Work

261.4.1.2.1 Asphalt Concrete D/WMA-D for the Bridge Deck shall be placed in one lift resulting in a total compacted thickness of 65 mm.

OR

261.4.1.2.1 Asphalt Concrete D/WMA-D shall be placed ___ m wide at a rate of ___ kg/m².

OR

261.4.1.2.1 Asphalt Concrete D/WMA-D shall be placed at a rate of ___ kg/m² at locations and widths as indicated in Table 261-B.

Table 261-BSchedule for Placement of Asphalt Concrete DWMA-D

Station to Station Width (m)

Additional width of 3.7 m where there is an extra lane.

AND (if paving an existing structure on a recap, do not include for new structures)

Page 51 of 68

Page 52: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.1.3 Bridge Decks shall be paved within 48 hours of completion of the work under Item 208.

Note to Designer: Use for Work Category 4 – Leveling only.

Add

261.4.1.2 Details of the Work

261.4.1.2.1 Approximately _____ tonnes of the tendered Quantity of Asphalt Concrete WMA-D is for pothole patching prior to spot leveling.

261.4.1.2.2 Spot leveling with Asphalt Concrete WMA-D shall be performed on the roads and rate(s) indicated in Table 261-A.

Table 261-ASchedule for Placement of Asphalt Concrete WMA-D

Roadway Station to Station Rate tonnes/kmRoute 000 CS0, 0+000 to 0+000 150Route 000 CS0, 0+000 to 0+000 200

261.4.1.2.5 Spot leveling shall be placed with the use of an asphalt spreader, over the existing road to achieve a straight edge of pavement, an acceptable crown, no visible potholes and smooth turning radii at intersections as directed by the Engineer.

261.4.1.2.5.1 Spot leveling shall be performed at pre-determined locations or as directed by the Engineer. Continuous, full width leveling shall occur only if approved by the Engineer.

261.4.1.2.6 Handwork may be required to patch potholes and large cracks, immediately prior to leveling operations.

261.4.1.2.7 Handwork shall be required at all starts, stops and longitudinal edges of paver patches, localized alligator cracking not covered by the paver, and tapers into asphalt driveways.

261.4.1.2.8 The paver used for leveling may be required to drag over an asphalt or chip seal surface.

261.4.1.2.9 Pavers shall be equipped with hydraulic screed extensions with the capability of varying the cross slope on the outer edge of the driving lane.

Replace

261.4.2.4 Compaction Equipment (Replace entire Sub-Section)

261.4.2.4.1 Compaction Equipment shall consist of at least one of each of the following and shall have a minimum mass of 8 tonnes:

261.4.2.4.1.1 Double drum vibratory roller.

261.4.2.4.1.1.1 A combination steel-drum vibratory/pneumatic-tired roller may be used in place of the vibratory rollers.

261.4.2.4.1.2 Pneumatic-tired roller.

Delete

Page 52 of 68

Page 53: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.2.5

Driveways, aprons, crossroads and railway crossing – Add and re-number as applicable

Add

261.4.1.2.6 Paved aprons are required at approximately ____ driveways and businesses.

261.4.1.2.7 Paved aprons are required at approximately _____ public roads or streets.

261.4.1.2.7.1 Asphalt placed in public roads or streets shall be included as part of the lot.

261.4.1.2.8 The Work shall include any handwork required at railway crossings.

Note to Designer: When paving bridge decks on a recap:

Add

261.4.1.3 Bridge Decks shall be paved within 48 hours of completion of the work under Item 208.

U se for all Work Category 3 and 4 and Work Category 2 < 5000 t on Collectors and Locals (if adding this, must also add 261.5.4 part specs

Add

261.4.2.5.2 The Contractor has the option of using a material transfer vehicle for the placement of all asphalt concrete, with compensation per 261.5.4.

Note to Designer: When there is more than 3000 t of Base, HRB/WMA-RB or WMA-B, use the following clauses:

Add

261.4.3.2.2 The Contractor has the option to place 250 t (maximum) Asphalt Concrete B, WMA-B or HRB/WMA-RB trial within the Work Site.

261.4.3.2.2.1 The Contractor shall identify the trial size before commencing the trial.

261.4.3.2.2.2 The trial shall not be incorporated into a lot.

261.4.3.2.2.3 The Contractor is permitted to do more than one trial within the 250 t allotment.

261.4.3.2.2.4 For each trial, a loose mix sample and a set of three cores shall be obtained and tested by the Owner for acceptance.

261.4.3.2.2.4.1 The Owner shall test for Air Voids and Density only.

261.4.3.2.2.4.2 The Owner shall release the results of the trial mix, once an approved JMF is received.

261.4.3.2.2.5 Acceptance and payment criteria are identified in Table 261-2A.

Table 261-2A

Page 53 of 68

Page 54: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Payment @ Unit Price Acceptance Criteria

100% Payment Air Voids 2.00% - 6.00%, Density >89.5%

50% Payment Air Voids: 1.50% - 1.99% or 6.01% - 6.50%; Density >89.5%

0% Payment Air Voids: 1.00% - 1.49% or 6.51% - 7.00%; Density >89.5%

Reject Air Voids: <1.00% or >7.00% orDensity <89.5%

261.4.3.2.2.6 Results of the trial are binding, and the Contractor is not permitted to appeal.

261.4.3.2.2.7 The Contractor shall stop production at the trial tonnage identified in 261.4.3.2.2.1 and construct a transverse construction joint, per 261.4.3.9.2.

261.4.3.2.2.8 Production shall not commence until a JMF has been received from the Contractor and approved by the Engineer.

If Milled Surface is Paved with Recycled Base Mix (261.HRB/WMA-RB)

Replace

261.4.3.5.3 If Asphalt Concrete B/WMA-B or Asphalt Concrete D/WMA-D is used in lieu of Asphalt Concrete HRB/HRD/WMA-RB/WMA-RD, paving shall commence within 14 Days of the commencement of the cold milling operation, and shall continue on a daily basis until the entire milled surface has received a lift of asphalt concrete.

Note to Designer: Use for Work Category 4 – Leveling only.

Add

261.4.3.6.3.2 Immediately prior to the placement of asphalt concrete, the surface to be leveled shall be swept clean.

Note to Designer: Use when calling warm mix and a binder with traffic designation of ‘H’ or higher:

Replace

261.4.3.6.8          The maximum temperature of the WMA behind the screed shall be 135˚C.

For Structures Only

Note to Designer: Use on bridge decks only, when placing over waterproofing.

Add

261.4.3.6.8.3 On the bridge deck, the maximum temperature of the WMA-D behind the screed shall be adjusted to match the waterproofing manufacturer’s recommendations.

Replace

Page 54 of 68

Page 55: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.3.6.16 For ESAL counts equal to or greater than 3 million, no traffic shall be permitted on newly placed asphalt concrete until the finish rolling is complete, and the surface temperature of the finished mat has been permitted to cool to 60˚C.

261.4.3.6.16.1 Water required to lower the mat temperature shall be supplied in accordance with 191.1, 191.2, 191.3, and 191.4, and shall be included in this Item.

Add

261.4.3.6.20 The Engineer shall approve any locations within the Work Area for cleaning out of all asphalt Equipment which shall be reinstated to the satisfaction of the Engineer upon completion of the Work.

Note to Designer: Use only on long paving jobs:

Add

261.4.3.6.21 The Contractor shall supply any pilot vehicles with operator, and all other labour, Equipment and material required to convoy traffic through or around the Work Area.

Note to Designer: Use only on Full Depth Construction (i.e. pulverizing FDR/New Construction/PDR only if placing 2 lifts of Asphalt etc.): (Discuss with Construction). Do not use when less than 300 m of new construction.

Add

261.4.3.9.4.2 Guarantee

261.4.3.9.4.2.1 The Contractor shall, for a period of two years after completion of the Work, guarantee all longitudinal joints against failure and defects.

261.4.3.9.4.2.2 Failure and defects shall include but not be limited to pot-holing, ravelling and cracking along the joint.

261.4.3.9.4.2.3 Cracking along the joint shall be repaired by routing and crack-sealing using a method, materials and schedule as submitted to and approved by the Engineer.

261.4.3.9.4.2.4 The Contractor shall submit, in writing, his proposed method and schedule for the repair of all other failures and defects, for the Engineer’s approval.

261.4.3.9.4.2.5 The Contractor shall carry out the repairs at his expense in accordance with the approved submissions or as otherwise approved by the Engineer.

For Structures Only

Note to Designer: Use on paving bridge deck projects

Add

261.4.3.11.5.1 The steel-drum tandem roller shall complete a minimum of eight passes. Additional passes may be required as determined by the roller pattern or as directed by the Engineer.

Page 55 of 68

Page 56: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.3.11.7.1 The pneumatic tired roller shall complete a minimum of six passes. Additional passes may be required as determined by the roller pattern or as directed by the Engineer.

261.4.3.11.8.1 The finish roller shall complete a minimum of six passes. Additional passes may be required as determined by the roller pattern or as directed by the Engineer.

261.4.3.11.10 A trial mix based on the DMF shall be prepared by the Contractor and the test results submitted to the Engineer prior to placing asphalt concrete on the bridge deck.

261.4.3.11.10.1 The Engineer may waive the trial mix requirement if the Contractor can demonstrate with recent mix results that the DMF used will produce acceptable test results.

261.4.3.11.11 A pre-paving meeting shall be held immediately prior to paving the bridge deck.

Note to Designer: Use on new bridge structure projects (may not be required for Rehabs)

261.4.3.11.13 Polymer modified bitumen strip joint sealer shall be placed at all asphalt to concrete vertical interfaces and asphalt joints on the bridge deck.

261.4.3.11.13.1 The polymer modified bitumen strip joint sealer shall be installed according to the manufacturers’ recommendations.

Delete

261.4.5.11.1.2

Replace

261.5.2.1.4 For Work Category 4, the UPAs for asphalt concrete are as shown in Table 261-8, 261-9 and 261-13.

Delete

261.5.2.1.4.1

If not calling Item 576 – Construction Traffic Control, add 261.4.3.12

Add

261.4.3.12 Temporary Pavement Markings

261.4.3.12.1 The Owner shall supply Temporary Pavement markings to the Contractor in the form of marking strips or raised markers, for placement as temporary centerline, laneline or edgeline delineation.

261.4.3.12.2 Temporary Pavement markings shall be placed on the same Day as the work is carried out, per Section 3.8 of WATCM, for the paving or milling operations.

261.4.3.12.3 Temporary Pavement markings shall not be placed on a chip seal surface unless otherwise directed by the Engineer.

261.4.3.12.4 The Contractor shall replace damaged or missing markings at the end of the day.

Page 56 of 68

Page 57: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Add

261.4.4.1.2 The Contractor shall submit QC results, including worksheets, for each lot using the NBDTI ‘Item 261 – Test Results QC Contractor Submission form’ posted at the following webpage: https://www2.gnb.ca/content/gnb/en/departments/dti/tenders_contracts.html

261.4.4.1.2.1 The Engineer may accept the Contractor’s worksheets as a substitution to those included in the ‘Item 261 Test Results QC Contractor Submission form’.

Note to designer: Use the following for Work Category 2 contracts.

Replace

261.4.5.3.2 For Work Category 2 all loose mix samples shall be tested for quality assurance.

Delete

261.4.5.3.2.1261.4.5.3.2.2261.4.5.3.2.3

Note to Designer: Use for Work Category 4 – Leveling only.

Replace

261.4.5.4.2 For Work Category 4 – Leveling, the Lot sample shall be tested for asphalt binder content only.

Delete

261.4.5.4.3261.4.5.4.4

Add

261.4.5.6.3 For Work Category 4 – Leveling, loose mix samples shall be taken on the road behind the paver before compaction, or as directed by the Engineer.

261.4.5.6.3.1 The number of loose mix samples shall be in accordance with 261.1.2.5.1.3.1.

Note to Designer: For Work Category 4 when total tonnage is < 50 t

Delete

261.4.5.5

Note to designer: Use the following for Work Category 2 contracts only when the contractor is controlling the rate.

Replace

261.4.5.5.2.2 For Work Category 2, five samples per Lot shall be selected, one from each of five segments of approximately equal length.

Page 57 of 68

Page 58: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Add

261.4.5.5.2.8.4 When placing multiple lifts in the same Day, the Engineer may request that cores be taken prior to placing the second lift.

Note to Designer: For all Work Category 4

Delete

261.4.5.7

Note to Designer: Use one of the following Requirements for Local Class Roadway (Discuss with Construction):

If there are No Smoothness Requirements (“Surface Defects Only”)

Delete

261.4.5.7

If Smoothness Requirement is Bump/Dip Only

Add

261.4.5.7.1.1.1 The only smoothness requirements to be checked on this contract shall be the “Bump/Dip” requirements per 261.4.5.7.3.

For Different Smoothness Requirements on Different Sections of the Contract

Add

261.4.5.7.1.1.1 The smoothness requirements shall be as indicated in Table 261-B.

Table 261-BSmoothness Requirements

Location (Sta. – Sta.) Smoothness RequirementsPer 261.4.5.6.2 IRI Smoothness Category __

Per 261.4.5.6.3 Bump/Dip Profile Requirement

Note to Designer: All Arterial and Collector Class Highways will have an IRI Smoothness Specification (Discuss with Construction). Chose appropriate Category.

Category “A” > 100 km/hCategory “B” 80 – 95 km/hNo Specification < 60 km/h

Add

261.4.5.7.2.1.1.1.1 For Route _, the Roadway shall be classified as a Category _.

Page 58 of 68

Page 59: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

Add

261.4.5.8.1.1.2 The Contractor shall ensure that their asphalt binder storage tank(s) are equipped with a sampling valve.

Note to Designer: If calling Category 1, when thickness is controlled by the Owner, use the following clauses:

Delete

261.4.5.9.2

Replace

261.4.5.9.3 For Work Category 1, the Asphalt Concrete ___ thickness shall be controlled by the owner.

Note to designer: Use the following for Work Category 2 contracts only when the contractor is controlling the rate.

Replace

261.4.5.9.2 For Work Category 1 and Work Category 2, thickness shall be evaluated on a Lot by Lot basis.

261.4.5.9.3 For Work Category 1 and Work Category 2, the Pavement thickness shall be determined from the test results of the cores obtained according to 261.4.5.5.

Delete

261.4.5.9.4

In Table 261-6 Note: 1(c)

Replace

In Table 261-6 Note 2: Specified Thickness for Work Category 1 and Work Category 2

Replace

261.4.5.10 Surface Defects (Replace entire subsection)

261.4.5.10.1 The finished surface of any Pavement course shall have a uniform texture and be free of visible signs of poor workmanship and bumps and/or dips exceeding 3 mm as measured with a 3 m straight edge.

261.4.5.10.2 Any defects, as determined by the Engineer, shall be cause for rejection of the Pavement course.

261.4.5.10.2.1 Multiple defects within a 10 m section shall be considered as one defect, and every 10 m section containing defects shall be counted as a separate defect for penalty adjustments.

261.4.5.10.2.2 A continuous defect shall be considered as one defect to a maximum of 50 m, after which, every 50 m section shall be counted as a separate defect for penalty adjustments.

261.4.5.10.3 Such defects shall include but are not limited to the following:

261.4.5.10.3.1 Segregated areas;261.4.5.10.3.2 Ravelling;

Page 59 of 68

Page 60: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.5.10.3.3 Roller marks;261.4.5.10.3.4 Cracking or tearing;261.4.5.10.3.5 Improper matching of longitudinal and transverse joints;261.4.5.10.3.6 Tire marks;261.4.5.10.3.7 Sampling locations not properly reinstated;261.4.5.10.3.8 Improperly constructed patches;261.4.5.10.3.9 Contaminant spills on the mat;261.4.5.10.3.10 Flushed Areas; 261.4.5.10.3.11 Pneumatic-tired roller pickup;261.4.5.10.3.12 Dust balls.

261.4.5.10.4 If during paving, continuous or reoccurring surface defects have been identified by the Engineer in writing, the Contractor shall be permitted to place a maximum of 500 t of asphalt concrete to correct the identified defects.

261.4.5.10.4.1 If the identified surface defects have not been eliminated within the tonnage specified in 261.4.5.10.4, paving operations shall be suspended immediately.

261.4.5.10.4.1.1 Prior to resuming paving operations, the Contractor shall provide, in writing, a detailed description of what measures will be taken to correct the surface defects, for approval by the Engineer.

261.4.5.10.4.1.2 A test strip of 500 t shall be constructed to demonstrate that the causes of the surface defects have been resolved.

261.4.5.10.4.1.3 The test strip shall be evaluated by the Engineer to determine if paving operations may resume.

261.4.5.10.4.1.3.1 If the test strip is not considered acceptable, the Contractor shall resubmit correction measures, per 261.4.5.10.4.1.1.

261.4.5.10.4.1.3.2 The Engineer may approve a maximum number of 2 test strips within the Work Area, after which the Contractor shall demonstrate corrections at a location outside of the Owner’s Right-of-Way, before paving operations will be permitted to resume.

Note to designer: Use the following for Work Category 2 contracts only when the Contractor is controlling the rate.

Replace

261.4.5.11.5.4 For Work Category 2, if the density of the Lot is appealed the Contractor shall take 5 more cores at random locations as determined by the Engineer. These Cores shall be tested by the Owner.

For Structures Only

Note to Designer:Use for ALL Contracts with an Integral Abutment

Add

261.4.6 Joint Sealing

261.4.6.1 The Contractor shall carry out the Work for sealing the joints at the end of the approach slabs, between the curb and gutter sections, and at the ends of wingwall, as detailed on the Plans and/or as specifically directed by the Engineer.

Page 60 of 68

Page 61: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

261.4.6.2 A transverse groove shall be routed at the end of the approach slabs, as detailed on the Plans to provide a clean, and sound vertical wall along each edge of the groove.

261.4.6.3 The joint sealing material shall be applied according to the manufacturer’s recommendations and/or as specifically directed by the Engineer.

Note to Designer: Use the following when calling a Work Category 2:

Add

261.5.1.1.2 For Work Category 2, the Quantity of asphalt concrete for a Lot shall not exceed that calculated as follows:

[1.10 x (application rate) x (length) x (specified width)] ÷ 1000

Note to Designer: For Work Category 4

Replace

261.5.2.1.4 For Work Category 4, the UPAs for asphalt concrete shown in Table 261-7, 261-8, 261-9 and 261-13 shall be subject to 50% of the values listed.

Replace

261.5.2.2 The UPA as shown in Table 261-7 shall not apply to Shoulder areas with a single lift of asphalt concrete or to Bridge Decks.

U se for all Work Category 3 and 4 and Work Category 2 < 5000 t on Collectors and Locals

Add

261.5.4 Payment Adjustment For Use of Material Transfer Vehicle (MTV)

261.5.4.1 A unit price adjustment of + $3.00/t shall apply to the total quantity of asphalt concrete acceptably placed using a material transfer vehicle in accordance with this Item.

Note to Designer: Use the following to delete Adjustment for Asphalt Binder Price on all contracts with less than 250 tonnes of Asphalt:

Delete

261.6.2261.6.3

For Regular Mixes

Replace

261.6.2.1.1 The maximum amount of asphalt content used in the above calculation shall be the assumed asphalt binder content, specified in 261.2.2.1, plus 0.5 % for Type B/HRB/WMA-B/WMA-RB mixes and 0.3 % for Type C/D/HRD/WMA-RD/WMA-D mixes.

OR

Page 61 of 68

Page 62: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

For Leveling Mixes only

Replace

261.6.2.1.1 The maximum amount of asphalt content used in the above calculation shall be the assumed asphalt binder content, specified in 261.2.2.1, 0.5 % for Type WMA-D mixes.

Note to Designer: Use on Work Category 4 Contracts with > 250 t:

Add

261.6.2.1.7 If ignition furnace results are not available, the Owner shall make the binder adjustment using the Job Mix Formula.

Note to Designer: For Bump/Dip Contracts

Replace

261.6.5 If the Contractor carries out Work to repair Surface Defects per 261.4.5.10, the smoothness shall be retested.

Note to Designer: Use when Contracts have multiple locations:

Add

261.6.6.1 For Contracts that have multiple sections, each section shall be assessed separately, per 261.6.6.

Replace

261.6.7 For each surface defect identified on the final surface lift per 261.4.5.10, the Contractor shall pay the Owner a penalty of $500.00 per defect.

April 21, 2021

Page 62 of 68

Page 63: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 262 – PARTIAL DEPTH RECYCLING - v03.2019

Replace

262.2.4.1 The asphalt binder grade shall be PG 58S-28.

262.2.4.2 Performance Grade (PG) asphalt binder shall meet the requirements of AASHTO M332, Table 1 – Performance Graded Asphalt Binder, and shall contain no anti-foaming agents.

Add

262.3.2.1         The Engineer shall approve the DMF submission before work is permitted to commence under this Item.

262.4.1.2.1 The average width of in-place Partial Depth reclaiming shall be ____ m.

262.4.1.3.1 The recycled cold bituminous mixture shall be spread and compacted to an average width of ____ m.

Note to designer: If the stabilized mat is wider that the existing mat to be recycled, use the following three clauses.

Add

262.4.1.3.2 Removal of the shoulder material 100 + 10 mm deep x ___ m wide each side shall be included in this Item.

262.4.1.3.2.1 Shoulder material shall not be bladed into the ditch.

262.4.1.3.2.2 Material removed from shoulders shall become property of the Contractor and disposed of outside the Work Site.

OR

262.4.1.3.2.2 The Contractor shall load and haul material removed from shoulders to _________ Road/Maintenance Depot at an average haul distance of _______km from the Work Area.

Note to Designer: Use only when the finished mat is >7.4m.

Add

262.4.1.6 The addition of a secondary milling machine, ahead of the recycling train, shall be utilized along the centerline of the road.

February 18, 2021

Page 63 of 68

Page 64: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 263 – FULL DEPTH RECYCLING - v02.2019

Replace

263.2.2.1 The asphalt binder grade shall be PG 58S-28.

263.2.2.2 Performance Grade (PG) asphalt binder shall meet the requirements of AASHTO M332, Table 1 – Performance Graded Asphalt Binder, and shall contain no anti-foaming agents.

Add

263.3.2.1         The Engineer shall approve the DMF submission before work is permitted to commence under this Item.

Replace

263.4.1.2 The existing asphalt concrete and underlying Aggregate Base shall be pulverized to an average width of ____ m and to a combined depth sufficient to satisfy the DMF.

OR

263.4.1.2 The existing asphalt concrete and underlying Aggregate Base shall be pulverized to an average width of 9.0 m, which includes ____m of shoulder material on each side, and to a combined depth sufficient to satisfy DMF.

Add

263.4.1.6 After pulverizing is complete, the Contractor shall stabilize to an average width of _____ m and a minimum depth of 150 mm.

Note to Designer: Use only when the finished mat is >7.4m.

Add

263.4.1.6.1 The addition of a secondary milling machine, ahead of the recycling train, shall be utilized along the centerline joint.

Add

263.4.2.5.1 The pulverized material shall be compacted by means of a vibratory padfoot roller of at least 15 t mass.

Note to Designer: Use on high volume Arterials

Replace

263.4.4.4 Expanded asphalt stabilization shall commence within 7 Days of the commencement of pulverizing and shall continue on a daily basis until the entire pulverized surface has received the expanded asphalt stabilization.

January 26, 2021

Page 64 of 68

Page 65: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 264 – MICROSURFACING - v01.2019

Add

264.4.1.2.1 Microsurfacing shall be placed ___ m wide on the driving lanes only.

264.4.1.3.1 The Work in 264.4.1.3 shall be preceded by a rut/fill application.

February 20, 2011

Page 65 of 68

Page 66: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 265 – CHIP SEAL - v02.2019

Add

265.4.4.7 The Work shall commence within 14 Days of commencement of Work under Item 267.

Replace

265.6.3 For each occurrence that chip sealing is not performed per 265.4.4.7, the Contractor shall pay the Owner a penalty of $1000 for each Day until chip sealing commences; and $1000 for each Day that chip sealing is not continuous (stopped on any Day for more than 40% of the Contractor’s normal work hours), until chip sealing resumes.

April 21, 2021

Page 66 of 68

Page 67: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 267 – PULVERIZING - v02.2019

Note to Designer: If the quantity of pulverizing is too small to warrant the pulverizer (< 2000 m2), use Item 774 (RESHAPING AGGREGATE BASE/SUBBASE) and its Library clauses.

Note to Designer: If the pulverizing is to be performed to a specified width instead of to daylight at the foreslope per the Standard Specifications, use the following:

Add

267.4.1.1 There shall be no work on Structure ___________________.

Replace

267.4.2 The average width of the Work shall be _____ m.

Note to Designer: If soil cement may be present use the following:

Add

267.4.3.1 The depth of pulverizing shall extend to the bottom of the soil cement layer or as directed by the Engineer.

Add

267.4.9 The Contractor shall supply any pilot vehicles with operator, and all other labour, Equipment and material required to convoy traffic through or around the Work Area.

January 26, 2021

Page 67 of 68

Page 68: Item 102 - Grubbingforms.dot.gnb.ca/partspec/design/Division 200.docx · Web view260.4.3.12.5A steel-drum tandem roller, operating in the non-vibratory mode and exerting a contact

ITEM 284 – SHOULDER PROCESSING - v01.2019

If Item 263 Full Depth Recycling is on the Contract

Replace

284.4.1.1 The Work shall be carried out after completion of the Work under Item 263.

If the driving lanes are paved after milling

Replace

284.4.1.1 The Work shall be carried out after placing Asphalt Concrete B on the adjacent driving lanes.

If processing is to a specified width instead of daylighting at the foreslope

Add

284.4.1.2 The average width of the Work shall be m.

Note to Designer: If the shoulders are to be paved after being processed under this Item, call Item 205 for fine grading the shoulders. Use the appropriate Particular Specs wording for Item 205 and the following under this Item:

Replace

284.4.7 After final shaping and compaction, the processed Shoulder shall be at the same elevation as the top of the abutting asphalt concrete surface / Asphalt Concrete B lift and extend at the Slope specified by the Engineer.

Add

284.4.7.1 The processed Shoulder shall be fine graded under Item 205.

December 3, 2010

Page 68 of 68