MODULE IV-PLANNING THE JOB
Plan a lead-based paint maintenance job.
Recognize an activity as either low risk or high risk.
Choose appropriate materials and equipment for the job.
Choose appropriate personal protective clothing and equipment for the job.
Learning Objectives
![Page 2: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/2.jpg)
IV-2
LEAD JOB CHECKLIST
If you don’t know when the building was built, treat the paint as lead-based paint. If the building was built after 1978,then lead-based paint is probably not present and this is not a lead job. If the building was built before 1978, then treat the paint as lead-based paint, unless a paint inspection report says that no lead-based paint is present.
1.1. Was the building built before 1978? Yes No
![Page 3: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/3.jpg)
IV-3
LEAD JOB CHECKLIST
2. Could this job: (Y=Yes, N=No)
Create dust that may contain lead? Disturb known or suspected lead-based paint ? Require cleanup of dust or debris that may contain lead? Disturb known or suspected lead contaminated soil?
Y NY NY NY N
![Page 4: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/4.jpg)
IV-4
HIGH RISK =
High levels of dust
expected to be generated, or Surface and paint in poor condition, or
Greater than two (2) square feet.
LEAD JOB CHECKLIST
3. If “Yes” to any of the above, or if you don’t know the answer to any of the questions, assume you are dealing with lead-based paint, and circle the level of risk below.
LOW RISK =
Low levels of dust expected to be generated, and
Surface and paint in good condition, and
Less than two (2) square feet.
![Page 5: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/5.jpg)
IV-5
LEAD JOB CHECKLIST
LOW RISK = • LOW RISK = • Low levels of dust Low levels of dust expected to be expected to be
generated, generated, and and • • Surface and paint in Surface and paint in good condition, and good condition, and • • Less than two (2) Less than two (2) square feet. square feet.
![Page 6: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/6.jpg)
IV-6
LOW RISK MAINTENANCE JOBS
Repair window panes Repair doors Replace or repair door locks Repair radiator leaks Patch walls Grounds keeping Routine vacancy preparation
![Page 7: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/7.jpg)
IV-7
LEAD JOB CHECKLIST
High Risk = • High levels of dustHigh Risk = • High levels of dust expected to be generated, or expected to be generated, or • • Surface and paint in poor Surface and paint in poor condition, or condition, or • • Greater than two (2) square Greater than two (2) square feet. feet.
![Page 8: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/8.jpg)
IV-8
POTENTIALLY HIGH RISK REHABILITATION JOBS
Stabilize large amounts of badly deteriorated paint
Knock out walls Replace windows Replace old or worn carpet Kitchen/bath remodel Replace kitchen cabinets
![Page 9: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/9.jpg)
IV-9
HIGH RISK MAINTENANCE JOBSBEYOND SCOPE OF TRAINING
The following high risk jobs are beyond the scope of this training: Replacing major building components Demolition Major Renovation Fire Restoration
![Page 10: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/10.jpg)
IV-10
LEAD JOB CHECKLIST
4. Who will do the job? Personnel must be properly trained and skilled, if they will have to wear a respirator, they must be medically qualified, fit-tested, and trained.
Name ____________ Name _____________
![Page 11: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/11.jpg)
IV-11
LEAD JOB CHECKLIST
5. 5. How will residents be notified and affected? Notification: Phone ______ Letter _____ Time_______ Date______ Work area instructions to residents Job scheduled: FROM: Time/Date ___TO: Time/ Date___ Resident asked to leave unit: FROM: Time/Date ___TO: Time/ Date___
Resident asked to move personal items? Yes No Temporary accommodations needed for resident? Yes No If “Yes” accommodation provided? Yes No If “Yes”WHERE ___________ PHONE # _______________
![Page 12: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/12.jpg)
IV-12
LEAD JOB CHECKLIST
6. How will work be performed to minimize exposure to lead? Circle specific cards to use for this job:
Materials Card Cleanup CardsEquipment Card Carpet Removal CardPersonal Protection Card Decontamination CardWork Practices Card Quality Control CardProhibited and Unsafe Practices
![Page 13: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/13.jpg)
IV-13
MATERIALS
All-Purpose Cleaner, or cleaner made specifically for lead
RAGS
LEADWASTE
Heavy Duty Plastic Sheeting
Tape
String Mop HeadsRags
Tack Pads
Disposable Towels
Circle Needed equipment ( Note for high risk.)
Heavy Duty Plastic Bags
![Page 14: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/14.jpg)
IV-14
EQUIPMENT
Circle Needed equipment ( Note for high risk.)
HEPA
Spray Mister
Stapler
Scraper
Utility Knife
Broom(Wet Sweep Only)
Dust Pan
HEPA Vacuum
Mop & Bucket
Mini - Containment
Signs & Barriers
WARNING
LEAD
HAZARD
![Page 15: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/15.jpg)
IV-15
PERSONAL PROTECTION
Circle needed protection (Note: for high risk)
ProtectiveEye Wear
Disposable Cotton Gloves
Latex/ Rubber Gloves
![Page 16: IV-1 MODULE IV-PLANNING THE JOB Plan a lead-based paint maintenance job. Recognize an activity as either low risk or high risk. Choose appropriate](https://reader036.vdocument.in/reader036/viewer/2022062801/56649e195503460f94b05cd4/html5/thumbnails/16.jpg)
IV-16
Disposable Full-BodyDisposable Full-BodyCoveralls/RecyclableCoveralls/RecyclableClothingClothing
RespiratorsRespirators w/HEPA Filtersw/HEPA Filters
PERSONAL PROTECTION - CONTINUED
Circle needed protection (Note: for high risk)