Jim Markey Commercial/Industrial Construction Professional A brief review of some of the projects I have directed since 2000.

Upload: j4359markey

Post on 14-Jul-2015

73 views

Category:

Career


1 download

TRANSCRIPT

Jim MarkeyCommercial/Industrial Construction Professional

A brief review of some of the projects I have directed since 2000.

Grand Rapids, MIFedEx Freight – New Distribution Facility, 2011

Size: 55,489 s.f. Land: 23.8 acres Cost: $3.8 mil Features:

Precast concrete exterior wall at offices Pre-engineered metal building warehouse 6,969 s.f. finished office and 1,880 s.f. office pod 93 dock doors 4-bay mechanic’s shop, wash bay and 2-lane fuel island

FXF-Grand Rapids – Precast office facility for 93 door distribution facility

FXF-Grand Rapids – View of interior of dock facility looking towards office

FXF-Grand Rapids – Mechanic’s Shop and 2-lane Fuel Island at site

So. Brunswick N.J.FedEx Ground Distribution Ctr, 2008

Size: 219,092 s.f. Land: 27 acres Cost: $29.5 mil Features:

Precast concrete Structural steel frame and roof Finished office Vehicle maintenance facility Truck fueling island Security facility

FXG-So. Brunswick – Aerial View to SW

FXG-So. Brunswick – SW Office Entrance

FXG-So. Brunswick – North Truck Dock

FXG-So. Brunswick – Fuel Island

Orion Township, MIFedEx Ground Distribution Ctr, 2007

Size: 193,660 s.f. Land: 25.7 acres Cost: $13.9 mil Features:

Precast concrete Structural steel frame Finished office Vehicle maintenance facility Truck fueling island Security facility

FXG-Orion Twnp – Aerial of Truck Docks

FXG-Orion Twnp – Package Sorting and Truck Loading

FXG-Orion Twnp – Vehicle Maintenance Facility

FXG-Orion Twnp – Vehicle Fueling Island

Clarksburg, WVFedEx Ground Distribution Ctr, 2006

Size: 39,383 s.f. Land: 7.5 acres Cost: $3.3 mil Features:

Pre-engineered metal building Split-face masonry office façade Infrared warehouse heating T5 Fluorescent warehouse lighting Abbreviated construction schedule

FXG-Clarksburg – Entrance to facility and view of docks and office

FXG-Clarksburg – Masonry façade of finished offices

FXG-Clarksburg – Corridor of the finished office area.

FXG-Clarksburg – Sorting line and interior of completed warehouse.

Kansas City, MOBunzl Distribution Center, 2004

Size: 102,119 s.f. Land: 8.1 acres Cost: $3.7 mil Features:

Cast-on-site Tilt-up concrete exterior walls Conventional structural steel framing 12 trailer positions with adjustable docks 1 drive-in door ESFR Sprinkler system

Bunzl Project – West side and office entrance of Bunzl facility

Bunzl Project – Office entrance to facility

Bunzl Project – Trailer docks and drive-in door to warehouse

Birmingham, ALFedEx Ground Distribution Ctr, 2004

Size: 96,406 s.f. Land: 14.3 acres Cost: $3.8 mil Features:

Cast-on-site Tilt-up concrete wall exterior Conventional steel frame and roof 4,524 s.f. of finished office 24 dock doors and 7 drive-in doors

FXG-Birmingham – Auto parking and distribution facility

FXG-Birmingham – Office entrance and view from NE

FXG - Birmingham – Package sorting facility in warehouse

Kansas City, MOPalestine Missionary Baptist Church, 2003

Overall project consisted of expansion and improvements in the sanctuary, including construction of a balcony for additional seating, installation of a lift to the choir stand for handicapped choir members, and relocation of the sound and media room. Exterior renovations included construction of a new two-story classroom addition and an adjoining two-tier concrete parking facility. The following photos illustrate construction of the temporary retaining wall erected to protect adjacent residences while building new parking and education facilities at the site.

PMBC – Temporary retaining wall utilizing oak timbers and I-beams was constructed during excavation for the new two-tier Parking Garage and two-story Classroom Facility.

PMBC – I-beams were placed in drilled shafts then wall sections were constructed as excavation was completed.

PMBC – Wall sections were constructed on the ground then set during excavation.

Independence, MOShops at Eastland Center, 2002

Cast-on-site Tilt-up concrete exterior walls Thinset brick inlay on all exterior panels Conventional steel frame and roof 20,000 s.f. retail center Tenant finish for banking client

Eastland Center – Anchor tenant is a banking client with drivethrough

Blue Springs, MOLunar Bowl Recreation Facility, 2001

39,000 s.f. Recreation Center 32 Lane Bowling Facility Game room Full-service restaurant Cast-on-site Tilt-up concrete exterior walls Glass curtain entries Pre-engineering frame and roof

Lunar Bowl Project – Main entry to recreation center

Lunar Bowl Project – Separate entry to restaurant

Lunar Bowl Project – Professional bowling facilities

Sugar Creek, MOLaFarge New Cement Production Facility, 2000

Multiple slipform concrete storage towers Tallest finished structure over 400 ft Precast exterior wall office facility Two deepshaft mines for raw materials Production facilities constructed of structural steel, cast

concrete and masonry Constructed over hundreds of acres

LaFarge Project – View of facility near midway point of construction

LaFarge Project – Slip-formed storage facilities and cement finishing facility

LaFarge Project – Office facility on left and kiln equipment on right

LaFarge Project – Raw material conveyor from mine to cement facility

Thank you.

This has been a sampling of the projects I have managed since the year 2000. Thanks for viewing my slideshow.