january 31, 2014 - chevron corporation...at the lng plant site piling works continue for the...

9
© 2014 Chevron Corporation. All rights reserved. Wheatstone Project Update January 31, 2014

Upload: others

Post on 11-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Wheatstone Project Update January 31, 2014

Page 2: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Platform Construction

At the DSME yard in Okpo, Korea, all primary decks of the topsides are structurally complete (left). The steel gravity structure (right) has left the dry dock and the erection of the final blocks has commenced.

2

Page 3: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

LNG Plant Site

Fill continues to be brought from nearby borrow pits to raise the site level.

3

Borrow Pit 2

Borrow Pit 3

Borrow Pit 1

Page 4: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Material Offloading Facility

At the Material Offloading Facility (MOF), works on the south and east quays, off-loading ramps, utility corridors and breakwater construction are more than 50 percent complete, and the first material shipments are expected shortly.

4

South Quay East Quay

MOF

Page 5: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Piling Works Continue to Progress at the LNG Plant Site

To date, approximately 9,500 of 23,000 piles have been driven for the foundations of LNG Train 1 and 2, the LNG storage and condensate tanks, and marine infrastructure.

5

Page 6: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Piling Works Continue to Progress at the LNG Plant Site

Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration compressor foundations for LNG Train 1 progress.

6

Refrigeration Compressor Foundation

Page 7: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

LNG Plant Site: Water Facilities

The water facilities, which will support Wheatstone’s water requirements throughout the primary construction phase, are nearing completion.

7

Page 8: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Construction Workforce Accommodation Facilities At the construction village, there is capacity to house approximately 3,800

workers onsite.

8

Page 9: January 31, 2014 - Chevron Corporation...at the LNG Plant Site Piling works continue for the foundations of the two LNG storage tanks (left), while construction of the refrigeration

© 2014 Chevron Corporation. All rights reserved.

Social Infrastructure: Onslow Airport Onslow Airport is now supporting 18 flights per week, and construction of the

new terminal is well under way.

9

New Terminal Building