Jadual Pembahagian (Wim) Amali MC-024-3:2012 Shielded Metal Arc Welding (SMAW) E01 Shielded Metal Arc Welding (SMAW) 6GR Work Activities Lesson plan Work sheet 1. Carry out safety assessment at work area MC-024-3:2012/E01/P(1/9)PM (Menjaga keselamatan dikawasan kerja) MC-024-3:2012/E01/K(1/9) (Menjaga keselamatan dikawasan kerja) 2. Complay to work instruction and releven Welding Procedure Specification (WPS) MC-024-3:2012/E01/P(2/9)PM (Penyedian bahan mengikut wps welding procedure specification) MC-024-3:2012/E01/K(2/9) (Penyedian bahan mengikut wps welding procedure specification) 3. Verify base metal material used MC-024-3:2012/E01/P(3/9)PM (memeriksa logam asas yang digunakan) MC-024-3:2012/E01/K(3/9) (memeriksa logam asas yang digunakan) 4. Verify consumable as MC-024-3:2012/E01/P(4/9)PM (megendali elektrod) MC-024-3:2012/E01/K(4/9) (megendali elektrod)

Upload: patricia-kc

Post on 05-Nov-2015

54 views

Category:

Documents


1 download

DESCRIPTION

t

TRANSCRIPT

Jadual Pembahagian (Wim) AmaliMC-024-3:2012 Shielded Metal Arc Welding (SMAW)E01 Shielded Metal Arc Welding (SMAW) 6GRWork ActivitiesLesson plan

Work sheet

1. Carry out safety assessment at work area

MC-024-3:2012/E01/P(1/9)PM(Menjaga keselamatan dikawasan kerja)

MC-024-3:2012/E01/K(1/9)(Menjaga keselamatan dikawasan kerja)

2. Complay to work instruction and releven Welding Procedure Specification (WPS)

MC-024-3:2012/E01/P(2/9)PM(Penyedian bahan mengikut wps welding procedure specification)

MC-024-3:2012/E01/K(2/9)(Penyedian bahan mengikut wps welding procedure specification)

3. Verify base metal material used

MC-024-3:2012/E01/P(3/9)PM(memeriksa logam asas yang digunakan)

MC-024-3:2012/E01/K(3/9)(memeriksa logam asas yang digunakan)

4. Verify consumable as specified

MC-024-3:2012/E01/P(4/9)PM(megendali elektrod)

MC-024-3:2012/E01/K(4/9)(megendali elektrod)

5. Chek SMAW equipment and accessories functionality

MC-024-3:2012/E01/P(5/9)PM(menservis mesin SMAW)

MC-024-3:2012/E01/K(5/9)(menservis mesin SMAW)

6. Perform SMAW process

MC-024-3:2012/E01/P(6/9)PM(megendali proses SMAW)MC-024-3:2012/E01/K(6/9)(megendali proses SMAW)

7. Perform visual inspection and testing (destructive test)

MC-024-3:2012/E01/P(7/9)PM(Mencari kecacatan kimpalan)MC-024-3:2012/E01/K(7/9)(Mencari kecacatan kimpalan)

MC-024-3:2012/E01/P(8/9)PM(melaksanakan ujian musnah)MC-024-3:2012/E01/K(8/9)(melaksanakan ujian musnah)

8. Compile work completion checklist

MC-024-3:2012/E01/P(9/9)PM(menyediakan senarai semak)MC-024-3:2012/E01/K(9/11)(menyediakan senarai semak)