ITER HCC Introduction
Spencer PitcherDivision Head HCC, Remote Handling, Radwaste
A multinational scientific collaboration without equivalent in history
A large-scale experiment to demonstrate the feasibilityof fusion energy
ITER
Headquarters
CEA Cadarache
Assembly Hall
Cryostat Workshop
Poloidal Field Coil Workshop Tokamak
Power Conversion
Cooling Towers
Cooling Basins
5
Because of the Activation and Contamination – In-Vessel Equipment is
transported to the HCB in automated Casks. These provide confinement
but no shielding.
HCC Functions
7
Hot Cell Building (B21)
• Refurbishment, maintenance and testing of activated and contaminated Tokamak
components
• Storage and maintenance of ex-tokamak equipment (e.g. port cell and interspace
structures, galleries, etc), slightly activated and contaminated
• Maintenance, testing and storage of contaminated remote handling (RH) equipment
• Processing, characterization and storage of Type B (intermediate, long-lived) Waste
• Storage and Processing of effluent, including LOCA waste water
• Processing, characterization and storage of Purely-Tritiated Waste
• Processing, characterization and export of Test Blanket Modules
• Access to the Tokamak Complex for large components and personnel
• Treatment and Disposal of Type A (low level) Solid Waste
• Laboratories for Type A Waste, TCWS and Health and Physics Control
• Treatment and Disposal of very lower level waste (TFA)
Personnel Access Control Building (B24)
• Control access to all Project radiological-controlled areas
• Welfare facilities for personnel working in these areas
• Environmental laboratory
• Control rooms for RH in (1) Tokamak (2) Hot Cell (3) Radwaste
B2
Drain Tanks
Liquid RW Treatment
RH Casks
RH Decontamination
Cask DockingRH Cleaning
RH Workshop
RH Workshop/Storage
RH Lift
RH Blanket
RH DivertorRH NB
Type B P Basket Storage
Hot Lift
Cargo Lift
B1
EPP PPTF
PPTF
PSS
UPP PPTF
RH Storage
RH Storage
RH Lift
PT Storage
Type B TreatmentCargo Lift
Hot Lift
L1
Cask Entrance
Cask DockingCleaning Cell
Refurbishment Cell
Buffer Storage
Barrier Room (L1)
Back-Up Control Room (L1M)
Truck-Bay
Type A Cutting Room
Type B Detritiation Ovens
Type B Volume Reduction
Type B Lab
Cargo Lift
Hot Lift
Personnel
B24 PACB
Personnel Access to TKC
Passage
L2
Type A Processing ADS
ADS
L1 Red Zone Services
L1 Red Zone Services
Labs
L1 Red Zone
Services
L1 Red Zone
Services
Cargo Lift
Cubicles
Cubicles
Cubicles
L3
Labs
Port Cell Equipment
Buffer Storage PT and Type A
Port Cell Equipment
Buffer Storage PT and Type A
Cargo Lift
Services
ADS
HVAC
HVAC
ADS
ADS
13
UKAEA Industry Day
08.10.2020
ITER HCC Procurement Strategy
Magnus GohranHCC Project Leader
UKAEA Industry Day – 08/10/2020
HCC Challenges
14
➢ Lessons Learnt from the Tokamak Complex actively taken into account:
✓ Concurrent design development (building/services/processes)
✓ Staged gate approach
✓ Construction will not commence until Input Data are defined
✓ Process led construction
✓ IO/F4E integrated team
✓ Close collaboration with the Safety Department
➢ Long term schedule/strategy
➢ Industry Feedback
➢ Building solution adaptable to the services and process needs
UKAEA Industry Day – 08/10/2020
HCC Strategic Objectives
15
UKAEA Industry Day – 08/10/2020
High Level Schedule
16
UKAEA Industry Day – 08/10/2020
Execution of the ITER HCC Delivery
17
Based on…
➢ Lessons learned from the Tokamak Construction➢ The fact that there are dual clients to deliver the project➢ The requirement “Design to Cost”➢ Risk mitigation
✓ Both in between companies and clients within the project✓ As well as towards stakeholders
➢ High demand on integration between building, building systems, remote handling and rad waste
➢ FOAK and high complexity
→ A Collaboration Contacting Strategy is proposed for the HCC delivery
UKAEA Industry Day – 08/10/2020
HCC Collaboration strategy
18
Parties to the Collaboration Agreement
a) The IO as nuclear operator and design authority
b) The IO and F4E in two roles: clients and partners (participants)
c) Contractors for the following scopes:✓ Project Integration
o System Engineering, Risk Management, QC, Integration, Engineering Process, Document review and Requirement Management
✓ Radwaste Process Equipment Workso Detailed Design, Manufacturing, Delivery, Installation and Commissioning
✓ Remote Handling System Workso Detailed Design, Manufacturing, Delivery, Installation and Commissioning
✓ Civil Workso Detailed Design, Construction and Commissioning
✓ Building Serviceso Detailed Design, Manufacturing, Installation and Commissioning
✓ Mechanical / Electrical Workso Detailed Design, Manufacturing, Installation and Commissioning
UKAEA Industry Day – 08/10/2020 19
Supporting functions for the IO and F4E
a) Support to the Clients
b) Collaboration Expert
c) Cost Expert
d) Collaboration Auditor
HCC Collaboration strategy
UKAEA Industry Day – 08/10/2020 20
Polly Party Agreement boundary
Cost Expert
Collaboration Expert
Collaboration Auditor
IOOwner/Operator
F4EStakeholder
Clients / Steering Committee
Collaboration Management Team
Collaboration Project Team(Participants)
IO F4EProject Integrator CivilRadwaste Building ServiceRemote Handling Mech/Elec.
HCC Collaboration Organization
Support to Owner
UKAEA Industry Day – 08/10/2020
Collaboration – Main Steps
21
The IO-F4E relationship - Collaboration preparation
a) Memorandum of Understanding (MoU) between the IO and F4E regulating their role of clients acting jointly towards the Collaboration as a single team
Contractual framework – Collaboration Agreement
a) Contracts between the contractors and the IO and/or F4E
→With the sole obligation to enter into the Collaboration Agreement
→ Contracts are deemed completed when the Collaboration Agreement is entered into
b) One Collaboration Agreement
→With the obligation to execute the Works in Collaboration
→Works may commence when the Collaboration Agreement is signed
UKAEA Industry Day – 08/10/2020 22
What We Want to Achieve
➢ Risk sharing – liability model to be detailed
➢ Open book commitment
➢ Gain share / Pain share
✓ Cost + Fee + Incentive payment scheme
➢ Collaborative attitude and aligned behavior
➢ One Collaboration Agreement
➢ Design to Cost with Quality and on Schedule
UKAEA Industry Day – 08/10/2020 23