jamie threader dm on file - ref: 13/57625 9/12/2013 waivers/ew_sg… · with 2 layers sl81 mesh...
TRANSCRIPT
1.0 Risk No.
1.01Risk Category: 1. Safety2. Assets3. Financial4. Environment5. Regulatory6. Reputation
1.1Hazard or scenario
or circumstance
1.2Caused by
2.0 Existing Control
2.01Control type
2.2Current
consequence
2.3Current
likelihood
2.4Current risk
level
5.0Has this workshop adequately addressed this risk?
5.2Comments / clarification
None
3.1 BENEFIT
3.2COST
3.3Decision
3.4Responsible
Party
3.5By when
Uncertain OR disputed (revisit this risk and attempt
to resolve)Concrete encasement of conduits (To provide physical barrier during excavation and mechanical protection to conduits)
Engineering/ Design
High Moderate Adopt RRLCMR 20-Nov-13
Relocate cable route Elimination High High Reject RRLCMR 20-Nov-13
Confirm that HV is at the base of cable routeEngineering/
DesignMinimal Minimal Adopt RRLCMR 20-Nov-13
Placement of marker tape along top of concrete encasement (To act as a visual indicator)
Engineering/ Design
Moderate Minimal Adopt RRLCMR 20-Nov-13
Placement of marker posts at pit locations (To identify route)
Engineering/ Design
Moderate Minimal Adopt RRLCMR 20-Nov-13
Track lifted to maximise cover (Reduces likeihood of encountering conduits)
Engineering/ Design
Moderate Minimal Adopt RRLCMR 20-Nov-13
Low speed (15km/hr) environment (Low dynamic loads)
Engineering/ Design
Moderate Minimal AdoptRRLCMR /
ARTC20-Nov-13
Excavation permits require service proving (Improves likelihood of identification of services prior to works)
Administrative Moderate Minimal Adopt ARTC 20-Nov-13
Production of as built drawings (Improves information on services for future works)
Administrative Moderate Minimal Adopt RRLCMR 20-Nov-13
1.0 Risk No.
1.01Risk Category: 1. Safety2. Assets3. Financial4. Environment5. Regulatory6. Reputation
1.1Hazard or scenario
or circumstance
1.2Caused by
2.0 Existing Control
2.01Control type
2.2Current
consequence
2.3Current
likelihood
2.4Current risk
level
5.0Has this workshop adequately addressed this risk?
5.2Comments / clarification
None
3.1 BENEFIT
3.2COST
3.3Decision
3.4Responsible
Party
3.5By when
Uncertain OR disputed (revisit this risk and attempt
to resolve)Concrete encasement of conduits to provide physical barrier during excavation and mechanical protection to conduits
Engineering/ Design
High Moderate Adopt RRLCMR 20-Nov-13
Relocate cable route Elimination High Moderate Reject RRLCMR 20-Nov-13Placement of marker tape along top of concrete encasement as visual indicator
Engineering/ Design
Moderate Minimal Adopt RRLCMR 20-Nov-13
Placement of marker posts at pit locations to identify route
Engineering/ Design
Moderate Minimal Adopt RRLCMR 20-Nov-13
Track lifted to maximise coverEngineering/
DesignModerate Minimal Adopt RRLCMR 20-Nov-13
Low speed (15km/hr) environment therefore low dynamic loads
Engineering/ Design
Moderate Minimal AdoptRRLCMR /
ARTC20-Nov-13
Excavation permits require service proving Administrative Moderate Minimal Adopt ARTC 20-Nov-13
Track operation and maintenance
Most Likely (Credible) Outcome
Worst Case (Credible) Outcome
4.2Revised risk level
Moderate Rare
1. RISK IDENTIFICATION 2. ANALYSIS AND EVALUATION 5. VALIDATION AND CLARIFICATION1.3
Leading to an Outcome
RRLCMR-2 Assets
Damage to signalling/comms cabling due to presence of cables conduits at less than the prescribed minimum values
SFAIRP TEST
Moderate Possible
Uncertain OR disputed (revisit this risk and attempt to resolve)
Refer to risk RRLCMR-1 for justification of rejected options.
ARTC to complete
5.1Do the decisions make
sense?
4. RESCORE TO REFLECT SFAIRP OUTCOMES4.0
Revised consequence
4.1Revised
likelihood
LOW - 3E
ARTC to complete
Signal failure and line closure
Loss of 2.2kV signalling to NME geographic area. Disruption to VicTrack fibre backbone
3. PROPOSED ADDITIONAL RISK TREATMENT3.0
Proposed Additional Control3.01
Control type
Assumes installation of current AFC design, which did not identify the presence of existing conduits
Assumes installation of current AFC design, which did not identify the presence of existing conduits
Major Possible
1. RISK IDENTIFICATION 2. ANALYSIS AND EVALUATION 5. VALIDATION AND CLARIFICATION1.3
Leading to an Outcome2.1
Responsible Party / Comments
RRLCMR - Risk Assessment to Support Standard Waiver Application
5.1Do the decisions make
sense?
RRLCMR-1 Safety
Worker comes in contact with signalling/comms cabling due to presence of cables conduits at less than the prescribed minimum values
Track operation and maintenance
Most Likely (Credible) Outcome
Worst Case (Credible) Outcome
Mild electric shock from LV signalling cabling
SFAIRP TEST
HIGH - 4C
Localised relocation was rejected on the basis that no appropriate location could be found clear of existing services and trackside structures in the near vicinity of the existing route for relocation. ARTC to complete
4.1Revised
likelihood
4.2Revised risk level
Moderate Unlikely LOW - 3D
ARTC to complete
Electrocution leading to single fatality from HV signalling cabling
3. PROPOSED ADDITIONAL RISK TREATMENT 4. RESCORE TO REFLECT SFAIRP OUTCOMES3.0
Proposed Additional Control3.01
Control type
4.0Revised
consequence
2.1Responsible Party / Comments
MED - 3C
WPA MCR along ARTC Freight Link Headshunt
Uncertain OR disputed (revisit this risk and attempt to resolve)
Pg. 1 of 1 Copy of ARTC RA Template.xls
01 01
A31:50
SSS_C0525
WPB-SKT-JAC-CRF-2-00-SSS-0525
RAILWAY TRACK & CIVILC PANNELL
SOUTHERN CROSS STATION
C DUCK
ARTC FREIGHT LINK HEADSHUNT
A
A
CONDUIT DETAILS
C.W.P.15/11/13 ISSUED FOR INFORMATION
4:1
2:0
1 P
M21/1
1/2
013
c:\pw_work\rrl_b\colin.duck\dms01482\WPB-SKT-JAC-CRF-2-00-SSS-0525.dgn
DescriptionDateIn Serv
Drawn By Designed By
Checked By
Approval Date
Drawing NumberIn Serv.
Scale Sheet Size
Sheet No.
Down LocationUp Location Datum
Approved
Ind. Review
Franchisee / Lessee
Consultant
East.
North.
ID#
East.
North.
ID#
Approv.Ind. Rev.Checked
File Name
Revised By Designed
Victrack's prior written consent.not be provided to, or used by, any other person withoutperson or organisation to whom Victrack provides it. It mayThis drawing is provided only for the information of the dimensions.All written dimensions take precedence over scaled drawing or the information contained in it.liability in relation to the use of, or any reliance on, thisVictrack from all and any loss, damage, cost, expense orcontained in this drawing. Each user of this drawing releasesthe completeness, accuracy or quality of any informationresponsibility for, and makes no representations in relation to,maximum extent permissible by law, Victrack takes noinformation provided by, persons other than Victrack. To theThis drawing has been prepared by, or compiled from
of
Certifie
d B
y:
(BL
OC
K L
ET
TE
RS)
(SIG
NA
TU
RE)
(DA
TE)
Project Title Project Drawing Number
DescriptionDateIn Serv Ver.
Drawn By Designed By
Checked By
Approval Date
Drawing NumberIn Serv.
Scale Sheet Size
Sheet No.
Down LocationUp Location Datum
Approved
Ind. Review
Version
Franchisee / Lessee
Consultant
East.
North.
ID#
East.
North.
ID#
Approv.Ind. Rev.Checked
File Name
Revised By Designed
Victrack's prior written consent.not be provided to, or used by, any other person withoutperson or organisation to whom Victrack provides it. It mayThis drawing is provided only for the information of the dimensions.All written dimensions take precedence over scaled drawing or the information contained in it.liability in relation to the use of, or any reliance on, thisVictrack from all and any loss, damage, cost, expense orcontained in this drawing. Each user of this drawing releasesthe completeness, accuracy or quality of any informationresponsibility for, and makes no representations in relation to,maximum extent permissible by law, Victrack takes noinformation provided by, persons other than Victrack. To theThis drawing has been prepared by, or compiled from
of
Ver.
Version
CL
1:60
CL
1:60
STRUCTURAL FILL
STRUCTURAL FILL
TRENCH ARRANGEMENT
REFER DETAIL A FOR
TRENCH ARRANGEMENT
REFER DETAIL B FOR
CL
1:60
STRUCTURAL FILL
2300 MIN
ARRANGEMENT
FOR TRENCH
ROUTE REFER DETAIL C
AS-CONSTRUCTED CABLE
STRUCTURAL FILL500 HAND COMPACTED
SHORTLY AFTER EXCAVATION
BACKFILL TO BE COMPLETED
850 MAX400 400
400 400150MIN
200
200
OPTIC TRACE WIRE
VICTRACK FIBRE
OPTIC TRACE WIRE
VICTRACK FIBRE
230 TYP 460 TYP
300
MIN 6
50
MARKER TAPE
150 CAPPING LAYER
(AS CONSTRUCTED BY WP-A)
CLASS 3 CRUSHED ROCK
(AS CONSTRUCTED BY WP-A)
SIGNALLING CONDUITS
EXTENDS 50 EITHER SIDE OF
VINIDEX PROTECTION STRIP
(AS CONSTRUCTED BY WP-A)
SIGNALLING CONDUITS
EXTENDS 50 EITHER SIDE OF
VINIDEX PROTECTION STRIP
FOR FULL WIDTH OF CONCRETE SLAB
TOP OF CONCRETE. MARKER TAPE TOI OVERLAP AND PROVIDE
150mm WIDE MARKER TAPE INSTALLED LONGITUDINALLY ALONG
FROM TOP, BOTTOM LAYER 150mm FROM TOP
WITH 2 LAYERS SL81 MESH CENTRAL, TOP LAYER 40mm
CONTINUOUS CONCRETE SLAB VR400/40 CONCRETE
WIDTH OF CONCRETE SLAB
OF CONCRETE. MARKER TAPE TOI OVERLAP AND PROVIDE FOR FULL
150mm WIDE MARKER TAPE INSTALLED LONGITUDINALLY ALONG TOP
TOP, BOTTOM LAYER 150mm FROM TOP
2 LAYERS SL81 MESH CENTRAL, TOP LAYER 40mm FROM
CONTINUOUS CONCRETE SLAB VR400/40 CONCRETE WITH
DETAIL
-
BSCALE 1:25
DETAIL
-
ASCALE 1:25
DETAIL
-
CSCALE 1:25
FREIGHT LINK HEADSHUNT
DUAL GAUGE
FREIGHT LINK HEADSHUNT
DUAL GAUGE
SCALE 1:50
(AT PIT LOCATIONS)
SEPARATE CONDUIT ROUTE DETAIL
FREIGHT LINK HEADSHUNT
FREIGHT LINK HEADSHUNT
DUAL GAUGE
SCALE 1:50
CONDUITS >1500 FROM NEAREST RAIL
CONDUIT ROUTE DETAIL WHERE
FREIGHT LINK HEADSHUNT
SCALE 1:50
COMBINED CONDUIT ROUTE DETAIL
FREIGHT LINK HEADSHUNT
150 MIN BALLAST
150 CAPPING
150 MIN BALLAST
150 CAPPING
CONCRETE SLAB
150 MIN CAPPING ABOVE
CONCRETE SLAB
150 MIN CAPPING ABOVE
150 MIN BALLAST
150 CAPPING
REVISION
IN PROGRESS
CHECK PRINTINITIAL DATE
DISCIPLINE
READY FOR ISSUE
DISCIPLINE
DISCIPLINE
DISCIPLINE
BACKDRAFTED/CORRECTED
CONFIRMED
1
Jessie Ellis
From: Patrick Gray <[email protected]>
Sent: Wednesday, 20 November 2013 9:50 PM
To: Jessie Ellis; Chris Pannell
Cc: Barry Toniolo; [email protected]; Doug Hayhoe; Ross Deacon; Phil Meehan;
rrlcmr.office
Subject: RE: ARTC Headshunt (DCR765)
Jessie,
Thank you for this summary.
Another appropriate Standard containing appropriate illustrations of cable location, depth and mechanical
protection is AS 4799, “Installation of underground utility services and pipelines within railway boundaries”.
There is some non compliance with the existing cable route depths under track and distances from track centre that
will be addressed by the proposed waiver. The depths below ground level established from service proving are
significantly greater than earlier sketches indicated.
There is some ambiguity between the minimum cable depth listed on Figure 6.2 of AS 4799 and Section 6..4.2.2. In
this case it is reasonable to adopt the value from Figure 6.2 which is consistent with the value from ESC-11-01. It is
noted that CMR have adopted the more conservative value from VRIOGS 12.2.1.
The WPA design with included mechanical protection can be considered to meet ARTC Standards for depth and
mechanical protection but not for distance from track centreline. The under track section of cable run did not meet
acceptable ARTC Standards but with proposed mitigation of reinforced concrete cover and concrete surround I am
hopeful that the proposed waiver has a good chance of being approved. Please submit the waiver documentation at
your early convenience.
Regards
Patrick Gray
ARTC RRL Interface Support M – 0417 820 676 Email – [email protected]
Australian Rail Track Corporation Ltd. Postal Address: Locked Bag 20013 Melbourne, Vic. 3001 Street Address: Level 1, 371 Spencer Street, West Melbourne, Vic 3003
From: Jessie Ellis [mailto:[email protected]]
Sent: Wednesday, 20 November 2013 7:03 PM
To: Patrick Gray; Chris Pannell Cc: Barry Toniolo; [email protected]; Doug Hayhoe; Ross Deacon; Phil Meehan; rrlcmr.office
Subject: RE: ARTC Headshunt (DCR765)
Good evening Pat,
We have completed a review of ESC-11-01 (ARTC), AS3000 and VRIOGS 012.2.1, in conjunction with the relevant
WPA and WPB drawings.
2
Firstly, to the establish context for the review, we provide an extract from our Scope and Technical Requirements
that provides a hierarchy for the design standards applicable the RRLCMR Alliance.
• Project Alliance Agreement
• Standards of Rail Infrastructure Managers
• VRIOG Standards
• VicTrack communications standards (where applicable)
• The Department’s Systems & Information Services Division standards
• VicRoads and Local Government standards
• Australian Standards
From this, the standards of the Infrastructure Manager and VRIOG standards take precedence over that of the
Australian Standards – the exception to this being when they make direct reference to an Australian Standard.
In response to your request of a review of the requirements of AS3000, we note that Section 3.11 of this standard
provides three categories of cable protection for buried routes, as follows:
• Category A – All cable types installed in heavy duty conduit or fully concrete encased trenches
• Category B – A shortlist of cable types in medium duty conduit or direct buried sheathed cables
• Category C – An underground wiring system laid in a channel chased in rock
Additional protection measures for each category are as follows:
• Category A – 50mm bedding sand top and bottom only, assumed to apply to traditionally backfilled
trenches. Minimum cover 500mm (outdoors applications).
• Category B – Additional mechanical protection in the form of a min 40mm thick precast concrete slab,
polymeric cable cover strip complying with AS4702, etc. 150mm width and 75mm above cable. Minimum
cover 500mm (outdoors applications).
• Category C – Concrete surround. Minimum cover 50mm (outdoors applications).
VRIOGS 012.2.1 Section 7.12 explicitly refers to AS3000 for mechanical protection requirements. EST-11-01 Section
6.4, while it doesn’t explicitly refer to AS3000, words the additional mechanical protection requirements for cables
similar to those for Category B installations. It is inferred that this relates to direct buried cables only, based upon all
references in this section referring to cables, not conduits, and the associated standard drawings in Appendix C only
applying the cover strip over direct buried cables, not buried cable in conduit (refer SC 09 01-04 vs SC 09 01/05
extracted and attached).
The design undertaken by WPA has adopted a Category B trenching configuration, as it does not specify heavy duty
conduit, but specifies the use of a “Vindex Protection Strip”. Vindex cable protection strips are manufactured to be
compliant with AS4702 – Polymeric Cable Protection Covers. Visual observation of sections of the WPA cable route
exposed by RRLCMR along the ARTC Headshunt have verified the presence of the protective strip in these areas.
The design undertaken by RRLCMR elsewhere has adopted a trenching configuration consistent with a Category A
installation, and which also complies with the requirements of ARTC standard drawing SC 09 01-05.
Additional service proving of as constructed conduit depths was undertaken by RRLCMR yesterday. This information
was unavailable at the time of our meeting yesterday afternoon. We have since reviewed the service proving
information which confirms that, where the cable route is beyond 1.5m from the nearest rail it achieves a cover of
650mm. Note ESC-11-01 requires 600mm cover, greater than the 500mm in AS3000, while VRIOGS 12.2.1 requires
650mm. We have adopted the greater of the three for the purpose of this review.
3
On the basis of the new service proving information, we believe only one that no intermediate protection type is
required. That is, there is no portion of the route outside the track loading zone of 1.5m from nearest rail that has
reduced cover. As such, RRLCMR proposed to provide full concrete encasement of the route where within the
agreed track loading zone, and undertake no modification to the existing protection measures outside this.
We note that VicTrack have undertaken some minor slewing of their own conduits to minimise the length along
which the conduits are under sleeper.
Regards,
Jessie Ellis – Construction Phase Services Lead Regional Rail Link: City - Maribyrnong River
171 Laurens Street, North Melbourne, VIC 3051 T. (03) 8327 7587 M. 0413 395 882 E. [email protected]
Please consider the environment before printing this e-mail.
From: Patrick Gray [mailto:[email protected]]
Sent: Tuesday, 19 November 2013 7:04 PM
To: Chris Pannell Cc: Barry Toniolo; [email protected]; Jessie Ellis; Doug Hayhoe; Ross Deacon; Phil Meehan
Subject: RE: ARTC Headshunt (DCR765)
Hi Chris,
I have been considering the requirements for these signal and high voltage cables.
ARTC diagrams differentiate between marker tape and cable cover slabs. These later are defined in Standard AS/NZ
3000 and can be provided in a number of different types including precast concrete, cast in situ concrete, plastic
strips, fibre cement strips etc.
There are no specific ARTC guidelines for conditions outside of the ARTC Standards. Therefore rather than
recommending a treatment for the cables outside of the encased concrete area (provided where conduits are closer
than 1500mm to nearest rail) ARTC requires the CMR designers to propose an arrangement compliant with AS/NZ
3000 Australian New Zealand Wiring Rules. The solution must consider the depth of conduits relative to finished
ground level including side drains.
This proposal was mentioned to Doug in a phone conversation this evening.
I look forward to receipt of your proposal for consideration in due course. Upon acceptance CMR will need to
complete and submit the ARTC Engineering Waiver Approval form.
Regards
Patrick Gray
ARTC RRL Interface Support M – 0417 820 676 Email – [email protected]