jet a1 fueling system

54
Saudia Aerospace Engineering Industries Aircrafts Maintenance Hangars JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 1 of 14 S09063-01D-PD-SPC-ME-02 REV 1 SECTION 40052 - JET A1 FUELING SYSTEM BASIC MECHANICAL REQUIREMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the contract, including conditions of contract and Division 1 of the specification apply to this section. 1.2 RELATED SECTIONS A. Division 40, “Jet A1 Fueling System – Cathodic Protection” B. Division 40, “Jet A1 Fueling System – Piping Construction” C. Division 40, “Jet A1 Fueling System – Coating And Corrosion” D. Division 40, “Jet A1 Fueling System – Monitoring And Control (EFSO & Leak Detection)” E. Division 40, “Jet A1 Fueling System – Inspection, Cleaning, Flushing, And Testing” 1.3 SUMMARY A. Installations to include all necessary apparatus, excavating, backfilling, pipes valves, and fittings herein described or called for on the Drawings and/or Specifications or as necessary to make the installations operational in a safe and satisfactory manner. B. It is of vital importance to keep the jet fuel network operational all the time. The contractor is to take all required precautions and coordinate with all authorities to meet this requirement. Disruption of the refueling system is not allowed for any reason related to the execution of the required work of this contract. The scope of work of the contract shall include the following: Coordinate with the Civil Aviation Authorities for the phasing of the work. 1. Prior to start of work, perform a complete survey of all existing conditions within the limit of the contract. The survey is needed to verify the location of the connection points, profiles and consequently the preparation of the network shop drawings. 2. Supply and install new fuel hydrant pipe. 3. Supply and install new hydrant pits. 4. For the newly installed fuel pipeline establish low point drains with low point drain pits and piping connections. 5. For the newly installed fuel pipeline, along the aircraft parking areas, establish high point vents to coincide with the hydrant points. This hydrant / vent will serve the dual purpose of aircraft loading and venting as required during the appropriate operation.

Upload: maaz-junaidi

Post on 02-Oct-2015

114 views

Category:

Documents


8 download

DESCRIPTION

Jet A1 Fuel System Specifications - SAEIAM

TRANSCRIPT

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 1 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    SECTION 40052 - JET A1 FUELING SYSTEM BASIC MECHANICAL REQUIREMENT

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the contract, including conditions of contract and

    Division 1 of the specification apply to this section.

    1.2 RELATED SECTIONS

    A. Division 40, Jet A1 Fueling System Cathodic Protection

    B. Division 40, Jet A1 Fueling System Piping Construction

    C. Division 40, Jet A1 Fueling System Coating And Corrosion

    D. Division 40, Jet A1 Fueling System Monitoring And Control (EFSO & Leak Detection)

    E. Division 40, Jet A1 Fueling System Inspection, Cleaning, Flushing, And Testing

    1.3 SUMMARY

    A. Installations to include all necessary apparatus, excavating, backfilling, pipes valves, and

    fittings herein described or called for on the Drawings and/or Specifications or as necessary

    to make the installations operational in a safe and satisfactory manner.

    B. It is of vital importance to keep the jet fuel network operational all the time. The contractor

    is to take all required precautions and coordinate with all authorities to meet this requirement.

    Disruption of the refueling system is not allowed for any reason related to the execution of

    the required work of this contract.

    The scope of work of the contract shall include the following:

    Coordinate with the Civil Aviation Authorities for the phasing of the work.

    1. Prior to start of work, perform a complete survey of all existing conditions within the

    limit of the contract. The survey is needed to verify the location of the connection

    points, profiles and consequently the preparation of the network shop drawings.

    2. Supply and install new fuel hydrant pipe.

    3. Supply and install new hydrant pits.

    4. For the newly installed fuel pipeline establish low point drains with low point drain

    pits and piping connections.

    5. For the newly installed fuel pipeline, along the aircraft parking areas, establish high

    point vents to coincide with the hydrant points. This hydrant / vent will serve the dual

    purpose of aircraft loading and venting as required during the appropriate operation.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 2 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    High point vents in other sections will be provided with the standard venting

    arrangement.

    6. Connect the MOVs, to the PLC remote I/O panel.

    7. Supply, install and test the Emergency Fuel Shut Off (EFSO) system and PLC Panel

    as shown and specified on the project drawings. The EFSO stations shall be connected to the new PLC remote I/O Panel with spare I/O modules.

    8. Install a leak detection system to cover the new pipelines.

    9. Make the required connection between the existing and new fuel pipes. Coordinate

    and schedule phasing of shutdown to allow for new connections without interruption

    of fuel supply.

    10. Establish pipe protective coating on the newly installed pipe section

    11. Execute all civil, instrumentation and electrical works associated with the above

    mentioned work

    12. Establish, supply and install cathodic protection for the fuel system under this

    contract.

    13. Cleaning, flushing, testing, and commissioning of the fuel hydrant network affected

    by the above works.

    14. Certification of the above works and installation as specified.

    C. Provide and pay for all materials, supervision, labor, tools, equipment, supplies, scaffolding

    and transportation required to execute the work specified or indicated on the drawings,

    except as otherwise noted.

    D. Perform all works described above as required by these specifications and/or indicated on the

    drawings.

    E. The completed works are to be aligned, grouted, and adjusted, and are permanent, and of safe

    and satisfactory operation. Furnish and install components not indicated but necessary for

    satisfactory and safe operation.

    F. Provide 380 VAC and 220 VAC power wiring and conduits to serve the required power

    needs.

    G. Fit all apparatus, equipment, piping, etc., into the space provided at such time and in such a

    manner as to avoid damage to existing structures or property, and as required by the work

    progress schedule.

    H. Cooperate and coordinate with the Engineer in the scheduling of work, moving of material,

    delivery and location of anchor bolts, sleeves, etc.

    I. Coordinate with other Contractors operating on site to ensure no interference or conflict.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 3 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    J. Coordinate with concerned Authorities to ensure that all matters related to security, safety,

    access, and services etc are being followed in full compliance with their regulations.

    K. Coordinate with Civil Aviation Authorities and other on-site Authorities for phasing of the

    Work in order to avoid any disturbance to the operation of flights and ground services.

    L. Coordinate with Jet Fuel Network Operator for proper execution, and compliance with their

    functional, safety and operational requirements.

    M. Coordinate with the Jet Fuel Network Operator for all data on existing network including

    related drawings and documents.

    N. Do not interrupt existing utilities serving facilities occupied by the Owner or others except

    when permitted in writing by the Engineer and then only after acceptable temporary utility

    services have been provided.

    O. Maintain access for vehicular and pedestrian traffic as required for other activities in the area

    and as discussed/directed by the Engineer.

    P. Review, stamp approved, and submit in orderly sequence, all Shop Drawings and Equipment

    Lists of materials and equipment required by the Contract Documents so as to cause no delay

    to the work progress schedule.

    Q. Interface the mechanical work of this contract with existing systems as required by the

    Contract Documents.

    R. Inspect, flush, clean, test and demonstrate the operation of the completed systems and train

    personnel for their use.

    S. Obtain and pay for all permits and licenses, but not permanent easements, pay all fees and

    taxes, and give all notices bearing on the conduct of the mechanical work as drawn and/or

    specified.

    T. Receive the approvals or acceptances from all authorities having jurisdiction over the work

    and deliver to the Engineer.

    U. All systems and appurtenances are subject to inspection by the Engineer. Such inspection

    shall not relieve the Contractor of his responsibility of furnishing materials and labor of the

    highest quality which are in strict compliance with code requirements and these

    Specifications. Materials, equipment, labor, or procedures rejected by the Engineer shall be

    replaced or corrected by the Contractor at no additional charge to the Owner.

    V. Fixtures and equipment shall be tightly covered and protected against dirt, water, moisture

    and chemical or mechanical injury. Pipe openings shall be closed with caps or plugs during

    installation.

    W. Instruction and warning signs shall be provided as necessary for operation and safety. Such

    signs shall be in both English and Arabic. The signs shall be sized to facilitate quick

    recognition, be non-corrosive, and be standardized in shape and material.

    X. Unless otherwise specified, all internal and external surfaces that require painting or coating

    for appearance or protection shall be cleaned and coated as specified in Section 40192, "Jet

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 4 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    A1 Fueling System - Piping Construction" and/or Section 40193, "Jet A1 Fueling System -

    Coatings and Corrosion Protection", as appropriate.

    1.3 ENGINEER'S DRAWINGS

    A. Engineer's Drawings are diagrammatic and are not to be scaled. Measurements are to be

    made from established benchmarks.

    B. Engineer's Drawings are to serve as working drawings for Contractor's shop drawings.

    C. No portion of the work requiring a shop drawing or sample submission is to be commenced

    until submission has been reviewed and approved by the Engineer. All such portions of the

    work are to be in accordance with approved shop drawings and samples.

    1.4 SUBMITTALS

    A. Product Data:

    1. General: Submit manufacturer's specifications, recommendations and installation

    instructions for mechanical work products required by these specifications. Include

    manufacturer's published data or certified laboratory test data indicating that each

    work product meets the specified requirements. Meet the Product Data submittal

    procedures specified in the following Paragraph.

    2. Data Included: Product data to include the following as applicable:

    a. Product name and model or catalog designation, and manufacturer's name.

    b. Physical description, dimensions, and weights.

    c. Product properties, characteristics, capabilities and limitations.

    d. Data for coordination with other project work.

    e. Clear spaces required for handling, installing, operating and maintaining

    products.

    f. Required installation clearances and tolerances, and the location and size of

    openings or sleeves necessary for installation.

    g. Applicable reference standard designations.

    h. Product specifications, including protective coatings.

    i. Information on any protective devices (e.g., stop blocks) or protective

    coatings that are applied to the equipment for protection during shipment that

    must be removed upon receipt at the Project site prior to installation.

    j. Methods and details for anchorage to supporting construction.

    k. Data which affects design and construction of supporting structure, including

    maximum reactions imposed on supporting structures at each connection or

    bearing point.

    3. Certification: When required, product data shall be certified by product

    manufacturer.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 5 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    B. Shop Drawings:

    1. General: Submit shop drawings for works required, Product Data and Samples, and

    additional requirements. Shop drawings shall indicate plan and section view layout

    of the works. Prepare and submit shop drawings. Shop drawings indicating the

    works associated with Jet A-1 fuel valve and hydrant pits or other congested areas

    shall be drawn at minimum scale of 1:50. When necessary for clarity shop drawings

    shall include sections drawn at a minimum scale of 1:20.

    2. Data Included: Shop drawings to include following, as applicable.

    a. Label and title which indicates the manufacturer's name and address, the

    drawing scale, and which clearly defines the item being submitted.

    b. General arrangement, physical description, dimensions, and weight of

    product.

    c. Enlarged scale details giving dimensions for locating the product and as

    required to clarify installation clearances and tolerances.

    d. Assembly drawings for work furnished consisting of two or more

    components.

    e. Design and actual details of manufacture or fabrication, including material

    specifications, dimensions, joining methods and protective coatings.

    f. Diagrams of wiring arrangement, actual arrangement of external connections

    as seen by the installer and terminal identification designation on actual

    product.

    g. Diagrams for operation and control of work, including location and function

    of instrumentation and control devices.

    3. Certification: When required, shop drawings shall be certified by originator of work.

    C. Inspection and Test Reports:

    1. General: Submit inspection and test reports for mechanical works required.

    2. Definition: Inspection and test reports shall be documented statements of methods,

    procedures, results and evaluations prepared by Contractor, an installer,

    manufacturer or supplier, or an Independent testing laboratory employed by any of

    these parties to indicate properties, characteristics and capabilities of a product or

    portion of the work.

    3. Presentation: Inspection and test reports shall identify products or work by

    designations indicated in the Contract Documents.

    4. Data Included: Inspection test reports shall include the following:

    a. Identification of product or work area represented by inspection or test.

    b. Methods, procedures and results of inspections and tests, including

    observations of unusual conditions.

    c. Evaluation of results, and acceptability and use limitations.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 6 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    5. Certification: Inspection and test reports shall be certified by organization who

    performed inspections, tests and evaluations.

    D. Compliance Certificates:

    1. General: Submit compliance certificates for mechanical work in accordance with the

    following requirements.

    2. Certification: Compliance certificates shall be certified by issuing organization

    3. Certificates Required: Submit compliance certificates for the following, in addition

    to compliance certificates required.

    a. Welding Procedures and Certification: Submit qualified welding procedures

    and welder certifications as applicable for required type of welding work.

    b. Products not of the manufacturer's standard design, modified to suit these

    requirements.

    c. Equipment bearing UL Listing Mark.

    E. Certified Submittals: Submittals for mechanical work required shall be certified.

    F. Operation and Maintenance Data: Prepare and submit operating and maintenance manuals.

    Submit operating and maintenance data, including instructions, schedules and parts lists, and

    recommended spare parts lists.

    G. Maintenance Products:

    1. General: Furnish maintenance products for work required.

    2. Delivery: Deliver maintenance products to the Project site at completion of the

    work; unload, and place in storage as directed by the Engineer.

    3. Maintenance Products Required: Furnish the following maintenance products:

    a. Special Tools: Tools required for servicing work.

    b. Touch-Up Finish Paint: When major products are required to be factory

    finished, furnish one quart of each type and color finish coat paint applied to

    product for field touch-up.

    H. Record Documents: Submit record documents of work.

    1.5 QUALITY ASSURANCE - FUEL HYDRANTS

    A. General:

    1. Perform the work to the satisfaction of the Engineer and inspecting authorities having

    jurisdiction.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 7 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    2. Notify the Engineer in writing of any instances in the Specifications or on the

    Drawings that are in conflict with any of the aforementioned authorities; required

    changes shall be adjusted before the Contract is awarded. If the Contractor performs

    any work contrary to such laws, rules, or regulations without notice, he shall bear all

    costs arising therefrom.

    3. Deviations from the Drawings and/or Specifications required for conformance with

    the applicable codes and/or laws shall be corrected immediately but not until such

    deviations have been brought to the attention of the Engineer.

    4. Applicable codes and/or laws to govern the minimum requirements only; where the

    Drawings and/or Specifications call for materials, vents, piping, sizes, etc., in excess

    of the code requirements, the Drawings and Specifications shall govern.

    B. Contractor Qualifications: All fueling system mechanical construction shall be by companies

    who have previously installed aviation fuel hydrant and fueling systems at major

    installations.

    1. All work done on the fuel system shall be performed by a company who has at least 5

    years experience.

    2. In addition, the person in charge of all craft personnel shall have at least 5 years

    experience in installing an aircraft fueling system.

    3. Prior to any activity under this specification section and no later than 30 days after

    Notice to Proceed, provide a listing of jobs which the company and the person in

    charge have performed which would qualify them to perform work under this

    specification section. This listing shall include job name, cost, location, duration,

    description of work and person whom the work was performed for, along with their

    telephone number(s).

    C. Welder Qualifications: All welding shall be performed by welders qualified to ANSI B31.4

    in accordance with the standards of American Welding Society. All welders shall be tested

    and certified as specified in AWS B3.0 Qualification Procedure, shall be qualified to perform

    any of the welding in compliance with standards and codes required irrespective of pressure

    or position classification. Test position required for each welder shall be 5G, inclined groove

    weld in pipe made by uphill procedures. All pipe welders shall be assigned an identification

    mark. Contractor shall secure the services of an Independent Testing Laboratory to certify

    each welder in accordance with ASME Boiler and Pressure Vessel Code, Section IX,

    Radiographic Examination. Welders failing to qualify after two unsuccessful attempts shall

    not be retested. Test welds shall be radiographed and radiographs shall be approved by the

    Engineer. Each welder shall possess a currently approved certificate issued by an

    Independent Testing Laboratory for this Contract; evidence of qualifications and certificate

    of possession shall be presented to the Engineer prior to performing welding under this

    Contract. Cost of welding certifications and radiographs shall be borne by Contractor.

    Contractor shall maintain an accurate, up-to-date list of welder identification marks.

    D. Mechanical Work Superintendent: Keep a competent superintendent and any necessary

    assistant satisfactory to the Engineer in charge during the progress of the work.

    Superintendent shall properly coordinate and time mechanical work with the work of other

    trades and in particular with concrete, masonry and formwork to avoid errors and delays.

    Contractor shall pay cost involved due to failure to comply with these requirements or due to

    failure to acquaint himself with the work and progress of other trades.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 8 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    E. Mechanical Work Coordinator:

    1. In addition to Contractor's Superintendent, furnish a coordinator for mechanical

    work. Coordinator shall be knowledgeable in the fabrication, assembly, and

    operation of the required mechanical systems and equipment, and the engineering

    essentials, including metallurgy, welding, rigging, and safety requirements.

    Coordinator shall be capable of reading, interpreting and coordinating the drawings,

    specifications, and submittal data of the mechanical work.

    2. Coordinator shall plan and expedite delivery of mechanical products to the Project

    site, and to schedule labor to meet the progress schedule of the work.

    3. Coordinator shall work with mechanical subcontractors and the contractors of other

    disciplines to coordinate the safe and timely completion of the work.

    F. Regulatory Requirements: The following codes, standards, and regulations cover the design,

    general hardware, construction, and quality control requirements for the fuel storage and

    handling systems. Unless otherwise indicated, the latest edition of the following codes and

    standards shall apply to the extent indicated herein:

    ANSI A13.1 Identification of Piping System

    ANSI B16.5 Steel Pipe Flanges and Flanged Fittings

    ANSI B16.9 Steel Butt Welded Fittings

    ANSI B16.10 Face to Face and End to End Dimensions of Ferrous Valves

    ANSI B16.11 Forge Steel Fittings, Socket Welding and Threaded

    ANSI B16.25 Butt Welded Ends

    ANSI B16.34 Valves, Flanged and Butt Welding Ends

    ANSI B18.2 Square and Hex Nuts

    ANSI B31.4 Liquid Transportation Systems for Hydrocarbons, Liquid

    Petroleum Gas, Anhydrous Ammonia, and Alcohols

    ANSI B36.10 Welded Seamless Wrought Steel Pipe

    ANSI B40.1 Gauges, Pressure indicating type, Elastic Element

    ANSI Z49.1 Welding and Cutting, Safety In

    API 5L Specification for Line Pipe

    API 6D Specification for Pipeline Valves, Enclosures, Connectors

    and Swivels

    API 601 Metallic Gaskets for piping, double Jacketed Corrugated

    and Spiral Wound

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 9 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    API 607 Valve Fire Safe

    API 609 Dimensional Standard for Butterfly Valves

    API 610 Centrifugal Pumps and Refinery Service

    API 1104 Standard for Welding Pipelines and Related Facilities

    API 1500 Storage and Handling of Aviation Fuels for Airports

    API 1529 Aviation Fueling Hose

    API 1542 Airport Equipment Marking for Fuel Identification

    API 1581 Specification and Qualification Procedures: Aviation jet

    Fuel Filter/Separators

    API 1584 Four Inch Hydrant System Components and Arrangements

    API RP2003 Protection Against Ignitions Arising out of Static, Lightning,

    Stray Currents

    API 2513 Cleaning Petroleum Storage Tanks

    ASME Section VIII Division 1 and 2 of Boiler and Pressure Vessel/Code

    (Unfired Pressure Vessels)

    ASTM A 36 Structural Steel

    ASTM A 53 Pipe, Steel, Black and Hot Dipped, Zinc-Coated Welded

    ASTM A 105 Forging, Carbon Steel for Piping Components

    ASTM A 216 Steel Castings, Carbon Suitable for Fusion Welding for

    High Temperature

    ASTM A 234 Piping Fittings or Wrought Carbon Steel and Alloy Steel

    for Moderate and Elevated Temperatures

    ASTM A 307 Carbon Steel Bolts and Studs, 60,000 psi Tensile

    Strength

    ASTM A 563 Carbon and Alloy Steel Nuts

    ASTM D 229 Rigid Sheet and Plate materials Used for Electrical Insulation

    ASTM E 94 Radiographic Testing

    NFPA 11 Four Inch Hydrant System Components

    NFPA 30 Flammable and Combustible Liquids Code

    NFPA 70 National Electrical Code

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 10 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    NFPA 78 Lightning Protection

    NFPA 410 Standard Aircraft Maintenance

    NFPA 407 Standard for Aircraft Fuel Servicing

    NFPA 415 Standard on Aircraft Fueling Ramp Drainage

    NFPA 419 Airport Water Systems

    SSPC SP-1 Solvent Cleaning

    SSPC-SP-10 Near-White Blast Cleaning

    1.6 PRODUCT HANDLING

    A. Provide and pay for all freight, express, trucking, transportation, cartage and handling of

    equipment and materials; assure materials, etc., be delivered to the Project site in ample

    quantities to ensure uninterrupted progress of work; provide and pay for extra handling and

    shipping expenses incurred in expediting materials, etc., to prevent interruption of the overall

    job progress.

    B. Protect all equipment, materials, specialties, etc., from any causes during shipment, storage,

    and erection until final acceptance by the Owner and be responsible for damages or losses

    incurred by these or other causes.

    C. Jet A-1 fuel Piping: Segregate aviation fuel piping from all other steel and follow special handling requirements. Take appropriate precautions and measures to protect the integrity of

    the Jet A-1 Fuel piping shop applied internal lining and externally applied coated or painted

    surfaces during receipt, storage, inspection, and installation, start-up and testing operations

    until final acceptance by the Owner and be responsible for damages or losses incurred by

    field handling operations.

    1.7 WARRANTY

    A. General: Warranty all works meeting provisions of the Conditions of the Contract, except

    warranty to include the additional provisions of this Article.

    B. Warranty shall extend to corrections of the work found to be defective or nonconforming to

    the Contract Documents at no additional charge to the Owner. Included are damages

    resulting from such defects or nonconformance with the Contract Documents. Excluded are

    defects resulting from improper maintenance, operation, or normal wear.

    C. Time Period: Repairs or replacement made to work within the warranty period shall be

    warranted for one year from date of final acceptance of each repair or replacement.

    PART 2 - PRODUCTS

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 11 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    2.1. All equipment and material shall be new, undamaged, of the best grade, unless otherwise

    specified; decisions concerning quality, fitness of materials, or workmanship shall be by the

    Engineer.

    2.2. Where items exceed one in number provide products with identical construction, model

    numbers, and appearance, from the same manufacturer.

    2.3. Insofar as possible, products shall be the standard design of the manufacturer. Manufacturer

    shall submit evidence that he has been engaged in the manufacture of the product for a

    minimum of 5 years. When standard products are modified to suit these Contract

    Documents, manufacturer shall certify operating conditions, ratings and capacity of the

    product and Contractor shall submit compliance certificates.

    2.4. Acceptable Products: Certain makes and/or manufacturers of material and equipment are

    specified herein and/or indicated on the accompanying Drawings as acceptable products.

    Prior to submittal, use manufacturer's published data to verify that the product meets the

    requirements of the Contract Documents. Notify the Engineer of conflicts.

    PART 3 - EXECUTION

    3.1 INSPECTION

    A. General: Examine the areas and conditions under which work is to be installed or performed,

    and remedy any conditions detrimental to the proper and timely completion of the work. Do

    not proceed with the work until unsatisfactory conditions have been corrected.

    B. Existing Facilities: Verify existence, location and operation of existing mechanical facilities

    to be abandoned, removed or altered.

    C. Cutting and Patching: Existing conditions of the work including elements subject to damage

    or to movement during cutting and patching. After uncovering work, inspect the conditions

    affecting installation of products, or performance of work.

    3.2 INSTALLATION

    A. General: Install work, meeting the requirements of the Contract Documents and in

    accordance with product manufacturer's instructions and recommendations.

    B. Workmanship:

    1. Perform the work as defined above in accordance with the best engineering practice

    and standards for this type of work. Follow the recommendations and instructions of

    the product manufacturer, unless otherwise specified or shown on the Contract

    Documents.

    2. Employ only competent, orderly persons, satisfactory to the Owner, who are skilled

    in the class of work to be performed.

    C. Cutting and Patching:

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 12 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    1. Perform all cutting, patching, carpentry, and masonry work required to accommodate

    work and to achieve the following:

    a. Make parts fit together properly.

    b. Remove and replace defective work.

    c. Remove and replace work not in conformance with Contract requirements.

    d. Remove samples of installed work as required for testing.

    e. Provide for penetration of non-structural surfaces for installation of piping,

    ducts, and electrical testing.

    f. Provide for previously approved penetration of structural surface for

    installation of piping, ducts, and electrical conduits.

    2. Provide adequate temporary support as necessary to assure structural value or

    integrity of affected portion of work. Provide devices or methods to protect other

    portions of Project which may be exposed to cutting and patching work.

    3. Patching shall conform to the surrounding surfaces in every respect, including

    painting, tiling, etc. Perform no cutting or patching without first obtaining approval

    of the Engineer. Cutting and patching of new concrete or masonry is not to be

    permitted unless absolutely necessary.

    4. Execute cutting and any demolition by methods which will prevent damage to other

    work, and will provide proper surface to receive installation of repairs.

    5. Execute fitting and adjustment of products to provide a finished installation to

    comply with specified products, functions, tolerance and finishes.

    6. Restore work which has been cut or removed; install new products to provide

    complete work in accordance with requirements of Contract Documents.

    7. Refinish entire surfaces as necessary to provide an even finish to match adjacent

    finishes. For continuous surfaces, refinish entire surface to the nearest natural break

    line.

    8. Fit work airtight and fire safe to pipes, sleeves, ducts, conduit and other penetrations

    through surfaces as required by the Contract Documents.

    9. Openings in existing concrete or masonry shall be core drilled, or perimeter scored,

    both sides, prior to removing construction from opening area.

    10. Do not cut metallic components, such as electrical conduits, piping and reinforcing

    steel, embedded in concrete for masonry construction, except after metallic

    components are identified and determined to be out of service or otherwise suitable

    for cutting.

    11. Do not permit fluid associated with cutting tools to migrate outside of immediate

    cutting area or into embedded conduit or piping.

    D. Welding:

    1. When required for safety, properly shield the welding area.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 13 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    2. Jet A-1 Fuel Piping Welding: Refer to Section 40192, "Jet A1 Fueling System -

    Piping Construction".

    3. Miscellaneous Welding: Welding procedure shall be governed by applicable service

    type specification of AWS D1.1.

    E. Surface Finishes: All surfaces and edges of miscellaneous steel, concrete, etc., shall be

    smooth and free of marks, burrs, roughness, and other defects. Finish welds to match parent

    material. Where possible, grind welds smooth; remove flux, oxide, splatter or any other

    residue from the weld and adjacent areas of exterior and interior surfaces. Do not use

    synthetic type filler putty as metal filler.

    F. Painting, Coatings, and Linings:

    1. All Jet A-1 Fuel piping to be installed below ground shall have the internal surfaces

    shop epoxy lined and the external surfaces shop coated in accordance with the

    instructions and requirements specified in Section 40193, Jet A1 Fueling System -

    Coatings and Corrosion Protection. All Jet A-1 Fuel piping to be installed

    aboveground shall be internally epoxy lined and externally primed and painted in

    accordance with Section 40193, Jet A1 Fueling System - Coatings and Corrosion

    Protection.

    2. All other miscellaneous items to be installed aboveground shall be primed and

    painted in accordance with the instructions and requirements specified in Section

    40193, Jet A1 Fueling System - Coatings and Corrosion Protection.

    3. Contractor shall be responsible for priming and painting all Jet A-1 fuel piping and

    ferrous metal surfaces not already suitably primed and painted in accordance with the

    requirements and limitations of Section 40193, Jet A1 Fueling System - Coatings

    and Corrosion Protection and the manufacturers instructions and recommended

    procedures.

    4. All machined surfaces shall be coated with a suitable rust preventative.

    G. Identification and Labeling:

    1. Provide labels and signs as called for in the Contract Documents and permanently

    attach or support same; piping identification in accordance with API 1542.

    2. All grades of pipe shall be identified by color code and also stamped with

    specification and grade. Shop wrapped pipe shall be stamped within 75 mm of ends

    to permit identification-after wrapping.

    H. Clean Up: Prior to acceptance tests and inspections, clean the Project site. Remove all

    miscellaneous construction equipment, dispose of all trash and unnecessary excavated

    material in a manner acceptable to the Engineer. Make the Project site as safe, clean and

    completely finished as possible.

    I. Inspections and Tests:

    1. General: Test all of the works covered by this Specification and demonstrate its

    proper operation to the Owner. Furnish all required labor, testing, instruments and

    devices required for tests and pay for all expenses involved in conducting such tests.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - BASIC MECHANICAL REQUIREMENT 40052 - Page 14 of 14 S09063-01D-PD-SPC-ME-02 REV 1

    If tests show work or equipment to be defective, immediately make all changes

    necessary to correct work and performance to the satisfaction of the Owner. Give 48

    hours written notice to the Owner of all tests and demonstrations. Provide safe

    access to the test area if the work is in preparation or in progress. Contractor will be

    given reasonable time to correct defects. If such correction of defects or performance

    requirements are neglected, the right is reserved to have defects remedied and to

    charge the cost of same against the account of the Contractor.

    2. Covered Equipment: No pipe or equipment shall be insulated or covered until

    hydrostatic or other required tests have been completed and approved. Where the

    Contractor considers this procedure unfeasible, he shall request a waiver from this

    requirement in writing which clearly defines, in a method statement, the exception to

    the procedure and the extent of the work involved. Where it is determined that

    taking exception to the procedure results in an increase in the cost of the project

    either in the first cost of material and labor or as a result of defects in the pipe or

    equipment which could have been corrected in a less costly fashion through the

    required tests prior to covering, the Contractor shall bear all costs associated with the

    exception to the procedure.

    3. Inspection: Inspection includes but is not limited to:

    a Blocking: Remove blocks and other similar devices used to block shafts

    during shipment to the field or during alignment work.

    b. Alignment: Check whether equipment has been aligned.

    c. Tension: Check belt or chain tension.

    d. Tightening: Tighten bolts, capscrews and other fasteners.

    e. Safety Guards: Check safety guards.

    J. Equipment Installation Acceptance: Before final acceptance, top-off all fluids, check all

    connections, and remove all remaining debris. Equipment installation will be accepted by

    Owner after running equipment under load in permanent operation.

    K. Contractor shall obtain prior approval from the Engineer when an existing fuel hydrant

    system is to be shutdown for modifications and or to support tie-in activities associated with

    the new fuel piping. Contractor shall obtain prior approval from the Engineer before cutting

    into any existing hydrant line(s).

    L. Jet A-1 Fuel drained out of existing hydrant lines, as part of or as a result of the Contractors

    work, shall be removed and returned to the Owner.

    END OF SECTION 40052

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - CATHODIC PROTECTION 40120 - Page 1 of 3 S09063-01D-SPC--ME-02 REV 1

    40120 - JET A1 FUELING SYSTEM - CATHODIC PROTECTION

    PART 1 GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the contract, including conditions of contract and

    Division 1 of the specification apply to this section.

    1.2 RELATED SECTIONS

    A. Division 40, Jet A1 Fueling System Basic Mechanical Requirement

    B. Division 40, Jet A1 Fueling System Inspection, Cleaning, Flushing, And Testing

    1.3 SUMMARY

    This Section details the minimum requirement for establishing, testing, commissioning and

    acceptance of the cathodic protection (CP) for the new fuel hydrant system.

    1.4 APPLICABLE CODES, STANDARD AND REGULATIONS

    The following International Codes, Standards and Regulation should be used as general

    source of reference:

    NACE RP0169-96 Control of External Corrosion on Underground or

    Submerged Metalic Piping Systems.

    BS 7361: Part 1: 1991 Cathodic Protection Part 1 Code of Practice for Land and

    Marine Applications.

    IEC 60502 External solid dielectric insulated power cables for rated

    voltages of 600/1000V up to 30kV

    PART 2 MATERIAL

    2.1 CP SYSTEM DESCRIPTION

    A. The CP system for the airside fuel line shall comprise of a CP transformer-rectifier (CP

    T/R) and a deep well groundbed. Location of CP transformer-rectifier to be within the fuel

    farm. Coordinate with engineer for location approval.

    Monitoring of the effectiveness of the CP system is made at test points installed along the

    route of the airside fuel line. The total number of test points shall be verified and justified

    through calculations and shall be submitted for Engineer approval.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - CATHODIC PROTECTION 40120 - Page 2 of 3 S09063-01D-SPC--ME-02 REV 1

    B. CP Transformer-Rectifier: The rating of the CP T/R is [60V / 100A] DC. The

    groundbed is assumed to be rated for minimum 20 years life at 100A output, but

    commissioning date is unavailable.

    C. CP Monitoring: The monitoring system shall comprise:

    1. Test facility as either,

    a) Cast iron heavy duty surface box Stanton, UK, model HB03, 225AN, BS grade A,

    test load 343kN c/w internal terminal board

    b) Cott Engineering, USA, Big Fink test post, c/w terminal board

    2. Permanent Cu/CuSO4 reference electrode at each test facility, Borin, USA STELTH 2

    brand, model SRE-007-CUY, c/w cable tail 15m of # 14 RHH-RHW.

    3. Test Cables as 1c x 16mm stranded Cu/HMWPE or XLPE/PVC (black)

    D. Summary: Sufficient capacity should be allowed in the installed cathodic protection system

    to allow for future piping additions. Allow for 200% extra capacity.

    2.2 TECHNICAL REQUIREMENT

    A. Scope of Work

    1. Submit calculation report justifying adequacy of cathodic protection system and

    describing monitoring philosophy.

    2. Confirm quantities and supply all cathodic protection equipment for fuel hydrant

    system.

    3. Install, test and commissioning all cathodic protection equipment.

    B. Material Specification

    1. Test Facilities

    Test facilities shall be Big Fink type at insulated flange/ insulation joint locations and

    flush surface box at other locations. The types shall be as detailed in 2.1.3 para a)

    above. A minimum of one test facility shall be provided between two fuel hydrant

    sectionalizing valves.

    2. Permanent Reference Cells

    These devices shall be as detailed in 2.1C.

    3. DC Cable

    This shall be 16mm copper conductor HMWPE or XLPE/PVC insulated.

    4. Ancillary Items

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - CATHODIC PROTECTION 40120 - Page 3 of 3 S09063-01D-SPC--ME-02 REV 1

    Items such as insulating materials, surge diverters, pipe connection material, cable lugs

    etc. shall be offered for acceptance by CONTRACTOR and are deemed included in

    scope of supply.

    PART 3 - EXECUTION

    A. Installation

    The CONTRACTOR shall produce method statements and procedures for all installation

    activities, for EMPLOYER/ENGINEER approval, prior to commencing on-site activities.

    B. Commissioning

    The CONTRACTOR shall produce method statements and procedures for all pre-

    commissioning and commissioning tests. These shall confirm satisfactory operation of all

    installed equipment and shall achieve protection of all structures in accordance with

    industry standards.

    A fully detailed commissioning report shall be produced.

    C. Operation and Maintenance

    A detailed O&M manual shall be produced containing all data pertaining to supply,

    installation, testing, commissioning, operation and maintenance of the completed CP

    system.

    END OF SECTION 40120

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 1 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    SECTION 40192 - JET A1 FUELING SYSTEM - PIPING CONSTRUCTION

    PART 1 - GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of the contract, including conditions of contract and

    Division 1 of the specification apply to this section.

    1.2 RELATED SECTIONS

    A. Division 140, Jet A1 Fueling System Cathodic Protection

    B. Division 40, Jet A1 Fueling System Basic Mechanical Requirement

    C. Division 40, Jet A1 Fueling System Coating And Corrosion

    D. Division 40, Jet A1 Fueling System Monitoring And Control (EFSO & Leak Detection)

    E. Division 40, Jet A1 Fueling System Inspection, Cleaning, Flushing, And Testing

    PART 2 - PRODUCTS

    2.1 STANDARD COMMERCIAL PRODUCTS

    A. Materials and equipment shall be standard products of a manufacturer regularly engaged in

    the manufacturing of such products, which are of a similar material, design and

    workmanship. The standard products shall have been in satisfactory commercial or industrial

    use for 5 years prior to bid opening. The 5 year use shall include applications of equipment

    and materials under similar circumstances and of similar size. The 5 years experience shall

    be satisfactorily completed by a product that has been sold or is offered for sale on the

    commercial market through advertisements, manufacturer's catalogs, or brochures. Products

    having less than a 5 year field service record shall not be acceptable. Products shall be

    supported by a service organization. System components shall be environmentally suitable

    for the indicated locations.

    B. Refer to Division 1 Section 01600, Paragragh 2.1

    2.2 PIPING MATERIALS

    A All Contractor supplied materials and equipment shall be new products of manufacturers

    regularly engaged in production of such equipment. All products shall conform to the

    applicable code or standard for its manufacturing, fabricating and installation.

    B. No zinc, cadmium, copper, or copper-bearing material shall be in liquid contact with the

    product fuel, unless otherwise specifically noted.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 2 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    C. Certification:

    1. All Contractor supplied pipe and fittings shall be tested and certified at the mill for

    conformance with the appropriate API or ASTM specification.

    2. Mill certification of all piping shall be submitted to the Engineer for approval.

    3. Mill identification shall be stamped and clearly visible within 50 mm of the pipe or

    fitting end. The mill identification on the pipe shall be directly traceable to the mill

    certification report, in order to specifically identify each piece of pipe or fitting as being

    fabricated from the steel tested under the mill certification.

    D. The ends of the pipe shall be capped at the factory using suitable galvanized metal or plastic

    caps, secured with a double wrap of 50-mm-wide pressure-sensitive tape. Plastic caps shall

    not be used in plugging or capping pipes after installation.

    E. Piping shall be internally epoxy lined and externally coated or painted in accordance with

    Section 40193 "Jet A1 Fueling System - Coatings and Corrosion Protection".

    2.3 PIPING SPECIFICATIONS

    A Jet A-1 Fuel Specification:

    Service Design Conditions Test

    Jet A-1 Fuel piping, including 264 psig; ambient 50C 396psig

    fuel drain and vent piping

    (including all lateral piping,

    and the normally pressurized

    portion of drain and vent piping).

    Jet A-1 Fuel piping vents and 264psig; ambient 50C 25 psig leak test.

    drain piping (normally non- (Compressed air

    pressurized portion of each of test with soap

    these lines) bubble check

    leaks)

    Jet A-1 Fuel piping, Double 264psig; ambient 50C 396psig

    Containment Pipe

    B. Piping and Fittings details:

    Item 2 Inch & Smaller 2-1/2 Inch & Larger

    Pipe API 5L Grade B Schedule 80, API 5L

    Seamless, plain ends. Grade B, Beveled ends Seamless or

    ERW, Schedule 40 for 3" to 10",

    standard wall thickness for 12" to

    16", and 0.500" nominal

    wall thickness pipe for 20" and 24

    diameter, longitudinal seam SAW or

    EFW, 0.500 nominal wall thickness

    for pipes 28 diameter and above.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 3 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    (SWA spiral seams are acceptable

    for casing pipe).

    Joints Use socket welded or Butt-weld

    screwed joints as specified

    for the piping construction on

    Design/Vendor drawings and/or

    to match the connecting equip-

    ment joint type/rating. Screwed

    joints shall not be used on any

    underground piping; screwed

    joints may be used only above

    ground or in pits (as required to

    connect to valves or equipment

    with threaded connections.)

    Flanges 150 lb. ANSI, B16.5 carbon steel, 150 lb. ANSI*, carbon steel,

    ASTM A 181 Class 70 or ASTM A 181 Class 70 or

    ASTM A 105 weld neck, RF ASTM A 105 weld neck,

    flanges. raised face (RF) flanges.

    *Note, that the 6 x 4 Hydrant Valves

    will be supplied with ANSI 300# RF

    flanged inlet connections. For each

    of these connections, use 300 lb.

    ANSI, carbon steel ASTM A181

    Class 70 weld neck RF flanges.

    Fittings ANSI b16.5 carbon steel,

    ASTM A 105, 3000 lb. rated Butt weld, ANSI B16.9, carbon

    for all underground services; steel, ASTM A 234 Grade B,

    Socket weld or screwed wall thickness to match pipe

    3000 lb. forge steel, ASTM

    A 105 Grade II, ANSI B16.11

    for aboveground services.

    Bolts, Same as 2-1/2 Inch & Larger Carbon steel, cadmium plated*,

    Studs, Nuts machine bolts and studs per ASTM

    A 193 Grade B7. Nuts shall be

    heavy hexagon, ASTM A 194 Grade

    2H, cadmium plated. *Note,

    cadmium shall not come into contact

    with the Jet A-1 Fuel and therefore

    these cadmium plated bolts, studs,

    and nuts shall only be used on the

    exterior of the Jet A-1 Fuel

    equipment and piping.

    Gaskets Same as 2-1/2 Inch & Larger Spiral-wound, Flexitallic Style

    CG.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 4 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2.4 LINING, COATING, AND PAINTING

    A. External surfaces of all mechanical equipment and aboveground steel piping shall be painted

    as specified in Section 40193 "Jet A1 Fueling System - Coatings and Corrosion Protection".

    Jet A-1 Fuel piping and fittings shall be internally epoxy lined and externally coated or

    painted as specified in Section 40193 "Jet A1 Fueling System - Coatings and Corrosion

    Protection".

    2.5 FITTINGS

    A. Butt-weld type carbon steel, ASTM A 234 Grade B, ANSI B16.9 for sizes 2-1/2 inches and

    larger. Wall thickness of fittings shall match wall thickness of pipe.

    B. Socket weld or screwed forged steel, ASTM A 105 Grade II, conforming to ANSI B16.11 for

    sizes 2 inches and smaller.

    C. Elbows shall be long radius 1.5D or 3D suitable for cleaning by pigging, unless otherwise

    specified and/or indicated on Drawings.

    D. Changes in direction of pipe, of other than 45 degrees or 90 degrees, shall be made as

    follows:

    1. With long-radius weld elbows cut to the proper angle and shop beveled.

    2. At the option of the Contractor, use long radius pipe-bends. Pipe roundness shall be

    maintained to factory tolerance for straight pipe lengths. Submit shop drawings of all

    bends and bending procedures for approval.

    3. Pipe bends are permitted in accordance with the requirements of ANSI B31.4.

    4. Pipe miters are not allowed.

    E. Branch Connections:

    1. Fabricated fittings may be used in lieu of butt welding tees branch connections.

    Fabricated fittings shall be forged steel fabricated from materials conforming to ASTM A

    105, standard weight steel, and shall conform to ANSI B16.11. Thickness shall match

    wall thickness of pipe.

    2. Forged fittings such as sweepolets or weldolets, or butt weld vesselets are to be as

    allowed under the requirements of ANSI B31.4.

    3. Threadolets or sockolets shall only be used for gauge, vent, sampling, and instrument

    connections.

    F. Finish of flange surfaces mating the gasket shall be phonographically serrated.

    G. Flange facings shall correspond to the equipment to which the piping is joined and shall,

    unless otherwise required, be standard 1.6-mm raised face flanges. Flanges for the

    horizontally installed Jet A-1 Fuel piping shall be oriented/ installed such that the bolt hole

    arrangement straddles the vertical line unless this conflicts with the flange bolt holes of

    interconnecting equipment (i.e., valves). Flange rating and drilling shall match the rating and

    drilling on equipment flanges.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 5 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2.6 GASKETS

    A. Gaskets shall be resistant to the effects of aviation hydrocarbon fuels and manufactured of

    fire-resistant materials.

    B. Ring gaskets shall be used for steel flanged joints with raised face flanges.

    C. Gaskets shall be spiral-wound construction with an integral 1/8-inch-thick metal gauge ring.

    D. Gasket shall be constructed from metal windings and an enclosed filler to a thickness of

    4.4 mm to compress to 3.2 mm to 3.4 mm under proper bolt torque.

    E. The metal windings shall be Type 304 stainless steel.

    2.7 BOLTS AND NUTS

    A. Machine alloy stud bolts shall be full thread, cadmium-plated carbon steel, heavy hexagon,

    conforming to ANSI B18.2.1 and ASTM A 193 Grade B7. Note: The cadmium plated

    material shall not be used at locations where it may come into contact with the Jet A-1 Fuel.

    Therefore, the use of cadmium-plated bolts, studs, nuts, washers, etc. is limited to Jet A-1

    Fueling system piping and equipment exterior applications.

    B. Nuts shall be cadmium-plated carbon steel, heavy hexagon conforming to ANSI B18.2.2 and

    ASTM A 194 Grade 2H.

    C. Cadmium plating shall be electro-deposit in accordance with ASTM A 165, Coating type TS.

    D. Provide washers under bolt head and nuts. Washers shall be cadmium plated ASTM F 436

    hardened steel washers.

    2.8 GATE VALVES

    A. Valves shall be steel valve, ANSI class 150, fire-safe rated in accordance with API 6FA,

    6FB, and 6FC. Valve flanges shall be steel, class 150 in accordance with ANSI B16.5.

    Valves shall be double block & bleed.

    B. Valves shall be rated for a minimum of 285 psig working pressure at 50 deg C.

    C. Valves shall be furnished with weatherproof handwheel operator and locking device.

    Valves 8 inches and larger shall be furnished with weatherproof gear operators with

    handwheel and locking device.

    D. Valve components shall be manufactured of the following materials:

    1. Valve body shall be cast carbon steel conforming to ASTM A 216, Grade WCB, or approved equal.

    2. Valve trim shall be 316 stainless steel, or approved equal.

    3. Seats and seals shall be Viton, or approved equal.

    4. Valve handle shall be Vinyl coated, plated carbon steel.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 6 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2.9 BALL VALVES

    A. Valves shall be ANSI class 150 valves, rated for 285 psig working pressure at 50 deg C.

    B. Valves shall be furnished with locking lever operators.

    C. Valve components shall be manufactured of the following materials:

    1. Valve body shall be cast carbon steel conforming to ASTM A 216, Grade WCB, or approved equal.

    2. Ball and trim shall be Type 316 stainless steel.

    3. Seats and seals shall be stainless steel or Viton.

    4. Handle shall be Vinyl coated, cadmium-plated carbon steel.

    D. Ball valves shall be rated fire safe in accordance with API 607.

    E. Acceptable Manufacturers:

    1. Grove Valve and Regulator Company

    2. Jamesbury Ball Valve.

    3. DeZurik, Unit of General Signal.

    4. Approved equal.

    2.10 DOUBLE BLOCK AND BLEED VALVES

    A. Double Block and Bleed (DB & B) plug valves shall be similar to Tru-Seal valves as

    manufactured by Orbit Valve Company or Twin Seal high-integrity positive shut-off

    valves, series C-800 as manufactured by General Valve Company or approved equal. The

    specifications listed below are for indication only. The DB&B valves shall meet the

    following requirements:

    1. Valves shall be quarter turn reduced port, non-lubricated, resilient seal, tapered

    plugged type with a mechanical means of freeing the plug before it is rotated from the

    closed to the opened position.

    2. Valves shall have manual body bleed valve to check scale integrity of valve in the

    closed position. Also each valve shall be provided with a thermal relief valve for

    body bleed.

    3. Valves shall have position indicator flag to show the exact plug position.

    B. Valve shall have ANSI 150 pound rating raised face body flanges.

    C. Valves smaller than 6 inch shall have hand wheel operators. Valves 6 inch and larger

    shall have gear operators with hand wheels.

    D. Valve components shall be manufactured of the following materials:

    1. Valve body, bonnet and plug shall be cast iron steel ASTM A 216-WCB chrome

    plated; or approved equal.

    2. Valve O-ring and back-up ring shall be viton.

    3. Seating slips shall be ductile iron ASTM A 536 GF 80-55-06; or approved equal

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 7 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2.11 WALL PENETRATION SEALS

    A. Pipe sleeves shall be installed at all points where the piping passes through concrete

    construction. Pipe-to-wall penetration closures shall be modular mechanical type, made

    up of jet fuel resistant interlocking rubber links shaped to fill the annular area between

    pipe and wall opening or outer casing, and joined together with machine bolts and nuts.

    Seal shall have sufficient inside diameter to provide a minimum of 13-mm clear distance

    between the pipe and the sleeve after being positioned and expanded against the outer

    wall by tightening the bolts. Seal shall be electrically non-conductive. Bearing plates or

    washers between seal elements and bolt heads and nuts shall be electrically non-

    conductive.

    B. Sleeves through concrete pits or slabs shall be 6.35 mm thick metal. Each sleeve shall

    extend through the respective pit wall or slab and shall be such that the pipe is accurately

    centered within the sleeve. The sleeve shall be securely anchored to prevent dislocation.

    C. Seal assembly shall be constructed of materials resistant to aviation jet fuels. "Link-Seal"

    seals as manufactured by Thunderline Corp., or approved equal, shall be deemed suitable

    to meet the requirements for wall penetration sealing.

    2.12 CASING INSULATORS

    A. Provide concentric insulators in pipe casing in intervals recommended by the insulator

    manufacturer, to support pipe without sags along the flow line gradient shown on the

    drawings, or as directed by the Engineer.

    B. Casing spacers shall be 300 mm wide, fusion coated, seal casing insulators with 50 mm wide,

    glass reinforced runners. The steel casing insulator shall be completely formed with runner

    studs, degreased, primed and heated. A polyvinyl chloride coating shall than be applied to a

    minimum thickness of 0.254 mm. Casing spacers shall be model C12G-2 as manufactured by

    PSI Industries, or approved equal.

    C. Insulators shall keep inner fuel pipe in concentric alignment throughout the casing length

    without obstruction continues draining and venting capabilities of the casing.

    2.13 HYDRANT VALVES

    A. New hydrant pit valves shall be manufactured by Avery-Hardoll, J.C. Carter, or approved

    equal. The specifications listed here-in after are for indication only.

    B. Hydrant pit valves will be 4" x 4" dual manually lanyard/air operated hydrant valves using

    dual operated pilot, with 4, 150 # ANSI B16.5 RF inlet flange, and outlet (top) connection

    shall be a 4 inch API 1584 adapter outlet flange. Valve assemblies shall include integral pilot

    valve and pressure equalizing valve, inlet side isolation valve (for maintenance of the upper

    valve assembly and pilot valve), integral 20 mesh screen, and 4 mesh inlet stone guard.

    C. Hydrant pit valve shall be supplied with inlet isolation ball valve for ease of removal and

    maintenance of the hydrant valve while the system is under pressure. The inlet isolation

    valve ball valve shall have 4 outlet to match the 4 inlet of the hydrant valve and 6, 300 #

    ANSI B 16.5 RF, inlet flange to match the 6 inch 300 # ANSI B16.5, RF flange suitable for

    handling type A-1 Jet Fuel. (Warner Lewis model WL 5518 or approved equal).

    D. Valve outlet shall consist of a self-sealing male coupling (API 1584 adapter) with a tethered

    dust cap. The hydrant valve outlet adapter shall be suitable for coupling the hydrant valve to

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 8 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    the hydrant dispenser inlet hose and shall be designed so that the hydrant dispensers can be

    connected or disconnected without spillage of fuel.

    E. Valve closing time shall be adjustable from 2 to 5 seconds.

    F. Materials:

    1. Outer housing shall be epoxy coated ASTM A 536, Grade 60-14-80 ductile iron; or

    approved equal.

    2. Trim shall be stainless steel, or approved equal.

    G. Valves shall be provided with 4 mesh stone guard (stainless steel strainer at inlet 6 inch

    flange), conical type.

    H. Hydrant valves shall not be installed until all tests and flushing are completed.

    2.14 LOW POINT AND HIGH POINT VALVES

    A. New low and high pit valves shall be similar to Avery-Hardoll, or approved equal, twin,

    40mm fire safe ball valves. The specifications listed here in after are for indication only.

    B. Valves shall be operated manually.

    C. Valves to be fitted with a standard 6 ANSI 300 (BS1560) flange it can be installed in

    standard hydrants pit externals.

    D. Venting valves shall be installed at high points in the hydrant line and at low draining points

    in the hydrant line.

    E. Vent and drainage valves shall not be installed until all tests are completed.

    2.15 HYDRANT VALVE, LOW-POINT DRAIN VALVE, AND HIGH-POINT VENT VALVE

    PITS

    A. Pits: Pits shall be environmentally friendly, prefabricated spehroidal graphite cast iron

    internally white epoxy coated in accordance with MIL-C-4556 D, and externally coated with

    black coal tar epoxy. Pits shall be accommodated with welded riser pipe, COPON, or

    approved equal, painted internally for bottom connection of fuel lines. Fuel piping

    connection to the pits shall be as shown on the Drawings and with sizes as follows:

    1. Hydrant Pits: 6-inch fuel line.

    2. Low-Point Drain Pits: 6-inch fuel line.

    3. High-Point Vent Pits: 6-inch fuel line.

    B. Pits: Pits shall have welded steel construction inner housing complete with 6" ANSI 300 lb

    raised face, made of carbon steel epoxy coated in accordance with MIL-C-4556D, with bolts,

    nuts and washers made of yellow anodized carbon steel with 3 spacer centralizing lugs. Pit

    shall be accommodated with fuel resistant sealing bellows type, elastometer, installed

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 9 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    between the outer housing and inner box to allow movement between boxes and shall be

    provided with removable leveling brackets to support the pit box while setting in concrete.

    C. Pit Covers:

    Light weight 18 inch diameter pit lid made of aluminium alloy designed to withstand aircraft

    tire loads with retaining cable secured with swivel fitting to prevent twisting/kinking, and

    fuel resilient pit lead seal.

    D. Potential Manufacturers include:

    1. Avery Hardoll.

    2. Warner Lewis.

    3. Dabico.

    4. or approved equal.

    PART 3 - EXECUTION

    3.1 PREPARATION FOR SHIPMENT - PIPE AND FITTINGS

    A General: Any Contractor furnished piping materials shall comply with the following marking

    requirements. After the piping coating has been inspected and approved, the following

    information shall be clearly stenciled onto the coated pipe surface. The paint used for

    stenciling shall not have any adverse effects on the coating.

    1. Purchasers name and purchase order number.

    2. Pipe and pipe tally number.

    B. The lined, coated pipe lengths and fittings shall be adequately cushioned for transport in

    order to prevent damage to the pipes or coating while loading and transporting. Suitable

    cushions may consist of wood-wool within sealed polyethylene sleeves.

    C. Unless otherwise specified, on completion of all coating work, pipe internals shall be visually

    inspected for cleanliness. Any dust or other debris shall be removed prior to fitting

    breathable covers for subsequent shipment.

    3.2 PIPE CLEANING REQUIREMENTS

    A. The importance of keeping the interior of the piping system thoroughly clean at all times is

    critical. Keep the interior of the piping clean of all visible dirt or foreign matter at all times

    and under all conditions. If, for any reason, the inside of the piping contains dirt or foreign

    matter, rectify this condition to the Engineer's satisfaction with all necessary material, labor,

    and equipment for cleaning being furnished at the Contractor's expense.

    B. The pipe shall be factory cleaned, internal surfaces epoxy lined, and external surfaces coated

    to a point 75 mm from each end in accordance with Section 40193 "Jet A1 Fueling System -

    Coatings and Corrosion Protection". The pipe shall be delivered to the Project site sealed.

    The seals shall not be removed until the pipe is installed. After each day's work, the open

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 10 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    ends of all pipes being installed shall be sealed closed with an expansion type weatherproof

    seal manufactured for this purpose.

    C. All fittings and valves shall be kept in a covered dry storage area until ready for installation.

    D. Pipe shall not be installed in ditches containing water or mud.

    E. At openings for branches in pipe, all material, which falls into the pipe, shall be removed

    before welding in the branch fittings.

    3.3 HANDLING PIPE

    A. Shipping, delivering, and installing pipe and accessories shall be handled in such manner as

    to ensure a sound undamaged condition. Particular care shall be taken not to injure pipe

    internal lining or external coating when storing pipe, lowering it into trench and when

    backfilling.

    B. No other pipe or materials of any kind shall be placed inside a pipe or fitting after the coating

    has been applied.

    C. Storage rack materials shall be 150 mm in bearing width and placed not more than 1830 mm

    apart.

    D. Do not rack pipe 10 inches in diameter and larger more than 2 sections in height; and pipe 8

    inches and smaller not more than 4 sections in height.

    E. Protect and prevent movement of all racked pipe by use of suitable padded material between

    sections.

    F. All trucks handling coated pipe shall have properly padded bolsters, padded chains, and

    padded binders so as to not damage the coating.

    G. Pipe shall not be dropped or rolled off the truck, but shall be carefully lowered onto skids

    using padded mechanical equipment.

    H. Coated and wrapped sections of pipe shall be lifted with nylon slings of approved width and

    shall not be dragged or pulled into position.

    3.4 LAYING UNDERGROUND PIPE

    A. Lay, embed, and maintain all underground pipelines to the flow-line elevation and grades

    shown on the Drawings or as directed by the Engineer. Pipelines shall be sloped uniformly

    between invert elevations.

    B. Unless otherwise specified on the Drawings or permitted by the Engineer, all pipe shall be

    installed in open cut trenches with vertical sides. Trenches shall be sheathed and braced to

    the extent necessary to maintain the sides of the trench in sloped or vertical position

    throughout the construction period. Adequacy of the sheathing and bracing shall be the

    responsibility of the Contractor. Excavation work shall be executed in accordance with the

    requirements specified below under "Civil Works Fuel Hydrants". Excavation work shall

    be planned such that the amount of trench can be safely excavated, the pipe laid, and the

    trench backfilled within a two day period. All trenching, excavation, sleeving and shoring

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 11 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    needed to cross under a utility shall be performed in accordance with the requirements

    specified below under "Civil Works Fuel Hydrants" and in the manner required by the

    party owning the utility and in such a manner as to assure no dislocation of the existing

    utility. Surface water and subsurface or ground water shall be prevented from flowing into

    trench excavations. Any accumulated water shall be promptly removed from the trench to

    prevent softening of the trench bottoms and soil changes detrimental to stability of the

    subgrade. Although trench size shall be minimized, the trench width and depth shall be such

    that proper clearance is provided adjacent to and beneath all parts of the piping and fittings

    for placement of the bedding material, cradle, jacket, etc. The minimum clearance on each

    side of the piping is 300 mm; the minimum clearance beneath the piping is 150 mm.

    C. All piping shall be installed in a continuous envelope of pipe bedding material. The bedding

    material shall extend from 150 mm below to 300 mm above the outer parts of the pipe,

    fittings, and accessories over the entire width of the excavation. Acceptable bedding

    materials/placement shall be as follows:

    1. Pipe Bedding: Sand: On-site borrow material, clay to silty fine sands that have been

    sampled, tested and approved by the Engineer and which complies with the requirements

    specified below under "Civil Works Fuel Hydrants". Place the bedding material such

    that the lower quarter of the pipe circumference is in continuous contact with backfill.

    Place the material carefully and uniformly up each side of the pipe in 0.15 m layers in a

    manner that assures compaction along the sides and haunches. Compact the bedding

    material uniformly under and around the pipe.

    2. Backfill: Backfill material, which is tested and complies with the requirements specified

    below under "Civil Works Fuel Hydrants". Place backfill immediately after the pipe

    has been bedded. When required by Section 40980, "Jet A1 Fueling System - Inspection,

    Cleaning, Flushing, and Testing", or by the Engineer, leave all joints exposed until all

    required testing is performed and accepted. Place and compact trench backfill to

    preclude a depression from ultimately forming at the surface along the trench.

    D. Complete backfill from top of bedding to grade with backfill. Place backfill materials in

    layers not more than 0.25 m in loose depth for material compacted by heavy compaction

    equipment and not more than 0.10 m in loose depth for material compacted by hand-operated

    equipment. Before compaction, moisten or aerate each layer as necessary to provide

    optimum moisture content of the soil material. Compact each layer to the required density

    for each area classification as defined below. Place backfill materials evenly adjacent to

    piping, tanks, and structures to the required elevations. Do not place layer of loose material

    until after compacted layer is tested and accepted by the Engineer.

    E. Compaction Density Requirements: Compaction of materials and compaction testing shall be

    in accordance with the requirements specified below under, "Civil Works". Results of the

    testing shall be submitted to the Engineer for evaluation and approval.

    F. Area Classification - Density: Compact soil materials for following area classifications to not

    less than the specified in-place density applicable for the type of soil material:

    1. Pipe Bedding - Sand: Compact top 150 mm of subgrade and each layer of backfill

    material to minimum of 98 percent maximum dry density at 2 percent of optimum

    moisture content.

    2. Backfill (Balance of Pipe Trench Excavations):

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 12 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    i. Within Structure Lines or Under Pavements: Compact each layer of backfill

    material to minimum of 98 percent maximum dry density at 2 percent of

    optimum moisture content.

    ii. Other areas: Compact each layer of backfill material to minimum of 90 percent

    maximum dry density.

    G. The full length of each section of pipe shall rest solidly upon the bedding material.

    H. Any pipe that has the grade or joint disturbed after being laid shall be taken up and re-laid.

    I. Do not lay pipe in water or when trench conditions are, in the judgment of the Engineer,

    unsuitable.

    J. Anchor pipe, in an approved manner, during installation to prevent flotation prior to

    placement in service. If the buoyancy requirements require the installation of concrete

    coating or installation of pipe weights, the Contractor shall notify, and obtain prior approval

    from, the Engineer, prior to proceeding with these installations.

    K. When work is not in progress, securely close open ends of pipe or fittings using approved

    expanding type watertight plugs to prevent trench water, earth, or other foreign substance

    from entering the pipe or fittings.

    L. Pipe coating shall be inspected with an electronic holiday tester in accordance with Section

    40980, "Jet A1 Fueling System - Inspection, Cleaning, Flushing, and Testing" prior to

    backfilling.

    3.5 WELDING

    A. Shop Welding: Piping shall be delivered to the Project site in double random pipe lengths.

    The shop welding shall be full penetration welds performed in accordance with welders and

    procedures qualified (certified) under API 1104 or Section IX of the ASME Boiler and

    Pressure Vessel Code. The pipe shall be designed and fabricated to the requirements of

    ANSI B31.4 and all shop welds shall be performed and 100 percent radiographically

    inspected in accordance with the requirements of API 1104. Welding operations,

    qualification of welders and welding procedures shall comply with the provisions of ANSI

    B31.4 and the requirements specified herein. Welding shall be done only by qualified

    welders and their qualifications shall be certified by the Contractor. Complete piping

    material certificates, weld records, welder qualification reports and weld inspections and

    radiographic records shall be submitted to the Engineer and piping and fittings materials

    delivered to the Project site.

    B. Field Welding, General: Unless otherwise approved, all field girth welds shall be complete

    penetration groove welds made in accordance with qualified welding procedures. Field

    welding operations, qualification of welders and welding procedures shall comply with the

    provisions of ANSI B31.4 and API 1104 and the requirements specified herein. Welding

    shall be accomplished by the use of the shielded metallic arc process and shall be performed

    in accordance with the requirements of ANSI B31.4. Welding processes and/or procedures

    that comply with any other standard will not be accepted. Welding shall be done only by

    qualified welders and their qualifications shall be certified by the Contractor.

    1. Definitions shall be in accordance with AWS A3.0.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 13 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2. Symbols shall be in accordance with AWS A2.4 for welding and non-destructive testing,

    unless otherwise indicated.

    3. Safety precautions shall conform to ANSI Z49.1.

    4. Weld preparation shall comply with the requirements of ANSI B31.4 and the

    Contractors qualified Welding Procedures.

    C. Welding electrodes shall be designed and made for use with the specific pipe metal to which

    it is applied and shall conform to the applicable AWS Specifications for welding rods and

    electrodes. Welding electrodes shall be suitably shielded. Prior to the start of field welding,

    Contractor shall obtain approval on the use of the specific welding electrode

    materials/procedures selected for the application.

    D. Not less than 15 days prior to performing any weld, submit to the Engineer for approval the

    welding procedure specifications (meeting the requirements of ANSI B31.4 and API 1104)

    proposed to be used on the work. Submittal shall include, as a minimum, the following:

    1. Certified copies of the procedure qualification test records confirming that the procedures

    have been qualified in accordance with ANSI B31.4 and Section IX of the ASME Code.

    2. Submit the records in a form similar to the "Procedure Qualification Record" and include

    the information required by Section IX of the ASME Code and ANSI B31.4.

    3. Welding procedure shall be designed for the conditions of this Project and shall be

    complete and specific, and shall differentiate between shop and field welding.

    4. Secure the services of a qualified independent testing laboratory to certify each welder.

    Welds shall be made and tested as required by ANSI B31.4, API 1104, and Section IX of

    the ASME Boiler Code. The following conditions shall apply for qualification testing of

    each welder:

    i. All welds shall be made in the uphill method.

    ii. All pipe groove welds shall be in test position 5G.

    iii. No backing rings shall be used.

    iv. All test welds shall be given a radiographic examination prior to the

    performance of bend test.

    v. All test welds shall be given the performance bend test.

    vi. Welders failing to qualify after two unsuccessful attempts shall not be re-

    tested and shall not be permitted to perform any welds on this Project.

    vii. All test results shall be submitted to the Engineer for approval.

    5. In addition to the above, each welder shall possess a currently approved certificate,

    meeting the requirements of these Specifications, issued by an approved testing authority.

    Satisfactory evidence as to qualifications and certificate possession shall be presented to

    the Engineer for each welder employed prior to any welding being performed.

    6. Costs incidental to these procedures and the welders qualification tests shall be borne by

    the Contractor.

    E. Identification:

    1. Each welder shall identify his weld with specific code marking signifying his name and

    assigned number.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 14 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    2. The Contractor shall maintain an up-to-date record of the welders and the code assigned

    to each welder.

    3. The welder shall stamp his code on the pipe, not farther than 100 mm from a weld, using

    a "low stress" steel stamp or other approved methods that will not damage the pipe or

    pipe coating system.

    4. The Contractor shall indicate, on his set of drawings for submittal as record drawings (as-

    built), the location of each weld by number and the respective welder's identification

    code. The identification methods to be used by the Contractor shall be submitted to the

    Engineer along with the respective welders' qualification test records.

    F. Preparation of Pipe Ends for Butt Welding:

    1. Preparing pipe ends shall be in accordance with ANSI B31.4.

    2. Shop and field bevels shall be machine cut; manual flame cutting will not be permitted.

    G. Backing rings shall not be used.

    H. All welds shall have full penetration and fusion and shall conform to ANSI B31.4.

    I. Align pipe joints with pipe clamps prior to welding. Clamps or other alignment devices shall

    not reduce the internal pipe diameter.

    J. Any weld or weld repair, once started, shall be continued until the weld has been completed.

    K. Defective welds shall be repaired or redone, in accordance with ANSI B31.4 and approved

    procedures at the Contractor's expense. Defects discovered between passes shall be repaired

    before additional weld material is deposited. Whenever a defect is removed and repair by

    welding is not required, the affected area shall be blended into the surrounding surface so as

    to avoid sharp notches, crevices, or corners. After a defect is thought to have been removed,

    and prior to rewelding, the area shall be examined by suitable methods to ensure that the

    defect has been eliminated. After repairs have been made, the repaired area shall be

    reinspected and shall meet the standards of acceptance for the original weld. Any indication

    of a defect shall be regarded as a defect unless reevaluation by nondestructive methods

    and/or by surface conditioning shows that no unacceptable defect is present.

    L. Repairs to defective welds shall not be made prior to authorization. The Engineer will

    determine on the basis of the testing laboratory report if repairs may be made or if the entire

    joint shall be cut out and welded again.

    M. No weld metal shall project within the piping at completion of the welding. All weld

    material and burrs protruding outside the pipe's outer surface shall be ground smooth.

    N. Prior to welding, each joint shall be cleaned and all rust and loose debris and contaminants

    removed.

    O. Any welder producing more than a total of 3 defective welds shall be disqualified and

    prohibited from performing any more welds on this Contract.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 15 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    3.6 RADIOGRAPHING AND MAGNETIC PARTICLE TESTING

    A. All welds on carbon steel pipe shall be examined by radiographic methods to determine

    conformance to the paragraph entitled "Standards of Acceptance". The Contractor shall

    employ, at no cost to the Owner, a recognized independent testing laboratory to test the items

    indicated below by radiography. All fillet and seal welds shall be tested by magnetic particle

    testing method. All costs of testing, including re-testing of repaired welds, shall be borne by

    the Contractor. Tests shall be performed for:

    1. 100 percent of all circumferential shop welds.

    2. 100 percent of all circumferential field welds on underground piping/fittings.

    3. Standards of Acceptance: Interpretation of test results for inadequate penetration,

    incomplete fusion, porosity or gas pockets, cracks, etc. in welds shall comply with the

    requirements set forth under "Standards of Acceptability - Nondestructive Testing" in

    API 1104.

    B. The Contractor shall cooperate with the testing laboratory and shall give the Owner, the

    Engineer, and the testing laboratory adequate advance notice of when welds will be available

    for radiographing and that all the work required by the Contractor in connection with the

    welding prior to radiographing is properly completed.

    C. Laboratory testing report shall be timely submitted, to the Engineer, throughout the progress

    of the work, and the Contractor will be notified of any encountered deficiency.

    D. Reports of all radiographing and magnetic particle testing shall be prepared in accordance

    with the requirements of ANSI B31.4. The reports shall include welder's code, weld

    identification and description, whether the weld meets the specification requirements, the

    film type and size, and remarks on imperfections. All subsequent report formats shall be in

    accordance with the requirements of Section IX of the ASME Code.

    E. Radiograph exposure film negatives will be kept on file by the Engineer; the record for such

    radiograph film negative will show the date, location of tested weld (coordinate d with weld

    location as shown on the Contractor's as-built drawings), area, film number, serial number,

    film combination, time, source-film distance, angulation and other pertinent information for

    each weld radiographed.

    F. A summary of these records along with an expert interpretation of the tests shall be prepared

    by the testing laboratory and submitted in a report form for each weld, to the Engineer.

    Interpretation of negatives shall be by a Level 3 radiographic technician certified by

    examination by the American Society of Non-Destructive Testing.

    G. All welds shall be left exposed until all testing (radiographing and magnetic particle) is

    completed and welds have been accepted by the Engineer.

    H. Acceptance criteria for welds shall be in accordance with ANSI B31.4 and API 1104

    requirements for severe cyclic conditions. Welds which do not meet the standards of

    acceptability will be judged unacceptable and shall be repaired or cut out and rewelded by

    the Contractor as directed by the Engineer at no additional cost to the Owner. Repaired and

    rewelded joints shall then be re-radiographed. If the same joint, after the second welding and

    radiographing fails again, then the section(s) of involved pipe shall be removed and replaced

    at no cost to the Owner.

  • Saudia Aerospace Engineering Industries

    Aircrafts Maintenance Hangars

    JET A1 FUELING SYSTEM - PIPING CONSTRUCTION 40192 - Page 16 of 16 S09063-01D-PD-SPC-ME-02 REV 1

    I. All the costs of the original radiographing and re-radiographing of unacceptable w