jfh construction vehicle movements
TRANSCRIPT
States of Jersey
Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706
Issue | 22 June 2017
This report takes into account the particular
instructions and requirements of our client.
It is not intended for and should not be relied
upon by any third party and no responsibility
is undertaken to any third party.
Job number 237035
Ove Arup & Partners Ltd
13 Fitzroy Street
London
W1T 4BQ
United Kingdom
www.arup.com
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Document Verification
Job title Jersey Future Hospital Job number
237035
Document title Construction Vehicle Movements - Version Two File reference
AB
Document ref REP/AEB/021706
Revision Date Filename 2017-06-14 JFH Car Park & Construction Logistics Trips
v2.docx
Issue 14 Jun
2017
Description Client comments addressed
Prepared by Checked by Approved by
Name Alan Beadle Fraser Dryburgh Fraser Dryburgh
Signature
Issue 22 Jun
2017 Filename
2017-06-21 JFH Car Park & Construction Logistics Trips
Issue.docx Description Included ready mix concrete data supplied by Arup Cardiff
Prepared by Checked by Approved by
Name
Signature
Filename
Description
Prepared by Checked by Approved by
Name
Signature
Issue Document Verification with Document
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Contents Page
1 Introduction 1
2 Assumptions 3
2.1 Trip Rates Construction Traffic 3
2.2 Working Hours 3
2.3 Construction Vehicle Profile 3
3 Construction Traffic 4
3.1 Construction Vehicles and Plant 4
3.2 Stakeholder Impact Assessment 6
3.3 Managing construction traffic 9
4 Construction Traffic Calculations 11
4.1 Demolition Phase 11
4.2 Construction Mobilisation Phase 11
4.3 Construction Phase 12
4.4 Post Completion Phase 13
4.5 Summary 13
Tables
Table 1 Demolition and construction area schedule
Table 2 Simplified demolition and construction programme
Table 3 Percentage by type of construction vehicle
Table 4 Percentage by purpose of delivery
Table 5 Summary of vehicle type and use
Table 6 Indicative list of plant and equipment by construction phase
Table 7 Potential impacts from demolition and construction activities
Table 8 Construction Traffic Management Plan
Table 9 Demolition vehicles
Table 10 Construction mobilisation vehicles
Table 11 Construction ready mix concrete deliveries
Table 12 Superstructure construction deliveries
Table 13 Post completion vehicles
Table 14 Summary of construction vehicle movements
Figures
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Figure 1 Site Location (Arup Structural Engineering Stage 1 report)
Appendices
Appendix A
Jersey Future Hospital - Worksheet
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 1
1 Introduction
As part of the ongoing redevelopment of the existing Jersey General Hospital an
area of the current estate, as well as some of the surrounding buildings, will be
demolished to make way for a new-build hospital, the project is known as Jersey
Future Hospital (JFH). This building consists of a single storey partial basement,
with up to 8 storeys above ground. In addition to this work, it is proposed to add
two half decks of car parking (1,290m2) as part of the extension. This process will
include the demolishing and rebuilding of an existing car park (900m2).
The current general hospital site is located on Gloucester Street to the west of St
Helier town centre, and is bounded by Kensington Place to the north, by Newgate
Street to the west and by The Parade to the east. The hospital estate consists of
nine main structures, refer to Figure 1.
Figure 1 Site Location (Arup Structural Engineering Stage 1 report)
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 2
The existing buildings to be demolished and the gross area used later in the report
for calculating construction traffic are set out in Table 1.
Jersey Future Hospital: Demolition & Construction Area Schedule
Building Gross Area (m2)
Peter Crill House 4,949
Gwyneth Huelin Block 5,693
Hotels (estimate) 6,000
Existing Car Parking (to be demolished) 900
Proposed Car Parking (to be constructed) 2,580
Total 20,122
Table 1 Demolition and construction area schedule
Those elements of the programme that have been used to calculate the level of
construction activity are as follows:
Demolition – break out and removal of any existing structures;
Construction Mobilisation – ground works and foundations;
Construction – above ground construction activities; and
Post Completion Activities – fit-out of completed structures.
The programme used for calculations within this report is shown in Table 2.
Construction Programme
Main Scheme Delivery Working Days Working Months
(Rounded Down)
Demolition 160 7
Construction Mobilisation 90 4
Construction 800 36
Post Completion Activities 90 4
Total 1,140 51
Table 2 Simplified demolition and construction programme
This report sets out the following:
Section Two – presents the assumptions used in the model used to calculate
the estimate vehicle movements to the construction site;
Section Three – presents information on the type and nature of vehicles
expected throughout the duration of construction activities. This is followed
by an assessment of the impact these vehicles may have on local stakeholders,
and finally a review of the requirements for a construction management plan.
Section Four – presents the estimated daily trips for construction activities
associated with the JFH.
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 3
2 Assumptions
This section sets out the assumptions for the calculations and sizing of logistics
areas.
2.1 Trip Rates Construction Traffic
Trip rates, expressed as number of vehicles/100m2, applied during this study are
as follows:
Demolition: 8 vehicles/100m2/day;
Sub Structure: 5 vehicles/100m2/day;
Concrete pours: 15 vehicles/100m2/day;
Super Structure: 10 vehicles/100m2/day; and
Fit-out: 7 vehicles/100m2/day.
2.2 Working Hours
Working hours will be in accordance with the requirements of the Considerate
Constructors Scheme, currently no anticipated requirement for activities to be
undertaken outside these times:
• 0800 – 1800 Monday to Friday.
2.3 Construction Vehicle Profile
The percentage of construction traffic by vehicle type is shown in Table 3.
Percentage - Construction Vehicle by Type
Vehicle Percentage
Light Goods Vehicle 14
Medium Goods Vehicle 66
Heavy Goods Vehicle 20
Table 3 Percentage by type of construction vehicle
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 4
The breakdown of construction trips used in the calculations are presented in
Table 4.
Percentage - Purpose of Delivery
Delivery Percentage
Collection 14
Delivery 80
Waste 6
Table 4 Percentage by purpose of delivery
3 Construction Traffic
This section sets out to provide guidance and information on the type of
construction movements and types of vehicles used to process waste and goods
into and away from the construction site. The types of vehicle movements
associated with construction traffic are as follows:
Workforce movements to/from the site;
Deliveries made to the site;
Removal of material from the site; and
Trips made by associated trades.
Each of these movements will be associated with different types of vehicle or
plant. These vehicles are considered in the next section.
3.1 Construction Vehicles and Plant
Consideration should be given to the type of vehicle and plant that is likely to be
used during the demolition and construction works. These may be identified and
grouped according to their size:
Car/pick up/3.5 ton van;
7.5 ton box van/panel van;
Low loader and articulated Heavy Goods Vehicle (HGV);
Ready mix concrete truck;
Mobile crane;
Water bowsers;
Road cleaning vehicles;
Skip lorry; and
32 ton tipper truck.
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 5
Vehicles and plant equipment associated with the construction process is
presented in Table 5.
Summary of Vehicle Type, Use and Distribution
Vehicle Type Use Distribution
Rigid Heavy Goods Vehicle Demolition arising, excavated
material removal. Tipper
trucks and ready-mix concrete
vehicles.
Strategic road network
Small Articulated Vehicle
Plant, steelwork, bricks
and cladding panels.
Strategic road network
Specialised Articulated Heavy
Goods Vehicle
Tower crane erection &
dismantle, mechanical &
electrical plant, cladding
panels. Roofing materials.
Strategic road network
Specialised Equipment Low
Loader
Occasional delivery of plant. Strategic road network
Vans Plant service, materials, other
suppliers. Existing tenant
deliveries.
Distributed to local
Table 5 Summary of vehicle type and use
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 6
The type of vehicle and plant that would be typically associated with each of the
construction phases is shown in Table 6.
Estimated Types of Plant and Equipment for Demolition and Construction
Plant Demolition Substructure Superstructure Fit out
Excavators / with
hydraulic cutting
shears √ √ - -
Mini / Tripod piling
rigs - √ - -
Excavators √ √ - -
Compressors √ √ √ √
Muck away lorries √ √ - -
Hoist tower √ √ √ √
Tower crane √ √ √ -
Mobile concrete
pump - √ √ -
General waste skips √ √ √ √
Power tools √ √ √ √
Delivery vehicles √ √ √ √
Forklifts √ √ √ √
Scaffold access
Platforms √ √ √ -
Mobile towers √ √ √ √
√ indicates plant will be used during that stage of the works
Table 6 Indicative list of plant and equipment by construction phase
Developments are often completed in phases, with earlier stages often requiring
greater use of HGVs for site clearance and bulk delivery of construction materials.
3.2 Stakeholder Impact Assessment
An assessment should be made to assess and address the impact of construction
activity upon all stakeholders, including pedestrians, cyclists, public transport and
vehicular users, and include consideration of the access and servicing
requirements of affected residential and commercial premises. The use of
temporary traffic and site management measures can have a wide range of
repercussions for different users, which are illustrated below:
Pedestrian footways narrowed, temporary closures, diversions and temporary
footways of varying quality;
Cycles routes closed, narrowed, diverted, reallocation of parking;
Bus services diverted, suspended and relocation of bus stops and stands;
Taxis rank relocation;
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 7
In terms of traffic movements:
Lane closures and/or shuttle working with signal control;
Introduction of one-way streets, reversed flows and removal or introduction of
banned turns;
Road closures with signed diversions;
Changes to traffic signal timings;
Temporary speed limits;
Parking suspension and/or reallocation; and
Disruption arising from the construction site is generally more localised in its
effects, typically noise, vibration, dust and dirt, and a loss of amenity due to
the presence of heavy construction traffic.
The potential source of adverse impacts associated with demolition and
construction works are presented in table 7.
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 8
Potential Impacts During Demolition and Construction
Issue Potential Impacts
Noise Increased road noise levels from vehicles. Increased noise levels
from plant during demolition, piling and general construction works
(e.g. from the use of air compressors and diamond cutters).
Vibration Increased vibration levels from vehicles. Increased vibration levels
from plant during demolition, piling and general construction works
(e.g. from piling rigs).
Dust / Air
Quality
Windblown dust from ground surfaces, stockpiles, vehicles, work
faces and cutting and grinding of materials. Exhaust emissions from
lorries and plant delivering and removing materials including dust
and particulates.
Waste Waste generation and its disposal.
Water Increased sediment loadings to storm-water system. Potentially
contaminated storm-water runoff.
Traffic Traffic congestion caused by site traffic and traffic associated with
road diversions and deliveries. Increased vehicle movements mainly
consisting of Heavy Goods Vehicles (HGVs). Transfer of mud and
material from vehicles onto the public highway. Disruption from
abnormal or hazardous loads. Exhaust emissions.
Storage of fuels and
construction
materials
Accidental spills, discharges to drains/storm-water systems,
contamination to ground.
Pedestrian access
Restrictions on pedestrian access to walkways, footpaths and roads.
Hazardous and contaminated
materials
Exposure of the workforce to deleterious / hazardous materials and
contaminated land, mobilisation of any source contaminants and
creation of pathway from source to groundwater receptor.
Ecology Water / mud runoff into the drains.
Energy Usage
Indirect impacts associated with energy consumption such as CO2
emissions, depletion of natural resources, air pollution etc.
Views
Views impacted and/ or impeded from construction equipment,
particularly cranes.
Table 7 Potential impacts from demolition and construction activities
The role of the principal contractor will be to implement a Demolition and
Construction Method Statement (DCMS). The DCMS will be a contractual
document outlining the different procedures to be undertaken to complete the
various works. Individual subcontractors will incorporate requirements for
environmental control, based on good working practice, such as careful
programming, resource conservation, adhering to health and safety regulations
and quality procedures. In this way those involved with the demolition and
construction phase, including subcontractors and site management, will be
committed to adopt the agreed best practice and environmentally sound methods.
The DCMS will be prepared in consultation with and approved by the local
authority. The subcontractors will be required to demonstrate how they will meet
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 9
the target of the DCMS and how the potential impacts will be offset, reduced or
minimised. The DCMS will include the following main items:
The Demolition and Construction Programme;
A broad plan of the demolition and construction works, highlighting the
various stages and their context within the project;
Detailed site layout arrangements (including requirements for temporary
works), plans for storage, accommodation, vehicular movements, delivery and
access;
Prohibited or restricted operations (locations, hours, etc.);
Details of operations that are likely to result in disturbance, with an indication
of the expected duration of each phase with key dates, including a procedure
for prior notification to the local authority and relevant statutory and non-
statutory (including neighbours) parties so that local arrangements can be
agreed; and
Site working hours.
A procedure to ensure communication is maintained via the contractor with the
local authority and local community to provide information on any operations
likely to cause disturbance (through, for example, meetings and newsletters).
3.3 Managing construction traffic
This should be prepared in consultation with highway and traffic authorities and
provide the strategy for managing and mitigating the identified impacts. It should
address:
site boundaries and main access/egress locations;
traffic management strategy;
temporary and permanent closures and diversions of highways and public
rights of way;
HGV routing (both locally and if necessary strategically), including signing,
holding areas/consolidation centres, abnormal loads, prohibited routes and means
of monitoring HGV use.
Requirements for a Construction Traffic Management Plan are set out in Table 8.
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 10
Construction Traffic Management Plan
Measure Considerations
Supply Chain
Optimisation
The logistics industry has developed a range of techniques to
maximise efficiencies within the supply chain. Perhaps most well-
known is the concept of ‘Just In Time’ delivery, although general
supply chain optimisation addresses ranging, procurement, storage,
distribution and back loading activities to maximise load
optimisation.
Delivery logistics Delivery booking (deliveries by pre-arranged time slots), which can
be used to enable delivery of materials either as part of a Just in
Time operation so that materials only arrive on site when needed
scheduled), or as part of a ‘smoothing’ operation to enable the peaks
and troughs in demand to be evened out over a period of time, or to
avoid certain time periods such as morning and evening peaks, or
school start and finish times.
Load Consolidation Off-site consolidation of materials (where suitable off-site can be
identified and procured), providing ‘Just In Time’ deliveries and
reducing access congestion and on-site material storage. This is
particularly useful if the development site is constrained for suitable
storage space, or faces access constraints.
Route Mapping Routing and scheduling arrivals may make it possible to reduce trips
to a site, by providing a more organised, logistical style method of
operation. Routes should be surveyed and swept path analysis
undertaken.
Operating Hours Restricted site operating hours, especially on sites adjacent to
sensitive sites such as schools, hospitals and residential areas.
Construction Travel Plan Employees to use walking, cycling and/or using public transport can
reduce the number of trips to a site. A minibus may be used to
transport workers in bulk to the site. This has the advantage of
restricting traffic generation to the daily arrival and departure of
staff employed on site, as well as removing the need for car parking
facilities on site.
Programme Compression The severity of any adverse impacts could be balanced by
compressing the programme of phases, thereby causing greater
disruption over a shorter time period, or overlapping certain
activities.
Noise Restrict operating hours, compress activities to minimise disruption.
Vibration Restrict operating hours, compress activities to minimise disruption.
Dirt Wheel washing and load covering.
Construction Methods Consider alternative construction methods, such as prefabrication,
onsite concrete mixing etc. to minimise external site trips.
Table 8 Construction Traffic Management Plan
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 11
4 Construction Traffic Calculations
This section sets out the estimated number of construction vehicles for JFH for
each of the four phases of construction. The calculations are based on survey data
obtained from a range of sites within central London. These sites varied from
small (12,999m2), medium (42,000m2) and large (68,000m2) developments in
terms of area. This study includes the number of vehicle movements associated
with the partial demolition and construction of the car park as follows:
The partial demolition of the existing car park applying an area of 900m2; and
The construction of the new half decks applying an area of 2,580m2.
4.1 Demolition Phase
This section looks at the number of vehicles anticipated to move the demolition
waste from the site. The estimated trips associated with demolition activities is
shown in Table 9.
Jersey Future Hospital – Demolition Vehicle Trips
Phase Duration
(months)
Total
Vehicles
Average
Vehicles/Month
Peak Day
Movements
Demolition 7 1,669 238 12
Table 9 Demolition vehicles
4.2 Construction Mobilisation Phase
The sub structure as defined in the model includes the construction mobilisation
activities (90 days) the first three months of the construction phase. Table 10
presents the estimated vehicle trips to the site.
Jersey Future Hospital – Construction Mobilisation Vehicle Trips
Phase Duration
(months)
Total
Vehicles
Average
Vehicles/Month
Peak Day
Movements
Sub Structure 3 1,044 348 18
Table 10 Construction mobilisation vehicles
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 12
4.3 Construction Phase
4.3.1 Concrete Pours - Foundations
This section sets out the total for the peak number of deliveries associated with the
construction phase of the project including the ready mix concrete trucks for
completing the foundations. This will be the busiest period of the process in terms
of daily deliveries. It is proposed to deliver concrete during following times:
12 No. deliveries between 08:30 – 09:30 hours, a total of 12 deliveries; and
10 No. deliveries per hour between 09:30 – 15:30 hours, a total of 60
deliveries.
A further 12 daily deliveries are proposed for all other site activities. Therefore, it
is estimated that 84 deliveries per day (with a peak hour of 12 deliveries) would
visit the construction site. Table 11 presents the estimated vehicle trips for this
time.
Jersey Future Hospital – Ready Mix Concrete Vehicle Trips
Phase Duration
(months)
Total
Vehicles
Average
Vehicles/Month
Peak Day
Movements
Sub Structure 3 5,544 1,848 84
Table 11 Construction ready mix concrete deliveries
4.3.2 Construction – Superstructure
Table 12 presents the estimated number of vehicles anticipated during the super
structure phase.
Jersey Future Hospital – Completion Vehicle Trips
Phase Duration
(months)
Total
Vehicles
Average
Vehicles/Month
Peak Day
Movements
Super Structure 24 1,945 81 5
Table 12 Superstructure construction deliveries
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page 13
4.4 Post Completion Phase
This section looks at the number of vehicles anticipated during the fit out stage of
the development and presented in Table 13.
Jersey Future Hospital – Post Completion Vehicle Trips
Phase Duration
(months)
Total
Vehicles
Average
Vehicles/Month
Peak Day
Movements
Fit Out 4 1,352 338 20
Table 13 Post completion vehicles
4.5 Summary
Table 14 summarises the number of vehicle trips estimated for each of the four
construction phases.
Jersey Future Hospital – Construction Logistics Vehicle Movements
Phase Vehicles Average
Vehicles/Month
Peak Day
Movements
Demolition 1,669 238 12
Construction Mobilisation 1,044 261 18
Ready mix concrete 5,544 1,848 84
Construction 1,949 81 5
Post Completion 1,352 338 20
Total 11,558 - -
Table 14 Summary of construction vehicle movements
States of Jersey Jersey Future Hospital
Construction Vehicle Movements - Version Two
REP/AEB/021706 | Issue | 22 June 2017
K:\23\237035-91 JERSEY FUTURE HOSPITAL\4 INTERNAL PROJECT DATA\4-05 REPORTS\2017-06-21 JFH CAR PARK & CONSTRUCTION LOGISTICS TRIPS ISSUE.DOCX
Page A1
A1 Construction Traffic Worksheet